Professional Documents
Culture Documents
Operator is mobilizing a turret moored (5 x 2 cluster) FPSO in the PY-3 Field, in the East coast of India.
a. Flowline Riser and ancillaries are ready at factory for transportation pending FAT.
c. Riser Buoyancy modules and Gravity Base block are currently in transit to India.
In line with the requirements for SURF installation, Contract has been awarded for project management
and suitable vessel meeting the requirements for installation shall be deployed.
There shall be separate Contractors to execute the scope of SURF installation and Mooring Installation
respectively. While SURF contractor shall carry out laying, installation and connecting subsea
umbilical, flowline and riser including decommissioning of existing system connected to PD-3S X-
MAS Tree, another Contractor shall carry out the scope of mooring system installation and FPSO hook
up activities.
The intention of this Contract is to provide a clear way of working on this engineering project which
allows the Operator to stay in complete control of its project while PMC Contractor manages the
complete process and provides end to end support. This means the PMC Contractor takes care of all the
stages of engineering & installation including planning and co-ordinating with all contractors and sub-
contractors on Operator’s behalf and being single point of contact.
This scope of services involves specialist engineering processes which requires to be detailed, planned,
coordinated and executed. This approach shall allow the Operator to have complete transparency and
involvement in engineering options and decisions that requires to be made, associated cost implications,
and provides Operator more control over the process. This is especially important in this kind of
technical speciality projects where the Operator shall get the benefit from the unique expertise,
qualifications and experience of the PMC Contractor to guide Operator on how best to achieve its
desired outcome.
The PMC Contractor requires to provide end to end construction management for the project with
comprehensive planning of the construction elements, costs, logistics and construction team; on-site
management of Contractors, individual operatives, equipment’s, alignment of services and office
facilities, all encompassed to effectively supervise the construction of the Operator’s project through to
completion. All the while, co-ordinating the supply of information provided by the Contractors and by
the project team through to the Operator at all times as per the PMC model of working.
“Management” is at the very core of this service, essentially a full-circle, all-encompassing project
management service which allows the benefits of specialist expertise to achieve engineering excellence
whilst at the same time allowing the Operator complete control over the entire process at all stages.
PMC Contractor shall ensure that Operator communications are exactly as needed and there exists no
potential gap in roles and responsibilities, from their side as well as from the engineering perspective.
PMC Contractor shall be responsible to fully comply and strictly adhere to all rules and regulations laid
in place by local government bodies, internationally and as per IMO guidelines. As a minimum the
following regulations are considered applicable to the WORK.
PMC Contractor shall be responsible for planning and administration of the WORK. Within fifteen (15)
calendar days from receipt of LOI / award of Contract (as the case may be), PMC Contractor shall
submit draft project execution plan including, but not limited to, following deliverables for Operator’s
review and approval.
Once the project execution plan is approved by the Operator, PMC Contractor shall perform its activities
to the approved project execution plan throughout the phases of WORK.
1. Project management and administration services for SURF & FPSO packages.
2. Develop plan for loading of flexible flowline riser from Asiaflex, Tanjung Langsat,
Malaysia on Operator provided installation reel complete with offshore cradle and
spreader bar involving scope including but not limited to:
a. Project management
b. Trans spooling to installation reel
c. Mobilisation plan inclusive of deck arrangement and craneage services.
3. Develop procedure & verify well integrity and X-mas tree valves operability for PD-3S
well for safe disconnection of existing flowline umbilical.
4. Develop commissioning and start-up manuals for newly installed SURF to existing
PD3S Christmas tree.
5. Interface Management for all work packages i.e. SURF, Mooring & FPSO.
6. Based on first CP inspection; anode replacement strategy to be developed.
Document review shall be in accordance to Master Document and Drawing Register (MDDR)
provided by SURF Installation Contractor & SURF OEMs and any Operator agreed revision to this
document. PMC Contractor shall review following and provide its timely suggestions, guidance to
improve the process/documents and to bridge any gaps/delay.
2. All inputs used and output generated by the sub-contractors through their software analysis/
calculations.
3. SURF Contractor submitted documents & engineering plans for loadout, transportation,
installation and pre-commissioning including punch point liquidation.
Apart from the above, PMC Contractor shall provide following services:
a. Review and verify the information to identify the gaps, if any, and to conform to
compliance with respect to installation procedures developed by the SURF Contractor.
b. Conduct engineering and safety audits of Contractor’s and sub-contractor’s vessel and
equipment, as required.
c. Support Operator on optimization and planning of various activities during the
Execution phase.
d. Support Operator for co-ordination with TPI & TPCA and active participation in
HAZID & HAZOP workshops including emergency disconnection strategy on FPSO.
e. Deployment of expert and experienced personnel to various locations, as required by
Operator. viz. Operator’s office, warehouse for verification on storage, preservation
techniques and identification of Operator free issued material to SURF Contractor,
installation vessel, FPSO for design review /supervision etc.
f. Facilitating the pre-start up safety audit and other statutory audits.
PMC Contractor shall be responsible for managing and acting as an interface in activities at
all phases of the project. By acting as the Operator's focal point of contact, PMC Contractor
shall be consolidating works of relevant Contractor’s & sub-contractors on various modules
of the project under one execution program to meet the objective of the project.
Project Execution Plan (PEP): PMC Contractor shall prepare PEP (Project Execution Plan) as
detailed below including but not limited to the following:
a. Develop, maintain and implement a detailed specific Project Execution Plan (PEP) for
the entire project. PEP may include key plans, directions and procedures necessary to
execute the work and shall cover all aspects of managing the project within
Contractual obligations, as more described in this document.
b. Due consideration shall be provided to HSE management, safety case, quality
management, project controls, information management, use of best practices in terms
of value and risk management during the project execution phase.
c. Details of personnel, systems, services, functions, equipment and material as
required during the contract phase.
1. PMC Contractor shall prepare the project schedule for continuous monitoring.
2. For documentation management, PMC shall use Operator provided platform for document
management.
3. The project schedule shall include interdependencies at micro level for improved interface
management.
4. With reference to an integrated project schedule, PMC Contractor shall review and validate
as provided by individual Contractor.
5. Analyze Contractors' schedule and advise Operator on the gaps and suggest remedial
measures for achieving the end goal of the project.
6. Identify critical path for the project and review regularly for improvement and risk
mitigation.
7. The presence and installation of the subsea assets may restrict the mooring leg pre-lay or
wet-storage patterns as well as introducing SIMOPS opportunities. In this scenario, PMC
Contractor shall consider such background factors and plan the WORK in such a way that
gives the maximum flexibility in responding to such potential restrictive situations.
8. In case of mismatch between SURF Contractor deliverables and Mooring Contractor
deliverables resulting into de-mob of SURF contractor, PMC contractor shall prepare
contingency plan indicating available/required resources and submit to the Operator for
review and approval.
CONTRACTOR’S DELIVERABLES
Below are the list of deliverables to be performed and provided in relation to the Contract.
1. Preparation of Project Execution Plan within 15 days from the date of LOI / Award of
Contract.
2. Regular progress report including overdue & look ahead plans, catch up plans & critical
path activities.
3. Developing procedure & manuals in native & approved version.
4. Providing interface register on weekly basis.
5. Site specific daily progress reports and updates during deployment of personnel offshore at
SURF Installation vessel and FPSO
OPTIONAL SCOPE
Contractor shall carry out the following activities for well start-up, as optional scope.