You are on page 1of 97

Document Number SHJ-PC-PLM-X-08361

Revision 0
Applicability Sharjah
Document Type Plans & Manuals

Planning, Scheduling, Progress Measurement and Schedule


Assurance Manual

REVISION / APPROVAL HISTORY

0 13-Jun-2011 BMS 1st Issue Debashish Jonathan Jonathan


Ghosh Mcgivern Mcgivern

Rev Date Description of Change Originator Reviewer Approver

Records of approval are retained in the BMS/Quality Department

Page 1 of 7
This document is an uncontrolled copy when printed or saved. Viewed by:
Ahmad Warsi 13-Mar-2012
Document Number Document Title Revision
Planning, Scheduling, Progress Measurement and
SHJ-PC-PLM-X-08361 0
Schedule Assurance Procedure

CONTENTS

1.0 PURPOSE ........................................................................................ 3

2.0 SCOPE ............................................................................................ 3

3.0 DEFINITIONS .................................................................................... 3

4.0 REFERENCES .................................................................................... 4

5.0 RESPONSIBILITY & AUTHORITY .............................................................. 4

6.0 DESCRIPTION ................................................................................... 4

7.0 RECORDS ........................................................................................ 7

8.0 APPENDICES..................................................................................... 7

Page 2 of 7
This document is an uncontrolled copy when printed or saved. Viewed by:
Ahmad Warsi 13-Mar-2012
Document Number Document Title Revision
Planning, Scheduling, Progress Measurement and
SHJ-PC-PLM-X-08361 0
Schedule Assurance Procedure

1.0 PURPOSE
The purpose of this Procedure is to provide direction for project control managers and
planning engineers for the set up and execution of the planning and scheduling functions
for all Petrofac Engineering and Construction Group projects.
The Procedure is the highest level of the Project Controls hierarchy of controls documents
and summarises the components that make up the entire suite of project controls for any
given project.

2.0 SCOPE
This procedure covers the proposal planning and engineering, procurement, construction
and completion planning scope for all Petrofac Engineering and Construction Group
proposals and projects.
Progress measurement activities for engineering, procurement, construction and
completion are also covered within this document for all Petrofac Engineering and
Construction Group proposals and projects.

3.0 DEFINITIONS
CDR Construction Documents Register
CPM Critical Path Method
IDC Inter Disciplinary Check
IFA/IFR Issued for Approval/Review
IFC Issued for Construction
IFD Issued for Design
IM Inch Meters
MC Mechanical Completion
P&ID Piping and Instrumentation Diagram
PCM Project Control Manager
PCS Project Control System
PEP Project Execution Plan
PM Project Manager
PTR Procurement Tracking Report
RFC Ready for Commissioning
RFSU Ready for Start-up
SBM Schedule Basis Memorandum
TDR Technical Documents Register
WBS Work Breakdown Structure
WDI Weld Diameter Inches

Page 3 of 7
This document is an uncontrolled copy when printed or saved. Viewed by:
Ahmad Warsi 13-Mar-2012
Document Number Document Title Revision

Planning, Scheduling, Progress Measurement and


SHJ-PC-PLM-X-08361 0
Schedule Assurance Manual

4.0 REFERENCES

SHJ-PC-WIN-X-0603 - Completions Progress Measurement Work Instruction

SHJ-PC-WIN-X-0602- Construction Progress Measurement Work Instruction.

SHJ-PC-WIN-X-10110-Schedule Assurance Work Instruction

SHJ-PC-WIN-X-0599 - Engineering, Procurement, Construction, Completion, Pre-


Commissioning and Commissioning Planning and Scheduling Work Instruction

SHJ-PC-WIN-X-0598 - Proposal Planning Work Instruction

SHJ-PC-WIN-X-0600 - Engineering Progress Measurement Work Instruction

SHJ-PC-WIN-X-0601 - Procurement Progress Measurement Work Instruction

5.0 RESPONSIBILITY & AUTHORITY

5.1 Project Manager


Approve the planning dossier

5.2 Project Engineering Manager


Review and endorse the planning dossier (as applicable)

5.3 Procurement Manager


Review and endorse the planning dossier (as applicable)

5.4 Contracts Manager


Review and endorse the planning dossier (as applicable)

5.5 Construction Manager


Review and endorse the planning dossier (as applicable)

5.6 Project Control Director / Project Control Manager


Review and endorse the planning dossier (as applicable)

5.7 Planning Engineer


Produce the components of the planning dossier. Maintain the production schedules
and progress records to support construction contracts administration and support in
the event of client, contractor or sub contractor claims.

6.0 DESCRIPTION

6.9 Proposal Planning

Proposals Planning is an intense period of conceptual planning work where the


overall schedule is determined, critical paths are established, schedules are
benchmarked and indicative progress ‘S’ curves and histograms are created.

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
Document Number Document Title Revision
Planning, Scheduling, Progress Measurement and
SHJ-PC-PLM-X-08361 0
Schedule Assurance Procedure

Project Controls documents prepared during the proposals phase generally include:

 Level 1 schedule – depicting the overall scope on 1 sheet of paper

 Level 2/3 schedule – CPM activity network suitable for Risk Analysis.

 Risk Analysis

 Progress ‘S’ Curves

 Manpower Histograms

 Benchmarking Data
There will be a number of reviews during the development of the proposal schedule
such that the entire proposal team is aware of and contributes to the schedule. The
schedule will be reviewed and endorsed by the Project Controls Director or his
assignee and approved by the Proposals Manager.
6.9 EPC Planning
Once Petrofac has received notification of a Project award, the project controls
team is assigned and begins work on the preparation of the Project Control
deliverables required for the execution phase. It is usual for the planning package
to be prepared during the first 90 days. In order to allow the Project Team to focus
on required early critical activities, a 90 day look-ahead work list is prepared and
used to keep track of the early project activities until such time as the complete
control system is in place. In some instances it will be necessary to measure
progress against the initial 90-day lookahead which will be superseded with the
overall project progress report, when available.
The EPC Work Instruction goes into some depth about the following components of
the EPC planning phase:
 Work Breakdown Structure

 Project Calendars

 Update to Level 1 EPC Schedule

 Update to Level 2 EPC Schedule

 Development of Level 3 EPC Schedule

 Path of Construction

 Contents of the Planning Dossier


o Schedule Basis Memorandum
o Key Milestone identification and Reporting
o Progress ‘S’ Curves
o Man-hour Histograms
o Key Commodity Curves

Page 5 of 7
This document is an uncontrolled copy when printed or saved. Viewed by:
Ahmad Warsi 13-Mar-2012
Document Number Document Title Revision
Planning, Scheduling, Progress Measurement and
SHJ-PC-PLM-X-08361 0
Schedule Assurance Procedure

o Fragnets
o Benchmarking data
o Critical path analysis and narrative
o Progress Measurement and control procedures
o Engineering Planning
 TDR
o Procurement Planning
 PTR
o Construction Planning
 CDR (Construction Documents Register)

 Level 3 and Level 4 Construction Planning

 Sub-Contract Tracking

 Completion planning

 Any project specific procedure which are required under the specific
contract, to be prioritised for the document which need client review and
approval
6.10 Engineering Progress Measurement
The Project Control System is used to configure deliverable weightings and link
the deliverables listed in the Technical Document Register (TDR) to level 3
activities. Each deliverable is tracked through the development cycle and
actual progress is reported against achieved stage of development.
The Project Controls system generates various status reports and provides
business intelligence dashboards that allow drill down through the WBS levels of
progress.
6.11 Procurement Progress Measurement
The Project Control System is used to configure deliverable weightings and link
the deliverables listed in the Procurement Tracking Register (PTR) to level 3
activities. Each deliverable is tracked through the procurement cycle and
actual progress is reported against achieved stage of development.
The Project Controls system generates various status reports and provides
business intelligence dashboards that allow drill down through the WBS levels of
progress.
6.12 Construction Progress Measurement
The Project Control System holds corporate standard rules of credit for
construction prefabrication and installation activity. Each level 3 activity is
described and supported by level 4 sub-activities and associated fragnets.

Page 6 of 7
This document is an uncontrolled copy when printed or saved. Viewed by:
Ahmad Warsi 13-Mar-2012
Document Number Document Title Revision
Planning, Scheduling, Progress Measurement and
SHJ-PC-PLM-X-08361 0
Schedule Assurance Procedure

Progress weightings are based on earned effort and physical progress updates
are entered in the system on a weekly basis.
The Project Controls system generates various status reports and provides
business intelligence dashboards that allow drill down through the WBS levels of
progress.
6.13 Completions Progress Measurement
The Project Controls System links to the Completions System to assess check
sheets completed versus the number of estimated checksheets. Checksheets
are tracked for Construction Completion, Pre-commissioning Completion and
Commissioning Completion.
The Project Controls system generates various status reports and provides
business intelligence dashboards that allow drill down through the sub systems
and systems.
6.14 Schedule Assurance
The schedule Assurance work instruction highlights the requirement for
independent reviews of schedule status, progress documentation and forecasts
at key points throughout the project life cycle.
The assurance process provides impartial assessment of schedule forecasts with
findings presented to all concerned stakeholders in a report.

7.0 RECORDS

N/A

8.0 APPENDICES
8.15 Some Rules of Thumb
8.16 Typical Level 1 Schedule
8.17 Standard WBS Structure
8.18 Standard Construction logic and fragnets
8.19 Engineering logic diagrams
8.20 List of standard activities
8.21 Standard EPC level 3 schedule
8.22 90 day look-a-head schedule
8.23 Example TDR format
8.24 Example PTR format – Equipment
8.25 Example PTR format – Bulks
8.26 Example CDR Format
8.27 Subcontracting Progress

Page 7 of 7
This document is an uncontrolled copy when printed or saved. Viewed by:
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROL DEPARTMENT NOVEMBER 2010
PLANNING, SCHEDULING, PROGRESS MEASUREMENT AND SCHEDULE ASSURANCE QUALITY DOCUMENTS ORGANISATION

Planning, Scheduling, Progress 
Measurement and Schedule Assurance 
Procedure

Engineering  Construction 
Schedule 
Proposal  Progress  Progress  Planning, Scheduling, 
Assurance 
Planning Work  Measurement  Measurement  Progress Measurement 
Work 
Instruction Work  Work  and Schedule Assurance 
Instruction
Instruction Instruction Manual

Procurement  Completion 
EPC Planning  Progress  Progress 
Work  Measurement  Measurement 
Instruction Work  Work 
Instruction Instruction

Project Control System (PCS)

ThisAPW 22/11/2010
document is an uncontrolled copy when Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\01a.Manual Flow Chart
printed or saved. Viewed by:
Ahmad Warsi 13-Mar-2012
Sl Major activities DURATION IN ORDINAL MONTHS
No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
2010 2011 2012 2013 2014 2015
O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A
CONTRACT MILESTONES
Š Effective Date ( 01.10.2010)
Š Base De Vie (At Insalah CPF) ‐ Handover (01‐Oct‐2012)
Š WELLS (Well Pad Ready for Drilling / Well Ready for Hook up)
1 2 3
GBF  (Garet el Befinat)
1 2 3
1 2 WI
HMN (Hassi Moumene) 2
1 WI
1 2 1 3 4 4 5 6
GMD (Gour Mahmoud)
2 3 5
1 2 3 4 5
IS (In Salah)
1 2 3
Š PIPELINE (Conditional Acceptance Certificate)

24" Dry Gas Pipeline (   ICP to Reg CPF),32" Dry Gas Pipeline (Reg CPF to IS 
CPF), 16 " Wet Gas Pipeline (GBF Wells to IS CPF),  16" Wet Gas Pipeline 
(HMN Wells to IS CPF)‐28.04.2013

16" Wet Gas Pipeline (IS Wells to IS CPF), 16" Wet Gas Pipeline (GMD Wells 
to IS CPF ) ‐05.05.2014
Š CPF ‐Ready for Startup (Conditional Acceptance Certificate)
In Salah CPF / Reg CPF (28.04.2013)

Š 2nd STAGE COMPRESSION (Conditional Acceptance Certificate)

Reg (28.04.2013) / Teg  & Krechba (01.09.2014)

Š All Works Completed (31.12.2014)
ENGINEERING 

Residual Feed Verification (Post Award)
P&ID-IDC P&ID-IFA P&ID-IFH P&ID-IFD P&ID-IFC
Process
HAZOP WITH
HAZOP WO
VENDOR PKG
VENDOR
HSE
D/S-Rot D/S-Stat

Mechanical
MTO X-Steel Drg- 1st Lot

Civil / Structural
Arch Drgs Fdn Drg

Buildings
30 % Review 60 % Review 90 % Review
3D Modeling
Plot Plan Plot Plan -IFC ISO-1st Lot

Piping
Pipeline MR s ALIGNMENT SHEETS release start
Pipeline
Cable-Layouts-Start
Load List Elect-MRs
Electrical
Instr. Index CR-Layouts
Instrumentation

Telecom
Engineering Substantially Complete
As‐Built
FREE ISSUE MATERIAL
13% Cr Line Pipes (FIM) ‐8",12" & 16"  Total 164 KM 18 20 20 19 19 18 19 32

PROCUREMENT 
Line Pipes Procurement (8" ,24" ,32")‐ 151 KM Approx. 26 25 25 25 25 25
E P D1 D

LP /HP Flare Package E P S D

Air Cooled Heat Exchangers E P S D1 D

Tanks E P S D

D1
Vessels / Separators E P S D

E S D
Glycol Regeneration Package P

Fuel Gas Heater E P S D

Diesel Coalsers & Filters E P S D

Scrapper Launchers / Receivers E P S D1 D

E S D
Incineration Package P

Gas Turbine Generator Package E P S D

Air Compressor & Dryer Package E P S D

Chemical Injection Package E P S D

Pumps , Other Packages & Equipments  E P S D1 D

ICS Package E P S D

Package Sub‐Stations  E P S D

 Transformers / Electric Diesel Generators E P S D

Piping  /Pipeline Bulks  E P S D1 D

Piping Pre‐Fabrication  ( By Sub‐contractor)

E / I / Telecom Cables  E P S D1 D

E / I / Telecom  Bulks E P S D1 D

CP System E P S D1 D

Structural Steel (Procurement & Fabrication) E P S D1 D

Pre‐Engineered Buildings ( Shelters ) E P S D1 D

CONSTRUCTION  & COMMISSIONING
Temporary Facilities ( All Sites )
Well Heads & Pipelines
Well  GBF & HMN well Pad Compln Well  GMD & IS well Pad Subst. Compln
Location Confirmation & Land
Well pad construction(Incl. Access Road) Handover Start
GBF & HMN hookup Compln GMD& IS hookup Compln
Well Head hook up 
GBF & HMN PL Compln
13 % Cr Steel Pipeline Laying (8" *& 12 ") ‐ Well Head‐36 KM ‐05.05.2014 (only 
Welding Compln
HMN & GBF ‐28.04.2013‐ 11 Km) GBF & HMN PL Compln
13 % Cr Steel Pipeline Laying (16 " Wet Gas ‐GBF Wells to IS CPF‐ 32 KM &   16" 
Wet Gas ‐HMN Wells to IS CPF‐ 13 KM, 8" CS water Inj ‐ IS CPF  to HMN wells‐
16 KM) ‐28.04.2013 Welding Compln Interfield Line IS & GMD
Compln
13% Cr Steel Pipeline Laying (16" Wet Gas ‐IS Wells to IS CPF & 16" Wet Gas ‐
GMD Wells to IS CPF )  ‐ Total  79 KM   ‐05‐05‐2014 Welding Compln
Reg & CPF PL Compln

CS Pipeline Laying ( 24" Dry Gas ‐ Reg CPF to ICP‐62 KM & 32" Dry Gas‐ Reg CPF 
to IS CPF‐73 KM)‐28.04.2013

In Salah CPF

Site Preparation & Access Road CR & S/stn - Ready for E& I works

Building Works 
UG Piping Works
Civil Works 
Structural Work 
Equipment Erection
Hydrotest Start
Piping Installation,Testing & Reinstatement      
Control System Power on
S/Stn Energisation
Electrical / Instrumentation / Telecom / HSE works

Interface works ( Piping , Elect , Instru ) 
Pre‐Commissioning (incl. Utilities)
Process Commissioning

Reg CPF

Site Preparation & Access Road CR & S/stn - Ready for E& I works

Building Works 
UG Piping Works
Civil Works 
Structural Work 
Equipment Erection
Hydrotest Start
Piping Installation,Testing & Reinstatement      
Control System Power on
S/Stn Energisation
Electrical / Instrumentation / Telecom / HSE works

Interface works ( Piping , Elect , Instru ) 
Pre‐Commissioning (incl. Utilities)
Process Commissioning

Teg CPF

Site Preparation & Access Road CR & S/stn - Ready for E& I works

Building Works 
UG Piping Works
Civil Works 
Structural Work 
Equipment Erection
Hydrotest Start
Piping Installation,Testing & Reinstatement      
Control System Power on
S/Stn Energisation
Electrical / Instrumentation / Telecom / HSE works

Interface works ( Piping , Elect , Instru ) 
Pre‐Commissioning (incl. Utilities)
Process Commissioning

Krechba CPF
Site Preparation
CR & S/stn - Ready for E& I works
Building Works 
Civil Works 
Structural Works 
Equipment Erection
Hydrotest Start
Piping Installation,Testing & Reinstatement      

Electrical / Instrumentation / Telecom / HSE works

Interface works ( Piping , Elect , Instru ) 
Pre‐Commissioning
Commissioning
Base de Vie / Military Camp Works

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Equipment Foundations

Excavation Blinding Rebar Shuttering

Pouring Coating Backfill

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Tank Foundations

Slab Concrete / 
Excavation Ring Beam Concrete Compacted Fill
Bituminous Layer

Area Clearance

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Building Construction

Foundations / 
Excavation Pedestals / Columns Brick Wall / Plastering
Footings

Door / Windows 
Roof Finishing Works
Fixing

Flooring / Painting / 
False Ceiling

MEP Works

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Static Equipment

Alignment and Bolt 
Install on Foundation Install Internals Grouting
Up

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Rotating Equipment

Alignment and Bolt 
Install on Foundation Install Internals Grouting
Up

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Site Fabricated Tanks

Painting / Finishing 
Fabrication Erection Hydrotesting
Works

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Structural Steel Fabrication

Marking and Cutting Laying and Fit‐up Welding NDT

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Structural Steel Erection

Installation on 
Welding / Bolt‐up NDT
Foundation

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Piping Prefabrication

Fit‐up Welding NDT

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Piping Erection

Installation Inch‐M Supports NDT

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Underground Piping

Coating and 
Fabrication Erection Leak Testing
Wrapping

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Electrical Equipment and Panel

Support Structure /  Inspection and 
Erection Internals and Wiring
Preparatory Work Acceptance

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Instrument Equipment and Panel

Support Structure /  Inspection and 
Handling and Setting Levelling and Fixing
Preparatory Work Acceptance

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Elec_Inst Cable Laying

Megger / Continuity 
Lay Cables Install Clips / Cleats
Test

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Instrument Installation

Instruments 
Supports Installation Inspection
Installation

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Painting

Shot Blasting and  Final Coat (Including 
Intermediate Coat
Prime Coat Inspection)

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD CONSTRUCTION FRAGNETS
Pipeline

Gauging, Testing and 
Right of Way Stringing
Dewatering

FF ‐ 14 Days (Typical)
SS ‐ 14 Days (Typical) Welding

Trenching

Cross Work

Laying

FF

Backfilling

This document is an uncontrolled copy


APW 5/12/2010 when printed or saved. Viewed by:
Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4
Ahmad Warsi 13-Mar-2012
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD LEVEL 3 LOGIC
Path of Construction

U/G Services (Pipe, 
Install Equipment 
Site Preparation Piling Piperack Foundations MH's, CB's, Drainage  Backfill and Paving Piping Erection
(Static & Rotating)
Trenches)

Earthing Grid under 
Underground Cable  Paving Erect Steelwork ‐ 
Temporary Facilities Buildings Cable Supports
Routes Technical Structures

Erect Steelwork ‐ 
Piperacks
Electrical 
Equipment Pre‐
Equipment Pre‐ Equipment 
Equipment
Steel Fabrication Tank Foundations Pull Cables Terminations at Field 
dressing Foundations
Equipment

Equipment 
Heavy Lift Install Switchgear &  Electrical 
Fireproofing Structure and Pipe 
Pipe Fabrication Tank Erection Electrical Panels &  Terminations in 
Support Foundations
JB's Buildings

Steel Concrete 
Install Control &  Instrument 
Pipe Supports  Fireproofing Cable Supports in  Steel Platforms & 
Instruments Panels &  Terminations in 
Fabrication Buildings Ladders
JB's Buildings

Final Fireproofing Temporary Power Instruments Control 


Instrument Stands  Small Power & 
Roads & Drainage System Site  Motor Runs
Fabrication Lighting
Acceptance Test

Pre‐calibrate Field  Instrument Stands  Piping Hydrotesting  Fencing & Site 


Insulation Turnover
Instruments Installation and Reinstatement Finishes

Field Instruments  Field Cable Routes &  Field Instruments  Systems Mechanical  Systems Pre‐ Systems 


Loop Check
Installation Cabling Cables Terminations Completion commissioning Commissioning

This document is an uncontrolled copy when printed or saved. Viewed by:


APW 13/12/2010 Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4a
Ahmad Warsi 13-Mar-2012
Load inputs from Inputs for
Steel MTO 1st fabrication Final fab
piping / electrical / secondary steel
bid/award drwg review drwg
instrumentation structure

Topo Main piperack Equipment Secondary Fabrication


survey steel framing steel steel structure steel drwgs
Procurement
cycle

Basis off G
Geotechh Geotechh Nozzle
Start Platform & Clip info to
design survey report orientations/
ladder drwgs vendors
piping inputs

Design Site prep 1st civil Final civil


Specs layouts MTO/REQ/Bid MTO/REQ/Bid

Eqpt data &


loads from
vendors Secondary Finish
Foundation Primary FDN
FDN drwgs
design drwgs
IFC
Road &
paving
Plot Plan Piling layouts Architectural
details &drwgs

Buildings space
req. from Preliminary Final Building Architecture Procurement
Elect & inst electrical / building design Layouts MTO/REQ/Bid cycle
eqpt layouts telecom

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Civil Structural Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
Process
datasheets Procurement Procurement
Mechanical
data sheets bid / receipt recovered /

Design basis / Inquiry Technical bid Purchase


Specifications
review Requisition evaluations requisitions
Receipt at
site per tag

Vendor data
Inspection Shipping /
Purchase order Vendor Design review & Manufacturing
& release delivery
approval

Expediting

Notes:
1) Logic to be used for each requisition.
2) Receipt at site milestone to identify each tag number.

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Equipment Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
Instrument Platform &
installation details ladder drwgs

Installation
specifications Instrument Cable Cable /
locations routings drum

Finish
Process
instrument
Instrument index Instrument index Loop
data
set up development diagrams

Instrument
Design basis / Design In line instruments Bulk instrument Procurement
Start process hook up
review Specifications REQ/Bid/Award MTO cycle
drwgs

Control system Distributed Termination


P&IDs IFA Vendor data
block diagram control system diagrams

Panel/distribution
I/O count boards
P&IDs IFD Control room Final building
REQ/Bid/Award
equipment layouts layouts

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Instrumentation Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
Complete
Eqpt modeling
equipment
(phase 1)
modeling

Key vendor Commence Complete


data isometric isometric
Design basis Design Plot plan, eqpt extraction extraction
Start
/ review Specifications layout IFA

P&IDs IFD
Material Finish
specifications

Piping modeling Piping Piping


(stage 1) modeling modeling

P&IDs IFA
Intermediate
Bulk MTO valves Stress Final MTO
MTO valves &
& piping sketches valves & piping
piping

Nozzle Final stress Pipe support


orientations analysis & pipe schedules

30% model 60% model 90% model


review review review

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 A/G Piping Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
Procurement Procurement Procurement
cycle cycle cycle

U/G
U/G bulk MTO intermediate
MTO
U/G final MTO

Design basis Design U/G isometrics


Fire water layouts
/ review Specifications IFC

Conceptual Cooling water Road and


design layouts paving
layouts

Drainage Installation
Drainage layouts details
calculations

Preliminary
Manhole
building Sewerage layouts
schedule
design

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 U/G Piping Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
To To
To dcs
mechanical instrument
vendor
revisions

Heat & Process


Design basis Process EQPT data
material instrument
/ review sheets Instrument
balances data
logic diagrams

Material
Process
Start l i
selection Equipment list
l IFA Equipment list Equipment list
simulations Finish
diagrams IFD IFC

To
Process flow Cause & effect
Line list IFA Line list IFD intermediate
diagrams diagrams
piping MTO
To Final
piping MTO

Operations &
Hydraulic Preliminary
P&IDs IFA P&IDs IFD P&IDs IFC maintenance
calculations HAZOP
manual

Line list IFC

To 3D model To piping bulk To instrument


Final HAZOP Key vendor
development MTO design
data

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Process Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
Major activities   DURATION IN ORDINAL MONTHS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

Del(M)
CONTRACT MILESTONES
Effective Date
Mechanical Completion of Water Intake & Water  27
Mechanical Completion of Train‐I of Gathering System  28
Mechanical Completion of Train‐II of Gathering System  33
Start‐up of Water Intake & Water Pipeline 28
Completion of Accomodation Camp 25
Start‐up of Train‐I of Gathering System and Central 
29
Processing Facilities (150K BPD)
Start‐up of Train‐II of Gathering System and Central 
34
Processing Facilities (250K BPD)
Completion of Work 36
ENGINEERING 

Feed 4
P&ID-IDC P&ID-IFA P&ID-IFD P&ID-IFC
P&ID-IFH

Process 12
HAZOP WO VENDOR PKG HAZOP WITH VENDOR PKG

HSE 10
D/ata Sheets

Mechanical 11
Topo/Soil MTO X-Steel Drg- 1st Lot

Civil / Structural 12
Arch Drgs Fdn Drg

Buildings 9
PO Place Piling Drg

Design Pre‐Cast
Design Pre‐Cast 6
30 % Review 60 % Review 90 % Review

3D Modeling 13
Plot Plan -IDC Plot Plan -IFA Plot Plan -IFD ISO-1st Lot

Piping 13
Pipeline MR s ALIGNMENT SHEETS release start

Pipeline 10
Load List Elect-MRs Cable-Layouts-Start
Electrical 13
ICSS D/S Instr. Index
CR-Layouts
Instrumentation 13

Telecom 9
As‐Built Updation 11
PROCUREMENT 
Line Pipes (PIL) 5 E P EW D1 D

LP /HP Flare Package (PIL) 9 E P EW D

Air Cooled Heat Exchangers(PIL) 11 E P EW D1 D

EW
Shell & Tube Heat Exchangers Skids ‐ Stage‐I 14 D1 D

Shell & Tube Heat Exchangers Skids ‐ Stage ‐II 18 EW D D1

Plate Heat Exchangers Skids ‐ Stage‐I 14 EW D1 D

Plate Heat Exchangers Skids ‐ Stage ‐II 18 EW D D1

EW
Desalter Package Skids ‐ Stage‐ I 14 D1 D

Desalter Package Skids ‐ Stage‐ II 18 EW D D1

Fired Heaters (PIL) [Hot Oil Heaters] ‐ 8 No 12 E P EW D1 D D1 = 3 No D = 5 No

10 ‐ 
10
Storage Tanks(PIL) E P EW D1 D
13
EW
HP LP Vessels Skids ‐ Stage‐I 14 D1 D

HP / LP  Skids ‐ Stage‐II 18 EW D D1

P EW D1 D
Liquid N2 Storage and Vapourization Skids (PIL) 5 E

EW
Electric Heater Skids ‐ Stage‐I 14 D1 D

Electric Heater Skids ‐ Stage‐II 18 EW D D1

Filter & Filter Skids (PIL) 9 E P EW D

Hydrocyclone Skids (PIL) 9 E P EW D

Scrapper Launchers / Receivers (PIL) 10 E P EW D1 D

EW
Manifolds Skids ‐ Stage‐I  14 D1 D

Manifolds Skids ‐ Stage‐II 18 EW D D1

E P EW D1
Shutdown vales on flowlines 10‐12 D

Air Compressor & Dryer Skids (PIL) 12 E P EW D1 D

Chemical Injection Skids (PIL) 8 E P EW D1 D

Export Pumps 10 E P EW D1 D

API Pumps 8 E P EW D1 D

General Purpose Pumps 4 E P EW D1 D

Well Head Control Panel (PIL) 9 E P EW D1 D

ICSS Package (PIL) 11 E P EW D1 D

33 KV GIS Package Sub‐Station (PIL) 1 No, Main CPF 13 E P EW D

6 kv Package Sub‐Stations (PIL) Stage 1 ‐ 6 No 12 E P EW D1 D2 D3
D1 = Utilities, Trains 1 & 2 D2 = Trains 3 & 4, Water Intake, Well Pad M5 D3 = Well Pad M6

D4 = Trains 5 & 6, Trains 7 & 8 D5 = Train 9, Well Pad M8 D = Well Pad M7, 
6 kv Package Sub‐Stations (PIL) Stage 2 ‐ 6 No 12 EW D4 D5 D Well Pad M10

132 kv GIS Switchgear 5 No 12 E P EW D1 D
D1 = Well Pads M5 & M6 D = Well Pads M7, M8 & M10

 Transformers / Electric Diesel Generators(PIL) 8 E P EW D1 D
Dely. at Fab Shop
Piping Bulks  7 E P EW D1 D
Rcvd at Site
Piping Fabrication 3 E P EW D1 D2 D

E / I / Telecom Cables  5 E P EW D1 D

E D
E / I / Telecom  Bulks 5 P EW D1

D
HT Cable 5 E P EW D1

CP System 6 E P EW D1 D
Dely. at Fab Shop

Structural Steel (procurement) 4 E P EW

Structural Steel ( Fabrication) 3 E P EW D1 D2 D

Shelters 6 E P EW D1 D2 D D1 = Life Support, Guard Post, FW Pumps, IA Compressor, Air Dryers

E P EW D1 D2 D
Pre‐engineered Substation Buildings for 132 KV 6

Pre‐Engineered Industrial Building 6 E P EW D1 D D1 = Lab, Office part 1, Canteen, F&G Station, Export S/V's room, Telecom Building, Stage 1 HVAC rooms

Accommodation Camp
E P EW
Accommodation Camp Building (Pre Engg, HVAC, Piping) 5‐8 D1 D2 D

Accommodation Camp Building (Containerized, HVAC,  E P EW D1 D2 D3 D
5
Piping)
E P D1 D
Accommodation Camp Building (Equipment) 7 EW

Accommodation Camp (Containerised Substation ‐33 kV  E P EW D
13
GIS) ‐ 1 No
Accommodation Camp (Containerised Substation ‐ 
13‐15 E P EW D
0.4kV) ‐ 3 No
E P D1 D
Accommodation Camp (E&I and Tel) 6 EW

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
PI 10031 Level-1 Schedule-Rev-14a Sheet 1 of 3
Major activities   DURATION IN ORDINAL MONTHS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

Del(M)

Accommodation Bulk Pipe EW D

CONSTRUCTION  & COMMISSIONING
Pioneer Camp 2
Temporary Facilities 6 A

Topographical & Geotechnical survey 3 A

Stage ‐I Gathering System & Central Processing Facilities 
Including Utilities
Site Preparation & Access Road (flooding protection) 
7 A
[Utility Area]
Site Preparation & Access Road (flooding protection) 
7
[Storage Tanks & CPF Area]
Security protection (fencing, trenching,) 12
Piling 6 A

Pilling (cast in‐situ) ‐ [Tank storage] 5
Industrial Building (pre‐engineered) 10
Tank Foundations 6
Start Skid fdn [Utility Area]
Start Slug Catcher Install Sleepers
Civil Works  ‐ Utility Area 18 Pre-cast Sleepers
Start Skid fdn [CPFArea]
Civil Works ‐ CPF Area 14 Pre-cast Sleepers
Install Sleepers

Tank Erection 6

Structural Work  7
Piping Work
UG Piping Works
i i k 7 Manhole Work
Last Delivery
Module Installation/ Equipment Erection 4

Fired Heaters  Installation 4
Tank Hydrotest Start
Hydrotest Start
Piping  Installation,Testing & Reinstatement       10
33 S/Stn Energisation
33 kv GIS Package Sub‐Station Installation 4
6 S/Stn Energisation
6 kv  Package Sub‐Stations Installation 4 D D

Electrical /CP 7
Control System Power on
ICSS
 Instrumentation / Telecom / HSE works 8 D

Pipeline (Trunk Line) from Well Pads M5 & M6 11
Interface works ( Piping , Elect , Inst. )  3
Pre‐Commissioning 4
Mechanical Completion & Commissioning 4 Start of Performance Test
Assistance for Start‐up and Start Performance Test  3
HV Overhead Lines

Engineering and Procurement 6 E A
WP5 WP6 WP8

OHL 132 kV (Supply + Construction) to Well Pads M5,  Ready for Energize


12
M6 & M8
WP7 WP10
OHL 132 kV (Supply + Construction) to Well Pads M7 &  Ready for Energize
8
M10
OHL 33 kV (Supply + Construction) to Accomodation 
7 Ready for Energize
Camp
Ready for Energize
OHL 33 kV (Supply + Construction) to Water Intake 15

Well Pad Stage I (M5)


Well Pad Stage I (M5)
Site Preparation (leveling ‐ grading only) and Access  A
2
Road
Security protection (fencing, trenching,) 6
Piling 1 A

Install Switchyard 1.5
Energising 132kV
Pre‐engineered Substation (132kV substation) 6 D

Civil Works and foundation 6

Equipment erection 3
Hydrotest Start

Piping  Installation,Testing & Reinstatement       5
6 S/Stn Energisation

6 kv  Package Sub‐Station Instatallation 3 D

Electrical /CP 4
Control System Power on
Instrumentation / Telecom / HSE works 5

Pre‐Commissioning 3
Mechanical Completion & Commissioning 3
Well Pad Stage I (M6)
Site Preparation (leveling ‐ grading only) and Access  A
2
Road
Security protection (fencing, trenching,) 6
Piling 1 A

Install Switchyard 1.5 Energising 132kV

Pre‐engineered Substation (132kV substation) 6 D

Civil Works and foundation 6
Well Pad M8 (Stage 2) fed from Well Pad M6 (Stage 1)
Equipment erection
Equipment erection 3
H d t t St
Hydrotest Startt
Piping  Installation,Testing & Reinstatement       5
S/Stn Energisation
6 kv Package Sub‐Station Instatallation 3 D

Electrical /CP 4
Control System Power on
Instrumentation / Telecom / HSE works 5

Pre‐Commissioning 3
Mechanical Completion & Commissioning 3
Well Pad Stage II (M8)
Site Preparation (leveling ‐ grading only) and Access  A
2
Road
Security protection (fencing, trenching,) 6
Piling 1 A

Install Switchyard 1.5
Pre‐engineered Substation (132kV substation) 6 D Energising 132KV

Civil Works and foundation 6

Equipment erection 3
Hydrotest Start

Piping  Installation,Testing & Reinstatement       5
S/Stn Energisation
6 kv  Package Sub‐Station Instatallation 3 D

Electrical /CP 4
Control System Power on
Instrumentation / Telecom / HSE works 5
Pre‐Commissioning 3
Mechanical Completion & Commissioning 3
Well Pad Stage II (M7)
Site Preparation (leveling ‐ grading only) and Access  A
2
Road
Security protection (fencing, trenching,) 6
Piling 1 A

Install Switchyard 1.5 Energising 132kV

Pre‐engineered Substation (132kV substation) 6 D

This document is an uncontrolled copy


Civil Works and foundation 6 when printed or saved. Viewed by:

Ahmad Warsi 13-Mar-2012


PI 10031 Level-1 Schedule-Rev-14a Sheet 2 of 3
Major activities   DURATION IN ORDINAL MONTHS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

Del(M)

Equipment erection 3
Hydrotest Start

Piping  Installation,Testing & Reinstatement       5
S/Stn Energisation

6 kv  Package Sub‐Station Instatallation 3 D

Electrical /CP 4
Control System Power on

Instrumentation / Telecom / HSE works 5
Pre‐Commissioning 3
Mechanical Completion & Commissioning 3
Well Pad Stage II (M10)
Site Preparation (leveling ‐ grading only) and Access  A
2
Road
Security protection (fencing, trenching,) 6
Piling 1 A

Install Switchyard 1.5 Energising 132kV

Pre‐engineered Substation (132kV substation) 5 D

Civil Works and foundation 6

Equipment erection 3
Hydrotest Start

Piping  Installation,Testing & Reinstatement       5
S/Stn Energisation
6 kv  Package Sub‐Station Instatallation 3 D

El
Electrical /CP
i l /CP 4
Control System Power on
Instrumentation / Telecom / HSE works 5

Pre‐Commissioning 3
Mechanical Completion & Commissioning 3
Water Intake
Site Preparation (leveling ‐ grading only) and Access  A
2
Road
Security protection (fencing, trenching,) 6
Piling 0.5 A

Install Switchyard 1.5
Civil Works and foundation 5

Equipment erection 3
Hydrotest Start

Piping  Installation,Testing & Reinstatement       5
S/Stn Energisation
6 kv Package Sub‐Station Installation 3 D

Electrical /CP 4
Control System Power on
Instrumentation / Telecom / HSE works 5
Hydrotest Start
Water Pipeline (14 KM) 6

Pre‐Commissioning 3
Mechanical Completion & Commissioning 3

Stage ‐II Gathering System & Central Processing Facilities

Site preparation & improvement for Stage II 7 A

Piling 4
Pilling (cast in‐situ) 5
Tank Foundation 8
Start Skid fdn
Civil  Works 14
Structural Work 8
Manhole Work
UG Piping 9
Module Installation /Equipment Erection 5
Fired Heaters  Installation 4
Tank Erection 9
Tank hydrotest Hydrotest Start
Piping  Installation, Testing & Re‐instatement 10
S/Stn Energisation
6 kv  Package Sub‐Stations Installation 4 D D
First Last
Electrical / HSE works 9
ICSS Control System Power on
Instrumentation / Telecom /  10 D

Pipeline (Trunk Line) from Well Pads M7, M8 & M10 11
Interface / Tie‐ins works ( Piping , Elect , Inst. )  4
Pre‐Commissioning 4
Comm. Complete
Mechanical Completion & Commissioning 4 Start of Performance
Test
Assistance for Start‐up and Start Performance Test  3
Accommodation Camp

Site Preparation & Access Road 7

Piling (steel) 5
Security protection (fencing/trenching) 9

Civil Work (incl Helipad) 12
Building Works ( Pre‐Engg)/HVAC/Piping}
Building Works  ( Pre‐Engg)/HVAC/Piping} 10

Building Works  ( Containerized/ HVAC/Piping) 9

Equipment erection 5
Piping (incl underground) 9
Install Switchyard 1.5
33 S/Stn Energisation

33 kv GIS Package Sub‐Station Instatallation 4 D
6 S/Stn Energisation
6 kv  Package Sub‐Station Instatallation 3 D

Electrical 9

Instrument/Telecom (incl CCTV) 8
Pre‐Commissioning 4

Mechanical Completion & Commissioning 2.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
LEGEND: FEED PERIOD E     ‐ Inquiry D    ‐ Delivery to Site(Complete)

P     ‐ Order     ‐ Ex‐Work
EW D1 Part Delivery to Site
13 05.01.2011
14a 26.03.2011 Updated for Bid APW JOB NO.: PI‐10031 CONTRACT NO.: DOCUMENT NO. REV. SHEET
2 28.10.2010 Issue for Proposal JK 3 of 3  
JK
OVERALL PROJECT SCHEDULE ‐ LEVEL 1 
1 26.10.2010 Issue for Comments
0 13.10.2010 Preliminary Sch ‐For Comments JK PROJECT : EPC of Oil Gathering System, CPF & Water Supply Project FORMAT NO.
REV DATE STATUS PREPD. CHECKED APPROVED CLIENT : LUKOIL MID‐EAST LIMITED PEC‐PCD‐F‐003 REV‐0 

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
PI 10031 Level-1 Schedule-Rev-14a Sheet 3 of 3
PETROFAC PROJECT CONTROLS DEPARTMENT DECEMBER 2010
STANDARD LEVEL 3 LOGIC
Path of Construction
STANDARD CONSTRUCTION LOGIC AND FRAGENTS-2

U/G Services (Pipe, 
Install Equipment 
Site Preparation Piling Piperack Foundations MH's, CB's, Drainage  Backfill and Paving Piping Erection
(Static & Rotating)
Trenches)

Earthing Grid under 
Underground Cable  Paving Erect Steelwork ‐ 
Temporary Facilities Buildings Cable Supports
Routes Technical Structures

Erect Steelwork ‐ 
Piperacks
Electrical 
Equipment Pre‐
Equipment Pre‐ Equipment 
Equipment
Steel Fabrication Tank Foundations Pull Cables Terminations at Field 
dressing Foundations
Equipment

Equipment 
Heavy Lift Install Switchgear &  Electrical 
Fireproofing Structure and Pipe 
Pipe Fabrication Tank Erection Electrical Panels &  Terminations in 
Support Foundations
JB's Buildings

Steel Concrete 
Install Control &  Instrument 
Pipe Supports  Fireproofing Cable Supports in  Steel Platforms & 
Instruments Panels &  Terminations in 
Fabrication Buildings Ladders
JB's Buildings

Final Fireproofing Temporary Power Instruments Control 


Instrument Stands  Small Power & 
Roads & Drainage System Site  Motor Runs
Fabrication Lighting
Acceptance Test

Pre‐calibrate Field  Instrument Stands  Piping Hydrotesting  Fencing & Site 


Insulation Turnover
Instruments Installation and Reinstatement Finishes

Field Instruments  Field Cable Routes &  Field Instruments  Systems Mechanical  Systems Pre‐ Systems 


Loop Check
Installation Cabling Cables Terminations Completion commissioning Commissioning

This document is an uncontrolled copy when printed or saved. Viewed by:


APW 13/12/2010 Z:\Project Controls\Project Controls & Planning\Planning\Procedure\Dept Manual\For BMS Upload 11_08\SHJ‐PC‐PRO‐X‐05491 App 4a
Ahmad Warsi 13-Mar-2012
ENGINEERING LOGIC DIAGRAMS

Load inputs from Inputs for


Steel MTO 1st fabrication Final fab
piping / electrical / secondary steel
bid/award drwg review drwg
instrumentation structure

Topo Main piperack Equipment Secondary Fabrication


survey steel framing steel steel structure steel drwgs
Procurement
cycle

Basis off G
Geotechh Geotechh Nozzle
Start Platform & Clip info to
design survey report orientations/
ladder drwgs vendors
piping inputs

Design Site prep 1st civil Final civil


Specs layouts MTO/REQ/Bid MTO/REQ/Bid

Eqpt data &


loads from
vendors Secondary Finish
Foundation Primary FDN
FDN drwgs
design drwgs
IFC
Road &
paving
Plot Plan Piling layouts Architectural
details &drwgs

Buildings space
req. from Preliminary Final Building Architecture Procurement
Elect & inst electrical / building design Layouts MTO/REQ/Bid cycle
eqpt layouts telecom

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Civil Structural Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
ENGINEERING LOGIC DIAGRAMS

Process
datasheets Procurement Procurement
Mechanical
data sheets bid / receipt recovered /

Design basis / Inquiry Technical bid Purchase


Specifications
review Requisition evaluations requisitions
Receipt at
site per tag

Vendor data
Inspection Shipping /
Purchase order Vendor Design review & Manufacturing
& release delivery
approval

Expediting

Notes:
1) Logic to be used for each requisition.
2) Receipt at site milestone to identify each tag number.

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Equipment Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
ENGINEERING LOGIC DIAGRAMS

Instrument Platform &


installation details ladder drwgs

Installation
specifications Instrument Cable Cable /
locations routings drum

Finish
Process
instrument
Instrument index Instrument index Loop
data
set up development diagrams

Instrument
Design basis / Design In line instruments Bulk instrument Procurement
Start process hook up
review Specifications REQ/Bid/Award MTO cycle
drwgs

Control system Distributed Termination


P&IDs IFA Vendor data
block diagram control system diagrams

Panel/distribution
I/O count boards
P&IDs IFD Control room Final building
REQ/Bid/Award
equipment layouts layouts

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Instrumentation Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
ENGINEERING LOGIC DIAGRAMS

Complete
Eqpt modeling
equipment
(phase 1)
modeling

Key vendor Commence Complete


data isometric isometric
Design basis Design Plot plan, eqpt extraction extraction
Start
/ review Specifications layout IFA

P&IDs IFD
Material Finish
specifications

Piping modeling Piping Piping


(stage 1) modeling modeling

P&IDs IFA
Intermediate
Bulk MTO valves Stress Final MTO
MTO valves &
& piping sketches valves & piping
piping

Nozzle Final stress Pipe support


orientations analysis & pipe schedules

30% model 60% model 90% model


review review review

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 A/G Piping Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
ENGINEERING LOGIC DIAGRAMS

Procurement Procurement Procurement


cycle cycle cycle

U/G
U/G bulk MTO intermediate
MTO
U/G final MTO

Design basis Design U/G isometrics


Fire water layouts
/ review Specifications IFC

Conceptual Cooling water Road and


design layouts paving
layouts

Drainage Installation
Drainage layouts details
calculations

Preliminary
Manhole
building Sewerage layouts
schedule
design

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 U/G Piping Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
ENGINEERING LOGIC DIAGRAMS

To To
To dcs
mechanical instrument
vendor
revisions

Heat & Process


Design basis Process EQPT data
material instrument
/ review sheets Instrument
balances data
logic diagrams

Material
Process
Start l i
selection Equipment list
l IFA Equipment list Equipment list
simulations Finish
diagrams IFD IFC

To
Process flow Cause & effect
Line list IFA Line list IFD intermediate
diagrams diagrams
piping MTO
To Final
piping MTO

Operations &
Hydraulic Preliminary
P&IDs IFA P&IDs IFD P&IDs IFC maintenance
calculations HAZOP
manual

Line list IFC

To 3D model To piping bulk To instrument


Final HAZOP Key vendor
development MTO design
data

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Process Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
LIST OF STANDARD ACTIVITES

Load inputs from Inputs


Inputs for
for 1st
Steel
Steel MTO
MTO 1st fabrication
1st fabrication
fabrication Final
Finalfab
Final fab
fab
piping / electrical / secondary
secondary steel
steel drwg
bid/award
bid/award drwg review
drwg review
review drwg
drwg
drwg
instrumentation structure
structure

Topo Main
Main piperack
piperack Equipment
Equipment Secondary
Secondary
Secondary Fabrication
Fabrication
Fabrication
survey steel
steel framing
framing steel
steel steel
steel structure
steel structure
structure steel
steeldrwgs
steel drwgs
drwgs
Procurement
Procurement
Procurement
cycle
cycle
cycle

Basis of Geotech Geotech


Geotech Nozzle
Nozzle
Start Platform
Platform && Clip
Clipinfo
Clip infoto
info to
to
design survey report
report orientations/
orientations/
ladder
ladder drwgs
drwgs vendors
vendors
vendors
piping
piping inputs
inputs

Design Site
Site prep
prep 1st
1st civil
civil Final
Finalcivil
Final civil
civil
Specs layouts
layouts MTO/REQ/Bid
MTO/REQ/Bid MTO/REQ/Bid
MTO/REQ/Bid
MTO/REQ/Bid

Eqpt
Eqpt data
data &
&
loads
loads from
from
vendors
vendors Secondary
Secondary
Secondary Finish
Finish
Finish
Foundation
Foundation Primary
Primary FDN
FDN
FDN
FDN drwgs
FDN drwgs
drwgs
design
design drwgs
drwgs
IFC
IFC
IFC
Road
Road &
&
paving
paving
Plot Plan Piling layouts Architectural
Architectural
details
details &drwgs
&drwgs

Buildings space
req. from Preliminary Final
Final Building
Building Architecture
Architecture Procurement
Procurement
Elect & inst
electrical / building design Layouts
Layouts MTO/REQ/Bid
MTO/REQ/Bid cycle
cycle
eqpt layouts telecom

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Civil Structural Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
LIST OF STANDARD ACTIVITES

Process
datasheets Procurement Procurement
Procurement
Mechanical
data sheets bid / receipt recovered
recovered //

Design basis / Inquiry Technical bid Purchase


Purchase
Specifications
review Requisition evaluations requisitions
requisitions
Receipt
Receipt at
at
site per tag
site per tag

Vendor data
Inspection
Inspection Shipping
Shipping //
Purchase order Vendor Design review & Manufacturing
Manufacturing
&
& release
release delivery
delivery
approval

Expediting

Notes:
1) Logic to be used for each requisition.
2) Receipt at site milestone to identify each tag number.

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Equipment Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
LIST OF STANDARD ACTIVITES

Instrument
Instrument Platform
Platform &
&
installation
installation details
details ladder
ladder drwgs
drwgs

Installation
Installation
specifications
specifications Instrument
Instrument Cable
Cable Cable
Cable ///
Cable
locations
locations routings
routings drum
drum
drum

Finish
Finish
Finish
Process
instrument
Instrument
Instrument index
index Instrument
Instrument index
index Loop
Loop
Loop
data
set
set up
up development
development diagrams
diagrams
diagrams

In line Instrument Bulk Procurement


Design basis / Design Instrument Bulk instrument
instrument Procurement
Start instruments process
review Specifications process hook
hook up
up MTO
MTO cycle
cycle
REQ/Bid/Award

Control system Distributed Termination


Termination
P&IDs IFA Vendor
Vendor data
data
block diagram control system diagrams
diagrams

Panel/distribution
I/O count boards
P&IDs IFD Control room Final building
REQ/Bid/Award
equipment layouts layouts

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Instrumentation Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
LIST OF STANDARD ACTIVITES

Complete
Complete
Eqpt modeling
modeling
equipment
equipment
(phase 1)
1)
modeling
modeling

Key
Key vendor
vendor Commence
Commence Complete
Complete
data
data isometric
isometric isometric
isometric
Design basis Design Plot plan, eqpt extraction
extraction extraction
extraction
Start
/ review Specifications layout IFA

P&IDs
P&IDs IFD
IFD
Material Finish
Finish
specifications

Piping modeling
modeling Piping
Piping Piping
Piping
(stage
(stage 1)
1) modeling
modeling modeling
modeling

P&IDs IFA
Intermediate
Intermediate
Bulk MTO
MTO valves
valves Stress
Stress Final
Final MTO
MTO
MTO
MTO valves
valves &
&
& piping
piping sketches
sketches valves
valves && piping
piping
piping
piping

Nozzle Final stress Pipe support


orientations analysis & pipe schedules

30% model 60% model 90% model


review review review

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 A/G Piping Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
LIST OF STANDARD ACTIVITES

Procurement
Procurement Procurement
Procurement Procurement
Procurement
cycle
cycle cycle
cycle cycle
cycle

U/G
U/G
U/G bulk MTO intermediate
intermediate
MTO
MTO
U/G
U/G final
final MTO
MTO

Design basis Design U/G isometrics


isometrics
Fire water layouts
/ review Specifications IFC

Conceptual Cooling water Road and


design layouts paving
layouts

Drainage Installation
Drainage layouts details
calculations

Preliminary
Manhole
building Sewerage layouts
schedule
design

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 U/G Piping Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
LIST OF STANDARD ACTIVITES

To
To To
To To
To dcs
dcs
mechanical
mechanical instrument
instrument vendor
vendor
revisions
revisions

Heat & Process


Process
Design basis Process
Process EQPT
EQPT data
data
material instrument
instrument
/ review sheets
sheets Instrument
Instrument
balances data
data
logic
logic diagrams
diagrams

Material
Process
Start selection Equipment
Equipment list
list IFA
IFA Equipment
Equipment list
list Equipment
Equipment list
Equipment list
list
simulations Finish
Finish
diagrams IFD
IFD IFC
IFC

To
To
To
Process flow Cause
Cause &
& effect
effect
Line list IFA Line
Line list
list IFD
IFD intermediate
intermediate
intermediate
diagrams diagrams
diagrams To
piping
piping MTO
piping MTO
MTO To Final
To Final
Final
piping
piping
piping
MTO
MTO
MTO

Operations
Operations &
Operations &
&
Hydraulic Preliminary
Preliminary
P&IDs IFA
IFA P&IDs
P&IDs IFD
IFD P&IDs
P&IDs IFC
IFC maintenance
maintenance
calculations HAZOP
HAZOP
manual
manual

Line
Line list
list IFC
IFC

To 3D model To piping bulk To instrument


Final HAZOP Key
Key vendor
vendor
development MTO design
data
data

Notes:

JOB NO.: JI-XX CONTRACT NO.: XX DOCUMENT NO. REV. SHEET

Level 2 Process Logic 0 1 OF 1

PROJECT: FORMAT NO.


REV DATE STATUS PREPD. CHECKED APPROVED CLIENT: PEC-PCD-F-002 REV-0

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE
Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

EPC CPF (Phase-I) at Badra Oil Field, Iraq - E&P 90583 01-Dec-11
DAYS 05-Jul-13
LA SCHEDULE
KEY MILESTONES 583 01-Dec-11 05-Jul-13

XXX10000 Commencement Date 0 01-Dec-11


XXX10010 Site Handover (By Company) 0 01-Dec-11
XXX10100 Commence Home Office Mobilisation - Key personnel 0 01-Dec-11
XXX10110 Complete Home Office Mobilisation - Key personal 0 31-Dec-11
XXX10120 Kick-off meeting with Company 0 15-Dec-11
XXX10130 Award Sub-contract - Camp construction 0 15-Dec-11
XXX10140 Award Sub-contract - Piling 0 30-Jan-12
XXX10150 Award Sub-contract - Civil works 0 30-Jan-12
XXX10160 Award Sub-contract - MEI works 0 29-Feb-12
XXX10170 Award Sub-contract - Pipeline 0 30-Jan-12
XXX10180 Award Sub-contract - Frieght Forwarder 0 30-Mar-12
XXX10190 Commence Camp construction Works 0 01-Jan-12
XXX10200 Orders for All Long Lead Items placed 0 31-Jan-12
XXX10210 Commencement of Ex-works delivery 0 01-May-12
XXX10220 Complete Ex-works delivery 0 30-Nov-12
XXX10230 Commence issue of Isometrics 0 24-Apr-12
XXX10240 Complete HAZID review 0 15-Feb-12
XXX10250 Complete HAZOP review 0 15-Feb-12
XXX10260 Complete SIL review 0 16-Mar-12
XXX10265 Complete Hazid/Hazop/SIL studies 0 30-Jun-12
XXX10270 Commence Equipment / Skid / Piperack Foundations Works
0 16-Mar-12
XXX10275 Complete Equipment / Skid / Piperack Foundation works 0 31-Oct-12
XXX10290 Commence Pipe Rack / Sleeper installation 0 01-Aug-12
XXX10295 Commence Building works 0 21-Mar-12
XXX10300 Complete Building works 0 15-Nov-12
XXX10305 Commence Skids/ Equipment installation 0 01-Aug-12
XXX10310 Complete Tank Installation 0 28-Feb-13
XXX10315 Complete Equipment Installation 0 05-Mar-13
XXX10325 Readiness of Tie-ins for Inlet line (By Company) 0 28-Feb-13
XXX10335 Readiness of Tie-ins for Export line (By Company) 0 28-Feb-13
XXX10400 Mechanical Completion - Train A 0 30-Mar-13
XXX10410 RFSU - Train A 0 15-May-13
XXX10420 Provisional Acceptance - Train A 0 05-Jun-13
XXX10430 Final Acceptance - Train A 0 05-Jul-13

GENERAL 230 01-Dec-11 17-Jul-12

PROJECT DELIVERABLES 230 01-Dec-11 17-Jul-12


EPD10000 Quality Manual, Organization Chart, Variation Procedure,
15 etc
01-Dec-11 15-Dec-11
EPD10010 Contract HSE Plan, Procedures & Work Instructions and45
Audit
01-Dec-11
Schdule 14-Jan-12
EPD10020 Project Specific Quality Plan, Procedures & Work Instructions,
45 01-Dec-11
Inspection 14-Jan-12
& Test Plans, Audit Schedule
EPD10030 Procurement & Contracting Policies & Procedures 45 01-Dec-11 14-Jan-12
EPD10040 Process & Procedures for the selection of Subcontractors45 01-Dec-11 14-Jan-12
EPD10050 Procedures for Packaging, Preservation, Segregation & Storage
45 01-Dec-11
at both works
14-Jan-12
& site
EPD10060 Procedures for Material, Spare Parts Traceability at both45
Works
01-Dec-11
& Site 14-Jan-12
EPD10070 Procedure for Logistic activities to and from both works 45
& site
01-Dec-11 14-Jan-12
EPD10080 Design Control & Change Management Procedures 45 01-Dec-11 14-Jan-12
EPD10090 Project Execution Plan (including Project control procedures
45 01-Dec-11
& Schedule) 14-Jan-12

Date Revision Checked Approved


KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 1 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE
Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
EPD10100 Project Execution Strategy 15 01-Dec-11 15-Dec-11
EPD10110 Pre-commissioning & Commissioning Procedures 120 20-Mar-12 17-Jul-12
EPD10120 Other Project deliverables 230 01-Dec-11 17-Jul-12

ENGINEERING 262 01-Dec-11 18-Aug-12

TRAIN A/B/C/UTILITIES/COMMON FACILITIES 262 01-Dec-11 18-Aug-12


EFED10000 Feed Verification & Closeout (Approval by Company) 31 01-Dec-11 31-Dec-11
PROCESS 183 16-Dec-11 15-Jun-12
EPR10000 Process & Instrumentation diagrams 183 16-Dec-11 15-Jun-12
EPR10010 P&IDs (IFH) 0 15-Mar-12
EPR10020 P&IDs (IFD) 0 30-Apr-12
EPR10030 P&IDs (IFC) 0 15-Jun-12
HSSE 213 01-Dec-11 30-Jun-12
EHS10000 Hazid / Hazop / SIL review 106 01-Dec-11 15-Mar-12
EHS10020 Hazid / Hazop / SIL studies & Closeout 107 16-Mar-12 30-Jun-12
METALLURGY & CORROSION 107 16-Dec-11 31-Mar-12
EMT10000 Specifications / Material Selection Diagrams etc 107 16-Dec-11 31-Mar-12
CIVIL / STRUCTURAL 262 01-Dec-11 18-Aug-12
ECS10000 Piling layouts, specifications & detail drawings 60 01-Dec-11 29-Jan-12
ECS10010 Equipment skids/ Pipe rack modules Foundation details180 15-Jan-12 12-Jul-12
ECS10020 Building Conceptual & Detail drawings 130 25-Jan-12 02-Jun-12
ECS10030 Structural - 1st MTO 15 16-Dec-11 30-Dec-11
ECS10040 Pipe racks modules, Other structural members GA drawings
120 10-Mar-12
& details 07-Jul-12
ECS10050 MR/TBE/PR - Pipe Rack Modules/ Structural Steel bulk3 2 31-Dec-11 31-Jan-12
ECS10060 Pipe Rack Modules/ Structural Vendor drawings review
170 02-Mar-12 18-Aug-12
MECHANICAL 211 01-Dec-11 28-Jun-12
EMC10000 Key Vendor Inputs (Load details, Utility consumption etc.)
46 01-Dec-11 15-Jan-12
EMC10010 MR/TBE/PR -Sweetening and Stabilization Column 46 16-Dec-11 30-Jan-12
EMC10020 Sweetening and Stabilization Column 100 20-Feb-12 29-May-12
EMC10030 MR/TBE/PR -Vessels 46 16-Dec-11 30-Jan-12
EMC10040 Vessels- Review vendor drgs 100 20-Feb-12 29-May-12
EMC10045 MR/TBE/PR -Filters 46 15-Jan-12 29-Feb-12
EMC10050 Filters- Review vendor drgs 70 21-Mar-12 29-May-12
EMC10055 MR/TBE/PR -Heat Exchangers 46 16-Dec-11 30-Jan-12
EMC10060 Heat Exchangers- Review vendor drgs 120 20-Feb-12 18-Jun-12
EMC10070 MR/TBE/PR -Tanks 46 15-Jan-12 29-Feb-12
EMC10080 Tanks- Review vendor drgs 100 21-Mar-12 28-Jun-12
EMC10090 MR/TBE/PR -Pig Launchers & Receivers 46 16-Dec-11 30-Jan-12
EMC10100 Pig Launchers & Receivers- Review vendor drgs 100 20-Feb-12 29-May-12
EMC10110 MR/TBE/PR -Flare Package 46 16-Dec-11 30-Jan-12
EMC10120 Flare Package- Review vendor drgs 110 20-Feb-12 08-Jun-12
EMC10130 MR/TBE/PR -Fuel Gas Membrane Package 46 16-Dec-11 30-Jan-12
EMC10140 Fuel Gas Membrane Package- Review vendor drgs 120 20-Feb-12 18-Jun-12
EMC10150 MR/TBE/PR -Air Coolers 46 16-Dec-11 30-Jan-12
EMC10160 Air Coolers- Review vendor drgs 100 20-Feb-12 29-May-12
EMC10170 MR/TBE/PR -Incinerators 46 16-Dec-11 30-Jan-12
EMC10180 Incinerators- Review vendor drgs 100 20-Feb-12 29-May-12
EMC10190 MR/TBE/PR -Pumps 46 16-Dec-11 30-Jan-12
EMC10200 Pumps- Review vendor drgs 100 20-Feb-12 29-May-12
EMC10210 MR/TBE/PR -Fire Water Pumps 46 15-Jan-12 29-Feb-12
EMC10220 Fire Water Pumps- Review vendor drgs 100 21-Mar-12 28-Jun-12
Date Revision Checked Approved
KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 2 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE
Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
EMC10230 MR/TBE/PR -Air Compressor Package 46 16-Dec-11 30-Jan-12
EMC10240 Air Compressor Package- Review vendor drgs 100 20-Feb-12 29-May-12
EMC10250 MR/TBE/PR -CI Skids 46 16-Dec-11 30-Jan-12
EMC10260 CI Skids- Review vendor drgs 110 20-Feb-12 08-Jun-12
EMC10265 MR/TBE/PR -GEG 46 16-Dec-11 30-Jan-12
EMC10268 GEG- Review vendor drgs 120 20-Feb-12 18-Jun-12
EMC10270 MR/TBE/PR -Nitrogen Package 46 16-Dec-11 30-Jan-12
EMC10280 Nitrogen Package- Review vendor drgs 65 20-Feb-12 24-Apr-12
EMC10290 MR/TBE/PR -Steam Generation Package 46 16-Dec-11 30-Jan-12
EMC10300 Steam Generation Package- Review vendor drgs 100 20-Feb-12 29-May-12
EMC10310 MR/TBE/PR -Water Treatment Package 46 15-Jan-12 29-Feb-12
EMC10320 Water Treatment Package- Review vendor drgs 100 21-Mar-12 28-Jun-12
PIPING / PIPELINE 230 01-Dec-11 17-Jul-12
EPI10000 Plant Modelling 200 01-Dec-11 17-Jun-12
EPI10010 Stress Analysis & Report 145 25-Jan-12 17-Jun-12
EPI10015 Model review (30%) 15 01-Feb-12 15-Feb-12
EPI10016 Model review (60%) 15 01-Apr-12 15-Apr-12
EPI10017 Model review (90%) 15 31-May-12 14-Jun-12
EPI10020 Model review (30%) 15 30-Jan-12 13-Feb-12
EPI10030 Model review (60%) 15 04-May-12 18-May-12
EPI10040 Model review (90%) 15 03-Jul-12 17-Jul-12
EPI10050 Finalise Equipment Layout 50 28-Dec-11 15-Feb-12
EPI10060 Nozzle orientation 60 21-Apr-12 19-Jun-12
EPI10070 Piping Isometrics - Extraction, Checking, Issue 70 16-Apr-12 24-Jun-12
EPI10080 Piping Plans (GADs) 70 16-Apr-12 24-Jun-12
EPI10090 Tie-in detail drawings 45 11-May-12 24-Jun-12
EPI10100 Pipe support schedule / details 70 16-Apr-12 24-Jun-12
EPI10110 Piping Final MTO / Top up 15 05-Jun-12 19-Jun-12
EPI10120 MR/TBE/PR - Piping material 60 16-Dec-11 13-Feb-12
EPI10130 MR/TBE/PR - Pipe Fittings, Flanges, Other bulk items 60 16-Dec-11 13-Feb-12
EPI10140 Pipeline Survey 70 01-Dec-11 08-Feb-12
EPI10150 Pipeline Engineering Design Basis 45 11-Dec-11 24-Jan-12
EPI10160 Pipeline route map/ GA drawings / details 70 21-Dec-11 28-Feb-12
EPI10170 Pipeline - MTO 15 31-Dec-11 14-Jan-12
EPI10175 Pipeline - MTO Top up 15 14-Feb-12 28-Feb-12
EPI10180 MR/TBE/PR - Pipeline items 70 31-Dec-11 09-Mar-12
EPI10190 Pipeline items - Review vendor drgs 25 20-Mar-12 13-Apr-12
ELECTRICAL 217 16-Dec-11 19-Jul-12
EEL10000 Load List - Final 40 16-Feb-12 26-Mar-12
EEL10010 Protection coordination / Relay settings 50 26-Feb-12 15-Apr-12
EEL10020 Single Line Diagrams - Final 80 12-Mar-12 30-May-12
EEL10030 Cable trench & cable trays Layouts 60 01-Apr-12 30-May-12
EEL10040 Cable schedules 120 22-Mar-12 19-Jul-12
EEL10050 Electrical Bulk MTO 15 16-Apr-12 30-Apr-12
EEL10060 Electrical MTO Top-Up 15 05-Jun-12 19-Jun-12
EEL10070 MR/TBE/PR - Diesel Generator Package 45 16-Dec-11 29-Jan-12
EEL10080 Diesel Generator Package - Review vendor drgs 120 10-Mar-12 07-Jul-12
EEL10090 MR/TBE/PR - Cables/ DBs/ JBs/ Cable Trays/ Elect bulk62materials
30-Jan-12 31-Mar-12
EEL10100 Cables/ DBs/ JBs/ Cable Trays/ Elect bulk materials - Review
60 11-May-12
vendor drgs 09-Jul-12
INSTRUMENT 220 16-Dec-11 22-Jul-12
Date Revision Checked Approved
KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 3 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE

Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
EIN10000 I/O lists 100 19-Feb-12 28-May-12
EIN10010 Cause & Effect diagrams 90 20-Jan-12 18-Apr-12
EIN10020 Instrument Index 80 09-Feb-12 28-Apr-12
EIN10030 Instrumentation Cable tray routing & Layout drawings 80 09-Feb-12 28-Apr-12
EIN10040 Instrumentation Bulk MTO 15 14-Apr-12 28-Apr-12
EIN10050 Piping & Electrical interface diagrams 80 09-Feb-12 28-Apr-12
EIN10060 Cable, Drum, JB & Label schedules 100 24-Feb-12 02-Jun-12
EIN10070 Instrument location plans / drawings 100 24-Feb-12 02-Jun-12
EIN10080 Instrument installation & Hook-up drawings 60 29-Apr-12 27-Jun-12
EIN10090 Instrument Loop drawings 60 24-May-12 22-Jul-12
EIN10100 Instrumentation Termination diagrams 85 29-Apr-12 22-Jul-12
EIN10110 MR/TBE/PR - Instrumentation Valves 45 15-Jan-12 28-Feb-12
EIN10120 Instrumentation Valves - Review vendor drgs 120 20-Mar-12 17-Jul-12
EIN10130 MR/TBE/PR - Field Instruments 45 04-Feb-12 19-Mar-12
EIN10140 Field Instruments - Review vendor drgs 90 09-Apr-12 07-Jul-12
EIN10150 MR/TBE/PR - Control Systems 45 16-Dec-11 29-Jan-12
EIN10160 Control Systems - Review vendor drgs 135 19-Feb-12 02-Jul-12
EIN10170 MR/TBE/PR - Instrument Cables/Cable Tray/JBs/Tubings/Bulk
70 31-Dec-11
items 09-Mar-12
EIN10180 Instrument Cables/Cable Tray/JBs/Tubings/Bulk items 110
- Review
30-Mar-12
vendor drgs
17-Jul-12
TELECOM 200 31-Dec-11 17-Jul-12
ETE10000 Design basis 15 31-Dec-11 14-Jan-12
ETE10010 Block diagrams/ Specifications 75 15-Jan-12 29-Mar-12
ETE10020 Telecom eqpt. Layouts - Plant area & Buildings 80 04-Feb-12 23-Apr-12
ETE10030 Cable layouts 80 24-Feb-12 13-May-12
ETE10040 Material take off -Telecom 55 04-Apr-12 28-May-12
ETE10050 Interconnection diagrams 80 25-Mar-12 12-Jun-12
ETE10060 Cable schedule 80 25-Mar-12 12-Jun-12
ETE10070 Installation details 70 24-Apr-12 02-Jul-12
ETE10080 Termination diagrams 70 09-May-12 17-Jul-12
ETE10090 MR/TBE/PR - Telecom system 30 01-Apr-12 30-Apr-12
ETE10100 Telecom system- Review vendor drgs 45 31-May-12 14-Jul-12

TRAIN-A / UTILITIES / COMMON FACILITIES 583 01-Dec-11 05-Jul-13

PROCUREMENT 381 31-Dec-11 14-Jan-13


Ordering 184 31-Dec-11 01-Jul-12
Structural 30 02-Jan-12 31-Jan-12
PSTOR10000 Ordering -Structural Steel 30 02-Jan-12 31-Jan-12
Piping 107 31-Dec-11 15-Apr-12
PPIOR10000 Ordering -Pipes 107 31-Dec-11 15-Apr-12
PPIOR10010 Ordering -Pipe Fittings, Flanges, Other bulk items 107 31-Dec-11 15-Apr-12
Mechanical 184 31-Dec-11 01-Jul-12
PMCOR10000 Ordering -Sweetening and Stabilization Column 31 31-Dec-11 30-Jan-12
PMCOR10010 Ordering -Vessels 31 31-Dec-11 30-Jan-12
PMCOR10020 Ordering -Filters 30 31-Jan-12 29-Feb-12
PMCOR10030 Ordering -Tanks 30 31-Jan-12 29-Feb-12
PMCOR10040 Ordering -Heat Exchangers 31 31-Dec-11 30-Jan-12
PMCOR10050 Ordering -Pig Launchers & Receivers 31 31-Dec-11 30-Jan-12
PMCOR10060 Ordering -Flare Package 31 31-Dec-11 30-Jan-12
PMCOR10070 Ordering -Fuel Gas Membrane Package 31 31-Dec-11 30-Jan-12
PMCOR10080 Ordering -Air Coolers 31 31-Dec-11 30-Jan-12
PMCOR10090 Ordering -Incinerators 31 31-Dec-11 30-Jan-12
Date Revision Checked Approved
KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 4 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE
Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PMCOR10100 Ordering -Pumps (Oil Export) 31 31-Dec-11 30-Jan-12
PMCOR10110 Ordering -Pumps (Others) 31 31-Dec-11 30-Jan-12
PMCOR10120 Ordering -Fire Water Pumps 30 31-Jan-12 29-Feb-12
PMCOR10130 Ordering -Air Compressor Package 31 31-Dec-11 30-Jan-12
PMCOR10140 Ordering -CI Skids 31 31-Dec-11 30-Jan-12
PMCOR10145 Ordering -GEG 31 31-Dec-11 30-Jan-12
PMCOR10150 Ordering -Nitrogen Package 31 31-Dec-11 30-Jan-12
PMCOR10160 Ordering -Steam Generation Package 31 31-Dec-11 30-Jan-12
PMCOR10170 Ordering -Water Treatment Package 30 31-Jan-12 29-Feb-12
PMCOR10180 Ordering -Cranes & Hoist 31 01-Jun-12 01-Jul-12
Electrical 122 31-Dec-11 30-Apr-12
PELOR10000 Ordering -Switchgear, UPS System, Transformers 30 31-Dec-11 29-Jan-12
PELOR10010 Ordering -Diesel Generator Package 30 31-Dec-11 29-Jan-12
PELOR10020 Ordering -Neutral Earthing Resistors 30 30-Mar-12 28-Apr-12
PELOR10030 Ordering -Normal/Emergency Lighting and small power 30
systems
30-Jan-12
/ DBs 28-Feb-12
PELOR10040 Ordering -MV/LV Power & Control Cables 31 01-Mar-12 31-Mar-12
PELOR10050 Ordering -Earthing & Lightning protection system 31 30-Jan-12 29-Feb-12
PELOR10060 Ordering -Lighting fixtures, Lighting Poles 31 31-Mar-12 30-Apr-12
PELOR10070 Ordering -Electrical Bulk items 31 30-Jan-12 29-Feb-12
PELOR10080 Ordering -Cathodic Protection System 31 16-Mar-12 15-Apr-12
Instrument 110 31-Dec-11 18-Apr-12
PINOR10000 Ordering -Instrumentation Valves 30 30-Jan-12 28-Feb-12
PINOR10010 Ordering -Field Instruments 30 19-Feb-12 19-Mar-12
PINOR10020 Ordering -Analysers 30 20-Mar-12 18-Apr-12
PINOR10030 Ordering -Control Systems( Workstation, Marshalling cabinet
30 31-Dec-11
etc.) 29-Jan-12
PINOR10040 Ordering -Instrument Cables/Cable Tray/JBs/Tubings/Bulk
30 items
09-Feb-12 09-Mar-12
HSE 30 01-May-12 30-May-12
PHSOR10000 Ordering -Fire Fighting Equipment 30 01-May-12 30-May-12
PHSOR10010 Ordering -Safety Equipment 30 01-May-12 30-May-12
PHSOR10020 Ordering -Gaseous Fire Extinguishing System 30 01-May-12 30-May-12
Telecom 30 01-Apr-12 30-Apr-12
PTEOR10000 Ordering -Transmission System / Radio System / Telephone
30 System
01-Apr-12 30-Apr-12
PTEOR10010 Ordering -PA/GA System 30 01-Apr-12 30-Apr-12
PTEOR10020 Ordering -CCTV / Accesss Control / Security System 30 01-Apr-12 30-Apr-12
PTEOR10030 Ordering -Telecom Cable 30 01-Apr-12 30-Apr-12
Manufacturing, Pre-commissioning, Testing & Ex-Works Delivery321 30-Jan-12 15-Dec-12
Structural 181 01-Feb-12 30-Jul-12
PSTMD10010 Manuf. & Delivery Ex-work -Structural Steel 181 01-Feb-12 30-Jul-12
Piping 243 01-Feb-12 30-Sep-12
PPIMD10020 Manuf. & Delivery Ex-work -Pipes 243 01-Feb-12 30-Sep-12
PPIMD10030 Manuf. & Delivery Ex-work -Pipe Fittings, Flanges, Other
243 bulk
01-Feb-12
items 30-Sep-12
Mechanical 320 31-Jan-12 15-Dec-12
PMCMD10190Manuf. & Delivery Ex-work -Sweetening and Stabilization
275 Column
31-Jan-12 31-Oct-12
PMCMD10200Manuf. & Delivery Ex-work -Vessels 244 31-Jan-12 30-Sep-12
PMCMD10210Manuf. & Delivery Ex-work -Filters 184 01-Mar-12 31-Aug-12
PMCMD10220Manuf. & Delivery Ex-work -Tanks 184 01-Mar-12 31-Aug-12
PMCMD10230Manuf. & Delivery Ex-work -Heat Exchangers 275 31-Jan-12 31-Oct-12
PMCMD10240Manuf. & Delivery Ex-work -Pig Launchers & Receivers
244 31-Jan-12 30-Sep-12
PMCMD10250Manuf. & Delivery Ex-work -Flare Package 275 31-Jan-12 31-Oct-12
PMCMD10260Manuf. & Delivery Ex-work -Fuel Gas Membrane Package
305 31-Jan-12 30-Nov-12

Date Revision Checked Approved


KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 5 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE
Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PMCMD10270Manuf. & Delivery Ex-work -Air Coolers 275 31-Jan-12 31-Oct-12
PMCMD10280Manuf. & Delivery Ex-work -Incinerators 244 31-Jan-12 30-Sep-12
PMCMD10290Manuf. & Delivery Ex-work -Pumps (Oil Export) 305 31-Jan-12 30-Nov-12
PMCMD10300Manuf. & Delivery Ex-work -Pumps (Others) 305 31-Jan-12 30-Nov-12
PMCMD10310Manuf. & Delivery Ex-work -Fire Water Pumps 214 01-Mar-12 30-Sep-12
PMCMD10320Manuf. & Delivery Ex-work -Air Compressor Package244 31-Jan-12 30-Sep-12
PMCMD10330Manuf. & Delivery Ex-work -CI Skids 244 31-Jan-12 30-Sep-12
PMCMD10335Manuf. & Delivery Ex-work -GEG 320 31-Jan-12 15-Dec-12
PMCMD10340Manuf. & Delivery Ex-work -Nitrogen Package 244 31-Jan-12 30-Sep-12
PMCMD10350Manuf. & Delivery Ex-work -Steam Generation Package
305 31-Jan-12 30-Nov-12
PMCMD10360Manuf. & Delivery Ex-work -Water Treatment Package1 84 01-Mar-12 31-Aug-12
PMCMD10370Manuf. & Delivery Ex-work -Cranes & Hoist 123 02-Jul-12 01-Nov-12
Electrical 306 30-Jan-12 30-Nov-12
PELMD10090 Manuf. & Delivery Ex-work -Switchgear, UPS System,306
Transformers
30-Jan-12 30-Nov-12
PELMD10100 Manuf. & Delivery Ex-work -Diesel Generator Package
306 30-Jan-12 30-Nov-12
PELMD10110 Manuf. & Delivery Ex-work -Neutral Earthing Resistors
155 29-Apr-12 30-Sep-12
PELMD10120 Manuf. & Delivery Ex-work -Normal/Emergency Lighting
246 and
29-Feb-12
small power31-Oct-12
systems / DBs
PELMD10130 Manuf. & Delivery Ex-work -MV/LV Power & Control183
Cables
01-Apr-12 30-Sep-12
PELMD10140 Manuf. & Delivery Ex-work -Earthing & Lightning protection
214 01-Mar-12
system 30-Sep-12
PELMD10150 Manuf. & Delivery Ex-work -Lighting fixtures, Lighting
123
Poles
01-May-12 31-Aug-12
PELMD10160 Manuf. & Delivery Ex-work -Electrical Bulk items 245 01-Mar-12 31-Oct-12
PELMD10170 Manuf. & Delivery Ex-work -Cathodic Protection System
153 16-Apr-12 15-Sep-12
Instrument 276 30-Jan-12 31-Oct-12
PINMD10050 Manuf. & Delivery Ex-work -Instrumentation Valves 246 29-Feb-12 31-Oct-12
PINMD10060 Manuf. & Delivery Ex-work -Field Instruments 215 20-Mar-12 20-Oct-12
PINMD10070 Manuf. & Delivery Ex-work -Analysers 184 19-Apr-12 19-Oct-12
PINMD10080 Manuf. & Delivery Ex-work -Control Systems( Workstation,
276 30-Jan-12
Marshalling cabinet
31-Oct-12
etc.)
PINMD10090 Manuf. & Delivery Ex-work -Instrument Cables/Cable 215
Tray/JBs/Tubings/Bulk
10-Mar-12 10-Oct-12
items
HSE 123 31-May-12 30-Sep-12
PHSMD10030 Manuf. & Delivery Ex-work -Fire Fighting Equipment 123 31-May-12 30-Sep-12
PHSMD10040 Manuf. & Delivery Ex-work -Safety Equipment 123 31-May-12 30-Sep-12
PHSMD10050 Manuf. & Delivery Ex-work -Gaseous Fire Extinguishing
123System
31-May-12 30-Sep-12
Telecom 245 01-Feb-12 02-Oct-12
PTEMD10040 Manuf. & Delivery Ex-work -Transmission System / Radio
155 System
01-May-12
/ Telephone
02-Oct-12
System
PTEMD10050 Manuf. & Delivery Ex-work -PA/GA System 245 01-Feb-12 02-Oct-12
PTEMD10060 Manuf. & Delivery Ex-work -CCTV / Accesss Control 245
/ Security
01-Feb-12
System 02-Oct-12
PTEMD10070 Manuf. & Delivery Ex-work -Telecom Cable 245 01-Feb-12 02-Oct-12
Shipment & Site delivery 260 30-Apr-12 14-Jan-13
Structural 184 30-Apr-12 30-Oct-12
PSTSD10020 Shipping & Delivery to Site -Structural Steel 184 30-Apr-12 30-Oct-12
Piping 140 13-Jun-12 30-Oct-12
PPISD10040 Shipping & Delivery to Site -Pipes 140 13-Jun-12 30-Oct-12
PPISD10050 Shipping & Delivery to Site -Pipe Fittings, Flanges, Other
130bulk
23-Jun-12
items 30-Oct-12
Mechanical 226 03-Jun-12 14-Jan-13
PMCSD10380 Shipping & Delivery to Site -Sweetening and Stabilization
60Column
02-Oct-12 30-Nov-12
PMCSD10390 Shipping & Delivery to Site -Vessels 60 01-Sep-12 30-Oct-12
PMCSD10400 Shipping & Delivery to Site -Filters 60 02-Aug-12 30-Sep-12
PMCSD10410 Shipping & Delivery to Site -Tanks 120 03-Jun-12 30-Sep-12
PMCSD10420 Shipping & Delivery to Site -Heat Exchangers 60 02-Oct-12 30-Nov-12
PMCSD10430 Shipping & Delivery to Site -Pig Launchers & Receivers60 01-Sep-12 30-Oct-12

Date Revision Checked Approved


KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 6 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE
Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PMCSD10440 Shipping & Delivery to Site -Flare Package 60 02-Oct-12 30-Nov-12
PMCSD10450 Shipping & Delivery to Site -Fuel Gas Membrane Package
120 02-Sep-12 30-Dec-12
PMCSD10460 Shipping & Delivery to Site -Air Coolers 60 02-Oct-12 30-Nov-12
PMCSD10470 Shipping & Delivery to Site -Incinerators 60 01-Sep-12 30-Oct-12
PMCSD10480 Shipping & Delivery to Site -Pumps (Oil Export) 70 22-Oct-12 30-Dec-12
PMCSD10490 Shipping & Delivery to Site -Pumps (Others) 180 04-Jul-12 30-Dec-12
PMCSD10500 Shipping & Delivery to Site -Fire Water Pumps 60 01-Sep-12 30-Oct-12
PMCSD10510 Shipping & Delivery to Site -Air Compressor Package 60 01-Sep-12 30-Oct-12
PMCSD10520 Shipping & Delivery to Site -CI Skids 60 01-Sep-12 30-Oct-12
PMCSD10525 Shipping & Delivery to Site -GEG 60 16-Nov-12 14-Jan-13
PMCSD10530 Shipping & Delivery to Site -Nitrogen Package 60 01-Sep-12 30-Oct-12
PMCSD10540 Shipping & Delivery to Site -Steam Generation Package 60 01-Nov-12 30-Dec-12
PMCSD10550 Shipping & Delivery to Site -Water Treatment Package 60 02-Aug-12 30-Sep-12
PMCSD10560 Shipping & Delivery to Site -Cranes & Hoist 60 03-Oct-12 01-Dec-12
Electrical 151 02-Aug-12 30-Dec-12
PELSD10180 Shipping & Delivery to Site -Switchgear, UPS System, 150
Transformers
03-Aug-12 30-Dec-12
PELSD10190 Shipping & Delivery to Site -Diesel Generator Package 60 01-Nov-12 30-Dec-12
PELSD10200 Shipping & Delivery to Site -Neutral Earthing Resistors 60 01-Sep-12 30-Oct-12
PELSD10210 Shipping & Delivery to Site -Normal/Emergency Lighting60and02-Oct-12
small power 30-Nov-12
systems / DBs
PELSD10220 Shipping & Delivery to Site -MV/LV Power & Control Cables
90 02-Aug-12 30-Oct-12
PELSD10230 Shipping & Delivery to Site -Earthing & Lightning protection
60 01-Sep-12
system 30-Oct-12
PELSD10240 Shipping & Delivery to Site -Lighting fixtures, Lighting Poles
60 02-Aug-12 30-Sep-12
PELSD10250 Shipping & Delivery to Site -Electrical Bulk items 90 02-Sep-12 30-Nov-12
PELSD10260 Shipping & Delivery to Site -Cathodic Protection System60 17-Aug-12 15-Oct-12
Instrument 111 12-Aug-12 30-Nov-12
PINSD10100 Shipping & Delivery to Site -Instrumentation Valves 60 02-Oct-12 30-Nov-12
PINSD10110 Shipping & Delivery to Site -Field Instruments 60 21-Sep-12 19-Nov-12
PINSD10120 Shipping & Delivery to Site -Analysers 60 20-Sep-12 18-Nov-12
PINSD10130 Shipping & Delivery to Site -Control Systems( Workstation,
90 Marshalling
02-Sep-12 cabinet
30-Nov-12
etc.)
PINSD10140 Shipping & Delivery to Site -Instrument Cables/Cable Tray/JBs/Tubings/Bulk
90 12-Aug-12 09-Nov-12
items
HSE 60 01-Sep-12 30-Oct-12
PHSSD10060 Shipping & Delivery to Site -Fire Fighting Equipment 60 01-Sep-12 30-Oct-12
PHSSD10070 Shipping & Delivery to Site -Safety Equipment 60 01-Sep-12 30-Oct-12
PHSSD10080 Shipping & Delivery to Site -Gaseous Fire Extinguishing60
System
01-Sep-12 30-Oct-12
Telecom 70 24-Aug-12 01-Nov-12
PTESD10080 Shipping & Delivery to Site -Transmission System / Radio
70System
24-Aug-12
/ Telephone
01-Nov-12
System
PTESD10090 Shipping & Delivery to Site -PA/GA System 60 03-Sep-12 01-Nov-12
PTESD10100 Shipping & Delivery to Site -CCTV / Accesss Control / Security
60 03-Sep-12
System 01-Nov-12
PTESD10110 Shipping & Delivery to Site -Telecom Cable 70 24-Aug-12 01-Nov-12
CONSTRUCTION 486 01-Dec-11 30-Mar-13
CPC10000 Site Handover (By Company) 0 01-Dec-11
PRE-CONSTRUCTION 137 16-Dec-11 30-Apr-12
CPC10100 Site Survey / Soil Investigation 62 16-Dec-11 15-Feb-12
CPC10110 Camp Construction 121 01-Jan-12 30-Apr-12
CPC10120 Site Establishment 121 01-Jan-12 30-Apr-12
CIVIL / STRUCTURAL 305 15-Feb-12 15-Dec-12
CCIS10000 Site Preparation 91 15-Feb-12 15-May-12
CCIS10010 Piling for Train A/B/C 61 01-Mar-12 30-Apr-12
CCIS10020 Equipment/Skid/Piperack Foundations 230 16-Mar-12 31-Oct-12
CCIS10030 Buildings (RCC Substructures/ Superstructures & Architectural
240 21-Mar-12
finishing works)
15-Nov-12

Date Revision Checked Approved


KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 7 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE
Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CCIS10040 Storage Tanks Foundation 122 01-Jun-12 30-Sep-12
CCIS10050 UG Civil works 153 01-Jul-12 30-Nov-12
CCIS10060 Erection - Pipe Rack/Misc. Structures, Pipe Supports, 137
Handrail,Grating,
01-Aug-12 Ladders
15-Dec-12
etc
MECHANICAL 217 01-Aug-12 05-Mar-13
CMC10000 Installation - Column 46 01-Dec-12 15-Jan-13
CMC10010 Installation - Vessels / Filters 76 01-Nov-12 15-Jan-13
CMC10020 Installation - Tanks 212 01-Aug-12 28-Feb-13
CMC10030 Installation - Heat Exchangers 62 01-Dec-12 31-Jan-13
CMC10040 Installation - Pig Launchers & Receivers 61 01-Nov-12 31-Dec-12
CMC10050 Installation - Flare Package 105 21-Nov-12 05-Mar-13
CMC10060 Installation - Fuel Gas Membrane Package 151 01-Oct-12 28-Feb-13
CMC10070 Installation - Air Coolers 77 01-Dec-12 15-Feb-13
CMC10080 Installation - Incinerators 92 01-Nov-12 31-Jan-13
CMC10090 Installation - Pumps (Oil Export) 31 01-Jan-13 31-Jan-13
CMC10100 Installation - Pumps (Others) 153 01-Sep-12 31-Jan-13
CMC10110 Installation - Fire Water Pumps 61 01-Nov-12 31-Dec-12
CMC10120 Installation - Air Compressor Package 76 01-Nov-12 15-Jan-13
CMC10130 Installation - CI Skids 45 17-Nov-12 31-Dec-12
CMC10135 Installation - GEG 44 15-Jan-13 27-Feb-13
CMC10140 Installation - Nitrogen Packages 61 01-Nov-12 31-Dec-12
CMC10150 Installation - Steam Generation Packages 59 01-Jan-13 28-Feb-13
CMC10160 Installation - Water Treatment Package 45 17-Oct-12 30-Nov-12
PIPING / PIPE LINE 276 13-Jun-12 15-Mar-13
CPI10000 2.8 KM Water pipeline installation 90 13-Jun-12 10-Sep-12
CPI10010 Piping Installation 136 16-Oct-12 28-Feb-13
CPI10020 Hydrotest / Flushing/Dewatering/Drying 80 26-Dec-12 15-Mar-13
ELECTRICAL 166 01-Oct-12 15-Mar-13
CEL10000 Switchgear/Power Transformers / UPS System installation
138 01-Oct-12 15-Feb-13
CEL10010 Diesel Generator Package installation 59 01-Jan-13 28-Feb-13
CEL10020 Neutral Earthing Resistors installation 61 01-Nov-12 31-Dec-12
CEL10030 Normal/Emergency Lighting & small power systems/DBs76installation
01-Nov-12 15-Jan-13
CEL10040 Install Cable Trays & accessories 108 16-Oct-12 31-Jan-13
CEL10050 Install HV/LV Power & Control Cables 110 24-Oct-12 10-Feb-13
CEL10060 Install Earthing & Lightning protection system 76 01-Nov-12 15-Jan-13
CEL10070 Install Lighting fixtures, Lighting Poles 107 01-Nov-12 15-Feb-13
CEL10080 Install Bulk Materials (Local Control Station/JB’s etc) 123 01-Oct-12 31-Jan-13
CEL10090 Install Cathodic Protection 90 03-Nov-12 31-Jan-13
CEL10100 Cable Glanding & Termination 120 16-Nov-12 15-Mar-13
INSTRUMENT 129 10-Nov-12 18-Mar-13
CIN10000 Install Cable Trays 83 10-Nov-12 31-Jan-13
CIN10010 Instrument Cable Laying 90 13-Nov-12 10-Feb-13
CIN10020 Install JB's 65 13-Dec-12 15-Feb-13
CIN10030 Cable Glanding & Terminations 90 16-Dec-12 15-Mar-13
CIN10040 Install Instrument Valves 77 01-Dec-12 15-Feb-13
CIN10050 Install Field Instruments 100 21-Nov-12 28-Feb-13
CIN10060 Install/Hook-up- Impulse Tubing 115 24-Nov-12 18-Mar-13
CIN10070 Install DCS/ESD/F&G System 90 01-Dec-12 28-Feb-13
CIN10080 Install Control Systems 90 01-Dec-12 28-Feb-13
TELECOM 102 03-Nov-12 12-Feb-13
CTE10000 Install Transmission System / Radio System / Telephone System
76 03-Nov-12 17-Jan-13

Date Revision Checked Approved


KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 8 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
STANDARD LEVEL 3 SCHEDULE

Activity ID Activity Name Orig Start Finish 2009 2010 2011 2012 2013
Dur Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S O N D Jan F Mar Apr M J Jul A S Oct N D J F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A
-38 -37 -36 -35 -34 -33 -32 -31 -30 -29 -28 -27 -26 -25 -24 -23 -22 -21 -20 -19 -18 -17 -16 -15 -14 -13 -12 -11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CTE10010 Telecom Cable Laying, Glanding & Terminations 92 03-Nov-12 02-Feb-13
CTE10020 Install PA/GA System 77 18-Nov-12 02-Feb-13
CTE10030 Install CCTV / Accesss Control / Security System 77 28-Nov-12 12-Feb-13
HSE 92 01-Nov-12 31-Jan-13
CHS10000 Installation of Safety & Fire Fighting Equipment 92 01-Nov-12 31-Jan-13
FIREPROOFING / PAINTING / INSULATION 136 15-Nov-12 30-Mar-13
CFP10000 Painting, Insulation & Fireproofing works 136 15-Nov-12 30-Mar-13
TIE-IN 31 28-Feb-13 30-Mar-13
TIE10000 Readiness of Tie-ins for Inlet line (By Company) 0 28-Feb-13*
TIE10005 Readiness of Tie-ins for Export line (By Company) 0 28-Feb-13
TIE10010 Tie-in for interface 31 28-Feb-13 30-Mar-13
PRE-COMMISSIONING, COMMISSIONING & START-UP 135 01-Jan-13 15-May-13
PRE-COMMISSIONING 106 01-Jan-13 16-Apr-13
CPCM10000 Pre-commissioning - E&I Systems 90 01-Jan-13 31-Mar-13
CPCM10100 Pre-commissioning - Utilities & Safety Systems 60 08-Feb-13 08-Apr-13
CPCM10200 Pre-commissioning - Process Systems 75 01-Feb-13 16-Apr-13
COMMISSIONING & START-UP 45 01-Apr-13 15-May-13
CCST10000 Commissioning - E&I Systems 29 01-Apr-13 29-Apr-13
CCST10100 Commissioning - Utilities & Safety Systems 29 09-Apr-13 07-May-13
CCST10200 Commissioning - Process Systems 29 17-Apr-13 15-May-13
PROVISIONAL AND FINAL ACCEPTANCE 30 05-Jun-13 05-Jul-13
PROVISIONAL ACCEPTANCE 0 05-Jun-13 05-Jun-13
CPAC10000 Provisional Acceptance 0 05-Jun-13
FINAL ACCEPTANCE 0 05-Jul-13 05-Jul-13
CCPT10000 Final Acceptance 0 05-Jul-13

Date Revision Checked Approved


KUWAIT OIL COMPANY (K.S.C)
14-Aug-08 Issued with Bid Nitin Deb

KOC Feed Pipelines For New Refinery Project (NRP)

Page 9 of 9

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
El Merk Project

CENTERAL PROCESS FACILITIES AND TELECOMMUNICATION SYSTEM (LOT 1+7)


EL MERK, ALGERIA

Contract No. : SC 4012100

Petrofac Job No.: JI-195

90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

TITLE :
90 DAYS FRONT END SCHEDULE
(UPTO 11-JUN-09)
ORIG. DOC SIZE: This is a Word document and must not be altered Rev.
Issued for
A4 manually
R1 Review 06/04/2009 CSS DG RV /CM GS

DOC NO. : ELM-PUL-PC-SCH-0002 Page 1 of 32 R1


REV DESCRIPTION DATE PRPD CHKD APPD APPD CA APPD

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

PROJECT MANAGEMENT
1 ELM-PUL-QA-PLN-0001 PROJECT QUALITY PLAN 1 11-Mar-09 15-Apr-09
2 ELM-PUL-SE-PLN-0001 PROJECT HSSE PLAN 1 11-Mar-09 14-Apr-09
3 ELM-PUL-PM-PLN-0001 PROJECT COMMUNICATION PLAN 1 11-Mar-09 26-Mar-09 11-Mar-09 26-Mar-09 80
4 ELM-PUL-PM-PEP-0002 PROJECT EXECUTION PLAN 1 11-Mar-09 16-Apr-09
5 ELM-PUL-PM-PLN-0003 CONTRACTS ADMINISTARTION PLAN 1 11-Mar-09 15-Apr-09
6 ELM-PUL-PM-PLN-0004 RISK MANAGEMENT AND CONTINGENCY PLAN 1 11-Mar-09 18-Apr-09
7 ELM-PUL-PE-PLN-0001 ENGINEERING EXECUTION PLAN 1 11-Mar-09 31-Mar-09 11-Mar-09 31-Mar-09 80
8 ELM-PUL-PU-PLN-0001 PROCUREMENT EXECUTION PLAN 1 11-Mar-09 20-Apr-09
9 ELM-PUL-CM-PLN-0001 CONSTRUCTION EXECUTION PLAN 1 11-Mar-09 20-Apr-09
10 ELM-PUL-CO-PLN-0001 COMMISSIONING PLAN 1 11-Mar-09 10-Apr-09
11 ELM-PUL-IM-PLN-0001 INTERFACE MANAGEMENT PLAN 1 11-Mar-09 2-Apr-09 11-Mar-09 2-Apr-09 80
12 ELM-PUL-PC-PLN-0001 PROJECT CONTROL PLAN 1 1-Apr-09 14-Apr-09
13 ELM-PUL-PC-PRC-0003 DOCUMENT CONTROL PLAN 1 20-Mar-09 5-Apr-09 20-Mar-09 5-Apr-09 80
14 ELM-PUL-PC-PRC-0005 PROJECT INVOICING AND PAYMENT PROCEDURE 1 7-Apr-09 30-Apr-09
15 ELM-PUL-PC-SCH-0001 CONTRACTS MASTER SCHEDULE (L3) 1 11-Mar-09 30-Apr-09
16 ELM-PUL-PC-SCH-0002 90 DAYS FRONT END SCHEDULE 1 11-Mar-09 6-Apr-09
17 ELM-PUL-PC-SCH-0003 TECHNICAL DOCUMENT REGISTER 1 11-Mar-09 30-Apr-09
18 ELM-PUL-PC-SCH-0004 PROCUREMENT TRACKING REGISTER 1 11-Mar-09 15-Apr-09
ENGINEERING
PROCESS
19 ELM-PUL-PR-BOD-0001 PROCESS DESIGN BASIS 1 9.60 11-Mar-09 15-Apr-09
20 ELM-PUL-PR-PHL-0001 WATER INJECTION & DILUTION PHILOSPHY 1 2.40 4-Apr-09 25-Apr-09

21 ELM-PUL-PR-PHL-0002 OFFSITES & CENTRAL PROCESSING FACILITY PROCESS 1 2.40 4-Apr-09 25-Apr-09
CONTROL PHILOSPHY
22 ELM-PUL-PR-PHL-0003 CHEMCIAL INJECTION PHILOSPHY 1 2.40 9-Apr-09 30-Apr-09

23 ELM-PUL-PR-PHL-0004 PROCESS FLUID SAMPLING PHILOSOPHY 1 2.40 9-Apr-09 30-Apr-09

24 ELM-PUL-PR-PHL-0005 DESIGN PHILOSOPHY - OPEN AND CLOSED DRAINS 1 2.40 9-Apr-09 30-Apr-09

25 ELM-PUL-PR-PHL-0006 DESIGN PHILOSOPHY OVERPRESSURE PROTECTION, 1 2.40 24-Apr-09 15-May-09


EMERGENCY BLOWDOWN, FLARE AND VENTING

26 ELM-PUL-PR-PHL-0007 EQUIPMENT ISOLATION PHILOSOPHY 1 2.40 24-Apr-09 15-May-09

27 ELM-PUL-PR-PHL-0008 DESIGN PRESSURE AND TEMPERATURE PHILOSOPHY 1 2.40 24-Apr-09 15-May-09

28 ELM-PUL-PR-PRC-0001 PROCEDURE FOR PREPATION OF P&IDS 2 2.40 27-Apr-09 18-May-09

29 ELM-PUL-PR-RPT-0002 SIMULATION REPORT 1 9.60 9-Apr-09 30-Apr-09

30 ELM-PUL-PR-RPT-0003 OFFSITES AND CENTRAL PROCESSING FACILITY PROCESS 1 4.80 24-Apr-09 15-May-09
DESCRIPTION
31 ELM-PUL-PR-RPT-0004 UTILITIES REPORT 1 4.80 9-Apr-09 30-Apr-09

32 ELM-PUL-PR-RPT-0005 FLARE SYSTEM DESIGN REPORT 1 14.40 9-May-09 30-May-09

33 ELM-PUL-PR-LST-0001 EQUIPMENT LIST - CPF 1 4.80 24-Apr-09 15-May-09

34 ELM-PUL-PR-BKD-0001 PRODUCTION FACILITIES OVERALL BLOCK FLOW 1 2.64 25-Mar-09 15-Apr-09


DIAGRAM
35 ELM-PUL-PR-PFD-1001 PFD - RECEPTION FACILITIES 1 2.64 11-Mar-09 15-Apr-09

36 ELM-PUL-PR-PFD-2001 PFD - OIL SEPARATION AND DESALTING 1 2.64 11-Mar-09 15-Apr-09

37 ELM-PUL-PR-PFD-2101 PFD - OIL AND CONDENSATE STABILIZATION 1 2.64 11-Mar-09 15-Apr-09

38 ELM-PUL-PR-PFD-2501 PFD - ASSOCIATED GAS COMPRESSOR 1 2.64 11-Mar-09 15-Apr-09

39 ELM-PUL-PR-PFD-2502 PFD - BOOSTER COMPRESSOR 1 2.64 11-Mar-09 15-Apr-09

40 ELM-PUL-PR-PFD-2601 PFD - GAS DEHYDRATION 1 2.64 11-Mar-09 15-Apr-09

41 ELM-PUL-PR-PFD-2701 PFD - NGL RECOVERY 1 2.64 11-Mar-09 15-Apr-09

42 ELM-PUL-PR-PFD-2702 PFD - NGL FRACTIONATION 1 2.64 11-Mar-09 15-Apr-09

43 ELM-PUL-PR-PFD-2801 PFD - RESIDUE GAS COMPRESSOR 1 2.64 11-Mar-09 15-Apr-09

44 ELM-PUL-PR-PFD-2901 PFD - INJECTION GAS COMPRESSOR 1 2.64 11-Mar-09 15-Apr-09

45 ELM-PUL-PR-PFD-2102 PFD - OIL STORAGE, EXPORT AND RE-RUN 1 2.64 11-Mar-09 15-Apr-09

46 ELM-PUL-PR-PFD-2401 PFD - LPG STORAGE, EXPORT AND RE-RUN 1 2.64 11-Mar-09 15-Apr-09

47 ELM-PUL-PR-PFD-2301 PFD - CONDENSATE STORAGE AND EXPORT 1 2.64 11-Mar-09 15-Apr-09

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 2 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

48 ELM-PUL-PR-HMB-0001 HEAT & MASS BALANCE- CENTRAL PROCESSING 1 9.60 25-Mar-09 7-Apr-09
FACILITY
49 ELM-PUL-PR-UFD-4101 UFD - HOT OIL SYSTEM - OIL STABILIZATION AREA 1 2.64 26-Mar-09 20-Apr-09

50 ELM-PUL-PR-UFD-4102 UFD - HOT OIL SYSTEM - NGL RECOVERY AREA 1 2.64 26-Mar-09 20-Apr-09

51 ELM-PUL-PR-UFD-4301 UFD - PRODUCTION CHEMICAL & METHANOL INJECTION 1 2.64 26-Mar-09 20-Apr-09

52 ELM-PUL-PR-UFD-4301 UFD - PRODUCTION CHEMICAL & METHANOL INJECTION 1 2.64 26-Mar-09 20-Apr-09

53 ELM-PUL-PR-UFD-4302 UFD - PRODUCTION CHEMICAL INJECTION 1 2.64 26-Mar-09 20-Apr-09

54 ELM-PUL-PR-UFD-4401 UFD - HP, HP/LT ATMOSPHERIC AND LP FLARE SYSTEMS 1 2.64 26-Mar-09 20-Apr-09

55 ELM-PUL-PR-UFD-4401 UFD - OIL TRAIN 1,OIL TRAIN 2 AND NGL FLARES 1 2.64 26-Mar-09 20-Apr-09

56 ELM-PUL-PR-UFD-4801 UFD - WARM AND COLD CLOSED DRAINS SYSTEMS 1 2.64 26-Mar-09 20-Apr-09

57 ELM-PUL-PR-UFD-5101 UFD - PRODUCED WATER TREATMENT-1 1 2.64 26-Mar-09 20-Apr-09

58 ELM-PUL-PR-UFD-5101 UFD - PRODUCED WATER TREATMENT-2 1 2.64 26-Mar-09 20-Apr-09

59 ELM-PUL-PR-UFD-5201 UFD - WATER INJECTION SYSTEM 1 2.64 26-Mar-09 20-Apr-09

60 ELM-PUL-PR-UFD-5201 UFD - WATER INJECTION SYSTEM 1 2.64 26-Mar-09 20-Apr-09

61 ELM-PUL-PR-UFD-5301 UFD - FUEL GAS SYSTEM 1 2.64 26-Mar-09 20-Apr-09

62 ELM-PUL-PR-UFD-5401 UFD - EVAPORATION PONDS 1 2.64 26-Mar-09 20-Apr-09

63 ELM-PUL-PR-UFD-6101 UFD - WATER SYSTEM 1 2.64 26-Mar-09 20-Apr-09

64 ELM-PUL-PR-UFD-6102 UFD - SOURCE WATER STORAGE 1 2.64 26-Mar-09 20-Apr-09

65 ELM-PUL-PR-UFD-6103 UFD - UTILITY AND FRESH WATER SYSTEMS 1 2.64 26-Mar-09 20-Apr-09

66 ELM-PUL-PR-UFD-6401 UFD - DIESEL FUEL RECEIVING, STORAGE AND 1 2.64 26-Mar-09 20-Apr-09
DISTRIBUTING
67 ELM-PUL-PR-UFD-6701 UFD - COMPRESSED AIR 1 2.64 26-Mar-09 20-Apr-09

68 ELM-PUL-PR-UFD-7001 UFD - OILY WATER TREATMENT SYSTEM 1 2.64 26-Mar-09 20-Apr-09

69 ELM-PUL-PR-UFD-7101 UFD - NITROGEN GENERATION AND DISTRIBUTION 1 2.64 26-Mar-09 20-Apr-09

70 ELM-PUL-PR-UFD-7301 UFD - SEWAGE TREATMENT SYSTEM 1 2.64 26-Mar-09 20-Apr-09

71 ELM-PUL-PR-UFD-7502 UFD - EMERGENCY GENERATOR 1 2.64 26-Mar-09 20-Apr-09

72 ELM-PUL-PR-PID-0001 PID -CENTRAL PROCESSING FACILITY - DRAWING INDEX 1 4.51 9-May-09 30-May-09
SHEET 1
73 ELM-PUL-PR-PID-0001 PID -CENTRAL PROCESSING FACILITY - DRAWING INDEX 1 4.51 9-May-09 30-May-09
SHEET 2
74 ELM-PUL-PR-PID-0010 PID -GENERAL NOTES 1 4.51 9-May-09 30-May-09

75 ELM-PUL-PR-PID-0011 PID -NUMBERING PHILOSPHY OF P&ID'S 1 4.51 9-May-09 30-May-09

76 ELM-PUL-PR-PID-0012 PID -PIPING SYMBOLOGY 1 4.51 9-May-09 30-May-09

77 ELM-PUL-PR-PID-0013 PID -EQUIPMENT SYMBOLOGY SHEET 1 4.51 9-May-09 30-May-09

78 ELM-PUL-PR-PID-0013 PID -EQUIPMENT SYMBOLOGY SHEET 1 4.51 9-May-09 30-May-09

79 ELM-PUL-PR-PID-0014 PID -INSTRUMENTATION SYMBOLOGY 1 4.51 9-May-09 30-May-09

80 ELM-PUL-PR-PID-0014 PID -INSTRUMENTATION SYMBOLOGY 1 4.51 9-May-09 30-May-09

81 ELM-PUL-PR-PID-0014 PID -INSTRUMENTATION SYMBOLOGY 1 4.51 9-May-09 30-May-09

82 ELM-PUL-PR-PID-0014 PID -SAMPLE CONNECTION DETAILS 1 4.51 9-May-09 30-May-09

83 ELM-PUL-PR-PID-0014 PID -SEAL PLAN DETAILS 1 4.51 9-May-09 30-May-09

84 ELM-PUL-PR-PID-1001 PID -BLOCK 208 OIL SLUG CATCHER HEADER 1 4.51 9-May-09 30-May-09

85 ELM-PUL-PR-PID-1001 PID -BLOCK 208 OIL SLUG CATCHER 1 4.51 9-May-09 30-May-09

86 ELM-PUL-PR-PID-1002 PID -EMK UNITIZED OIL SLUG CATCHER HEADER 1 4.51 9-May-09 30-May-09

87 ELM-PUL-PR-PID-1002 PID -EMK UNITIZED OIL SLUG CATCHER 1 4.51 9-May-09 30-May-09

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 3 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

88 ELM-PUL-PR-PID-1003 PID -BLOCK 208 GAS CONDENSATE SLUG CATCHER 1 4.51 9-May-09 30-May-09
HEADER
89 ELM-PUL-PR-PID-1003 PID -BLOCK 208 GAS CONDENSATE SLUG CATCHER 1 4.51 9-May-09 30-May-09

90 ELM-PUL-PR-PID-1005 PID -BLOCK 208 & EMK UNITIZED OIL INLET GAS AND 1 4.51 9-May-09 30-May-09
LIQUID PIPING
91 ELM-PUL-PR-PID-1006 PID -BLOCK 208 CONDENSATE INLET GAS AND LIQUID 1 4.51 9-May-09 30-May-09
PIPING
92 ELM-PUL-PR-PID-1007 PID -BLOCK 208 & EMK UNITIZED OIL INLET WATER 1 4.51 9-May-09 30-May-09
PIPING
93 ELM-PUL-PR-PID-1008 PID -BLOCK 208 CONDENSATE INLET WATER PIPING 1 4.51 9-May-09 30-May-09

94 ELM-PUL-PR-PID-1015 PID -BLOCK 208 GAS CONDENSATE INLET SEPARATOR 1 4.51 9-May-09 30-May-09

95 ELM-PUL-PR-PID-2001 PID -TRAIN 1 - INLET LIQUID MANIFOLD 1 4.51 9-May-09 30-May-09

96 ELM-PUL-PR-PID-2001 PID -TRAIN 2 - INLET LIQUID MANIFOLD 1 4.51 9-May-09 30-May-09

97 ELM-PUL-PR-PID-2010 PID -TRAIN 1 - HP SEPARATOR FEED PRE-HEATER 1 4.51 9-May-09 30-May-09

98 ELM-PUL-PR-PID-2010 PID -TRAIN 2 - HP SEPARATOR FEED PRE-HEATER 1 4.51 9-May-09 30-May-09

99 ELM-PUL-PR-PID-2012 PID -TRAIN 1 - HP SEPARATOR 1 4.51 9-May-09 30-May-09

100 ELM-PUL-PR-PID-2012 PID -TRAIN 2 - HP SEPARATOR 1 4.51 9-May-09 30-May-09

101 ELM-PUL-PR-PID-2013 PID -TRAIN 1 - OIL TRANSFER PUMPS 1 4.51 9-May-09 30-May-09

102 ELM-PUL-PR-PID-2013 PID -TRAIN 2 - OIL TRANSFER PUMPS 1 4.51 9-May-09 30-May-09

103 ELM-PUL-PR-PID-2014 PID -TRAIN 1 - 1ST STAGE DESALTER 1 4.51 9-May-09 30-May-09

104 ELM-PUL-PR-PID-2014 PID -TRAIN 2 - 1ST STAGE DESALTER 1 4.51 9-May-09 30-May-09

105 ELM-PUL-PR-PID-2015 PID -TRAIN 1 - 2ND STAGE DESALTER 1 4.51 9-May-09 30-May-09

106 ELM-PUL-PR-PID-2015 PID -TRAIN 2 - 2ND STAGE DESALTER 1 4.51 9-May-09 30-May-09

107 ELM-PUL-PR-PID-2016 PID -TRAIN 1 - OIL STABILIZER FEED HEATER 1 4.51 9-May-09 30-May-09

108 ELM-PUL-PR-PID-2016 PID -TRAIN 2 - OIL STABILIZER FEED HEATER 1 4.51 9-May-09 30-May-09

109 ELM-PUL-PR-PID-2017 PID -TRAIN 1 - OIL STABILIZER 1 4.51 9-May-09 30-May-09

110 ELM-PUL-PR-PID-2017 PID -TRAIN 2 - OIL STABILIZER 1 4.51 9-May-09 30-May-09

111 ELM-PUL-PR-PID-2018 PID -TRAIN 1 - OIL STABILIZER REBOILER 1 4.51 9-May-09 30-May-09

112 ELM-PUL-PR-PID-2018 PID -TRAIN 2 - OIL STABILIZER REBOILER 1 4.51 9-May-09 30-May-09

113 ELM-PUL-PR-PID-2019 PID -TRAIN 1 - OIL STABILIZER SIDE DRAW DRUM 1 4.51 9-May-09 30-May-09

114 ELM-PUL-PR-PID-2019 PID -TRAIN 2 - OIL STABILIZER SIDE DRAW DRUM 1 4.51 9-May-09 30-May-09

115 ELM-PUL-PR-PID-2020 PID -TRAIN 1 - CONDENSATE FLASH HEATER 1 4.51 9-May-09 30-May-09

116 ELM-PUL-PR-PID-2020 PID -TRAIN 1 - STABILIZED OIL TRANSFER PUMP SURGE 1 4.51 9-May-09 30-May-09
DRUM
117 ELM-PUL-PR-PID-2020 PID -TRAIN 1 - STABILIZED OIL TRANSFER PUMPS 1 4.51 9-May-09 30-May-09

118 ELM-PUL-PR-PID-2020 PID -TRAIN 2 - CONDENSATE FLASH HEATER 1 4.51 9-May-09 30-May-09

119 ELM-PUL-PR-PID-2020 PID -TRAIN 2 - STABILIZED OIL TRANSFER PUMP SURGE 1 4.51 9-May-09 30-May-09
DRUM
120 ELM-PUL-PR-PID-2020 PID -TRAIN 2 - STABILIZED OIL TRANSFER PUMPS 1 4.51 9-May-09 30-May-09

121 ELM-PUL-PR-PID-2021 PID -TRAIN 1 - STABILIZER CONDENSATE CONDENSER 1 4.51 9-May-09 30-May-09

122 ELM-PUL-PR-PID-2021 PID -TRAIN 2 - STABILIZER CONDENSATE CONDENSER 1 4.51 9-May-09 30-May-09

123 ELM-PUL-PR-PID-2022 PID -TRAIN 1 - STABILIZED CONDENSATE DRUM AND 1 4.51 9-May-09 30-May-09
PUMPS
124 ELM-PUL-PR-PID-2022 PID -TRAIN 2 - STABILIZED CONDENSATE DRUM AND 1 4.51 9-May-09 30-May-09
PUMPS
125 ELM-PUL-PR-PID-2023 PID -TRAIN 1 - OIL RUNDOWN COOLERS 1 4.51 9-May-09 30-May-09

126 ELM-PUL-PR-PID-2023 PID -TRAIN 2 - OIL RUNDOWN COOLERS 1 4.51 9-May-09 30-May-09

127 ELM-PUL-PR-PID-2024 PID -OIL RUNDOWN MANIFOLD 1 4.51 9-May-09 30-May-09

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 4 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

128 ELM-PUL-PR-PID-2025 PID -TRAIN 1 - DESALTER WASH WATER HEATER 1 4.51 9-May-09 30-May-09

129 ELM-PUL-PR-PID-2025 PID -TRAIN 2 - DESALTER WASH WATER HEATER 1 4.51 9-May-09 30-May-09

130 ELM-PUL-PR-PID-2102 PID -OIL STORAGE TANK A 1 4.51 9-May-09 30-May-09

131 ELM-PUL-PR-PID-2103 PID -OIL STORAGE TANK B 1 4.51 9-May-09 30-May-09

132 ELM-PUL-PR-PID-2104 PID -OIL BOOSTER PUMPS 1 4.51 9-May-09 30-May-09

133 ELM-PUL-PR-PID-2106 PID -OIL FISCAL METER 1 4.51 9-May-09 30-May-09

134 ELM-PUL-PR-PID-2107 PID -OIL EXPORT PUMPS 1 4.51 9-May-09 30-May-09

135 ELM-PUL-PR-PID-2108 PID -OIL EXPORT PUMP RECYCLE COOLER 1 4.51 9-May-09 30-May-09

136 ELM-PUL-PR-PID-2109 PID -OIL LAUNCHER 1 4.51 9-May-09 30-May-09

137 ELM-PUL-PR-PID-2120 PID -OIL/CONDENSATE RE-RUN FLASH DRUM 1 4.51 9-May-09 30-May-09

138 ELM-PUL-PR-PID-2121 PID -OIL/CONDENSATE RE-RUN TANK 1 4.51 9-May-09 30-May-09

139 ELM-PUL-PR-PID-2122 PID -OIL/CONDENSATE RE-RUN PUMPS 1 4.51 9-May-09 30-May-09

140 ELM-PUL-PR-PID-2303 PID -CONDENSATE STORAGE TANK A 1 4.51 9-May-09 30-May-09

141 ELM-PUL-PR-PID-2304 PID -CONDENSATE STORAGE TANK B 1 4.51 9-May-09 30-May-09

142 ELM-PUL-PR-PID-2305 PID -CONDENSATE BOOSTER PUMPS 1 4.51 9-May-09 30-May-09

143 ELM-PUL-PR-PID-2306 PID -CONDENSATE FISCAL METER 1 4.51 9-May-09 30-May-09

144 ELM-PUL-PR-PID-2307 PID -CONDENSATE EXPORT PUMPS 1 4.51 9-May-09 30-May-09

145 ELM-PUL-PR-PID-2307 PID -CONDENSATE EXPORT PUMP RECYCLE COOLER 1 4.51 9-May-09 30-May-09

146 ELM-PUL-PR-PID-2308 PID -CONDENSATE LAUNCHER 1 4.51 9-May-09 30-May-09

147 ELM-PUL-PR-PID-2401 PID -LPG STORAGE SPHERE A 1 4.51 9-May-09 30-May-09

148 ELM-PUL-PR-PID-2402 PID -LPG STORAGE SPHERE B 1 4.51 9-May-09 30-May-09

149 ELM-PUL-PR-PID-2403 PID -LPG BOOSTER PUMPS 1 4.51 9-May-09 30-May-09

150 ELM-PUL-PR-PID-2405 PID -LPG EXPORT PUMPS 1 4.51 9-May-09 30-May-09

151 ELM-PUL-PR-PID-2406 PID -LPG EXPORT PUMP RECYCLE COOLER 1 4.51 9-May-09 30-May-09

152 ELM-PUL-PR-PID-2408 PID -LPG LAUNCHER / FISCAL METER 1 4.51 9-May-09 30-May-09

153 ELM-PUL-PR-PID-2410 PID -LPG RE-RUN SPHERE 1 4.51 9-May-09 30-May-09

154 ELM-PUL-PR-PID-2411 PID -LPG RE-RUN PUMPS 1 4.51 9-May-09 30-May-09

155 ELM-PUL-PR-PID-2501 PID -1ST STAGE ASSOCIATED GAS SUCTION HEADER 1 4.51 9-May-09 30-May-09

156 ELM-PUL-PR-PID-2510 PID -TRAIN 1 - ASSOCIATED GAS INLET COOLER 1 4.51 9-May-09 30-May-09

157 ELM-PUL-PR-PID-2510 PID -TRAIN 2 - ASSOCIATED GAS INLET COOLER 1 4.51 9-May-09 30-May-09

158 ELM-PUL-PR-PID-2510 PID -TRAIN 3 - ASSOCIATED GAS INLET COOLER 1 4.51 9-May-09 30-May-09

159 ELM-PUL-PR-PID-2511 PID -TRAIN 1 - 1ST STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM
160 ELM-PUL-PR-PID-2511 PID -TRAIN 2 - 1ST STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM
161 ELM-PUL-PR-PID-2511 PID -TRAIN 3 - 1ST STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM
162 ELM-PUL-PR-PID-2511 PID -TRAIN 1 - 1ST STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM PUMP
163 ELM-PUL-PR-PID-2511 PID -TRAIN 2 - 1ST STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM PUMP
164 ELM-PUL-PR-PID-2511 PID -TRAIN 3 - 1ST STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM PUMP
165 ELM-PUL-PR-PID-2512 PID -TRAIN 1 - 1ST STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
COMPRESSOR
166 ELM-PUL-PR-PID-2512 PID -TRAIN 2 - 1ST STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
COMPRESSOR
167 ELM-PUL-PR-PID-2512 PID -TRAIN 3 - 1ST STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
COMPRESSOR

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 5 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

168 ELM-PUL-PR-PID-2513 PID -2ND STAGE ASSOCIATED GAS SUCTION AND 1 4.51 9-May-09 30-May-09
CONDENSATE HEADERS
169 ELM-PUL-PR-PID-2514 PID -TRAIN 1 - 2ND STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
COOLER
170 ELM-PUL-PR-PID-2514 PID -TRAIN 2 - 2ND STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
COOLER
171 ELM-PUL-PR-PID-2514 PID -TRAIN 3 - 2ND STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
COOLER
172 ELM-PUL-PR-PID-2515 PID -TRAIN 1 - 2ND STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM
173 ELM-PUL-PR-PID-2515 PID -TRAIN 2 - 2ND STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM
174 ELM-PUL-PR-PID-2515 PID -TRAIN 3 - 2ND STAGE ASSOCIATED GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM
175 ELM-PUL-PR-PID-2516 PID -TRAIN 1 - 2ND STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
COMPRESSOR
176 ELM-PUL-PR-PID-2516 PID -TRAIN 2 - 2ND STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
COMPRESSOR
177 ELM-PUL-PR-PID-2516 PID -TRAIN 3 - 2ND STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
COMPRESSOR
178 ELM-PUL-PR-PID-2517 PID -TRAIN 1 - 2ND STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
AFTERCOOLER
179 ELM-PUL-PR-PID-2517 PID -TRAIN 2 - 2ND STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
AFTERCOOLER
180 ELM-PUL-PR-PID-2517 PID -TRAIN 3 - 2ND STAGE ASSOCIATED GAS 1 4.51 9-May-09 30-May-09
AFTERCOOLER
181 ELM-PUL-PR-PID-2520 PID -GAS BOOSTER COMPRESSORS SUCTION HEADERS 1 4.51 9-May-09 30-May-09

182 ELM-PUL-PR-PID-2521 PID -TRAIN 1 - BOOSTER COMPRESSOR SUCTION DRUM 1 4.51 9-May-09 30-May-09

183 ELM-PUL-PR-PID-2521 PID -TRAIN 2 - BOOSTER COMPRESSOR SUCTION DRUM 1 4.51 9-May-09 30-May-09

184 ELM-PUL-PR-PID-2521 PID -TRAIN 3 - BOOSTER COMPRESSOR SUCTION DRUM 1 4.51 9-May-09 30-May-09

185 ELM-PUL-PR-PID-2522 PID -TRAIN 1 - BOOSTER COMPRESSOR 1 4.51 9-May-09 30-May-09

186 ELM-PUL-PR-PID-2522 PID -TRAIN 2 - BOOSTER COMPRESSOR 1 4.51 9-May-09 30-May-09

187 ELM-PUL-PR-PID-2522 PID -TRAIN 3 - BOOSTER COMPRESSOR 1 4.51 9-May-09 30-May-09

188 ELM-PUL-PR-PID-2523 PID -TRAIN 1 - BOOSTER COMPRESSOR AFTERCOOLER 1 4.51 9-May-09 30-May-09

189 ELM-PUL-PR-PID-2523 PID -TRAIN 2 - BOOSTER COMPRESSOR AFTERCOOLER 1 4.51 9-May-09 30-May-09

190 ELM-PUL-PR-PID-2523 PID -TRAIN 3 - BOOSTER COMPRESSOR AFTERCOOLER 1 4.51 9-May-09 30-May-09

191 ELM-PUL-PR-PID-2601 PID -GAS DEHYDRATION INLET GAS COOLER 1 4.51 9-May-09 30-May-09

192 ELM-PUL-PR-PID-2602 PID -GAS DEHYDRATION INLET FEED K.O. DRUM 1 4.51 9-May-09 30-May-09

193 ELM-PUL-PR-PID-2603 PID -GAS DEHYDRATION COMMON HEADER 1 4.51 9-May-09 30-May-09

194 ELM-PUL-PR-PID-2610 PID -GAS DEHYDRATION INLET COALESCER 1 4.51 9-May-09 30-May-09

195 ELM-PUL-PR-PID-2612 PID -GAS MOL SIEVE BEDS 1 4.51 9-May-09 30-May-09

196 ELM-PUL-PR-PID-2613 PID -GAS MOL SIEVE BEDS 1 4.51 9-May-09 30-May-09

197 ELM-PUL-PR-PID-2614 PID -GAS MOL SIEVE BED FILTERS 1 4.51 9-May-09 30-May-09

198 ELM-PUL-PR-PID-2615 PID -GAS DEHYDRATION REGENERATION GAS 1 4.51 9-May-09 30-May-09
COMPRESSION
199 ELM-PUL-PR-PID-2616 PID -GAS DEHYDRATION REGENERATION GAS FIRED 1 4.51 9-May-09 30-May-09
HEATER
200 ELM-PUL-PR-PID-2617 PID -GAS DEHYDRATION REGENERATION GAS COOLER 1 4.51 9-May-09 30-May-09
AND SEPARATOR
201 ELM-PUL-PR-PID-2704 PID -ABSORBER 1 4.51 9-May-09 30-May-09

202 ELM-PUL-PR-PID-2705 PID -DEETHANIZER OVERHEAD CONDENSER 1 4.51 9-May-09 30-May-09

203 ELM-PUL-PR-PID-2706 PID -DEETHANIZER FEED PUMPS 1 4.51 9-May-09 30-May-09

204 ELM-PUL-PR-PID-2708 PID -NGL FEED PRE-COOLER 1 4.51 9-May-09 30-May-09

205 ELM-PUL-PR-PID-2710 PID -NGL FEED GAS-GAS EXCHANGER 1 4.51 9-May-09 30-May-09

206 ELM-PUL-PR-PID-2711 PID -NGL FEED GAS-LIQUID EXCHANGER 1 4.51 9-May-09 30-May-09

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 6 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

207 ELM-PUL-PR-PID-2712 PID -NGL EXPANDER SUCTION DRUM 1 4.51 9-May-09 30-May-09

208 ELM-PUL-PR-PID-2713 PID -NGL EXPANDER / COMPRESSOR 1 4.51 9-May-09 30-May-09

209 ELM-PUL-PR-PID-2713 PID -NGL EXPANDER / COMPRESSOR 1 4.51 9-May-09 30-May-09

210 ELM-PUL-PR-PID-2714 PID -NGL EXPANDER / COMPRESSOR AFTERCOOLER 1 4.51 9-May-09 30-May-09

211 ELM-PUL-PR-PID-2715 PID -DEETHANIZER 1 4.51 9-May-09 30-May-09

212 ELM-PUL-PR-PID-2715 PID -DEETHANIZER REBOILER 1 4.51 9-May-09 30-May-09

213 ELM-PUL-PR-PID-2717 PID -DEBUTANIZER FEED HEATER 1 4.51 9-May-09 30-May-09

214 ELM-PUL-PR-PID-2718 PID -DEBUTANIZER 1 4.51 9-May-09 30-May-09

215 ELM-PUL-PR-PID-2718 PID -DEBUTANIZER REBOILERS 1 4.51 9-May-09 30-May-09

216 ELM-PUL-PR-PID-2719 PID -DEBUTANIZER CONDENSER OVERHEAD 1 4.51 9-May-09 30-May-09

217 ELM-PUL-PR-PID-2720 PID -DEBUTANIZER REFLUX DRUM AND PUMPS 1 4.51 9-May-09 30-May-09

218 ELM-PUL-PR-PID-2721 PID -CONDENSATE RUNDOWN COOLER 1 4.51 9-May-09 30-May-09

219 ELM-PUL-PR-PID-2722 PID -LPG RUNDOWN COOLER 1 4.51 9-May-09 30-May-09

220 ELM-PUL-PR-PID-2723 PID -RESIDUE GAS COMPRESSOR COMMON HEADER 1 4.51 9-May-09 30-May-09

221 ELM-PUL-PR-PID-2724 PID -TRAIN 1 - 1ST STAGE RESIDUE GAS SUCTION DRUM 1 4.51 9-May-09 30-May-09

222 ELM-PUL-PR-PID-2724 PID -TRAIN 2 - 1ST STAGE RESIDUE GAS SUCTION DRUM 1 4.51 9-May-09 30-May-09

223 ELM-PUL-PR-PID-2725 PID -TRAIN 1 - RESIDUE GAS COMPRESSOR - STAGE 1 1 4.51 9-May-09 30-May-09

224 ELM-PUL-PR-PID-2725 PID -TRAIN 2 - RESIDUE GAS COMPRESSOR - STAGE 1 1 4.51 9-May-09 30-May-09

225 ELM-PUL-PR-PID-2726 PID -TRAIN 1 - 1ST STAGE RESIDUE GAS AFTERCOOLER 1 4.51 9-May-09 30-May-09

226 ELM-PUL-PR-PID-2726 PID -TRAIN 2 - 1ST STAGE RESIDUE GAS AFTERCOOLER 1 4.51 9-May-09 30-May-09

227 ELM-PUL-PR-PID-2728 PID -TRAIN 1 - 2ND STAGE RESIDUE GAS SUCTION DRUM 1 4.51 9-May-09 30-May-09

228 ELM-PUL-PR-PID-2728 PID -TRAIN 2 - 2ND STAGE RESIDUE GAS SUCTION DRUM 1 4.51 9-May-09 30-May-09

229 ELM-PUL-PR-PID-2729 PID -TRAIN 1 - RESIDUE GAS COMPRESSOR - STAGE 2 1 4.51 9-May-09 30-May-09

230 ELM-PUL-PR-PID-2729 PID -TRAIN 2 - RESIDUE GAS COMPRESSOR - STAGE 2 1 4.51 9-May-09 30-May-09

231 ELM-PUL-PR-PID-2730 PID -TRAIN 1 - 2ND STAGE RESIDUE GAS AFTERCOOLER 1 4.51 9-May-09 30-May-09

232 ELM-PUL-PR-PID-2730 PID -TRAIN 2 - 2ND STAGE RESIDUE GAS AFTERCOOLER 1 4.51 9-May-09 30-May-09

233 ELM-PUL-PR-PID-2901 PID -GAS COMPRESSOR COMMON HEADER 1 4.51 9-May-09 30-May-09

234 ELM-PUL-PR-PID-2910 PID -TRAIN 1 - 1ST STAGE INJECTION SUCTION DRUM 1 4.51 9-May-09 30-May-09

235 ELM-PUL-PR-PID-2910 PID -TRAIN 2 - 1ST STAGE INJECTION SUCTION DRUM 1 4.51 9-May-09 30-May-09

236 ELM-PUL-PR-PID-2910 PID -TRAIN 3 - 1ST STAGE INJECTION SUCTION DRUM 1 4.51 9-May-09 30-May-09

237 ELM-PUL-PR-PID-2911 PID -TRAIN 1 - 1ST STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09

238 ELM-PUL-PR-PID-2911 PID -TRAIN 2 - 1ST STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09

239 ELM-PUL-PR-PID-2911 PID -TRAIN 3 - 1ST STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09

240 ELM-PUL-PR-PID-2912 PID -TRAIN 1 - 1ST STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09
AFTERCOOLER
241 ELM-PUL-PR-PID-2912 PID -TRAIN 2 - 1ST STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09
AFTERCOOLER
242 ELM-PUL-PR-PID-2912 PID -TRAIN 3 - 1ST STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09
AFTERCOOLER
243 ELM-PUL-PR-PID-2914 PID -TRAIN 1 - 2ND STAGE INJECTION GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM
244 ELM-PUL-PR-PID-2914 PID -TRAIN 2 - 2ND STAGE INJECTION GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 7 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

245 ELM-PUL-PR-PID-2914 PID -TRAIN 3 - 2ND STAGE INJECTION GAS SUCTION 1 4.51 9-May-09 30-May-09
DRUM
246 ELM-PUL-PR-PID-2915 PID -TRAIN 1 - 2ND STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09

247 ELM-PUL-PR-PID-2915 PID -TRAIN 2 - 2ND STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09

248 ELM-PUL-PR-PID-2915 PID -TRAIN 3 - 2ND STAGE INJECTION GAS COMPRESSOR 1 4.51 9-May-09 30-May-09

249 ELM-PUL-PR-PID-2916 PID -TRAIN 1 - 2ND STAGE INJECTION GAS 1 4.51 9-May-09 30-May-09
AFTERCOOLER
250 ELM-PUL-PR-PID-2916 PID -TRAIN 2 - 2ND STAGE INJECTION GAS 1 4.51 9-May-09 30-May-09
AFTERCOOLER
251 ELM-PUL-PR-PID-2916 PID -TRAIN 3 - 2ND STAGE INJECTION GAS 1 4.51 9-May-09 30-May-09
AFTERCOOLER
252 ELM-PUL-PR-PID-2980 PID -INJECTION GAS 1 4.51 9-May-09 30-May-09

253 ELM-PUL-PR-PID-4101 PID -HOT OIL STORAGE 1 4.51 9-May-09 30-May-09

254 ELM-PUL-PR-PID-4101 PID -HOT OIL DRAINS 1 4.51 9-May-09 30-May-09

255 ELM-PUL-PR-PID-4102 PID -TRAIN 1 - HOT OIL EXPANSION DRUM OIL AREA 1 4.51 9-May-09 30-May-09

256 ELM-PUL-PR-PID-4102 PID -TRAIN 1 - HOT OIL CIRCULATION PUMP OIL AREA 1 4.51 9-May-09 30-May-09

257 ELM-PUL-PR-PID-4102 PID -TRAIN 2 - HOT OIL EXPANSION DRUM OIL AREA 1 4.51 9-May-09 30-May-09

258 ELM-PUL-PR-PID-4102 PID -TRAIN 2 - HOT OIL CIRCULATION PUMP OIL AREA 1 4.51 9-May-09 30-May-09

259 ELM-PUL-PR-PID-4103 PID -TRAIN 1 - HOT OIL FILTERS OIL AREA 1 4.51 9-May-09 30-May-09

260 ELM-PUL-PR-PID-4103 PID -TRAIN 2 - HOT OIL FILTERS OIL AREA 1 4.51 9-May-09 30-May-09

261 ELM-PUL-PR-PID-4104 PID -TRAIN 1 - HOT OIL FIRED HEATER OIL AREA 1 4.51 9-May-09 30-May-09

262 ELM-PUL-PR-PID-4104 PID -TRAIN 2 - HOT OIL FIRED HEATER OIL AREA 1 4.51 9-May-09 30-May-09

263 ELM-PUL-PR-PID-4107 PID -TRAIN 1 - HOT OIL DISTRIBUTION SYSTEM OIL AREA 1 4.51 9-May-09 30-May-09

264 ELM-PUL-PR-PID-4107 PID -TRAIN 2 - HOT OIL DISTRIBUTION SYSTEM OIL AREA 1 4.51 9-May-09 30-May-09

265 ELM-PUL-PR-PID-4109 PID -HOT OIL DRAIN COLLECTION 1 4.51 9-May-09 30-May-09

266 ELM-PUL-PR-PID-4112 PID -HOT OIL EXPANSION DRUM NGL AREA 1 4.51 9-May-09 30-May-09

267 ELM-PUL-PR-PID-4112 PID -HOT OIL RECIRCULATION PUMP NGL AREA 1 4.51 9-May-09 30-May-09

268 ELM-PUL-PR-PID-4113 PID -HOT OIL FILTERS NGL AREA 1 4.51 9-May-09 30-May-09

269 ELM-PUL-PR-PID-4114 PID -HOT OIL FIRED HEATER NGL AREA 1 4.51 9-May-09 30-May-09

270 ELM-PUL-PR-PID-4117 PID -HOT OIL DISTRIBUTION SYSTEM NGL AREA 1 4.51 9-May-09 30-May-09

271 ELM-PUL-PR-PID-4118 PID -HOT OIL STORAGE FILTER 1 4.51 9-May-09 30-May-09

272 ELM-PUL-PR-PID-4119 PID -HOT OIL DRAIN FILTER 1 4.51 9-May-09 30-May-09

273 ELM-PUL-PR-PID-4120 PID -HOT OIL DRAIN COLLECTION 1 4.51 9-May-09 30-May-09

274 ELM-PUL-PR-PID-4121 PID -HOT OIL DRAINS NGL AREA 1 4.51 9-May-09 30-May-09

275 ELM-PUL-PR-PID-4302 PID -OXYGEN SCAVENGER INJECTION SYSTEM 1 4.51 9-May-09 30-May-09

276 ELM-PUL-PR-PID-4303 PID -BIOCIDE INJECTION SYSTEM 1 4.51 9-May-09 30-May-09

277 ELM-PUL-PR-PID-4304 PID -DEMULSIFIER INJECTION SYSTEM (INLET AREA) 1 4.51 9-May-09 30-May-09

278 ELM-PUL-PR-PID-4304 PID -DEMULSIFIER INJECTION SYSTEM (OIL AREA) 1 4.51 9-May-09 30-May-09

279 ELM-PUL-PR-PID-4305 PID -SCALE INHIBITOR INJECTION SYSTEM (INLET AREA) 1 4.51 9-May-09 30-May-09

280 ELM-PUL-PR-PID-4305 PID -SCALE INHIBITOR INJECTION SYSTEM (OIL AREA) 1 4.51 9-May-09 30-May-09

281 ELM-PUL-PR-PID-4306 PID -METHANOL INJECTION SYSTEM (NGL AREA) 1 4.51 9-May-09 30-May-09

282 ELM-PUL-PR-PID-4307 PID -POLYELECTROLYTE INJECTION SYSTEM 1 4.51 9-May-09 30-May-09

283 ELM-PUL-PR-PID-4308 PID -CORROSION INHIBITOR INJECTION SYSTEM (INLET 1 4.51 9-May-09 30-May-09
AREA)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 8 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

284 ELM-PUL-PR-PID-4308 PID -CORROSION INHIBITOR INJECTION SYSTEM 1 4.51 9-May-09 30-May-09
(DEHYDRATION AREA)
285 ELM-PUL-PR-PID-4308 PID -CORROSION INHIBITOR SYSTEM 1 4.51 9-May-09 30-May-09

286 ELM-PUL-PR-PID-4401 PID -HIGH PRESSURE FLARE COLLECTION HEADER 1 4.51 9-May-09 30-May-09

287 ELM-PUL-PR-PID-4401 PID -HIGH PRESSURE FLARE KO DRUM AND PUMPS 1 4.51 9-May-09 30-May-09

288 ELM-PUL-PR-PID-4401 PID -HIGH PRESSURE FLARE PACKAGE 1 4.51 9-May-09 30-May-09

289 ELM-PUL-PR-PID-4501 PID -LOW PRESSURE FLARE COLLECTION HEADER 1 4.51 9-May-09 30-May-09

290 ELM-PUL-PR-PID-4501 PID -LOW PRESSSURE FLARE KO DRUM 1 4.51 9-May-09 30-May-09

291 ELM-PUL-PR-PID-4501 PID -LOW PRESSURE FLARE PACKAGE 1 4.51 9-May-09 30-May-09

292 ELM-PUL-PR-PID-4601 PID -HP/LT FLARE HEADER 1 4.51 9-May-09 30-May-09

293 ELM-PUL-PR-PID-4601 PID -HP/LT FLARE HEADER 1 4.51 9-May-09 30-May-09

294 ELM-PUL-PR-PID-4601 PID -HP/LT FLARE KO DRUM 1 4.51 9-May-09 30-May-09

295 ELM-PUL-PR-PID-4601 PID -HP/LT FLARE PACKAGE 1 4.51 9-May-09 30-May-09

296 ELM-PUL-PR-PID-4701 PID -ATMOSPHERIC PRESSURE FLARE COLLECTION 1 4.51 9-May-09 30-May-09
HEADER
297 ELM-PUL-PR-PID-4701 PID -ATMOSPHERIC PRESSURE FLARE KO DRUM AND 1 4.51 9-May-09 30-May-09
PUMPS
298 ELM-PUL-PR-PID-4701 PID -ATMOSPHERIC PRESSURE FLARE PACKAGE 1 4.51 9-May-09 30-May-09

299 ELM-PUL-PR-PID-4810 PID -WET DRAIN COLLECTION 1 4.51 9-May-09 30-May-09

300 ELM-PUL-PR-PID-4810 PID -WET DRAIN COLLECTION 1 4.51 9-May-09 30-May-09

301 ELM-PUL-PR-PID-4811 PID -COMMON CLOSED DRAIN COLLECTION HEADER 1 4.51 9-May-09 30-May-09

302 ELM-PUL-PR-PID-4811 PID -COMMON CLOSED COLLECTION DRUM 1 4.51 9-May-09 30-May-09

303 ELM-PUL-PR-PID-4814 PID -WET CLOSED DRAIN DRUM 1 4.51 9-May-09 30-May-09

304 ELM-PUL-PR-PID-4815 PID -LT CLOSED DRAIN COLLECTION HEADER 1 4.51 9-May-09 30-May-09

305 ELM-PUL-PR-PID-4815 PID -LT CLOSED DRAIN DRUM 1 4.51 9-May-09 30-May-09

306 ELM-PUL-PR-PID-4816 PID -OIL/CONDENSATE LAUNCHER DRAIN COLLECTION 1 4.51 9-May-09 30-May-09

307 ELM-PUL-PR-PID-4816 PID -OIL/CONDENSATE LAUNCHER CLOSED DRAIN DRUM 1 4.51 9-May-09 30-May-09

308 ELM-PUL-PR-PID-4901 PID -OIL TRAIN-1 FLARE HEADER 1 4.51 9-May-09 30-May-09

309 ELM-PUL-PR-PID-4901 PID -OIL TRAIN-2 FLARE HEADER 1 4.51 9-May-09 30-May-09

310 ELM-PUL-PR-PID-4901 PID -OIL TRAIN-1 FLARE KO DRUM 1 4.51 9-May-09 30-May-09

311 ELM-PUL-PR-PID-4901 PID -OIL TRAIN-2 FLARE KO DRUM 1 4.51 9-May-09 30-May-09

312 ELM-PUL-PR-PID-4901 PID -OIL TRAIN-1 FLARE PACKAGE 1 4.51 9-May-09 30-May-09

313 ELM-PUL-PR-PID-4901 PID -OIL TRAIN-2 FLARE PACKAGE 1 4.51 9-May-09 30-May-09

314 ELM-PUL-PR-PID-5101 PID -PRODUCED WATER COLLECTION HEADERS 1 4.51 9-May-09 30-May-09

315 ELM-PUL-PR-PID-5110 PID -TRAIN 1 - PRODUCED WATER DEGASSER 1 4.51 9-May-09 30-May-09

316 ELM-PUL-PR-PID-5110 PID -TRAIN 2 - PRODUCED WATER DEGASSER 1 4.51 9-May-09 30-May-09

317 ELM-PUL-PR-PID-5111 PID -TRAIN 1 - PRODUCED WATER DEGASSER 1 4.51 9-May-09 30-May-09
(PRODUCTED WATER TREATMENT 2)
318 ELM-PUL-PR-PID-5122 PID -TRAIN 1 - INDUCED GAS FLOTATION UNIT 1 4.51 9-May-09 30-May-09

319 ELM-PUL-PR-PID-5122 PID -TRAIN 2 - INDUCED GAS FLOTATION UNIT 1 4.51 9-May-09 30-May-09

320 ELM-PUL-PR-PID-5123 PID -TRAIN 1 - INDUCED GAS FLOTATION 1 4.51 9-May-09 30-May-09
UNIT(PRODUCTED WATER TREATMENT 2)
321 ELM-PUL-PR-PID-5126 PID -TRAIN 1 - TREATED PRODUCED WATER PUMPS 1 4.51 9-May-09 30-May-09

322 ELM-PUL-PR-PID-5126 PID -TRAIN 2 - TREATED PRODUCED WATER PUMPS 1 4.51 9-May-09 30-May-09

323 ELM-PUL-PR-PID-5127 PID -TRAIN 1 - TREATED PRODUCED WATER PUMPS 1 4.51 9-May-09 30-May-09
(PRODUCTED WATER TREATMENT 2)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 9 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

324 ELM-PUL-PR-PID-5202 PID -INJECTION WATER SURGE TANK 1 4.51 9-May-09 30-May-09

325 ELM-PUL-PR-PID-5203 PID -INJECTION WATER SURGE TANK (PRODUCTED 1 4.51 9-May-09 30-May-09
WATER TREATMENT 2)
326 ELM-PUL-PR-PID-5204 PID -WATER INJECTION BOOSTER PUMPS 1 4.51 9-May-09 30-May-09

327 ELM-PUL-PR-PID-5205 PID -WATER INJECTION BOOSTER PUMPS (PRODUCTED 1 4.51 9-May-09 30-May-09
WATER TREATMENT 2)
328 ELM-PUL-PR-PID-5209 PID -WATER INJECTION AND DILUTION DISTRIBUTION 1 4.51 9-May-09 30-May-09
MANIFOLD
329 ELM-PUL-PR-PID-5301 PID -HP FUEL GAS SURGE DRUM 1 4.51 9-May-09 30-May-09

330 ELM-PUL-PR-PID-5301 PID -FUEL GAS FILTERS 1 4.51 9-May-09 30-May-09

331 ELM-PUL-PR-PID-5302 PID -FUEL GAS HEATER 1 4.51 9-May-09 30-May-09

332 ELM-PUL-PR-PID-5303 PID -START-UP FUEL GAS HEATER 1 4.51 9-May-09 30-May-09

333 ELM-PUL-PR-PID-5304 PID -LP FUEL GAS SURGE DRUM 1 4.51 9-May-09 30-May-09

334 ELM-PUL-PR-PID-5305 PID -LP FUEL GAS DISTRIBUTION HEADER 1 4.51 9-May-09 30-May-09

335 ELM-PUL-PR-PID-5306 PID -HP FUEL GAS DISTRIBUTION HEADER 1 4.51 9-May-09 30-May-09

336 ELM-PUL-PR-PID-5410 PID -OILY SLUDGE EVAPORATION POND 1 4.51 9-May-09 30-May-09

337 ELM-PUL-PR-PID-5420 PID -CLEAN SLUDGE EVAPORATION POND 1 4.51 9-May-09 30-May-09

338 ELM-PUL-PR-PID-5501 PID -NGL FLARE HEADER 1 4.51 9-May-09 30-May-09

339 ELM-PUL-PR-PID-5500 PID -NGL FLARE KO DRUM 1 4.51 9-May-09 30-May-09

340 ELM-PUL-PR-PID-5500 PID -NGL FLARE PACKAGE 1 4.51 9-May-09 30-May-09

341 ELM-PUL-PR-PID-6102 PID -MIO-PLIOCENE SOURCE WATER WELL COLLECTOR 1 4.51 9-May-09 30-May-09
HEADER
342 ELM-PUL-PR-PID-6110 PID -SOURCE WATER STORAGE TANK AND PUMPS 1 0.00 9-May-09 30-May-09

343 ELM-PUL-PR-PID-6150 PID -UTILITY WATER DISTRIBUTION 1 0.00 9-May-09 30-May-09

344 ELM-PUL-PR-PID-6201 PID -POTABLE WATER DISTRIBUTION 1 0.00 9-May-09 30-May-09

345 ELM-PUL-PR-PID-6701 PID -AIR COMPRESSORS 1 4.51 9-May-09 30-May-09

346 ELM-PUL-PR-PID-6705 PID -AIR FILTER/DRYER PACKAGES 1 4.51 9-May-09 30-May-09

347 ELM-PUL-PR-PID-6708 PID -INSTRUMENT AIR RECEIVERS 1 4.51 9-May-09 30-May-09

348 ELM-PUL-PR-PID-6710 PID -PLANT AIR RECEIVER 1 4.51 9-May-09 30-May-09

349 ELM-PUL-PR-PID-6720 PID -INSTRUMENT AIR DISTRIBUTION 1 4.51 9-May-09 30-May-09

350 ELM-PUL-PR-PID-6730 PID -PLANT AIR DISTRIBUTION 1 4.51 9-May-09 30-May-09

351 ELM-PUL-PR-PID-7001 PID -SLUG CATCHER AREA OILY WATER SUMP AND 1 4.51 9-May-09 30-May-09
PUMPS
352 ELM-PUL-PR-PID-7004 PID -OIL TRAIN 1 & 2 AREA OILY WATER SUMP AND 1 4.51 9-May-09 30-May-09
PUMPS
353 ELM-PUL-PR-PID-7006 PID -DEHYDRATION TRAIN 1 & 2 AREA OILY WATER 1 4.51 9-May-09 30-May-09
SUMP AND PUMPS
354 ELM-PUL-PR-PID-7008 PID -NGL TRAIN 1 & 2 AREA OILY WATER SUMP AND 1 4.51 9-May-09 30-May-09
PUMPS
355 ELM-PUL-PR-PID-7010 PID -RE-INJECTION COMPRESSOR AREA OILY WATER 1 4.51 9-May-09 30-May-09
SUMP AND PUMPS
356 ELM-PUL-PR-PID-7012 PID -HOT OIL AREA OILY WATER SUMP AND PUMPS 1 4.51 9-May-09 30-May-09

357 ELM-PUL-PR-PID-7014 PID -FLARE KO DRUM AREA OILY WATER SUMP AND 1 4.51 9-May-09 30-May-09
PUMPS
358 ELM-PUL-PR-PID-7030 PID -OILY WATER COLECTOR 1 4.51 9-May-09 30-May-09

359 ELM-PUL-PR-PID-7031 PID -CPI SEPARATOR 1 4.51 9-May-09 30-May-09

360 ELM-PUL-PR-PID-7101 PID -NITROGEN GENERATOR PACKAGE 1 4.51 9-May-09 30-May-09

361 ELM-PUL-PR-PID-7102 PID -NITROGEN SURGE DRUM 1 4.51 9-May-09 30-May-09

362 ELM-PUL-PR-PID-7103 PID -HP NITROGEN SYSTEM 1 4.51 9-May-09 30-May-09

363 ELM-PUL-PR-PID-7110 PID -NITROGEN DISTRIBUTION 1 4.51 9-May-09 30-May-09

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 10 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

364 ELM-PUL-PR-PID-7301 PID -SANITARY LIFT STATION & SEWAGE TREATMENT 1 4.51 9-May-09 30-May-09
PACKAGE
365 ELM-PUL-PR-PID-7501 PID -DIESEL DISTRIBUTION 1 4.51 9-May-09 30-May-09

366 ELM-PUL-PR-PSD-0001 PSFD- CENTRAL PROCESSING FACIITY 1 14.40 9-May-09 30-May-09

367 ELM-PUL-PR-LST-0002 LINE LIST 1 24.00 9-May-09 30-May-09

368 ELM-PUL-PR-DAT-0001 1 1.06 2-Apr-09 14-Apr-09


PDS - OIL RUN DOWN COOLER
369 ELM-PUL-PR-DAT-0002 1 1.06 2-Apr-09 14-Apr-09
PDS - STABILIZED CONDENSATE CONDENSER
370 ELM-PUL-PR-DAT-0003 1 1.06 2-Apr-09 14-Apr-09
PDS - 1ST STAGE ASSOCIATED GAS SUCTION COOLER

371 ELM-PUL-PR-DAT-0004 1 1.06 2-Apr-09 14-Apr-09


PDS - 2ND STAGE ASSOCIATED GAS SUCTION COOLER

372 ELM-PUL-PR-DAT-0005 1 1.06 2-Apr-09 14-Apr-09


PDS - 2ND STAGE ASSOCIATED GAS AFTERCOOLER
373 ELM-PUL-PR-DAT-0006 1 1.06 2-Apr-09 14-Apr-09
PDS - BOOSTER COMPRESSOR AFTERCOOLER
374 ELM-PUL-PR-DAT-0007 1 1.06 11-Apr-09 23-Apr-09
PDS - GAS DEHYDRATION INLET GAS COOLER
375 ELM-PUL-PR-DAT-0008 1 1.06 11-Apr-09 23-Apr-09
PDS - GAS DEHYDRATION REGENERATION GAS COOLER

376 ELM-PUL-PR-DAT-0009 1 1.06 2-Apr-09 14-Apr-09


PDS - NGL EXPANDER COMPRESSOR AFTERCOOLER
377 ELM-PUL-PR-DAT-0010 1 1.06 5-Apr-09 17-Apr-09
PDS - DEBUTANIZER CONDENSER
378 ELM-PUL-PR-DAT-0013 1 1.06 5-Apr-09 17-Apr-09
PDS - NGL CONDENSATE RUNDOWN COOLER
379 ELM-PUL-PR-DAT-0014 1 1.06 5-Apr-09 17-Apr-09
PDS - LPG RUNDOWN COOLER
380 ELM-PUL-PR-DAT-0015 1 1.06 2-Apr-09 14-Apr-09
PDS - 1ST STAGE RESIDUE GAS AFTERCOOLER
381 ELM-PUL-PR-DAT-0016 1 1.06 2-Apr-09 14-Apr-09
PDS - 2ND STAGE RESIDUE GAS AFTERCOOLER

382 ELM-PUL-PR-DAT-0017 1 1.06 2-Apr-09 14-Apr-09


PDS - 1ST STAGE INJECTION GAS AFTERCOOLER
383 ELM-PUL-PR-DAT-0018 1 1.06 2-Apr-09 14-Apr-09
PDS - 2ND STAGE INJECTION GAS AFTERCOOLER
384 ELM-PUL-PR-DAT-0019 1 1.06 29-Mar-09 10-Apr-09
PDS - HOT OIL TRIM COOLER
385 ELM-PUL-PR-DAT-0020 1 1.06 11-Apr-09 23-Apr-09
PDS - NGL TRAIN 1 HOT OIL TRIM COOLER
386 ELM-PUL-PR-DAT-0022 1 1.06 2-Apr-09 14-Apr-09
PDS - OIL EXPORT PUMP RECYCLE COOLER
387 ELM-PUL-PR-DAT-0023 1 1.06 2-Apr-09 14-Apr-09
PDS - CONDENSATE EXPORT PUMP RECYCLE COOLER

388 ELM-PUL-PR-DAT-0024 1 1.06 5-Apr-09 17-Apr-09


PDS - LPG EXPORT PUMP RECYCLE COOLER
389 ELM-PUL-PR-DAT-0025 1 1.06 14-Mar-09 26-Mar-09
PDS - OIL STABILIZER
390 ELM-PUL-PR-DAT-0026 1 1.06 14-Mar-09 26-Mar-09
PDS - DEETHANIZER
391 ELM-PUL-PR-DAT-0027 1 1.06 14-Mar-09 26-Mar-09
PDS - DEBUTANIZER
392 ELM-PUL-PR-DAT-0029 1 1.06 15-Mar-09 27-Mar-09
PDS - ABSORBER
393 ELM-PUL-PR-DAT-0031 1 1.06 15-Mar-09 27-Mar-09
PDS - HOT OIL FIRED HEATER (TRAIN 1 & TRAIN 2)

394 ELM-PUL-PR-DAT-0032 1 1.06 16-Mar-09 28-Mar-09


PDS - NGL TRAIN 1 HOT OIL FIRED HEATER
395 ELM-PUL-PR-DAT-0034 1 1.06 16-Mar-09 28-Mar-09
PDS - ASSOCIATED GAS COMPRESSOR
396 ELM-PUL-PR-DAT-0035 1 1.06 16-Mar-09 28-Mar-09
PDS - BOOSTER COMPRESSOR
397 ELM-PUL-PR-DAT-0037 1 1.06 26-Mar-09 7-Apr-09
PDS - NGL EXPANDER EXPANDER/COMPRESSOR
398 ELM-PUL-PR-DAT-0040 1 1.06 16-Apr-09 28-Apr-09
PDS - HP SEPARATOR FEED PRE-HEATER
399 ELM-PUL-PR-DAT-0041 1 1.06 16-Apr-09 28-Apr-09
PDS - OIL STABILIZER FEED HEATER
400 ELM-PUL-PR-DAT-0042 1 1.06 16-Apr-09 28-Apr-09
PDS - CONDENSATE FLASH HEATER
401 ELM-PUL-PR-DAT-0043 1 1.06 16-Apr-09 28-Apr-09
PDS - OIL STABILIZER REBOILER
402 ELM-PUL-PR-DAT-0044 1 1.06 16-Apr-09 28-Apr-09
PDS - DESALTER WASH WATER HEATER
403 ELM-PUL-PR-DAT-0045 1 1.06 9-Apr-09 21-Apr-09
PDS - NGL FEED GAS GAS EXCHANGER
404 ELM-PUL-PR-DAT-0046 1 1.06 9-Apr-09 21-Apr-09
PDS - NGL FEED GAS LIQUID EXCHANGER

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 11 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

405 ELM-PUL-PR-DAT-0047 1 1.06 26-Mar-09 7-Apr-09


PDS - DEETHANIZER REBOILER
406 ELM-PUL-PR-DAT-0048 1 1.06 30-Mar-09 11-Apr-09
PDS - DEBUTANIZER FEED HEATER
407 ELM-PUL-PR-DAT-0049 1 1.06 26-Mar-09 7-Apr-09
PDS - DEBUTANIZER REBOILER
408 ELM-PUL-PR-DAT-0050 1 1.06 9-Apr-09 21-Apr-09
PDS - NGL FEED PRE-COOLER
409 ELM-PUL-PR-DAT-0051 1 1.06 30-Mar-09 11-Apr-09
PDS - DEETHANIZER OVERHEAD CONDENSER
410 ELM-PUL-PR-DAT-0052 1 1.06 30-Mar-09 11-Apr-09
PDS - DEBUTANIZER FEED PRODUCT EXCHANGER
411 ELM-PUL-PR-DAT-0054 1 1.06 26-Apr-09 8-May-09
PDS - NGL FLARE KO DRUM HEATER
412 ELM-PUL-PR-DAT-0055 1 1.06 26-Apr-09 8-May-09
PDS - LT FLARE KO DRUM ELECTRICAL HEATER
413 ELM-PUL-PR-DAT-0056 1 1.06 26-Apr-09 8-May-09
PDS - LT CLOSED DRAIN DRUM HEATER
414 ELM-PUL-PR-DAT-0057 1 1.06 26-Apr-09 8-May-09
PDS - HP FUEL GAS HEATER
415 ELM-PUL-PR-DAT-0058 1 1.06 26-Apr-09 8-May-09
PDS - START UP FUEL GAS HEATER
416 ELM-PUL-PR-DAT-0059 1 1.06 26-Mar-09 7-Apr-09
PDS - OIL TRANSFER PUMP
417 ELM-PUL-PR-DAT-0060 1 1.06 26-Apr-09 8-May-09
PDS - STABILIZED OIL TRANSFER PUMPS
418 ELM-PUL-PR-DAT-0061 1 1.06 26-Apr-09 8-May-09
PDS - STABILIZED CONDENSATE TRANSFER PUMPS
419 ELM-PUL-PR-DAT-0062 PDS - 1ST STAGE ASSOCIATED GAS SUCTION DRUM 1 1.06 26-Apr-09 8-May-09
PUMPS
420 ELM-PUL-PR-DAT-0063 1 1.06 21-Mar-09 2-Apr-09
PDS - DEBUTANIZER REFLUX PUMPS
421 ELM-PUL-PR-DAT-0065 1 1.06 21-Mar-09 2-Apr-09
PDS - DEETHANIZER FEED FUMP
422 ELM-PUL-PR-DAT-0066 1 1.06 26-Mar-09 7-Apr-09
PDS - OIL BOOSTER PUMPS
423 ELM-PUL-PR-DAT-0067 1 1.06 26-Mar-09 7-Apr-09
PDS - OIL EXPORT PUMPS
424 ELM-PUL-PR-DAT-0068 1 1.06 26-Mar-09 7-Apr-09
PDS - OIL/CONDENSATE RERUN PUMPS
425 ELM-PUL-PR-DAT-0069 1 1.06 26-Mar-09 7-Apr-09
PDS - CONDENSATE BOOSTER PUMPS
426 ELM-PUL-PR-DAT-0070 1 1.06 26-Mar-09 7-Apr-09
PDS - CONDENSATE EXPORT PUMPS
427 ELM-PUL-PR-DAT-0071 1 1.06 23-Mar-09 4-Apr-09
PDS - LPG RERUN PUMPS
428 ELM-PUL-PR-DAT-0072 1 1.06 23-Mar-09 4-Apr-09
PDS - LPG BOOSTER PUMPS
429 ELM-PUL-PR-DAT-0073 1 1.06 23-Mar-09 4-Apr-09
PDS - LPG EXPORT PUMPS
430 ELM-PUL-PR-DAT-0074 1 1.06 30-Mar-09 11-Apr-09
PDS - HOT OIL RECIRCULATION PUMPS
431 ELM-PUL-PR-DAT-0075 1 1.06 3-Apr-09 15-Apr-09
PDS - HOT OIL CIRCULATION PUMPS NGL
432 ELM-PUL-PR-DAT-0076 1 1.06 26-Apr-09 8-May-09
PDS - TREATED PRODUCED WATER PUMPS
433 ELM-PUL-PR-DAT-0077 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL DRAIN PUMP
434 ELM-PUL-PR-DAT-0078 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL STORAGE PUMPS
435 ELM-PUL-PR-DAT-0080 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL DRAIN PUMP
436 ELM-PUL-PR-DAT-0081 1 1.06 11-Apr-09 23-Apr-09
PDS - OIL TRAIN 1 FLARE KO DRUM PUMP
437 ELM-PUL-PR-DAT-0082 1 1.06 11-Apr-09 23-Apr-09
PDS - OIL TRAIN 2 FLARE KO DRUM PUMP
438 ELM-PUL-PR-DAT-0083 1 1.06 11-Apr-09 23-Apr-09
PDS - H P FLARE KO DRUM PUMPS
439 ELM-PUL-PR-DAT-0084 1 1.06 11-Apr-09 23-Apr-09
PDS - LP FLARE KO DRUM PUMPS
440 ELM-PUL-PR-DAT-0085 1 1.06 11-Apr-09 23-Apr-09
PDS - AP FLARE KO DRUM PUMPS
441 ELM-PUL-PR-DAT-0086 1 1.06 26-Apr-09 8-May-09
PDS - CLOSED DRAIN DRUM PUMPS
442 ELM-PUL-PR-DAT-0087 1 1.06 26-Apr-09 8-May-09
PDS - COMMON CLOSED DRAIN DRUM PUMP
443 ELM-PUL-PR-DAT-0088 1 1.06 26-Apr-09 8-May-09
PDS - LT CLOSED DRAIN DRUM PUMPS
444 ELM-PUL-PR-DAT-0089 PDS - EXPORT LAUNCHER AREA LT CLOSED DRAIN DRUM 1 1.06 26-Apr-09 8-May-09
PUMPS
445 ELM-PUL-PR-DAT-0090 1 1.06 26-Apr-09 8-May-09
PDS - SLUG CATCHER AREA OILY WATER PUMPS

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 12 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

446 ELM-PUL-PR-DAT-0091 1 1.06 26-Apr-09 8-May-09


PDS - OIL TRAIN 1&2 AREA OILY WATER PUMPS
447 ELM-PUL-PR-DAT-0092 1 1.06 26-Apr-09 8-May-09
PDS - DEHYDRATION AREA OILY WATER PUMPS
448 ELM-PUL-PR-DAT-0093 1 1.06 26-Apr-09 8-May-09
PDS - NGL TRAIN AREA OILY WATER PUMPS
449 ELM-PUL-PR-DAT-0094 PDS - REINJECTION COMPRESSOR AREA OILY WATER 1 1.06 26-Apr-09 8-May-09
PUMPS
450 ELM-PUL-PR-DAT-0095 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL AREA OILY WATER PUMPS
451 ELM-PUL-PR-DAT-0096 1 1.06 26-Apr-09 8-May-09
PDS - FLARE KO AREA OILY WATER PUMPS
452 ELM-PUL-PR-DAT-0097 1 1.06 26-Apr-09 8-May-09
PDS - TREATED PRODUCED WATER PUMPS
453 ELM-PUL-PR-DAT-0098 1 1.06 5-Apr-09 17-Apr-09
PDS - WATER INJECTION BOOSTER PUMPS
454 ELM-PUL-PR-DAT-0099 1 1.06 5-Apr-09 17-Apr-09
PDS - WATER INJECTION BOOSTER PUMPS
455 ELM-PUL-PR-DAT-0100 1 1.06 3-Apr-09 15-Apr-09
PDS - SOURCE WATER PUMPS
456 ELM-PUL-PR-DAT-0101 1 1.06 26-Apr-09 8-May-09
PDS - CPI SEPARATOR OIL PUMPS
457 ELM-PUL-PR-DAT-0102 1 1.06 26-Apr-09 8-May-09
PDS - CPI SEPARATOR EFFLUENT PUMPS
458 ELM-PUL-PR-DAT-0103 1 1.06 26-Apr-09 8-May-09
PDS - GAS MOL SIEVE BED FILTERS
459 ELM-PUL-PR-DAT-0105 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL FILTERS (OIL TRAIN 1)
460 ELM-PUL-PR-DAT-0106 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL FILTERS (NGL AREA)
461 ELM-PUL-PR-DAT-0107 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL DRAIN FILTER
462 ELM-PUL-PR-DAT-0108 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL STORAGE FILTER
463 ELM-PUL-PR-DAT-0110 1 1.06 26-Apr-09 8-May-09
PDS - WATER INJECTION COURSE FILTERS
464 ELM-PUL-PR-DAT-0111 1 1.06 26-Apr-09 8-May-09
PDS - WATER INJECTION COURSE FILTERS
465 ELM-PUL-PR-DAT-0112 1 1.06 26-Apr-09 8-May-09
PDS - FUEL GAS FILTERS
466 ELM-PUL-PR-DAT-0113 1 1.06 19-Mar-09 31-Mar-09
PDS - OIL STORAGE TANK
467 ELM-PUL-PR-DAT-0114 1 1.06 19-Mar-09 31-Mar-09
PDS - OIL/CONDENSATE RERUN TANK
468 ELM-PUL-PR-DAT-0115 1 1.06 19-Mar-09 31-Mar-09
PDS - CONDENSATE STORAGE TANK
469 ELM-PUL-PR-DAT-0116 1 1.06 17-Mar-09 29-Mar-09
PDS - HOT OIL STORAGE TANK
470 ELM-PUL-PR-DAT-0117 1 1.06 17-Mar-09 29-Mar-09
PDS - INJECTION WATER SURGE TANK
471 ELM-PUL-PR-DAT-0118 1 1.06 17-Mar-09 29-Mar-09
PDS - INJECTION WATER SURGE TANK
472 ELM-PUL-PR-DAT-0119 1 1.06 17-Mar-09 29-Mar-09
PDS - SOURCE WATER STORAGE TANK
473 ELM-PUL-PR-DAT-0120 1 1.06 26-Apr-09 8-May-09
PDS - SLUG CATCHER AREA OILY WATER SUMP
474 ELM-PUL-PR-DAT-0121 1 1.06 26-Apr-09 8-May-09
PDS - OIL TRAIN 1&2 AREA OILY WATER SUMP
475 ELM-PUL-PR-DAT-0122 PDS - DEHYDRATION TRAIN 1&2 AREA OILY WATER 1 1.06 26-Apr-09 8-May-09
SUMP
476 ELM-PUL-PR-DAT-0123 1 1.06 26-Apr-09 8-May-09
PDS - NGL TRAIN 1&2 AREA OILY WATER SUMP
477 ELM-PUL-PR-DAT-0124 PDS - REINJECTION COMPRESSOR AREA OILY WATER 1 1.06 26-Apr-09 8-May-09
SUMP
478 ELM-PUL-PR-DAT-0125 1 1.06 26-Apr-09 8-May-09
PDS - HOT OIL AREA OILY WATER SUMP
479 ELM-PUL-PR-DAT-0126 1 1.06 26-Apr-09 8-May-09
PDS - FLARE KO AREA OILY WATER SUMP
480 ELM-PUL-PR-DAT-0127 1 1.06 17-Mar-09 29-Mar-09
PDS - LPG RERUN SPHERE
481 ELM-PUL-PR-DAT-0128 1 1.06 17-Mar-09 29-Mar-09
PDS - LPG STORAGE SPHERE
482 ELM-PUL-PR-DAT-0129 1 1.06 16-Apr-09 28-Apr-09
PDS - HP SEPARATOR
483 ELM-PUL-PR-DAT-0130 1 1.06 16-Apr-09 28-Apr-09
PDS - STABILIZED CONDENSATE DRUM
484 ELM-PUL-PR-DAT-0131 1 1.06 16-Apr-09 28-Apr-09
PDS - OIL STABILIZER SIDE DRAW DRUM
485 ELM-PUL-PR-DAT-0132 1 1.06 16-Apr-09 28-Apr-09
PDS - OIL TRANSFER PUMP SURGE DRUM
486 ELM-PUL-PR-DAT-0133 1 1.06 16-Apr-09 28-Apr-09
PDS - 1ST STAGE ASSOCIATED GAS SUCTION DRUM

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 13 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

487 ELM-PUL-PR-DAT-0134 1 1.06 16-Apr-09 28-Apr-09


PDS - 2ND STAGE ASSOCIATED GAS SUCTION DRUM

488 ELM-PUL-PR-DAT-0135 1 1.06 16-Apr-09 28-Apr-09


PDS - BOOSTER COMPRESSOR SUCTION DRUM
489 ELM-PUL-PR-DAT-0140 1 1.06 13-Mar-09 25-Mar-09
PDS - NGL EXPANDER SUCTION DRUM
490 ELM-PUL-PR-DAT-0141 1 1.06 12-Apr-09 24-Apr-09
PDS - DE-BUTANIZER REFLUX DRUM
491 ELM-PUL-PR-DAT-0142 1 1.06 22-Mar-09 3-Apr-09
PDS - 1ST STAGE RESIDUE GAS SUCTION DRUM
492 ELM-PUL-PR-DAT-0143 1 1.06 22-Mar-09 3-Apr-09
PDS - 2ND STAGE RESIDUE GAS SUCTION DRUM
493 ELM-PUL-PR-DAT-0144 1 1.06 13-Mar-09 25-Mar-09
PDS - 1ST STAGE INJECTION GAS SUCTION DRUM
494 ELM-PUL-PR-DAT-0145 1 1.06 13-Mar-09 25-Mar-09
PDS - 2ND STAGE INJECTION GAS SUCTION DRUM
495 ELM-PUL-PR-DAT-0146 1 1.06 26-Apr-09 8-May-09
PDS - BLOCK 208 OIL SLUG CATCHER
496 ELM-PUL-PR-DAT-0147 1 1.06 26-Apr-09 8-May-09
PDS - EMK UNITIZED OIL SLUG CATCHER
497 ELM-PUL-PR-DAT-0148 1 1.06 26-Apr-09 8-May-09
PDS - BLOCK 208 CONDENSATE SLUG CATCHER
498 ELM-PUL-PR-DAT-0149 1 1.06 26-Apr-09 8-May-09
PDS - BLOCK 208 CONDENSATE INLET SEPARATOR
499 ELM-PUL-PR-DAT-0150 1 1.06 26-Apr-09 8-May-09
PDS - OIL/CONDENSATE RERUN FLASH DRUM
500 ELM-PUL-PR-DAT-0151 1 1.06 26-Apr-09 8-May-09
PDS - OIL/CONDENSATE DEGASSING BOOT
501 ELM-PUL-PR-DAT-0153 1 1.06 16-Apr-09 28-Apr-09
PDS - HOT OIL EXPANSION DRUM
502 ELM-PUL-PR-DAT-0154 1 1.06 16-Apr-09 28-Apr-09
PDS - NGL HOT OIL EXPANSION DRUM
503 ELM-PUL-PR-DAT-0155 1 1.06 16-Apr-09 28-Apr-09
PDS - HOT OIL EXPANSION DRUM
504 ELM-PUL-PR-DAT-0156 1 1.06 16-Apr-09 28-Apr-09
PDS - HOT OIL DRAIN DRUM
505 ELM-PUL-PR-DAT-0157 1 1.06 16-Apr-09 28-Apr-09
PDS - HOT OIL DRAIN DRUM
506 ELM-PUL-PR-DAT-0158 1 1.06 16-Apr-09 28-Apr-09
PDS - HP FLARE KO DRUM
507 ELM-PUL-PR-DAT-0159 1 1.06 16-Apr-09 28-Apr-09
PDS - LP FLARE KO DRUM
508 ELM-PUL-PR-DAT-0160 1 1.06 16-Apr-09 28-Apr-09
PDS - HP- LT FLARE KO DRUM
509 ELM-PUL-PR-DAT-0161 1 1.06 16-Apr-09 28-Apr-09
PDS - AP FLARE KO DRUM
510 ELM-PUL-PR-DAT-0162 1 1.06 16-Apr-09 28-Apr-09
PDS - FLARE KO DRUM (OIL TRAIN 1 & TRAIN 2)
511 ELM-PUL-PR-DAT-0163 1 1.06 16-Apr-09 28-Apr-09
PDS - FLARE KO DRUM (NGL AREA)
512 ELM-PUL-PR-DAT-0164 1 1.06 16-Apr-09 28-Apr-09
PDS - WET CLOSED DRAIN DRUM
513 ELM-PUL-PR-DAT-0165 1 1.06 16-Apr-09 28-Apr-09
PDS - COMMON CLOSED DRAIN DRUM
514 ELM-PUL-PR-DAT-0166 1 1.06 16-Apr-09 28-Apr-09
PDS - LT CLOSED DRAIN DRUM
515 ELM-PUL-PR-DAT-0167 1 1.06 16-Apr-09 28-Apr-09
PDS - EXPORT LAUNCHER AREA LT CLOSED DRAIN DRUM

516 ELM-PUL-PR-DAT-0168 1 1.06 16-Apr-09 28-Apr-09


PDS - HP FUEL GAS SURGE DRUM
517 ELM-PUL-PR-DAT-0169 1 1.06 16-Apr-09 28-Apr-09
PDS - LP FUEL GAS SURGE DRUM
518 ELM-PUL-PR-DAT-0170 1 1.06 16-Apr-09 28-Apr-09
PDS - INSTRUMENT AIR RECEIVER
519 ELM-PUL-PR-DAT-0171 1 1.06 16-Apr-09 28-Apr-09
PDS - PLANT AIR RECEIVER
520 ELM-PUL-PR-DAT-0172 1 1.06 16-Apr-09 28-Apr-09
PDS - NITROGEN SURGE DRUM
521 ELM-PUL-PR-DAT-0173 1 1.06 16-Apr-09 28-Apr-09
PDS - HP NITROGEN STORAGE VESSEL
522 ELM-PUL-PR-DAT-0174 1 1.06 16-Apr-09 28-Apr-09
PDS - HP FLARE KO DRUM
523 ELM-PUL-PR-DAT-0175 1 1.06 16-Apr-09 28-Apr-09
PDS - LP FLARE KO DRUM
524 ELM-PUL-PR-DAT-0176 1 1.06 16-Apr-09 28-Apr-09
PDS - HP- LT FLARE KO DRUM
525 ELM-PUL-PR-DAT-0177 1 1.06 16-Apr-09 28-Apr-09
PDS - AP FLARE KO DRUM
526 ELM-PUL-PR-DAT-0178 1 1.06 16-Apr-09 28-Apr-09
PDS - FLARE KOD (OIL TRAIN 1 & TRAIN 2)
527 ELM-PUL-PR-DAT-0179 1 1.06 16-Apr-09 28-Apr-09
PDS - FLARE KO DRUM (NGL AREA)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 14 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

528 ELM-PUL-PR-DAT-0180 1 1.06 16-Apr-09 28-Apr-09


PDS - DESALTER
529 ELM-PUL-PR-DAT-0181 1 1.06 26-Apr-09 8-May-09
PDS - FLARE PACKAGE (OIL TRAIN 1)
530 ELM-PUL-PR-DAT-0182 1 1.06 26-Apr-09 8-May-09
PDS - FLARE PACKAGE (OIL TRAIN 2)
531 ELM-PUL-PR-DAT-0183 1 1.06 26-Apr-09 8-May-09
PDS - FLARE PACKAGE (NGL AREA)
532 ELM-PUL-PR-DAT-0184 1 1.06 26-Apr-09 8-May-09
PDS - HP FLARE PACKAGE
533 ELM-PUL-PR-DAT-0185 1 1.06 26-Apr-09 8-May-09
PDS - LP FLARE PACKAGE
534 ELM-PUL-PR-DAT-0186 1 1.06 26-Apr-09 8-May-09
PDS - LT FLARE PACKAGE
535 ELM-PUL-PR-DAT-0187 1 1.06 26-Apr-09 8-May-09
PDS - AP FLARE PACKAGE
536 ELM-PUL-PR-DAT-0188 1 1.06 6-Apr-09 18-Apr-09
PDS - PRODUCED WATER TREATMENT PACKAGE
537 ELM-PUL-PR-DAT-0189 1 1.06 11-May-09 23-May-09
PDS - OXYGEN SCAVENGER INJECTION SYSTEM
538 ELM-PUL-PR-DAT-0190 PDS - SCALE INHIBITOR INJECTION SYSTEM 1 1.06 11-May-09 23-May-09
INLET/RECEPTION AREA
539 ELM-PUL-PR-DAT-0191 1 1.06 11-May-09 23-May-09
PDS - SCALE INHIBITOR INJECTION SYSTEM OIL AREA

540 ELM-PUL-PR-DAT-0192 1 1.06 11-May-09 23-May-09


PDS - BIOCIDE INJECTION SYSTEM
541 ELM-PUL-PR-DAT-0193 PDS - METHANOL INJECTION SYSTEM NGL & 1 1.06 11-May-09 23-May-09
DEHYDRATION AREA
542 ELM-PUL-PR-DAT-0194 1 1.06 11-May-09 23-May-09
PDS - POLYELECTROLYTE INJECTION SYSTEM
543 ELM-PUL-PR-DAT-0195 PDS - DEMULSIFIER INJECTION SYSTEM 1 1.06 26-Apr-09 8-May-09
INJECTION/RECEPTION & OIL AREA
544 ELM-PUL-PR-DAT-0196 1 1.06 26-Apr-09 8-May-09
PDS - REVERSE DEMULSIFIER INJECTION SYSTEM
545 ELM-PUL-PR-DAT-0197 PDS - CORROSION INHIBITOR INJECTION SYSTEM 1 1.06 26-Apr-09 8-May-09
INLET/RECEPTION AREA
546 ELM-PUL-PR-DAT-0198 PDS - CORROSION INHIBITOR INJECTION SYSTEM 1 1.06 26-Apr-09 8-May-09
DEHYDRATION AREA
547 ELM-PUL-PR-DAT-0199 PDS - CORROSION INHIBITOR CHEMICAL INJECTION 1 1.06 26-Apr-09 8-May-09
SYSTEM
548 ELM-PUL-PR-DAT-0200 1 1.06 11-Mar-09 21-Mar-09
PDS - AIR COMPRESSORS PACKAGES
549 ELM-PUL-PR-DAT-0201 1 1.06 15-Mar-09 27-Mar-09
PDS - AIR FILTER/DRYER PACKAGES
550 ELM-PUL-PR-DAT-0202 1 1.06 26-Apr-09 8-May-09
PDS - CPI SEPARATOR PACKAGE
551 ELM-PUL-PR-DAT-0203 1 1.06 11-Mar-09 21-Mar-09
PDS - NITROGEN GENERATION PACKAGE
552 ELM-PUL-PR-DAT-0204 1 1.06 16-Mar-09 28-Mar-09
PDS - HP NITROGEN COMPRESSOR PACKAGE
MECHANICAL ROTATING
553 ELM-PUL-MJ-DAT-0001 MECHANICAL DATA SHEET FOR OIL TRANSFER PUMPS 2 0.24 6-Apr-09 16-Apr-09
(P01-2001-A/B)
554 ELM-PUL-MJ-DAT-0004 MECHANICAL DATA SHEET FOR DEBUTANIZER REFLUX 2 0.24 11-May-09 21-May-09
PUMPS (P01-2702-A/B)
555 ELM-PUL-MJ-DAT-0005 MECHANICAL DATA SHEET FOR DEETHANIZER FEED 2 0.24 11-May-09 21-May-09
PUMPS ( P01-2703-A/B)
556 ELM-PUL-MJ-DAT-0006 MECHANICAL DATA SHEET FOR HOT OIL 2 0.24 6-Apr-09 16-Apr-09
RECIRCULATION PUMPS (P01-4101-A/B/C)
557 ELM-PUL-MJ-DAT-0007 2 0.24 6-Apr-09 16-Apr-09
MECHANICAL DATA SHEET FOR HOT OIL CIRCULATION
PUMPS NGL AREA ( P01-4102-A/B/C)

558 ELM-PUL-MJ-DAT-0008 MECHANICAL DATA SHEET FOR OIL TRANSFER PUMP 2 0.24 6-Apr-09 16-Apr-09
(P02-2001-A/B)
559 ELM-PUL-MJ-DAT-0011 2 0.24 6-Apr-09 16-Apr-09
MECHANICAL DATA SHEET FOR HOT OIL
RECIRCULATION PUMPS OIL AREA (P02-4101-A/B/C)

560 ELM-PUL-MJ-DAT-0012 MECHANICAL DATA SHEET FOR OIL BOOSTER PUMPS 2 0.24 6-Apr-09 16-Apr-09
(P08-2101-A/B/C)
561 ELM-PUL-MJ-DAT-0013 MECHANICAL DATA SHEET FOR OIL EXPORT PUMPS ( 1 0.24 6-Apr-09 16-Apr-09
P08-2102-A/B/C)
562 ELM-PUL-MJ-DAT-0014 MECHANICAL DATA SHEET FOR OIL / CONDENSATE RE- 2 0.24 11-May-09 21-May-09
RUN PUMPS ( P08-2104-A/B)
563 ELM-PUL-MJ-DAT-0015 MECHANICAL DATA SHEET FOR CONDENSATE BOOSTER 2 0.24 11-May-09 21-May-09
PUMPS (P08-2301-A/B/C)
564 ELM-PUL-MJ-DAT-0016 MECHANICAL DATA SHEET FOR CONDENSATE EXPORT 1 0.24 6-Apr-09 16-Apr-09
PUMPS (P08-2302-A/B/C)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 15 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

565 ELM-PUL-MJ-DAT-0017 MECHANICAL DATA SHEET FOR LPG RE-RUN PUMPS (P08- 2 0.24 11-May-09 21-May-09
2401-A/B)
566 ELM-PUL-MJ-DAT-0018 MECHANICAL DATA SHEET FOR LPG BOOSTER PUMPS 2 0.24 11-May-09 21-May-09
(P08-2402-A/B/C)
567 ELM-PUL-MJ-DAT-0019 MECHANICAL DATA SHEET FOR LPG EXPORT PUMPS 1 0.24 6-Apr-09 16-Apr-09
(P08-2403-A/B/C)
568 ELM-PUL-MJ-DAT-0020 MECHANICAL DATA SHEET FOR HOT OIL DRAIN DRUM 2 0.24 17-May-09 27-May-09
PUMPS (P08-4101 A/B)
569 ELM-PUL-MJ-DAT-0022 MECHANICAL DATA SHEET FOR HP FLARE KO DRUM 2 0.24 11-May-09 21-May-09
PUMPS (P08-4401-A/B)
570 ELM-PUL-MJ-DAT-0023 MECHANICAL DATA SHEET FOR LOW PRESSURE FLARE 2 0.24 11-May-09 21-May-09
KO DRUM PUMPS (P08-4501-A/B)
571 ELM-PUL-MJ-DAT-0024 MECHANICAL DATA SHEET FOR AP FLARE KO DRUM 2 0.24 11-May-09 21-May-09
PUMPS (P08-4701-A/B)
572 ELM-PUL-MJ-DAT-0025 MECHANICAL DATA SHEET FOR CLOSED DRAINS DRUM 2 0.24 17-May-09 27-May-09
PUMPS (P08-4801-A/B)
573 ELM-PUL-MJ-DAT-0026 MECHANICAL DATA SHEET FOR OFF SPEC AREA CLOSED 2 0.24 17-May-09 27-May-09
DRAINS DRUM PUMPS (P08-4802-A/B)
574 ELM-PUL-MJ-DAT-0027 MECHANICAL DATA SHEET FOR LT CLOSED DRAINS 2 0.24 17-May-09 27-May-09
DRUM PUMPS (P08-4803-A/B)
575 ELM-PUL-MJ-DAT-0028 MECHANICAL DATA SHEET FOR SLUG CATCHER AREA 2 0.24 17-May-09 27-May-09
OILY WATER PUMPS (P08-4901-A/B)
576 ELM-PUL-MJ-DAT-0029 MECHANICAL DATA SHEET FOR OIL TRAIN 1&2 AREA 2 0.24 17-May-09 27-May-09
OILY WATER PUMPS (P08-4902-A/B)
577 ELM-PUL-MJ-DAT-0030 2 0.24 17-May-09 27-May-09
MECHANICAL DATA SHEET FOR BOOSTER COMPRESSOR
AREA OILY WATER PUMPS (P08-4903-A/B)

578 ELM-PUL-MJ-DAT-0031 MECHANICAL DATA SHEET FOR NGL AREA TRAIN 1 OILY 2 0.24 17-May-09 27-May-09
WATER PUMPS (P08-4904-A/B)
579 ELM-PUL-MJ-DAT-0032 2 0.24 17-May-09 27-May-09
MECHANICAL DATA SHEET FOR REINJECTION
COMPRESSOR AREA OILY WATER PUMPS (P08-4905-A/B)

580 ELM-PUL-MJ-DAT-0033 MECHANICAL DATA SHEET FOR HOT OIL STORAGE AREA 2 0.24 17-May-09 27-May-09
OILY WATER PUMPS (P08-4906-A/B)
581 ELM-PUL-MJ-DAT-0034 MECHANICAL DATA SHEET FOR FLARE KO AREA OILY 2 0.24 17-May-09 27-May-09
WATER PUMPS (P08-4907-A/B)
582 ELM-PUL-MJ-DAT-0035 MECHANICAL DATA SHEET FOR WATER INJECTION 2 0.24 6-Apr-09 16-Apr-09
BOOSTER PUMPS ( P08-5201-A/B/C/D)
583 ELM-PUL-MJ-DAT-0036 MECHANICAL DATA SHEET FOR SOURCE WATER PUMPS ( 2 0.24 6-Apr-09 16-Apr-09
P08-6101-A/B)
584 ELM-PUL-MJ-DAT-0037 MECHANICAL DATA SHEET FOR CPI SEPARATOR OIL 2 0.24 17-May-09 27-May-09
PUMPS (P08-7001-A/B)
585 ELM-PUL-MJ-DAT-0038 MECHANICAL DATA SHEET FOR CPI SEPARATOR 2 0.24 17-May-09 27-May-09
EFFLUENT PUMPS (P08-7002-A/B)
586 ELM-PUL-MJ-DAT-0039 MECHANICAL DATA SHEET FOR OIL TRAIN 1 FLARE KO 2 0.24 11-May-09 21-May-09
DRUM PUMPS (P01-4908 A/B)
587 ELM-PUL-MJ-DAT-0040 MECHANICAL DATA SHEET FOR OIL TRAIN 2 FLARE KO 2 0.24 11-May-09 21-May-09
DRUM PUMPS (P02-5001 A/B)
588 ELM-PUL-MJ-DAT-0042 MECHANICAL DATA SHEET FOR TREATED PRODUCED 2 0.00 17-May-09 27-May-09
WATER PUMPS (P01-5101-A/B)
589 ELM-PUL-MJ-DAT-0043 MECHANICAL DATA SHEET FOR TREATED PRODUCED 2 0.00 17-May-09 27-May-09
WATER PUMPS (P02-5101-A/B)
590 ELM-PUL-MJ-DAT-0044 MECHANICAL DATA SHEET FOR TREATED PRODUCED 2 0.00 17-May-09 27-May-09
WATER PUMPS (P08-5101-A/B)
591 ELM-PUL-MJ-DAT-0045 MECHANICAL DATA SHEET FOR WATER INJECTION 2 0.24 6-Apr-09 16-Apr-09
BOOSTER PUMPS ( P08-5202-A/B)
592 ELM-PUL-MJ-DAT-0046 2 0.24 17-May-09 27-May-09
MECHANICAL DATA SHEET FOR EXPORT LAUNCHER
AREA LT CLOSED DRAIN DRUM PUMPS (P08-4804 A/B)

593 ELM-PUL-MJ-DAT-0047 MECHANICAL DATA SHEET FOR HOT OIL DRAIN PUMPS 2 0.00 17-May-09 27-May-09
NGL AND HBNS AREA (P08-4104 A/B)
594 ELM-PUL-MZ-DAT-0048 MECHANICAL DATA SHEET FOR ELECTRIC MOTOR 2 0.24 17-May-09 27-May-09
DRIVEN FIRE WATER PUMP (P08-6302-A/B)
595 ELM-PUL-MZ-DAT-0049 MECHANICAL DATA SHEET FOR DIESEL ENGINE DRIVEN 2 0.24 17-May-09 27-May-09
FIRE WATER PUMP (P08-6303-A/B)
596 ELM-PUL-MZ-DAT-0050 MECHANICAL DATA SHEET FOR FIRE WATER JOCKEY 2 0.24 17-May-09 27-May-09
PUMPS (P08-6304-A/B)
597 ELM-PUL-MJ-DAT-0051 MECHANICAL DATA SHEET FOR ASSOCIATED GAS 1 0.48 27-Mar-09 6-Apr-09
COMPRESSOR PACKAGE (X01, X02, X03-2502)
598 ELM-PUL-MJ-DAT-0052 MECHANICAL DATA SHEET FOR BOOSTER COMPRESSOR 1 0.48 27-Mar-09 6-Apr-09
PACKAGE (X01, X02, X03-2503)
599 ELM-PUL-MJ-DAT-0053 MECHANICAL DATA SHEET FOR GAS DEHYDRATION 1 0.48 27-Mar-09 6-Apr-09
REGEN COMPRESSOR (X01-2601)
600 ELM-PUL-MJ-DAT-0054 MECHANICAL DATA SHEET FOR HP NITROGEN 2 0.24 17-May-09 27-May-09
COMPRESSOR (X08-7102A/B)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 16 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

601 ELM-PUL-MJ-DAT-0055 MECHANICAL DATA SHEET FOR NGL EXPANDER 1 0.48 26-Apr-09 6-May-09
COMPRESSOR PACKAGE (X01-2701/X02-2701)
602 ELM-PUL-MJ-DAT-0056 MECHANICAL DATA SHEET FOR RESIDUE GAS 1 0.72 26-Apr-09 6-May-09
COMPRESSOR (X01-2702, X02-2702)
603 ELM-PUL-MJ-DAT-0057 MECHANICAL DATA SHEET FOR INJECTION GAS 1 0.72 26-Apr-09 6-May-09
COMPERSSOR (X01-2901, X02-2901 & X03-2901)
604 ELM-PUL-MJ-DAT-0070 2 0.48 18-Mar-09 28-Mar-09
MECHANICAL DATA SHEET FOR INSTRUMENT AIR
COMPRESSOR & DRYER PACKAGES (X08-6701 A/B/C/D)

605 ELM-PUL-MJ-REQ-0051 REQUISITION - ELECTRIC MOTOR DRIVEN COMPRESSOR 1 1.44 5-Apr-09 15-Apr-09
PACKAGES
606 ELM-PUL-MJ-REQ-0052 1 1.44 15-Apr-09 25-Apr-09
REQUISITION - HEAVY DUTY HORIZONTAL PUMPS
607 ELM-PUL-MJ-REQ-0053 1 1.44 5-Apr-09 15-Apr-09
REQUISITION - GT DRIVEN COMPRESSOR PACKAGES

608 ELM-PUL-MJ-REQ-0054 1 4.80 15-Apr-09 25-Apr-09


REQUISITION - NGL EXPANDER COMPRESSOR PACKAGES

609 ELM-PUL-MZ-REQ-0055 2 1.44 17-May-09 27-May-09


REQUISITION - FIREWATER PUMPS PACKAGE
610 ELM-PUL-MJ-REQ-0056 2 1.44 11-May-09 21-May-09
REQUISITION - VERTICAL CAN PUMPS
611 ELM-PUL-MJ-REQ-0057 REQUISITION - INSTRUMENT AIR COMPRESSOR & DRYER 2 1.44 26-Mar-09 5-Apr-09
PACKAGE
612 ELM-PUL-MJ-REQ-0058 2 1.44 17-May-09 27-May-09
REQUISITION - NITROGEN GENERATION PACKAGE
613 ELM-PUL-MJ-REQ-0060 REQUISITION - GAS DEHYDRATION REGENERATION 1 1.44 27-Mar-09 6-Apr-09
COMPRESSOR PACKAGE
614 ELM-PUL-MJ-REQ-0063 2 1.44 17-May-09 27-May-09
REQUISITION - VERTICAL SUMP PUMPS
615 ELM-PUL-MJ-REQ-0064 2 1.44 17-May-09 27-May-09
REQUISITION - LIGHT DUTY PUMPS (ANSI)
616 ELM-PUL-MJ-TRQ-0001 TECHNICAL REQUISITION FOR PROCESS CENTRIFUGAL 1 1.44 5-Apr-09 25-Apr-09
PUMPS (API 610)
617 ELM-PUL-MJ-TRQ-0002 TECHNICAL REQUISITION FOR ELECTRIC MOTOR DRIVEN 1 1.44 26-Mar-09 15-Apr-09
COMPRESSOR PACKAGES
618 ELM-PUL-MJ-TRQ-0003 TECHNICAL REQUISITION FOR GT DRIVEN GAS 1 1.44 26-Mar-09 15-Apr-09
COMPRESSOR PACKAGES
619 ELM-PUL-MJ-TRQ-0005 TECHNICAL REQUISITION FOR NGL EXPANDER 1 1.44 5-Apr-09 25-Apr-09
COMPRESSOR
620 ELM-PUL-MJ-TRQ-0006 TECHNICAL REQUISITION FOR NITROGEN GENERATION 2 1.44 7-May-09 27-May-09
PACKAGE
621 ELM-PUL-MJ-TRQ-0007 TECHNICAL REQUISITION FOR GAS DEHYDRATION 1 1.44 17-Mar-09 6-Apr-09
REGENERATION COMPRESSOR PACKAGE
622 ELM-PUL-MJ-TRQ-0008 TECHNICAL REQUISITION FOR INSTRUMENT AIR 2 1.44 16-Mar-09 5-Apr-09
COMPRESSOR & DRYER PACKAGE
623 ELM-PUL-MZ-TRQ-0009 TECHNICAL REQUISITION FOR FIREWATER PUMPS 2 1.44 7-May-09 27-May-09
PACKAGE
624 ELM-PUL-MJ-TBE-0001 1 4.80 16-May-09 29-May-09
TBE - HEAVY DUTY PUMPS
625 ELM-PUL-MJ-TBE-0002 TBE - ELECTRIC MOTOR DRIVEN COMPRESSOR 1 9.60 6-May-09 21-May-09
PACKAGES
626 ELM-PUL-MJ-TBE-0003 1 9.60 6-May-09 21-May-09
TBE - GT DRIVEN COMPRESSOR PACKAGES
627 ELM-PUL-MJ-TBE-0004 1 14.40 16-May-09 31-May-09
TBE - NGL EXPANDER COMPRESSOR
628 ELM-PUL-MJ-TBE-0006 4 4.80 11-Jun-09 25-Jun-09
TBE - VERTICAL CAN PUMPS
629 ELM-PUL-MJ-TBE-0007 TBE - INSTRUMENT AIR COMPRESSOR & DRYER 4 4.80 26-Apr-09 3-May-09
PACKAGE
630 ELM-PUL-MJ-TBE-0010 TBE - GAS DEHYDRATION REGENERATION COMPRESSOR 1 9.60 27-Apr-09 19-May-09
PACKAGE
631 ELM-PUL-HV-CAL-0001 COOLING / HEATING LOAD CALCULATIONS FOR 2 1.92 31-Mar-09 20-Apr-09
CONTROL BUILDING
632 ELM-PUL-HV-CAL-0003 COOLING / HEATING LOAD CALCULATIONS FOR MAIN 2 1.92 10-Apr-09 30-Apr-09
SWITCH GEAR BUILDING
MECHANICAL ROTATING
633 ELM-PUL-HV-CAL-0004 COOLING / HEATING LOAD CALCULATIONS FOR UTILITY 2 1.92 31-Mar-09 20-Apr-09
SWITCH GEAR BUILDING
634 ELM-PUL-MD-DAT-0001 MECHANICAL DATA SHEET FOR OIL STABILIZER (C01- 2 2.11 26-Apr-09 6-May-09
2001/C02-2001)
635 ELM-PUL-MD-DAT-0002 MECHANICAL DATA SHEET FOR DEBUTANIZER (C01- 2 2.11 26-Apr-09 6-May-09
2702)
636 ELM-PUL-MD-DAT-0004 MECHANICAL DATA SHEET FOR DEETHANIZER (C01- 2 2.11 26-Apr-09 6-May-09
2701)
637 ELM-PUL-MD-DAT-0005 2 2.11 26-Apr-09 6-May-09
MECHANICAL DATA SHEET FOR ABSORBER (C01-2703)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 17 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

638 ELM-PUL-MD-DAT-0006 MECHANICAL DATA SHEET FOR GAS DEHYDRATION 2 2.40 17-Mar-09 6-Apr-09
INLET COALESCER (V01-2601)
639 ELM-PUL-MD-DAT-0007 MECHANICAL DATA SHEET FOR GAS MOLECULAR SIEVE 2 2.40 27-Mar-09 6-Apr-09
BED (V01-2602/2603/2604/2605)
640 ELM-PUL-MD-DAT-0008 MECHANICAL DATA SHEET FOR GAS DEHYDRATION FEED 2 2.40 27-Mar-09 6-Apr-09
K.O. DRUM (V01-2607)
641 ELM-PUL-MD-DAT-0009 MECHANICAL DATA SHEET FOR NGL EXPANDER SUCTION 2 2.40 17-Mar-09 6-Apr-09
DRUM (V01-2701)
642 ELM-PUL-MD-DAT-0010 MECHANICAL DATA SHEET FOR 1ST STAGE INJECTION 2 2.40 27-Mar-09 6-Apr-09
GAS SUCTION DRUM (V01/V02/V03-2901)

643 ELM-PUL-MD-DAT-0011 MECHANICAL DATA SHEET FOR 2ND STAGE INJECTION 1 2.40 27-Mar-09 6-Apr-09
GAS SUCTION DRUM (V01/V02/V03-2902)

644 ELM-PUL-MD-DAT-0012 MECHANICAL DATA SHEET FOR HP SEPARATOR 2 2.40 3-Apr-09 13-Apr-09
(V01/V02-2001)
645 ELM-PUL-MD-DAT-0013 MECHANICAL DATA SHEET FOR 1ST STAGE DESALTER 2 2.16 3-Apr-09 13-Apr-09
(V01/V02-2002)
646 ELM-PUL-MD-DAT-0014 MECHANICAL DATA SHEET FOR 2ND STAGE DESALTER 2 2.16 3-Apr-09 13-Apr-09
(V01/V02-2003)
647 ELM-PUL-MD-DAT-0015 MECHANICAL DATA SHEET FOR STABILIZED 2 0.96 3-Apr-09 13-Apr-09
CONDENSATE DRUM (V01/V02-2004)
648 ELM-PUL-MD-DAT-0016 MECHANICAL DATA SHEET FOR OIL STABILIZER SIDE 2 0.96 3-Apr-09 13-Apr-09
DRAW DRUM (V01/V02-2005)
649 ELM-PUL-MD-DAT-0017 MECHANICAL DATA SHEET FOR OIL TRANSFER PUMP 2 0.96 3-Apr-09 13-Apr-09
SURGE DRUM (V01/V02-2006)
650 ELM-PUL-MD-DAT-0018 MECHANICAL DATA SHEET FOR 1ST STAGE ASSOCIATED 2 0.96 3-Apr-09 13-Apr-09
GAS SUCTION DRUM (V01/V02-2501)
651 ELM-PUL-MD-DAT-0019 MECHANICAL DATA SHEET FOR 2ND STAGE ASSOCIATED 2 0.96 3-Apr-09 13-Apr-09
GAS SUCTION DRUM (V01/V02-2502)
652 ELM-PUL-MD-DAT-0020 MECHANICAL DATA SHEET FOR BOOSTER COMPRESSOR 2 0.96 3-Apr-09 13-Apr-09
SUCTION DRUM (V01/V02/V03-2505)
653 ELM-PUL-MD-DAT-0021 MECHANICAL DATA SHEET FOR GAS DEHYDRATION 2 1.44 3-Apr-09 13-Apr-09
REGENERATION GAS SEPARATOR (V01-2606)

654 ELM-PUL-MD-DAT-0022 MECHANICAL DATA SHEET FOR DE-BUTANIZER REFLUX 2 0.96 3-Apr-09 13-Apr-09
DRUM (V01-2702)
655 ELM-PUL-MD-DAT-0023 MECHANICAL DATA SHEET FOR 1ST STAGE RESIDUE GAS 2 0.96 3-Apr-09 13-Apr-09
SUCTION DRUM (V01/V02-2703)
656 ELM-PUL-MD-DAT-0024 MECHANICAL DATA SHEET FOR 2ND STAGE RESIDUE GAS 2 0.96 3-Apr-09 13-Apr-09
SUCTION DRUM (V01/V02-2704)
657 ELM-PUL-MD-DAT-0025 MECHANICAL DATA SHEET FOR HOT OIL EXPANSION 2 0.96 3-Apr-09 13-Apr-09
DRUM - OIL AREA (V01/V02-4101)
658 ELM-PUL-MD-DAT-0026 MECHANICAL DATA SHEET FOR HOT OIL EXPANSION 2 0.96 3-Apr-09 13-Apr-09
DRUM - NGL AREA (V01-4102)
659 ELM-PUL-MD-DAT-0027 MECHANICAL DATA SHEET FOR OIL TRAIN 1 FLARE KO 2 0.96 3-Apr-09 13-Apr-09
DRUM (V01-4901)
660 ELM-PUL-MD-DAT-0028 MECHANICAL DATA SHEET FOR OIL TRAIN 2 FLARE KO 2 0.96 3-Apr-09 13-Apr-09
DRUM (V02-5001)
661 ELM-PUL-MD-DAT-0029 MECHANICAL DATA SHEET FOR BLOCK 208 CONDENSATE 2 0.96 3-Apr-09 13-Apr-09
INLET SEPARATOR (V08-1005)
662 ELM-PUL-MD-DAT-0030 MECHANICAL DATA SHEET FOR OIL/CONDENSATE 2 0.96 3-Apr-09 13-Apr-09
RERUN FLASH DRUM (V08-2102)
663 ELM-PUL-MD-DAT-0031 MECHANICAL DATA SHEET FOR OIL/CONDENSATE 2 0.96 3-Apr-09 13-Apr-09
DEGASSING BOOT (V08-2103)
664 ELM-PUL-MD-DAT-0032 MECHANICAL DATA SHEET FOR HOT OIL DRAIN DRUM - 2 0.96 3-Apr-09 13-Apr-09
OIL AREA (V08-4101)
665 ELM-PUL-MD-DAT-0033 MECHANICAL DATA SHEET FOR HOT OIL DRAIN DRUM - 2 0.96 3-Apr-09 13-Apr-09
NGL AND HBNS AREA (V08-4102)
666 ELM-PUL-MD-DAT-0034 MECHANICAL DATA SHEET FOR HP FLARE KO DRUM (V08- 2 0.96 3-Apr-09 13-Apr-09
4401)
667 ELM-PUL-MD-DAT-0035 MECHANICAL DATA SHEET FOR LP FLARE KO DRUM (V08- 2 0.96 3-Apr-09 13-Apr-09
4501)
668 ELM-PUL-MD-DAT-0036 MECHANICAL DATA SHEET FOR HP-LT FLARE KO DRUM 2 0.96 3-Apr-09 13-Apr-09
(V08-4601)
669 ELM-PUL-MD-DAT-0037 MECHANICAL DATA SHEET FOR AP FLARE KO DRUM (V08- 2 0.96 3-Apr-09 13-Apr-09
4701)
670 ELM-PUL-MD-DAT-0038 MECHANICAL DATA SHEET FOR WET CLOSED DRAIN 2 0.96 3-Apr-09 13-Apr-09
DRUM (V08-4801)
671 ELM-PUL-MD-DAT-0039 MECHANICAL DATA SHEET FOR COMMON CLOSED DRAIN 2 0.96 3-Apr-09 13-Apr-09
DRUM (V08-4802)
672 ELM-PUL-MD-DAT-0040 MECHANICAL DATA SHEET FOR LT CLOSED DRAIN DRUM 2 0.96 3-Apr-09 13-Apr-09
(V08-4803)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 18 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

673 ELM-PUL-MD-DAT-0041 MECHANICAL DATA SHEET FOR EXPORT LAUNCHER 2 0.96 3-Apr-09 13-Apr-09
AREA LT CLOSED DRAIN DRUM (V08-4804)

674 ELM-PUL-MD-DAT-0042 MECHANICAL DATA SHEET FOR HP FUEL GAS SURGE 2 0.96 3-Apr-09 13-Apr-09
DRUM (V08-5301)
675 ELM-PUL-MD-DAT-0043 MECHANICAL DATA SHEET FOR LP FUEL GAS SURGE 2 0.96 3-Apr-09 13-Apr-09
DRUM (V08-5302)
676 ELM-PUL-MD-DAT-0044 MECHANICAL DATA SHEET FOR NGL TRAIN 1 FLARE KO 2 0.96 3-Apr-09 13-Apr-09
DRUM (V08-5501)
677 ELM-PUL-MD-DAT-0045 MECHANICAL DATA SHEET FOR INSTRUMENT AIR 2 0.96 3-Apr-09 13-Apr-09
RECEIVER (V08-6701A/B)
678 ELM-PUL-MD-DAT-0046 MECHANICAL DATA SHEET FOR PLANT AIR RECEIVER 2 0.96 3-Apr-09 13-Apr-09
(V08-6702)
679 ELM-PUL-MD-DAT-0047 MECHANICAL DATA SHEET FOR NITROGEN SURGE DRUM 2 0.96 3-Apr-09 13-Apr-09
(V08-7101)
680 ELM-PUL-MD-DAT-0048 MECHANICAL DATA SHEET FOR HP NITROGEN STORAGE 2 0.96 3-Apr-09 13-Apr-09
VESSEL (V08-7102)
681 ELM-PUL-MD-DAT-0100 MECHANICAL DATA SHEET FOR OIL STORAGE TANK (T08- 2 1.44 10-Apr-09 20-Apr-09
2101 A/B)
682 ELM-PUL-MD-DAT-0101 MECHANICAL DATA SHEET FOR OIL / CONDENSATE 2 1.44 10-Apr-09 20-Apr-09
RERUN TANK (T08-2102)
683 ELM-PUL-MD-DAT-0102 MECHANICAL DATA SHEET FOR CONDENSATE STORAGE 2 1.44 10-Apr-09 20-Apr-09
TANK (T08-2303 A/B)
684 ELM-PUL-MD-DAT-0103 MECHANICAL DATA SHEET FOR HOT OIL STORAGE TANK 2 1.44 10-Apr-09 20-Apr-09
(T08-4101)
685 ELM-PUL-MD-DAT-0104 MECHANICAL DATA SHEET FOR INJECTION WATER 2 1.44 10-Apr-09 20-Apr-09
SURGE TANK (T08-5201)
686 ELM-PUL-MD-DAT-0105 MECHANICAL DATA SHEET FOR INJECTION WATER 2 1.44 10-Apr-09 20-Apr-09
SURGE TANK (T08-5202)
687 ELM-PUL-MD-DAT-0106 MECHANICAL DATA SHEET FOR SOURCE WATER 2 1.44 10-Apr-09 20-Apr-09
STORAGE TANK (T08-6101)
688 ELM-PUL-MD-DAT-0107 MECHANICAL DATA SHEET FOR FIRE WATER STORAGE 2 1.44 10-Apr-09 20-Apr-09
TANK (T08-6301 A/B)
689 ELM-PUL-MD-DAT-0108 MECHANICAL DATA SHEET FOR LPG STORAGE SPHERE 2 1.44 10-Apr-09 20-Apr-09
(V08-2402 A/B)
690 ELM-PUL-MD-DAT-0109 MECHANICAL DATA SHEET FOR LPG RE-RUN SPHERE 2 1.44 10-Apr-09 20-Apr-09
(V08-2401)
691 ELM-PUL-MC-DAT-0001 MECHANICAL DATA SHEET FOR HP SEPARATOR FEED 2 0.96 18-Mar-09 28-Mar-09
PRE-HEATER (E01/E02-2001-1/2)
692 ELM-PUL-MC-DAT-0002 MECHANICAL DATA SHEET FOR OIL STABILIZER FEED 2 1.01 18-Mar-09 28-Mar-09
HEATER (E01/E02-2003-1/2)
693 ELM-PUL-MC-DAT-0003 MECHANICAL DATA SHEET FOR DESALTER WASH WATER 2 1.01 18-Mar-09 28-Mar-09
HEATER (E01/E02-2006)
694 ELM-PUL-MC-DAT-0004 MECHANICAL DATA SHEET FOR NGL FEED GAS GAS 2 1.01 18-Mar-09 28-Mar-09
EXCHANGER (E01-2701-1/2/3/4)
695 ELM-PUL-MC-DAT-0005 MECHANICAL DATA SHEET FOR NGL FEED GAS LIQUID 2 1.01 18-Mar-09 28-Mar-09
EXCHANGER (E01-2702-1/2)
696 ELM-PUL-MC-DAT-0006 MECHANICAL DATA SHEET FOR DE ETHANIZER REBOILER 2 1.01 18-Mar-09 28-Mar-09
(E01-2703)
697 ELM-PUL-MC-DAT-0007 MECHANICAL DATA SHEET FOR DE ETHANIZER OVER 2 1.01 18-Mar-09 28-Mar-09
HEAD CONDENSER (E01-2707-1/2)
698 ELM-PUL-MC-DAT-0008 MECHANICAL DATA SHEET FOR CONDENSATE FLASH 2 1.01 18-Mar-09 28-Mar-09
HEATER (E01/E02-2004-1/2)
699 ELM-PUL-MC-DAT-0009 MECHANICAL DATA SHEET FOR OIL STABILIZER 2 1.01 18-Mar-09 28-Mar-09
REBOILER (E01/E02-2005-1/2)
700 ELM-PUL-MC-DAT-0010 MECHANICAL DATA SHEET FOR DE BUTANIZER FEED 2 1.01 18-Mar-09 28-Mar-09
HEATER (E01-2704)
701 ELM-PUL-MC-DAT-0011 MECHANICAL DATA SHEET FOR DE BUTANIZER REBOILER 2 1.01 18-Mar-09 28-Mar-09
(E01-2705-1/2)
702 ELM-PUL-MC-DAT-0012 MECHANICAL DATA SHEET FOR NGL FEED PRE-COOLER 2 1.01 18-Mar-09 28-Mar-09
(E01-2706)
703 ELM-PUL-MC-DAT-0050 MECHANICAL DATA SHEET FOR OIL RUN DOWN COOLER 2 0.96 15-Apr-09 25-Apr-09
(A01/A02/-2001)
704 ELM-PUL-MC-DAT-0051 MECHANICAL DATA SHEET FOR STABILIZED 2 0.96 15-Apr-09 25-Apr-09
CONDENSATE CONDENSER (A01/A02-2002)
705 ELM-PUL-MC-DAT-0052 MECHANICAL DATA SHEET FOR HOT OIL TRIM COOLER 2 0.96 15-Apr-09 25-Apr-09
(A01/A02-4101)
706 ELM-PUL-MC-DAT-0053 MECHANICAL DATA SHEET FOR 1ST STAGE ASSOCIATED 2 0.96 15-Apr-09 25-Apr-09
GAS SUCTION COOLER (A01/A02-2501)

707 ELM-PUL-MC-DAT-0054 MECHANICAL DATA SHEET FOR 2ND STAGE ASSOCIATED 2 0.96 15-Apr-09 25-Apr-09
GAS SUCTION COOLER (A01/A02-2502)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 19 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

708 ELM-PUL-MC-DAT-0055 MECHANICAL DATA SHEET FOR GAS DEHYDRATION 1 0.96 15-Apr-09 25-Apr-09
REGENERATION GAS COOLER (A01-2602)

709 ELM-PUL-MC-DAT-0056 MECHANICAL DATA SHEET FOR 2ND STAGE ASSOCIATED 2 0.96 15-Apr-09 25-Apr-09
GAS AFTERCOOLER (A01/A02-2503)
710 ELM-PUL-MC-DAT-0057 MECHANICAL DATA SHEET FOR BOOSTER COMPRESSOR 2 0.96 15-Apr-09 25-Apr-09
AFTERCOOLER (A01/A02/A03-2504)
711 ELM-PUL-MC-DAT-0058 MECHANICAL DATA SHEET FOR 1ST STAGE RESIDUE GAS 2 0.96 15-Apr-09 25-Apr-09
AFTERCOOLER (A01/A02-2705)
712 ELM-PUL-MC-DAT-0059 MECHANICAL DATA SHEET FOR 2ND STAGE RESIDUE GAS 2 0.96 15-Apr-09 25-Apr-09
AFTERCOOLER (A01/A02-2706)
713 ELM-PUL-MC-DAT-0060 MECHANICAL DATA SHEET FOR 1ST STAGE INJECTION 1 0.96 15-Apr-09 25-Apr-09
GAS AFTERCOOLER (A01/A02/A03-2901)

714 ELM-PUL-MC-DAT-0061 MECHANICAL DATA SHEET FOR 2ND STAGE INJECTION 1 0.96 15-Apr-09 25-Apr-09
GAS AFTERCOOLER (A01/A02/A03-2902)

715 ELM-PUL-MC-DAT-0062 MECHANICAL DATA SHEET FOR GAS DEHYDRATION 2 0.96 15-Apr-09 25-Apr-09
INLET GAS COOLER (A01-2601)
716 ELM-PUL-MC-DAT-0063 MECHANICAL DATA SHEET FOR OIL EXPORT PUMP 2 0.96 10-Apr-09 20-Apr-09
RECYCLE COOLER (A08-2101)
717 ELM-PUL-MC-DAT-0064 MECHANICAL DATA SHEET FOR CONDENSATE EXPORT 2 0.96 10-Apr-09 20-Apr-09
PUMP RECYCLE COOLER (A08-2303)
718 ELM-PUL-MC-DAT-0065 MECHANICAL DATA SHEET FOR LPG EXPORT PUMP 2 0.96 10-Apr-09 20-Apr-09
RECYCLE COOLER (A08-2401)
719 ELM-PUL-MC-DAT-0066 MECHANICAL DATA SHEET FOR NGL EXPANDER 2 0.96 15-Apr-09 25-Apr-09
COMPRESSOR AFTERCOOLER (A01-2701)
720 ELM-PUL-MC-DAT-0067 MECHANICAL DATA SHEET FOR DEBUTANIZER 2 0.96 15-Apr-09 25-Apr-09
CONDENSER (A01-2702)
721 ELM-PUL-MC-DAT-0068 MECHANICAL DATA SHEET FOR NGL CONDENSATE 2 0.96 15-Apr-09 25-Apr-09
RUNDOWN COOLER (A01-2703)
722 ELM-PUL-MC-DAT-0069 MECHANICAL DATA SHEET FOR LPG RUNDOWN COOLER 2 0.96 15-Apr-09 25-Apr-09
(A01-2704)
723 ELM-PUL-MC-DAT-0070 MECHANICAL DATA SHEET FOR HOT OIL TRIM COOLER 2 0.96 15-Apr-09 25-Apr-09
(A01-4102)
724 ELM-PUL-ML-DAT-0001 MECHANICAL DATA SHEET FOR GAS MOL SIEVE BED 2 1.06 26-May-09 5-Jun-09
FILTERS (S01-2602 A/B)
725 ELM-PUL-ML-DAT-0002 MECHANICAL DATA SHEET FOR OIL TRAIN 1 HOT OIL 2 1.06 26-May-09 5-Jun-09
FILTERS (S01-4101 A/B)
726 ELM-PUL-ML-DAT-0003 MECHANICAL DATA SHEET FOR NGL TRAIN 1 HOT OIL 2 1.06 26-May-09 5-Jun-09
FILTERS (S01-4102 A/B)
727 ELM-PUL-ML-DAT-0004 MECHANICAL DATA SHEET FOR OIL TRAIN 2 HOT OIL 2 1.06 26-May-09 5-Jun-09
FILTERS (S02-4101 A/B)
728 ELM-PUL-ML-DAT-0005 MECHANICAL DATA SHEET FOR HOT OIL DRAIN FILTER 2 1.06 26-May-09 5-Jun-09
(S08-4101)
729 ELM-PUL-ML-DAT-0006 MECHANICAL DATA SHEET FOR HOT OIL STORAGE 2 1.06 26-May-09 5-Jun-09
FILTER (S08-4102)
730 ELM-PUL-ML-DAT-0007 MECHANICAL DATA SHEET FOR WATER INJECTION 2 1.06 26-May-09 5-Jun-09
COARSE FILTERS (S08-5201 A/B/C)
731 ELM-PUL-ML-DAT-0008 MECHANICAL DATA SHEET FOR WATER INJECTION 2 1.06 26-May-09 5-Jun-09
COARSE FILTERS (S08-5202 A/B)
732 ELM-PUL-ML-DAT-0009 MECHANICAL DATA SHEET FOR FUEL GAS FILTERS (S08- 2 1.06 26-May-09 5-Jun-09
5301 A/B)
733 ELM-PUL-MU-DAT-0001 PACKAGE DATA SHEET FOR PWT PACKAGE (X01- 2 1.92 31-May-09 10-Jun-09
5101/X02-5101/X08-5102)
734 ELM-PUL-MB-DAT-0001 MECHANICAL DATA SHEET FOR GAS DEHYDRATION 2 1.68 25-Mar-09 4-Apr-09
REGENERATION GAS FIRED HEATER (H01-2601)

735 ELM-PUL-MB-DAT-0002 MECHANICAL DATA SHEET FOR HOT OIL FIRED HEATER - 2 1.68 25-Mar-09 4-Apr-09
OIL AREA (H01-4101/H02-4101)
736 ELM-PUL-MB-DAT-0003 MECHANICAL DATA SHEET FOR HOT OIL FIRED HEATER - 2 1.68 25-Mar-09 4-Apr-09
NGL AREA (H01-4102)
737 ELM-PUL-MB-DAT-0004 MECHANICAL DATA SHEET FOR HP FLARE PACKAGE 2 1.68 24-May-09 3-Jun-09
(M08-4401)
738 ELM-PUL-MB-DAT-0005 MECHANICAL DATA SHEET FOR LP FLARE PACKAGE (M08- 2 1.68 24-May-09 3-Jun-09
4501)
739 ELM-PUL-MB-DAT-0006 MECHANICAL DATA SHEET FOR HP-LT FLARE PACKAGE 2 1.68 24-May-09 3-Jun-09
(M08-4601)
740 ELM-PUL-MB-DAT-0007 MECHANICAL DATA SHEET FOR AP FLARE PACKAGE (M08- 2 1.68 24-May-09 3-Jun-09
4701)
741 ELM-PUL-MB-DAT-0008 MECHANICAL DATA SHEET FOR OIL TRAIN-1 FLARE (M01- 2 1.68 24-May-09 3-Jun-09
4901)
742 ELM-PUL-MB-DAT-0009 MECHANICAL DATA SHEET FOR OIL TRAIN-2 FLARE (M02- 2 1.68 24-May-09 3-Jun-09
5001)

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 20 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

743 ELM-PUL-MB-DAT-0010 MECHANICAL DATA SHEET FOR NGL TRAIN-1 FLARE 2 1.68 24-May-09 3-Jun-09
(M08-5501)
744 ELM-PUL-MD-TRQ-0001 TECHNICAL REQUISITION FOR COLUMNS 2 1.68 16-Apr-09 6-May-09

745 ELM-PUL-MD-TRQ-0003 TECHNICAL REQUISITION FOR HP VESSELS 1 1.92 17-Mar-09 6-Apr-09

746 ELM-PUL-MD-TRQ-0008 TECHNICAL REQUISITION FOR STORAGE TANK 2 3.36 31-Mar-09 20-Apr-09
(KNOCKED DOWN)
747 ELM-PUL-MD-DSN-0001 USERS DESIGN SPECIFICATION FOR GAS DEHYDRATION 2 1.92 27-Mar-09 6-Apr-09
INLET COALESCER (V01-2601)
748 ELM-PUL-MD-DSN-0002 USERS DESIGN SPECIFICATION FOR GAS DEHYDRATION 2 1.92 27-Mar-09 6-Apr-09
FEED K.O. DRUM (V01-2607)
749 ELM-PUL-MD-DSN-0003 USERS DESIGN SPECIFICATION FOR GAS MOL SIEVE BED 2 1.92 27-Mar-09 6-Apr-09
(V01-2602,V01-2603,V01-2604,V01-2605)

750 ELM-PUL-MD-DSN-0004 USERS DESIGN SPECIFICATION FOR 1ST STAGE 1 1.44 27-Mar-09 6-Apr-09
INJECTION GAS SUCTION DRUM (V01/V02/V03-2901)

751 ELM-PUL-MD-DSN-0005 USERS DESIGN SPECIFICATION FOR 2ND STAGE 1 1.44 27-Mar-09 6-Apr-09
INJECTION GAS SUCTION DRUM (V01/V02/V03-2902)

752 ELM-PUL-MD-REQ-0001 REQUISITION - COLUMNS 1 1.44 26-Apr-09 6-May-09

753 ELM-PUL-MD-REQ-0003 REQUISITION - HP VESSELS 1 1.44 27-Mar-09 6-Apr-09

754 ELM-PUL-MD-REQ-0004 REQUISITION - LP VESSELS 2 2.88 3-Apr-09 13-Apr-09

755 ELM-PUL-MD-REQ-0006 REQUISITION - MOLECULAR SIEVE BED INTERNALS 2 0.96 17-May-09 27-May-09

756 ELM-PUL-MD-REQ-0008 REQUISITION - STORAGE TANK (KNOCKED DOWN) 1 2.88 10-Apr-09 20-Apr-09

757 ELM-PUL-MD-REQ-0009 REQUISITION - SPHERE 1 1.44 10-Apr-09 20-Apr-09

758 ELM-PUL-MC-REQ-0010 REQUISITION - AIR COOLED HEAT EXCHANGER 1 2.88 15-Apr-09 25-Apr-09

759 ELM-PUL-MC-REQ-0011 REQUISITION - SHELL & TUBE HEAT EXCHANGER 2 4.32 18-Mar-09 28-Mar-09

760 ELM-PUL-MB-REQ-0013 REQUISITION - FIRED HEATER PACKAGE 1 1.44 25-Mar-09 4-Apr-09

761 ELM-PUL-MB-REQ-0014 REQUISITION - FLARE PACKAGE 2 5.76 24-May-09 3-Jun-09

762 ELM-PUL-ML-REQ-0015 REQUISITION - FILTERS 2 1.20 26-May-09 5-Jun-09

763 ELM-PUL-MU-REQ-0016 REQUISITION - PWT PACKAGE 2 6.72 31-May-09 10-Jun-09

764 ELM-PUL-MB-REQ-0019 REQUISITION - FIRED HEATER FABRICATION 4 2.40 17-Apr-09 27-Apr-09

765 ELM-PUL-MD-TBE-0001 TBE - COLUMNS 1 5.76 27-May-09 10-Jun-09

766 ELM-PUL-MD-TBE-0003 TBE - HP VESSELS 1 22.08 27-Apr-09 19-May-09

767 ELM-PUL-MD-TBE-0004 TBE - LP VESSELS 4 53.76 4-May-09 26-May-09

768 ELM-PUL-MD-TBE-0008 TBE - STORAGE TANK (KNOCKED DOWN) 1 11.52 11-May-09 25-May-09

769 ELM-PUL-MD-TBE-0009 TBE - SPHERE 1 2.88 11-May-09 25-May-09

770 ELM-PUL-MC-TBE-0001 TBE - AIR COOLED HEAT EXCHANGER 1 25.20 16-May-09 2-Jun-09

771 ELM-PUL-MC-TBE-0002 TBE - SHELL & TUBE HEAT EXCHANGER 2 16.32 18-Apr-09 3-May-09

772 ELM-PUL-MB-TBE-0001 TBE - FIRED HEATER PACKAGE 1 14.40 25-Apr-09 4-May-09

773 ELM-PUL-MB-TBE-0003 TBE - FIRED HEATER FABRICATION 4 4.80 18-May-09 9-Jun-09

774 ELM-PUL-MD-REQ-0025 REQUISITION - CS PLATES - HP VESSELS / COLUMNS 4 16.80 18-Mar-09 28-Mar-09

775 ELM-PUL-MD-REQ-0026 REQUISITION - CS PLATES - LP VESSELS 4 24.00 23-Mar-09 2-Apr-09

776 ELM-PUL-MD-REQ-0027 REQUISITION - SS CLAD PLATE - CLADDED VESSELS 4 7.20 17-Apr-09 27-Apr-09

777 ELM-PUL-MD-REQ-0028 REQUISITION - SS PLATES 4 4.80 22-Apr-09 2-May-09

778 ELM-PUL-MD-REQ-0031 REQUISITION - LTCS & SS -FORGINGS - HP VESSELS 4 12.00 17-Apr-09 27-Apr-09

779 ELM-PUL-MD-REQ-0034 4 7.20 17-May-09 27-May-09


REQUISITION - SS PIPES
780 ELM-PUL-MD-REQ-0036 REQUISITION - CS PLATES - STORAGE TANKS 4 7.20 18-Mar-09 28-Mar-09

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 21 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

781 ELM-PUL-MD-TBE-0020 TBE - CS PLATES FOR HP VESSELS / COLUMNS 4 9.60 18-Apr-09 3-May-09

782 ELM-PUL-MD-TBE-0021 TBE - CS PLATES FOR LP VESSELS 4 14.40 23-Apr-09 8-May-09

783 ELM-PUL-MD-TBE-0022 TBE - SS CLAD PLATE FOR CLADDED VESSELS 4 4.80 18-May-09 2-Jun-09

784 ELM-PUL-MD-TBE-0023 TBE - SS PLATES 4 4.80 23-May-09 7-Jun-09

785 ELM-PUL-MD-TBE-0026 TBE - SRF NOZZLES ( CS & SS) 4 12.00 18-May-09 2-Jun-09

786 ELM-PUL-MD-TBE-0031 TBE - CS PLATES FOR STORAGE TANKS 4 9.60 18-Apr-09 3-May-09

PIPING
787 ELM-PUL-PI-BOD-0003 NOZZLE LOADING DESIGN BASIS 2 0.72 15-Mar-09 2-Apr-09

788 ELM-PUL-PI-GEN-0001 PURCHASE SPEC (VALVES) 2 2.40 15-Mar-09 2-Apr-09

789 ELM-PUL-PI-GEN-0002 PURCHASE SPEC (PIPE, FITTINGS, FLANGES) 2 2.40 20-Mar-09 2-Apr-09

790 ELM-PUL-PI-GEN-0003 PURCHASE SPEC (HDPE) 2 2.40 15-Apr-09 30-Apr-09

791 ELM-PUL-PI-GEN-0006 SPECIFICATION FOR MARKING, COLOR CODING 2 2.40 22-Mar-09 2-Apr-09

792 ELM-PUL-PI-PMC-0001 PMS 2 151.93 11-Mar-09 16-Apr-09

793 ELM-PUL-PI-PPS-0001 PIPE SUPPORT SPECIFICATION 2 14.40 16-Apr-09 16-May-09

794 ELM-PUL-PI-DAT-0001 HIGH PRESS & LOW TEMP. VALVE DATASHEETS 1 14.40 19-Mar-09 16-Apr-09

795 ELM-PUL-PI-DAT-0002 VALVE DATASHEETS 2 130.33 19-Mar-09 16-Apr-09

796 ELM-PUL-PI-DAT-0003 SPECIAL ITEM DATASHEETS 3 14.40 19-May-09 18-Jun-09

797 ELM-PUL-PI-PRC-0001 3D MODELING PROCEDURE 3 1.68 15-Mar-09 2-Apr-09

798 ELM-PUL-PI-PRC-0002 2D DRAFTING PROCEDURE 3 0.72 15-Apr-09 30-Apr-09

799 ELM-PUL-PI-REQ-0100 REQUISITION - CS & LTCS PIPES (SEAMLESS) 4 6.05 13-Mar-09 28-Mar-09

800 ELM-PUL-PI-REQ-0101 REQUISITION - CS & LTCS PIPES (WELDED) 4 6.05 13-Mar-09 28-Mar-09

801 ELM-PUL-PI-REQ-0102 REQUISITION - SS PIPES (SEAMLESS) 4 6.05 20-Mar-09 4-Apr-09

802 ELM-PUL-PI-REQ-0103 REQUISITION - SS PIPES (WELDED) 4 6.05 20-Mar-09 4-Apr-09

803 ELM-PUL-PI-REQ-0104 REQUISITION - DSS PIPES 4 6.05 28-Mar-09 12-Apr-09

804 ELM-PUL-PI-REQ-0106 REQUISITION - CS & LTCS FITTINGS (WROUGHT) 4 6.05 23-Mar-09 7-Apr-09

805 ELM-PUL-PI-REQ-0107 REQUISITION - SS FITTINGS (WROUGHT) 4 6.05 23-Mar-09 7-Apr-09

806 ELM-PUL-PI-REQ-0108 REQUISITION - DSS FITTINGS (WROUGHT) 4 6.05 28-Mar-09 12-Apr-09

807 ELM-PUL-PI-REQ-0109 REQUISITION - FORGED FITTINGS 4 6.05 23-Mar-09 7-Apr-09

808 ELM-PUL-PI-REQ-0110 REQUISITION - CS & LTCS FLANGES & SPECTACLE 4 6.05 23-Mar-09 7-Apr-09
BLINDS
809 ELM-PUL-PI-REQ-0111 REQUISITION - SS & DSS FLANGES & SPECTACLE BLINDS 4 6.05 28-Mar-09 12-Apr-09

810 ELM-PUL-PI-TBE-0001 TBE - CS & LTCS PIPES (SEAMLESS) 4 2.35 18-Apr-09 3-May-09

811 ELM-PUL-PI-TBE-0002 TBE - CS & LTCS PIPES (WELDED) 4 2.35 18-Apr-09 3-May-09

812 ELM-PUL-PI-TBE-0003 TBE - SS PIPES (SEAMLESS) 4 2.35 25-Apr-09 10-May-09

813 ELM-PUL-PI-TBE-0004 TBE - SS PIPES (WELDED) 4 2.35 25-Apr-09 10-May-09

814 ELM-PUL-PI-TBE-0005 TBE - DSS PIPES 4 2.35 3-May-09 18-May-09

815 ELM-PUL-PI-TBE-0007 TBE - CS & LTCS FITTINGS (WROUGHT) 4 2.35 28-Apr-09 13-May-09

816 ELM-PUL-PI-TBE-0008 TBE - SS FITTINGS (WROUGHT) 4 2.35 28-Apr-09 13-May-09

817 ELM-PUL-PI-TBE-0009 TBE - DSS FITTINGS (WROUGHT) 4 2.35 3-May-09 18-May-09

818 ELM-PUL-PI-TBE-0010 TBE - FORGED FITTINGS 4 2.35 28-Apr-09 13-May-09

819 ELM-PUL-PI-TBE-0011 TBE - CS & LTCS FLANGES & SPECTACLE BLINDS 4 2.35 28-Apr-09 13-May-09

820 ELM-PUL-PI-TBE-0012 TBE - SS & DSS FLANGES & SPECTACLE BLINDS 4 2.35 3-May-09 18-May-09

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 22 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

821 ELM-PUL-PI-PLT-0001 OVERALL PLOT PLAN 1 3.60 11-Mar-09 11-May-09

822 ELM-PUL-MT-RPT-0001 MATERIAL SELECTION REPORT 26.40 15-May-09


1 15-Apr-09
823 ELM-PUL-MT-MSD-1001 RECEPTION FACILITIES 4.80 15-Apr-09
1 16-Mar-09
824 ELM-PUL-MT-MSD-2001 OIL SEPARATION AND DESALTING 4.80 15-Apr-09
1 16-Mar-09
825 ELM-PUL-MT-MSD-2101 OIL AND CONDENSATE STABILIZATION 4.80 15-Apr-09
1 16-Mar-09
826 ELM-PUL-MT-MSD-2501 ASSOCIATED GAS COMPRESSOR 4.80 15-Apr-09
1 16-Mar-09
827 ELM-PUL-MT-MSD-2502 BOOSTER COMPRESSOR 4.80 15-Apr-09
1 16-Mar-09
828 ELM-PUL-MT-MSD-2601 GAS DEHYDRATION 4.80 15-Apr-09
1 16-Mar-09
829 ELM-PUL-MT-MSD-2701 NGL RECOVERY 4.80 15-Apr-09
1 16-Mar-09
830 ELM-PUL-MT-MSD-2702 NGL FRACTIONATION 4.80 15-Apr-09
1 16-Mar-09
831 ELM-PUL-MT-MSD-2801 RESIDUE GAS COMPRESSOR 4.80 15-Apr-09
1 16-Mar-09
832 ELM-PUL-MT-MSD-2901 INJECTION GAS COMPRESSOR 4.80 15-Apr-09
1 16-Mar-09
833 ELM-PUL-MT-MSD-2102 OIL STORAGE, EXPORT AND RE-RUN 4.80 15-Apr-09
1 16-Mar-09
834 ELM-PUL-MT-MSD-2401 LPG STORAGE, EXPORT AND RE-RUN 4.80 15-Apr-09
1 16-Mar-09
835 ELM-PUL-MT-MSD-2301 CONDENSATE STORAGE AND EXPORT 4.80 15-Apr-09
1 16-Mar-09
836 ELM-PUL-MT-MSD-4101 HOT OIL SYSTEM - OIL STABILIZATION AREA 4.80 30-Apr-09
1 31-Mar-09
837 ELM-PUL-MT-MSD-4102 HOT OIL SYSTEM - NGL RECOVERY AREA 4.80 30-Apr-09
1 31-Mar-09
838 ELM-PUL-MT-MSD-4301 PRODUCTION CHEMICAL & METHANOL INJECTION 4.80 30-Apr-09
1 31-Mar-09
839 ELM-PUL-MT-MSD-4302 PRODUCTION CHEMICAL & METHANOL INJECTION 4.80 30-Apr-09
1 31-Mar-09

840 ELM-PUL-MT-MSD-4303 PRODUCTION CHEMICAL INJECTION 4.80 30-Apr-09


1 31-Mar-09
841 ELM-PUL-MT-MSD-4401 HP, HP/LT ATMOSPHERIC AND LP FLARE SYSTEMS 4.80 30-Apr-09
1 31-Mar-09
842 ELM-PUL-MT-MSD-4402 OIL TRAIN 1,OIL TRAIN 2 AND NGL FLARES 4.80 30-Apr-09
1 31-Mar-09
843 ELM-PUL-MT-MSD-4801 WARM AND COLD CLOSED DRAINS SYSTEMS 4.80 30-Apr-09
1 31-Mar-09
844 ELM-PUL-MT-MSD-5101 PRODUCED WATER TREATMENT-1 4.80 30-Apr-09
1 31-Mar-09
845 ELM-PUL-MT-MSD-5102 PRODUCED WATER TREATMENT-2 4.80 30-Apr-09
1 31-Mar-09
846 ELM-PUL-MT-MSD-5201 WATER INJECTION SYSTEM 4.80 30-Apr-09
1 31-Mar-09
847 ELM-PUL-MT-MSD-5202 WATER INJECTION SYSTEM 4.80 30-Apr-09
1 31-Mar-09
848 ELM-PUL-MT-MSD-5301 FUEL GAS SYSTEM 4.80 30-Apr-09
1 31-Mar-09
849 ELM-PUL-MT-MSD-5401 EVAPORATION PONDS 4.80 30-Apr-09
1 31-Mar-09
850 ELM-PUL-MT-MSD-6101 WATER SYSTEM 4.80 30-Apr-09
1 31-Mar-09
851 ELM-PUL-MT-MSD-6001 SOURCE WATER STORAGE 4.80 30-Apr-09
1 31-Mar-09
852 ELM-PUL-MT-MSD-6102 UTILITY AND FRESH WATER SYSTEMS 4.80 30-Apr-09
1 31-Mar-09
853 ELM-PUL-MT-MSD-6401 DIESEL FUEL RECEIVING, STORAGE AND DISTRIBUTING 4.80 30-Apr-09
1 31-Mar-09

854 ELM-PUL-MT-MSD-6701 COMPRESSED AIR 4.80 30-Apr-09


1 31-Mar-09
855 ELM-PUL-MT-MSD-5501 OILY WATER TREATMENT SYSTEM 4.80 30-Apr-09
1 31-Mar-09
856 ELM-PUL-MT-MSD-7101 NITROGEN GENERATION AND DISTRIBUTION 4.80 30-Apr-09
1 31-Mar-09
857 ELM-PUL-MT-MSD-7301 SEWAGE TREATMENT SYSTEM 4.80 30-Apr-09
1 31-Mar-09
858 ELM-PUL-MT-MSD-7801 EMERGENCY GENERATOR 4.80 30-Apr-09
1 31-Mar-09
859 ELM-PUL-MT-GEN-0010 12.00 31-May-09
CORROSION MONITORING SPECIFICATION 1 1-May-09
860 ELM-PUL-MT-GEN-0011 12.00 31-May-09
CORROSION INHIBITION SPECIFICATION 1 1-May-09
861 ELM-PUL-MT-RPT-0003 2.40 20-Apr-09
FEED VERIFICATION - CP SYSTEM 1 21-Mar-09

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 23 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

862 ELM-PUL-MT-REQ-190 2.40 27-Apr-09


REQUISITION - CATHODIC PROTECTION SYSTEM 1 7-Apr-09
863 ELM-PUL-MT-TBE-190 2.40 2-Jun-09
TBE - CATHODIC PROTECTION SYSTEM 1 18-May-09
HSE
864 ELM-PUL-LC-CAL-0001 1 9.60 2-Apr-09 3-Apr-09 1-Apr-09 2-Apr-09 80 7.68
FIREWATER SYSTEM ANALYSIS & DEMAND CALCULATION
865 ELM-PUL-LC-CAL-0001 BLAST HAZARD ANALYSIS REPORT 1 5.76 2-Apr-09 3-Apr-09 1-Apr-09 2-Apr-09 80 4.61
ELECTRICAL
866 ELM-PUL-EL-CAL-0001 LOAD SCHEDULE (HV) 1 7.20 31-Mar-09 30-Apr-09

867 ELM-PUL-EL-CAL-0002 LOAD SCHEDULE (LV) 1 33.60 31-Mar-09 30-Apr-09

868 ELM-PUL-EL-CAL-0003 CABLE SIZING 1 19.20 21-Mar-09 20-Apr-09

869 ELM-PUL-EL-REQ-0410 REQUISITION - HV / MV SWITCBOARD 1 7.20 16-May-09 5-Jun-09

870 ELM-PUL-EL-REQ-0401 REQUISITION - DG SET 4 7.20 2-Apr-09 12-Apr-09

871 ELM-PUL-EL-REQ-0407 REQUISITION - POWER & DIST.TRANSFORMERS 4 7.20 10-Apr-09 20-Apr-09

872 ELM-PUL-EL-TBE-0401 TBE - DG SET 4 9.60 3-May-09 18-May-09

873 ELM-PUL-EL-TBE-0407 TBE - POWER & DIST.TRANSFORMERS 4 7.20 11-May-09 26-May-09

874 ELM-PUL-EL-LGN-0001 ELECTRICAL SYMBOL & LEGEND 1 0.96 31-Mar-09 30-Apr-09

875 ELM-PUL-EL-SLD-0001 KEY SINGLE LINE DIAGRAM 1 2.40 31-Mar-09 30-Apr-09

876 ELM-PUL-EL-SLD-0801 SINGLE LINE DIAGRAM FOR MSB, 30KV SWITCHGEAR 1 4.80 21-Mar-09 20-Apr-09
(SG08-7601)
877 ELM-PUL-EL-SLD-0802 SINGLE LINE DIAGRAM FOR MSB, 5.5KV SWITCHGEAR 1 4.80 26-Mar-09 25-Apr-09
(SG08-7604)
878 ELM-PUL-EL-SLD-0803 SINGLE LINE DIAGRAM FOR MSB 5.5KV SWITCHGEAR 1 4.80 26-Mar-09 25-Apr-09
(SG08-7607)
879 ELM-PUL-EL-SLD-0804 SINGLE LINE DIAGRAM FOR MSB 5.5KV SWITCHGEAR 1 4.80 26-Mar-09 25-Apr-09
(SG08-7608)
880 ELM-PUL-EL-SLD-0805 SINGLE LINE DIAGRAM FOR MSB, 400V SWITCHBOARD 1 7.20 30-Apr-09 30-May-09
(SG08-7801)
881 ELM-PUL-EL-SLD-0806 SINGLE LINE DIAGRAM FOR MSB, 400V SWITCHBOARD 1 7.20 30-Apr-09 30-May-09
(SG08-7802)
882 ELM-PUL-EL-SLD-0807 SINGLE LINE DIAGRAM FOR MSB, 400V SWITCHBOARD 1 7.20 30-Apr-09 30-May-09
(SG08-7701)
883 ELM-PUL-EL-SLD-0901 SINGLE LINE DIAGRAM FOR USB, 30KV SWITCHGEAR 1 4.80 21-Mar-09 20-Apr-09
(SG08-7602)
884 ELM-PUL-EL-SLD-0902 SINGLE LINE DIAGRAM FOR USB, 5.5KV SWITCHGEAR 1 3.84 26-Mar-09 25-Apr-09
(SG08-7605)
885 ELM-PUL-EL-SLD-0903 SINGLE LINE DIAGRAM FOR USB, 400V SWITCHBOARD 1 5.76 26-Mar-09 25-Apr-09
(SG08-7702)
886 ELM-PUL-EL-SLD-0904 SINGLE LINE DIAGRAM FOR USB, 50KVA AC UPS FOR USB 1 1.92 26-Mar-09 25-Apr-09

887 ELM-PUL-EL-ELO-0901 ELECTRICAL EQUIPMENT LAYOUT - PLAN FOR UTILITY 2 5.76 21-Mar-09 20-Apr-09
SUBSTATION BUILDING
888 ELM-PUL-EL-ELO-0902 ELECTRICAL EQUIPMENT LAYOUT - PLAN FOR UTILITY 2 5.76 21-Mar-09 20-Apr-09
SUBSTATION BUILDING
889 ELM-PUL-EL-CCR-0002 OVERALL CABLE ROUTING LAYOUT 2 3.60 27-Mar-09 26-Apr-09

INSTRUMENTATION
890 ELM-PUL-IC-REQ-0501 REQUISITION - INTEGRATED CONTROL & SAFETY 1 19.20 20-Mar-09 7-Apr-09
SYSTEM
891 ELM-PUL-IC-REQ-0506 REQUISITION - TANK GAUGING SYSTEM 2 9.60 24-Apr-09 15-May-09

892 ELM-PUL-IC-REQ-0508 REQUISITION - FLOW METERING / PROVING SYSTEM 1 19.20 25-Mar-09 15-Apr-09

893 ELM-PUL-IC-REQ-0511 REQUISITION - CONTROL & SELF REGULATING VALVES 1 14.40 4-May-09 25-May-09

894 ELM-PUL-IC-REQ-0512 REQUISITION - SHUTDOWN VALVES 2 14.40 25-Mar-09 15-Apr-09

895 ELM-PUL-IC-REQ-0514 REQUISITION - PRESSURE RELIEF VALVES 1 12.00 9-May-09 30-May-09

896 ELM-PUL-IC-REQ-0571 REQUISITION - INSTRUMENT CABLES 2 3.60 17-Mar-09 7-Apr-09

897 ELM-PUL-IC-DAT-0506 DATA SHEETS FOR TANK GAUGING SYSTEM 2 9.60 24-Apr-09 15-May-09

898 ELM-PUL-IC-DAT-0508 DATA SHEETS FOR FLOW METERING / PROVING SYSTEM 1 28.80 25-Mar-09 15-Apr-09

899 ELM-PUL-IC-DAT-0511 DATA SHEETS FOR CONTROL & SELF REGULATING 1 38.40 4-May-09 25-May-09
VALVES

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 24 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

900 ELM-PUL-IC-DAT-0512 DATA SHEETS FOR SHUTDOWN VALVES 2 36.00 25-Mar-09 15-Apr-09

901 ELM-PUL-IC-DAT-0514 DATA SHEETS FOR PRESSURE RELIEF VALVES 1 31.20 9-May-09 30-May-09

902 ELM-PUL-IC-DAT-0571 DATA SHEETS FOR INSTRUMENT CABLES 2 14.40 17-Mar-09 7-Apr-09

903 ELM-PUL-IC-TBE-0501 TBE - ICSS 1 28.80 28-Apr-09 7-Jun-09

904 ELM-PUL-IC-TBE-0571 TBE - INSTRUMENT CABLES 4 4.80 9-May-09 30-May-09

905 ELM-PUL-IC-BKD-0002 OVERALL INTEGRATED CONTROL & SAFETY SYSTEM 1 4.08 20-Mar-09 10-Apr-09
ARCHITECTURE DRAWING
906 ELM-PUL-IC-BKD-0003 OVERALL INTEGRATED CONTROL & SAFETY SYSTEM 1 4.08 9-May-09 30-May-09
ARCHITECTURE DRAWING (WITH TELECOMMUNICATION
INTERFACES)
907 ELM-PUL-IC-BKD-0004 CONTROL & MONITORING SYSTEM ARCHITECTURE 1 4.08 20-Mar-09 10-Apr-09
DRAWING
908 ELM-PUL-IC-BKD-0005 SAFE GUARDING SYSTEM ARCHITECTURE DRAWING 1 4.08 20-Mar-09 10-Apr-09

909 ELM-PUL-IC-BKD-0006 FIRE & GAS SYSTEM ARCHITECTURE DRAWING 1 4.08 20-Mar-09 10-Apr-09

910 ELM-PUL-IC-BKD-0007 SUPERVISORY CONTROL & DATA ACQUISITION SYSTEM 1 4.08 9-May-09 30-May-09
ARCHITECTURE DRAWING
911 ELM-PUL-IC-BKD-0011 OIL FISCAL METERING BLOCK DIAGRAM 1 4.08 17-Mar-09 7-Apr-09

912 ELM-PUL-IC-BKD-0012 CONDENSATE FISCAL METERING BLOCK DIAGRAM 1 4.08 17-Mar-09 7-Apr-09

913 ELM-PUL-IC-BKD-0013 LPG FISCAL METERING BLOCK DIAGRAM 1 4.08 17-Mar-09 7-Apr-09

914 ELM-PUL-IC-BKD-0014 FISCAL METERING SYSTEM ARCHITECTURE DRAWING 1 4.08 16-Mar-09 15-Apr-09

915 ELM-PUL-IC-BKD-0016 INSTRUMENT - ELECTRICAL EARTHING PHILOSOPHY 2 1.92 17-Mar-09 15-Apr-09

916 ELM-PUL-IC-SKE-0001 CONTROL BLOCK DIAGRAM (TURBO EXPANDER 2 3.60 20-Mar-09 10-Apr-09
COMPRESSOR PACKAGE)
917 ELM-PUL-IC-CED-1001 CAUSE & EFFECT DIAGRAM SGS - P1OIL 1 4.80 24-Apr-09 15-May-09

918 ELM-PUL-IC-CED-2001 CAUSE & EFFECT DIAGRAM SGS - P2OIL 1 3.12 24-Apr-09 15-May-09

919 ELM-PUL-IC-CED-6001 CAUSE & EFFECT DIAGRAM SGS - U1 1 6.00 24-Apr-09 15-May-09

920 ELM-PUL-IC-CED-7001 CAUSE & EFFECT DIAGRAM SGS - U2 1 3.12 24-Apr-09 15-May-09

921 ELM-PUL-IC-CED-9001 CAUSE & EFFECT DIAGRAM SGS - UTILITIES 1 4.80 24-Apr-09 15-May-09

922 ELM-PUL-IC-IAP-8001 CENTRAL CONTROL ROOM LAYOUT 1 3.60 16-Mar-09 15-Apr-09

923 ELM-PUL-IC-FGP-0001 FIRE & GAS DETECTOR LEGEND AND NOTES SHEET 1 1.68 9-Apr-09 30-Apr-09

924 ELM-PUL-IC-FGP-1001 FIRE & GAS DETECTOR LAYOUTS - DRAWING AND FIRE 1 1.58 4-May-09 25-May-09
ZONE KEY PLAN - OIL TRAIN 1
925 ELM-PUL-IC-FGP-1002 INSTRUMENT LOCATION LAYOUTS - FIRED HEATER AREA 1 1.58 4-May-09 25-May-09
- OIL TRAIN 1
926 ELM-PUL-IC-FGP-1003 INSTRUMENT LOCATION LAYOUTS - CONDENSATE 1 1.58 4-May-09 25-May-09
RECOVERY AREA -OIL TRAIN 1
927 ELM-PUL-IC-FGP-1004 INSTRUMENT LOCATION LAYOUTS - OIL TREATMENT 1 1.58 4-May-09 25-May-09
AREA - OIL TRAIN 1
928 ELM-PUL-IC-FGP-1005 INSTRUMENT LOCATION LAYOUTS - CHEMICAL 1 1.58 4-May-09 25-May-09
INJECTION AREA - OIL TRAIN 1
929 ELM-PUL-IC-FGP-1006 INSTRUMENT LOCATION LAYOUTS - CONDENSATE 1 1.58 4-May-09 25-May-09
RECOVERY AREA -OIL TRAIN 1
930 ELM-PUL-IC-FGP-1007 INSTRUMENT LOCATION LAYOUTS - OIL TREATMENT 1 1.58 4-May-09 25-May-09
AREA - OIL TRAIN 1
931 ELM-PUL-IC-FGP-1008 INSTRUMENT LOCATION LAYOUTS - OIL TREATMENT 1 1.58 4-May-09 25-May-09
AREA - OIL TRAIN 1
932 ELM-PUL-IC-FGP-1009 INSTRUMENT LOCATION LAYOUTS - OIL TREATMENT 1 1.58 4-May-09 25-May-09
AREA - OIL TRAIN 1
933 ELM-PUL-IC-FGP-2001 FIRE & GAS DETECTOR LAYOUTS - DRAWING AND FIRE 1 1.58 17-May-09 7-Jun-09
ZONE KEY PLAN - OIL TRAIN 2
934 ELM-PUL-IC-FGP-2002 FIRE & GAS DETECTOR LAYOUTS - FIRED HEATER AREA - 1 1.58 17-May-09 7-Jun-09
OIL TRAIN 2
935 ELM-PUL-IC-FGP-2003 FIRE & GAS DETECTOR LAYOUTS - CONDENSATE 1 1.58 17-May-09 7-Jun-09
RECOVERY AREA -OIL TRAIN 2
936 ELM-PUL-IC-FGP-2004 FIRE & GAS DETECTOR LAYOUTS - OIL TREATMENT 1 1.58 17-May-09 7-Jun-09
AREA - OIL TRAIN 2
937 ELM-PUL-IC-FGP-2005 FIRE & GAS DETECTOR LAYOUTS - HOT OIL SURGE 1 1.58 17-May-09 7-Jun-09
DRUM AREA

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 25 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

938 ELM-PUL-IC-FGP-2006 FIRE & GAS DETECTOR LAYOUTS - CONDENSATE 1 1.58 17-May-09 7-Jun-09
RECOVERY AREA -OIL TRAIN 2
939 ELM-PUL-IC-FGP-2007 FIRE & GAS DETECTOR LAYOUTS - OIL TREATMENT 1 1.58 17-May-09 7-Jun-09
AREA - OIL TRAIN 2
940 ELM-PUL-IC-FGP-2008 FIRE & GAS DETECTOR LAYOUTS - OIL TREATMENT 1 1.58 17-May-09 7-Jun-09
AREA - OIL TRAIN 2
941 ELM-PUL-IC-FGP-3001 FIRE & GAS DETECTOR LAYOUTS - DRAWING AND FIRE 1 1.58 9-May-09 30-May-09
ZONE KEY PLAN - AG/BG COMPRESSOR AREA
942 ELM-PUL-IC-FGP-3002 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR TRAIN-1 KOD AREA
943 ELM-PUL-IC-FGP-3003 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR TRAIN-2 KOD AREA
944 ELM-PUL-IC-FGP-3004 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR TRAIN-3 KOD AREA
945 ELM-PUL-IC-FGP-3005 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 1
946 ELM-PUL-IC-FGP-3006 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 1
947 ELM-PUL-IC-FGP-3007 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 2
948 ELM-PUL-IC-FGP-3008 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 2
949 ELM-PUL-IC-FGP-3009 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 3
950 ELM-PUL-IC-FGP-3010 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 3
951 ELM-PUL-IC-FGP-3011 FIRE & GAS DETECTOR LAYOUTS - ASSOCIATED GAS 1 1.58 9-May-09 30-May-09
COMPRESSOR N-S PIPERACK
952 ELM-PUL-IC-FGP-3014 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR TRAIN 1 KOD AREA
953 ELM-PUL-IC-FGP-3015 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR TRAIN 1 KOD AREA
954 ELM-PUL-IC-FGP-3016 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR TRAIN 1 KOD AREA
955 ELM-PUL-IC-FGP-3017 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 1
956 ELM-PUL-IC-FGP-3018 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 1
957 ELM-PUL-IC-FGP-3019 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 2
958 ELM-PUL-IC-FGP-3020 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 2
959 ELM-PUL-IC-FGP-3021 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 3
960 ELM-PUL-IC-FGP-3022 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR BUILDING TRAIN 3
961 ELM-PUL-IC-FGP-3023 FIRE & GAS DETECTOR LAYOUTS - BOOSTER 1 1.58 9-May-09 30-May-09
COMPRESSOR N-S PIPERACK
962 ELM-PUL-IC-FGP-4001 FIRE & GAS DETECTOR LAYOUTS - DRAWING AND FIRE 1 1.58 20-May-09 10-Jun-09
ZONE KEY PLAN - RG COMPRESSOR AREA
963 ELM-PUL-IC-FGP-4002 FIRE & GAS DETECTOR LAYOUTS - FUEL GAS AREA 1 1.58 20-May-09 10-Jun-09

964 ELM-PUL-IC-FGP-4003 FIRE & GAS DETECTOR LAYOUTS - CPI SEPARATOR AREA 1 1.58 20-May-09 10-Jun-09

965 ELM-PUL-IC-FGP-9001 FIRE & GAS DETECTOR LAYOUTS - DRAWING & FIRE 3 1.58 20-May-09 10-Jun-09
ZONE KEY PLAN - UTILITIES
966 ELM-PUL-IC-FGP-9002 FIRE & GAS DETECTOR LAYOUTS - PLANT AND 3 1.58 20-May-09 10-Jun-09
INSTRUMENT AIR COMPRESSOR AREA
967 ELM-PUL-IC-FGP-9003 FIRE & GAS DETECTOR LAYOUTS - NITROGEN 3 1.58 20-May-09 10-Jun-09
GENERATION AREA
968 ELM-PUL-IC-FGP-9015 FIRE & GAS DETECTOR LAYOUTS - DIESEL STORAGE 3 1.58 20-May-09 10-Jun-09
AREA
969 ELM-PUL-IC-FGP-9016 FIRE & GAS DETECTOR LAYOUTS - HOT OIL STORAGE 3 1.58 20-May-09 10-Jun-09
TANK AREA
970 ELM-PUL-IC-FGP-9021 FIRE & GAS DETECTOR LAYOUTS - DRAWING KEY PLAN - 3 2.45 20-May-09 10-Jun-09
FIRE WATER AREA
971 ELM-PUL-IC-FGP-9022 FIRE & GAS DETECTOR LAYOUTS - FIRE WATER 3 2.45 20-May-09 10-Jun-09
STORAGE TANK AREA
972 ELM-PUL-IC-FGP-9023 FIRE & GAS DETECTOR LAYOUTS - FIRE WATER PUMPS 3 2.45 20-May-09 10-Jun-09
AREA
CIVIL
973 ELM-PUL-CV-BOD-0001 CONCEPT NOTE FOR THE DESIGN OF OILY WATER - 9.60
STORM WATER - SANITARY SEWAGE AND CHEMICAL 1 31-Mar-09 30-Apr-09
DRAINAGE SYSTEMS

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 26 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

974 ELM-PUL-ST-BOD-0002 9.60


CIVIL & STRUCTURAL DESIGN BASIS 1 13-Mar-09 12-Apr-09
975 ELM-PUL-ST-BOD-0003 CONCEPT NOTE FOR THE DESIGN OF PIPE RACKS AND 9.60
1 13-Mar-09 12-Apr-09
THEIR FOUNDATIONS
976 ELM-PUL-ST-BOD-0004 CONCEPT NOTE FOR THE DESIGN OF STEEL BUILDINGS 9.60
1 17-Mar-09 16-Apr-09
& SHELETRS
977 ELM-PUL-ST-BOD-0005 CONCEPT NOTE FOR THE DESIGN OF BLAST RESISTANT 9.60
1 10-Apr-09 10-May-09
BUILDINGS
978 ELM-PUL-ST-BOD-0008 CONCEPT NOTE FOR THE DESIGN OF RIGID BLOCK 9.60
1 9-May-09 8-Jun-09
FOUNDATIONS FOR ROTATING EQUIPMENT
979 ELM-PUL-ST-DWG-0026 GENERAL NOTES, ABBREVIATIONS AND LEGEND FOR 2.16
1 21-Mar-09 20/04/2009
CONCRETE WORKS - 1
980 ELM-PUL-ST-DWG-0026 GENERAL NOTES, ABBREVIATIONS AND LEGEND FOR 2.16
1 21-Mar-09 20-Apr-09
CONCRETE WORKS - 2
981 ELM-PUL-ST-DWG-0027 GENERAL NOTES, ABBREVIATIONS AND LEGEND FOR 2.16
1 21-Mar-09 20-Apr-09
STRUCTURAL STEEL WORKS - 1
982 ELM-PUL-ST-DWG-0027 GENERAL NOTES, ABBREVIATIONS AND LEGEND FOR 2.16
1 21-Mar-09 20-Apr-09
STRUCTURAL STEEL WORKS - 2
983 ELM-PUL-ST-DWG-0027 GENERAL NOTES, ABBREVIATIONS AND LEGEND FOR 2.16
1 21-Mar-09 20-Apr-09
STRUCTURAL STEEL WORKS - 3
984 ELM-PUL-ST-DWG-0029 2.16
STANDARD DETAILS OF ANCHOR BOLT ASSEMBLIES - 1 1 21-Mar-09 20-Apr-09

985 ELM-PUL-ST-DWG-0044 1.92


STANDARD DETAILS OF CABLE DUCT BANK - 1 1 17-Mar-09 16-Apr-09
986 ELM-PUL-ST-DWG-0045 OILY WATER SEWER - STANDARD DETAILS OF MANHOLE 2.16
1 24-Mar-09 23-Apr-09
AND COVER
987 ELM-PUL-ST-DWG-0050 1.68
STANDARD DETAILS OF EARTHING PIT 1 17-Mar-09 16-Apr-09
988 ELM-PUL-CV-CFG-1201 2.64
SITE GRADING LAYOUT - 1 2 11-May-09 10-Jun-09
989 ELM-PUL-CV-CFG-1202 2.64
SITE GRADING LAYOUT - 2 2 11-May-09 10-Jun-09
990 ELM-PUL-CV-CFG-1203 2.64
SITE GRADING LAYOUT - 3 2 11-May-09 10-Jun-09
991 ELM-PUL-CV-CFG-1204 2.64
SITE GRADING LAYOUT - 4 2 11-May-09 10-Jun-09
992 ELM-PUL-AR-DWG-3506 CONTROL BUILDING - ARCHITECTURAL PLAN DRAWINGS 1.92
1 21-May-09 20-Jun-09
-1
993 ELM-PUL-AR-DWG-3507 CONTROL BUILDING - ARCHITECTURAL PLAN DRAWINGS 1.92
1 21-May-09 20-Jun-09
-2
994 ELM-PUL-AR-DWG-3508 CONTROL BUILDING - ARCHITECTURAL PLAN DRAWINGS 1.92
1 21-May-09 20-Jun-09
-3
995 ELM-PUL-AR-DWG-3509 CONTROL BUILDING - ARCHITECTURAL PLAN DRAWINGS 1.92
1 21-May-09 20-Jun-09
-4
996 ELM-PUL-AR-DWG-3510 CONTROL BUILDING - ARCHITECTURAL PLAN DRAWINGS 1.92
1 21-May-09 20-Jun-09
-5
997 ELM-PUL-AR-DWG-3511 CONTROL BUILDING - ARCHITECTURAL PLAN DRAWINGS 1.92
1 21-May-09 20-Jun-09
-6
998 ELM-PUL-AR-DWG-3512 CONTROL BUILDING - ARCHITECTURAL ELEVATION 1.92
1 21-May-09 20-Jun-09
DRAWINGS - 1
999 ELM-PUL-AR-DWG-3513 CONTROL BUILDING - ARCHITECTURAL ELEVATION 1.92
1 21-May-09 20-Jun-09
DRAWINGS - 2
1000 ELM-PUL-AR-DWG-3514 CONTROL BUILDING - ARCHITECTURAL ELEVATION 1.92
1 21-May-09 20-Jun-09
DRAWINGS - 3
1001 ELM-PUL-AR-DWG-3515 CONTROL BUILDING - ARCHITECTURAL ELEVATION 1.92
1 21-May-09 20-Jun-09
DRAWINGS - 4
1002 ELM-PUL-AR-DWG-3516 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 1
1003 ELM-PUL-AR-DWG-3517 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 2
1004 ELM-PUL-AR-DWG-3518 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 3
1005 ELM-PUL-AR-DWG-3519 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 4
1006 ELM-PUL-AR-DWG-3520 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 5
1007 ELM-PUL-AR-DWG-3521 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 6
1008 ELM-PUL-AR-DWG-3522 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 7
1009 ELM-PUL-AR-DWG-3523 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 8
1010 ELM-PUL-AR-DWG-3524 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 9
1011 ELM-PUL-AR-DWG-3525 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 10

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 27 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

1012 ELM-PUL-AR-DWG-3526 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92


1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 11
1013 ELM-PUL-AR-DWG-3527 CONTROL BUILDING - ARCHITECTURAL SECTIONAL 1.92
1 21-May-09 20-Jun-09
DRAWINGS AT DIFFERENT GRID - 12
1014 ELM-PUL-AR-DWG-4001 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL PLAN 1.44
1 8-May-09 7-Jun-09
DRAWINGS - 1
1015 ELM-PUL-AR-DWG-4002 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL PLAN 1.44
1 8-May-09 7-Jun-09
DRAWINGS - 2
1016 ELM-PUL-AR-DWG-4003 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL PLAN 1.44
1 8-May-09 7-Jun-09
DRAWINGS - 3
1017 ELM-PUL-AR-DWG-4004 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL PLAN 1.44
1 8-May-09 7-Jun-09
DRAWINGS - 4
1018 ELM-PUL-AR-DWG-4005 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
ELEVATION DRAWINGS - 1
1019 ELM-PUL-AR-DWG-4006 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
ELEVATION DRAWINGS - 2
1020 ELM-PUL-AR-DWG-4007 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
ELEVATION DRAWINGS - 3
1021 ELM-PUL-AR-DWG-4008 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
ELEVATION DRAWINGS - 4
1022 ELM-PUL-AR-DWG-4009 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
SECTIONAL DRAWINGS AT DIFFERENT GRIDS - 1
1023 ELM-PUL-AR-DWG-4010 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
SECTIONAL DRAWINGS AT DIFFERENT GRIDS - 2
1024 ELM-PUL-AR-DWG-4011 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
SECTIONAL DRAWINGS AT DIFFERENT GRIDS - 3
1025 ELM-PUL-AR-DWG-4012 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
SECTIONAL DRAWINGS AT DIFFERENT GRIDS - 4
1026 ELM-PUL-AR-DWG-4013 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
SECTIONAL DRAWINGS AT DIFFERENT GRIDS - 5
1027 ELM-PUL-AR-DWG-4014 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
SECTIONAL DRAWINGS AT DIFFERENT GRIDS - 6
1028 ELM-PUL-AR-DWG-4015 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
SECTIONAL DRAWINGS AT DIFFERENT GRIDS - 7
1029 ELM-PUL-AR-DWG-4016 MAIN SWITCHGEAR BUILDING - ARCHITECTURAL 1.44
1 8-May-09 7-Jun-09
SECTIONAL DRAWINGS AT DIFFERENT GRIDS - 8
1030 ELM-PUL-CV-REQ-0301 4.80
REQUISITION - TOPOGRAPHIC SURVEY 4 11-Mar-09 14-Mar-09
1031 ELM-PUL-CV-REQ-0302 7.20
REQUISITION - GEOTECHNICAL INVESTIGATION WORKS 4 11-Mar-09 14-Mar-09

1032 ELM-PUL-ST-REQ-0304 REQUISITION - SUPPLY OF STRUCTURAL STEEL 12.00


4 11-Mar-09 13-Mar-09
PROFILES INCLUDING PLATES
1033 ELM-PUL-ST-REQ-0306 REQUISITION - FABRICATION AND 12.00
PAINTING/GALVANISING OF MISCELLANEOUS
4 11-Mar-09 27-Apr-09
STRUCTURAL STEEL WORKS (GRATINGS, CHEQUERED
PLATES, LADDER, ETC)
1034 ELM-PUL-ST-REQ-0307 REQUISITION - ANCHOR BOLTS, NUTS, LOCK NUTS AND 12.00
4 11-Mar-09 28-Mar-09
WASHERS
1035 ELM-PUL-ST-REQ-0314 12.00
REQUISITION - PRE ENGINEERED BUILDINGS / SHEDS 4 6-May-09 27-May-09

1036 ELM-PUL-ST-REQ-0315 REQUISITION - CONTAINERIZED BUILDINGS (LEER & 12.00


4 13-May-09 3-Jun-09
LIER)
1037 ELM-PUL-ST-REQ-0316 10.80
REQUISITION - X STEEL 4 6-Apr-09 27-Apr-09
1038 ELM-PUL-CV-TBE-0301 4.80
TBE - TOPOGRAPHIC SURVEY 4 24-Mar-09 31-Mar-09
1039 ELM-PUL-CV-TBE-0302 4.80
TBE - GEOTECHNICAL INVESTIGATION WORKS 4 24-Mar-09 31-Mar-09
1040 ELM-PUL-ST-TBE-0304 TBE - SUPPLY OF STRUCTURAL STEEL PROFILES 4.80
4 3-Apr-09 18-Apr-09
INCLUDING PLATES
1041 ELM-PUL-ST-TBE-0306 TBE - FABRICATION AND PAINTING/GALVANISING OF 4.80
MISCELLANEOUS STRUCTURAL STEEL WORKS 4 18-May-09 2-Jun-09
(GRATINGS, CHEQUERED PLATES, LADDER, ETC)
1042 ELM-PUL-ST-TBE-0307 4.80
TBE - ANCHOR BOLTS, NUTS, LOCK NUTS AND WASHERS 4 18-Apr-09 3-May-09

1043 ELM-PUL-ST-TBE-0316 4.80


TBE - X STEEL 4 18-May-09 2-Jun-09
1044 ELM-PUL-ST-MTO-0009 1.20
MTO FOR STRUCTURAL STEEL - 1ST LOT 4 1-Apr-09 20-Apr-09
TELECOM
1045 ELM-PUL-TE-BOD-0001 TELECOMS DESIGN BASIS 1 12.00 16-Mar-09 6-Apr-09

1046 ELM-PUL-TE-BKD-0002 TELECOMS FIBER OPTIC TRANSMISSION/MULTIPLEXER 1 1.44 16-Mar-09 23-Apr-09


SYSTEM BLOCK DIAGRAM

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 28 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

1047 ELM-PUL-TE-BKD-0003 TELECOMS CLOSE CIRCUIT TELEVISION (CCTV) SYSTEM 1 1.44 18-Mar-09 23-Apr-09
BLOCK DIAGRAM
1048 ELM-PUL-TE-BKD-0004 TELECOMS TELEPHONE SYSTEM BLOCK DIAGRAM 1 1.44 22-Mar-09 23-Apr-09

1049 ELM-PUL-TE-BKD-0005 TELECOMS PUBLIC ADDRESS GENERAL ALARM (PA/GA) 1 1.44 24-Mar-09 23-Apr-09
SYSTEM BLOCK DIAGRAM
1050 ELM-PUL-TE-BKD-0006 TELECOMS RADIO SYSTEMS BLOCK DIAGRAM 1 1.44 26-Mar-09 23-Apr-09

1051 ELM-PUL-TE-BKD-0007 TELECOMS INFORMATION TECHNOLOGY (IT) SYSTEM 1 1.44 30-Mar-09 23-Apr-09
BLOCK DIAGRAM
1052 ELM-PUL-TE-BKD-0008 TELECOMS SECURITY SYSTEM BLOCK DIAGRAM 1 1.44 1-Apr-09 23-Apr-09

1053 ELM-PUL-TE-BKD-0009 TELECOMS WEATHER MONITORING SYSTEM BLOCK 1 1.44 5-Apr-09 23-Apr-09
DIAGRAM
1054 ELM-PUL-TE-BKD-0010 TELECOMS ENTERTAINMENT SYSTEM BLOCK DIAGRAM 1 1.44 7-Apr-09 23-Apr-09

1055 ELM-PUL-TE-BKD-0011 TELECOMS STRUCTURED CABLING SYSTEM BLOCK 1 1.44 9-Apr-09 23-Apr-09
DIAGRAM
1056 ELM-PUL-TE-BKD-0012 TELECOMS FIBER OPTIC CABLE ARCHITECTURE BLOCK 1 1.44 12-Apr-09 23-Apr-09
DIAGRAM - CPF AREAS
1057 ELM-PUL-TE-BKD-0013 TELECOMS FIBER OPTIC CABLE ARCHITECTURE BLOCK 1 3.84 15-Apr-09 23-Apr-09
DIAGRAM - OFFSITES
1058 ELM-PUL-TE-LGN-0001 TELECOMS SYMBOLS AND LEGENDS DRAWING 1 1.44 28-Mar-09 23-Apr-09

1059 ELM-PUL-TE-LST-0001 TELECOMS EQUIPMENT TAGGING INDEX 1 1.92 29-Mar-09 23-Apr-09

1060 ELM-PUL-TE-DSN-0011 TELECOMS FIBER OPTIC CABLE SPECIFICATION 1 0.96 30-Mar-09 23-Apr-09

1061 ELM-PUL-TE-DSN-0012 TELECOMS FIBER OPTIC CABLE INSTALLATION 1 1.44 31-Mar-09 23-Apr-09
SPECIFICATION
1062 ELM-PUL-TE-DSN-0013 TELECOMS COPPER CABLE SPECIFICATIONS 1 1.44 1-Apr-09 23-Apr-09

1063 ELM-PUL-TE-BKD-0014 TELECOMS SYSTEMS GROUNDING BLOCK DIAGRAM 2 2.88 2-Apr-09 23-Apr-09

1064 ELM-PUL-TE-STU-0001 TELECOMS RADIO COVERAGE STUDY 1 6.24 3-May-09 5-Jun-09

1065 ELM-PUL-TE-ELO-0001 TELECOMS CONCEPTUAL EQUIPMENT LAYOUT - CCTV 2 1.44 15-Apr-09 5-May-09
CAMERAS
1066 ELM-PUL-TE-ELO-0002 TELECOMS CONCEPTUAL EQUIPMENT LAYOUT - PA/GA 2 2.64 15-Apr-09 5-May-09
LOUDSPEAKERS
1067 ELM-PUL-TE-BKD-0015 UPDATED TELECOMS AND IT OVERALL SYSTEM BLOCK 1 5.76 19-Apr-09 10-May-09
DIAGRAM
1068 ELM-PUL-TE-BKD-0016 INTERFIELD PORTION OFFSITES LOCAL AREA NETWORK 1 3.84 21-Apr-09 10-May-09
(OLAN) BLOCK DIAGRAM
1069 ELM-PUL-TE-DSN-0014 UPDATED GENERAL SPECIFICATIONS FOR PUBLIC 1 1.44 23-Apr-09 10-May-09
ADDRESS GENERAL ALARM (PA/GA) SYSTEM
1070 ELM-PUL-TE-DSN-0015 UPDATED TELECOMS GENERAL SPECIFICATIONS FOR 1 1.44 27-Apr-09 10-May-09
STRUCTURED AND CATV CABLING SYSTEM
1071 ELM-PUL-TE-DSN-0016 UPDATED TELECOMS ENTERTAINMENT SYSTEM 1 1.44 29-Apr-09 10-May-09
SPECIFICATIONS
1072 ELM-PUL-TE-DSN-0017 UPDATED TELECOMS SECURITY SYSTEM SPECIFICATIONS 1 1.44 4-May-09 20-May-09

1073 ELM-PUL-TE-DSN-0018 UPDATED GENERAL SPECIFICATIONS FOR WEATHER 1 1.44 6-May-09 20-May-09
MONITORING SYSTEM
1074 ELM-PUL-TE-DSN-0019 UPDATED GENERAL SEPECIFICATIONS FOR PBX, LAN, 1 1.44 10-May-09 20-May-09
WAN, IT AND NETWORK MANAGEMENT SYSTEMS

1075 ELM-PUL-TE-DSN-0020 UPDATED RADIO SYSTEMS SPECIFICATIONS 1 1.44 12-May-09 20-May-09

1076 ELM-PUL-TE-DSN-0021 UPDATED CLOSE CIRCUIT TELEVISION (CCTV) SYSTEM 1 1.44 14-May-09 20-May-09
SPECIFICATIONS
1077 ELM-PUL-TE-DSN-0022 UPDATED RADIO TOWER SPECIFICATIONS 1 1.44 17-May-09 20-May-09

PROCUREMENT
CIVIL
1076 ISSUE INQUIRY - FABRICATION & PAINTING OF
20-Apr-09 27-Apr-09
STRUCTURAL STEEL NA 244.54
1077 ISSUE INQUIRY - STRUCTURAL STEEL PROFILES
11-Mar-09 13-Mar-09
INCLUDING PLATES NA 163.02
1078
ISSUE INQUIRY - ANCHOR BOLTS 21-Mar-09 28-Mar-09
NA 1.77
1079
ISSUE INQUIRY - TOPOSURVEY 11-Mar-09 14-Mar-09
NA 0.89
1080
ISSUE INQUIRY - GEOTECHNICAL INVESTIGATION 11-Mar-09 14-Mar-09
NA 0.89
1081
ISSUE INQUIRY - X-STEEL 12-Apr-09 27-Apr-09
NA 0.89

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 29 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

1082 RECEIVE BIDS - FABRICATION & PAINTING OF


12-May-09 18-May-09
STRUCTURAL STEEL NA 122.27
1083 RECEIVE BIDS - STRUCTURAL STEEL PROFILES
28-Mar-09 3-Apr-09
INCLUDING PLATES NA 81.51
1084
RECEIVE BIDS - ANCHOR BOLTS 12-Apr-09 18-Apr-09
NA 0.89
1085
RECEIVE BIDS - TOPOSURVEY 21-Mar-09 24-Mar-09
NA 0.44
1086
RECEIVE BIDS - GEOTECHNICAL INVESTIGATION 21-Mar-09 24-Mar-09
NA 0.44
1087
RECEIVE BIDS - X-STEEL 12-May-09 18-May-09
NA 0.44
1088 TBE COMPLETE - STRUCTURAL STEEL PROFILES
3-Apr-09 18-Apr-09
INCLUDING PLATES NA 407.56
1089
TBE COMPLETE - ANCHOR BOLTS 18-Apr-09 3-May-09
NA 4.43
1090
TBE COMPLETE - TOPOSURVEY 24-Mar-09 31-Mar-09
NA 2.22
1091
TBE COMPLETE - GEOTECHNICAL INVESTIGATION 24-Mar-09 31-Mar-09
NA 2.22
1092 PLACE ORDER - STRUCTURAL STEEL PROFILES
18-Apr-09 25-Apr-09
INCLUDING PLATES NA 163.02
1093
PLACE ORDER - ANCHOR BOLTS 3-May-09 10-May-09
NA 1.77
1094
PLACE ORDER - TOPOSURVEY 31-Mar-09 5-Apr-09
NA 0.89
1095
PLACE ORDER - GEOTECHNICAL INVESTIGATION 31-Mar-09 5-Apr-09
NA 0.89
MECHANICAL STATIC
1096
ISSUE INQUIRY - COLUMN 29-Apr-09 6-May-09
NA 97.46
1097
ISSUE INQUIRY - HP VESSELS 30-Mar-09 6-Apr-09
NA 225.93
1098
ISSUE INQUIRY - LP VESSELS 6-Apr-09 13-Apr-09
NA 210.87
1099
ISSUE INQUIRY - AIR COOLED HEAT EXCHANGERS 13-Apr-09 20-Apr-09
NA 273.77
1100
ISSUE INQUIRY - FIRED HEATER PACKAGE 15-Mar-09 22-Mar-09
NA 61.67
1101
22-Apr-09 27-Apr-09
ISSUE INQUIRY - FABRICATION FIRED HEATER PACKAGE NA 92.50
1102
ISSUE INQUIRY - SPHERE FABRICATION 11-Mar-09 15-Mar-09
NA 31.01
1103
ISSUE INQUIRY - S&T HEAT EXCHANGERS 21-Mar-09 28-Mar-09
NA 349.97
1104
ISSUE INQUIRY - TANK FABRICATION 13-Mar-09 20-Mar-09
NA 193.15
1105
RECEIVE BIDS - COLUMN 27-May-09 3-Jun-09
NA 48.73
1106
RECEIVE BIDS - HP VESSELS 27-Apr-09 4-May-09
NA 112.97
1107
RECEIVE BIDS - LP VESSELS 4-May-09 11-May-09
NA 105.43
1108
RECEIVE BIDS - AIR COOLED HEAT EXCHANGERS 11-May-09 18-May-09
NA 136.89
1109
RECEIVE BIDS - FIRED HEATER PACKAGE 12-Apr-09 19-Apr-09
NA 30.83
1110
18-May-09 25-May-09
RECEIVE BIDS - FABRICATION FIRED HEATER PACKAGE NA 46.25
1111
RECEIVE BIDS - SPHERE FABRICATION 30-Mar-09 4-Apr-09
NA 15.51
1112
RECEIVE BIDS - S&T HEAT EXCHANGERS 12-Apr-09 18-Apr-09
NA 174.99
1113
RECEIVE BIDS - TANK FABRICATION 4-Apr-09 10-Apr-09
NA 96.57
1114
TBE COMPLETE - FIRED HEATER PACKAGE 19-Apr-09 4-May-09
NA 154.16
1115
TBE COMPLETE - SPHERE FABRICATION 4-Apr-09 19-Apr-09
NA 77.53
1116
TBE COMPLETE - S&T HEAT EXCHANGERS 18-Apr-09 3-May-09
NA 874.93
1117
TBE COMPLETE - TANK FABRICATION 10-Apr-09 25-Apr-09
NA 482.87
1118
TBE COMPLETE - HP VESSELS 4-May-09 25-Apr-09
NA 564.83
1119
TBE COMPLETE - LP VESSELS 11-May-09 25-Apr-09
NA 527.17
1120
TBE COMPLETE - CS PLATES FOR LP VESSELS 23-Apr-09 8-May-09
NA 0.00
1121 TBE COMPLETE - CS PLATES FOR HP VESSELS /
18-Apr-09 3-May-09
COLUMNS NA 0.00

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 30 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

1122
TBE COMPLETE - CS PLATES FOR STORAGE TANKS 18-Apr-09 3-May-09
NA 0.00
1123
PLACE ORDER - SPHERE FABRICATION 19-Apr-09 10-May-09
NA 31.01
1124
PLACE ORDER - S&T HEAT EXCHANGERS 3-May-09 10-May-09
NA 349.97
1125
PLACE ORDER - TANK FABRICATION 25-Apr-09 10-May-09
NA 193.15
1126
PLACE ORDER - HP VESSELS 25-Apr-09 10-May-09
NA 225.93
1127
PLACE ORDER - LP VESSELS 25-Apr-09 10-May-09
NA 210.87
MECHANICAL ROTATING
1028 ISSUE INQUIRY - ASSOCIATED & BOOSTER GAS
11-Mar-09 11-Mar-09
COMPRESSOR PACKAGE (MOTOR DRIVEN) NA 460.72
1029 ISSUE INQUIRY - GAS DEHYDRATION REGENERATION
30-Mar-09 6-Apr-09
GAS COMPRESSOR NA 138.22
1030 ISSUE INQUIRY - INJECTION GAS COMPRESSOR PACKAGE
29-Apr-09 6-May-09
(GT DRIVEN) NA 895.75
1031
ISSUE INQUIRY - TURBO EXPANDER PACKAGE 29-Apr-09 6-May-09
NA 76.20
1032
ISSUE INQUIRY - HEAVY DUTY HORIZONTAL PUMPS 9-Apr-09 16-Apr-09
NA 149.73
1033 ISSUE INQUIRY - INSTRUMENT AIR COMPRESSOR AND
21-Mar-09 28-Mar-09
DRYER PACKAGE NA 65.56
1034 RECEIVE BIDS - ASSOCIATED & BOOSTER GAS
1-Apr-09 4-Apr-09
COMPRESSOR PACKAGE (MOTOR DRIVEN) NA 230.36
1035 RECEIVE BIDS - GAS DEHYDRATION REGENERATION
27-Apr-09 4-May-09
GAS COMPRESSOR NA 69.11
1036 RECEIVE BIDS - INJECTION GAS COMPRESSOR PACKAGE
27-May-09 3-Jun-09
(GT DRIVEN) NA 447.87
1037
RECEIVE BIDS - TURBO EXPANDER PACKAGE 27-May-09 3-Jun-09
NA 38.10
1038
RECEIVE BIDS - HEAVY DUTY HORIZONTAL PUMPS 7-May-09 14-May-09
NA 74.87
1039 RECEIVE BIDS - INSTRUMENT AIR COMPRESSOR AND
12-Apr-09 18-Apr-09
DRYER PACKAGE NA 32.78
1040 TBE COMPLETE - ASSOCIATED & BOOSTER GAS
4-Apr-09 19-Apr-09
COMPRESSOR PACKAGE (MOTOR DRIVEN) NA 1151.80
1041 TBE COMPLETE - INJECTION GAS COMPRESSOR
3-Jun-09 24-Apr-09
PACKAGE (GT DRIVEN) NA 2239.37
1042 TBE COMPLETE - INSTRUMENT AIR COMPRESSOR AND
18-Apr-09 3-May-09
DRYER PACKAGE NA 163.91
1043 PLACE ORDER - ASSOCIATED & BOOSTER GAS
19-Apr-09 10-May-09
COMPRESSOR PACKAGE (MOTOR DRIVEN) NA 460.72
1044 PLACE ORDER - INJECTION GAS COMPRESSORS (GT
24-Apr-09 15-May-09
DRIVEN) NA 895.75
1045 PLACE ORDER - INSTRUMENT AIR COMPRESSOR AND
3-May-09 10-May-09
DRYER PACKAGE NA 65.56
PIPING
1046
ISSUE INQUIRY - CS & LTCS PIPES ( SEAMLESS ) 21-Mar-09 28-Mar-09
NA 115.18
1047
ISSUE INQUIRY - CS & LTCS PIPES ( WELDED ) 21-Mar-09 28-Mar-09
NA 127.58
1048
ISSUE INQUIRY - SS PIPES ( SEAMLESS ) 28-Mar-09 4-Apr-09
NA 16.83
1049
ISSUE INQUIRY - SS PIPES ( WELDED ) 28-Mar-09 4-Apr-09
NA 23.04
1050
ISSUE INQUIRY - DSS PIPES 5-Apr-09 12-Apr-09
NA 53.16
1051
ISSUE INQUIRY - CS & LTCS WROUGHT FITTINGS 31-Mar-09 7-Apr-09
NA 90.37
1052
ISSUE INQUIRY - SS WROUGHT FITTINGS 31-Mar-09 7-Apr-09
NA 16.83
1053
ISSUE INQUIRY - DSS WROUGHT FITTINGS 5-Apr-09 12-Apr-09
NA 19.49
1054
ISSUE INQUIRY - FORGED FITTINGS 31-Mar-09 7-Apr-09
NA 3.54
1055 ISSUE INQUIRY - CS & LTCS FLANGES AND SPECTACLE
7-Apr-09 7-Apr-09
BLINDS NA 23.92
1056 ISSUE INQUIRY - SS & DSS FLANGES AND SPECTACLE
12-Apr-09 12-Apr-09
BLINDS NA 17.72
1057
ISSUE INQUIRY - CATHODIC PROTECTION SYSTEM 20-Apr-09 27-Apr-09
NA 1.77
1058
RECEIVE BIDS - CS & LTCS PIPES ( SEAMLESS ) 12-Apr-09 18-Apr-09
NA 57.59
1059
RECEIVE BIDS - CS & LTCS PIPES ( WELDED ) 12-Apr-09 18-Apr-09
NA 63.79

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 31 OF 32
El-Merk Project
CPF & Telecommunication Systems (Lot 1 & 7), Algeria

Petrofac Job No.: JI-195


Contract No. : SC 4012100
Document No: ELM-PUL-PC-SCH-0002
90 DAYS FRONT END SCHEDULE (UPTO 11-JUN-09)

SR. NO. Document No. Document Description Approval CWF Plan Start Plan Finish Actual Actual Progress EV
category Start Finish %

1060
RECEIVE BIDS - SS PIPES ( SEAMLESS ) 22-Apr-09 25-Apr-09
NA 8.42
1061
RECEIVE BIDS - SS PIPES ( WELDED ) 25-Apr-09 25-Apr-09
NA 11.52
1062
RECEIVE BIDS - DSS PIPES 27-Apr-09 3-May-09
NA 26.58
1063
RECEIVE BIDS - CS & LTCS WROUGHT FITTINGS 22-Apr-09 28-Apr-09
NA 45.19
1064
RECEIVE BIDS - SS WROUGHT FITTINGS 22-Apr-09 28-Apr-09
NA 8.42
1065
RECEIVE BIDS - DSS WROUGHT FITTINGS 27-Apr-09 3-May-09
NA 9.75
1066
RECEIVE BIDS - FORGED FITTINGS 22-Apr-09 28-Apr-09
NA 1.77
1067 RECEIVE BIDS - CS & LTCS FLANGES AND SPECTACLE
22-Apr-09 28-Apr-09
BLINDS NA 11.96
1068 RECEIVE BIDS - SS & DSS FLANGES AND SPECTACLE
27-Apr-09 3-May-09
BLINDS NA 8.86
1069
RECEIVE BIDS - CATHODIC PROTECTION SYSTEM 12-May-09 18-May-09
NA 0.89
1070
TBE COMPLETE - CS & LTCS PIPES ( SEAMLESS ) 18-Apr-09 3-May-09
NA 287.95
1071
TBE COMPLETE - CS & LTCS PIPES ( WELDED ) 18-Apr-09 3-May-09
NA 318.96
1072
TBE COMPLETE - SS PIPES ( SEAMLESS ) 25-Apr-09 10-May-09
NA 42.09
1073
TBE COMPLETE - SS PIPES ( WELDED ) 25-Apr-09 10-May-09
NA 57.59
1074
PLACE ORDER - CS & LTCS PIPES ( SEAMLESS ) 3-May-09 10-May-09
NA 115.18
1075
PLACE ORDER - CS & LTCS PIPES ( WELDED ) 3-May-09 10-May-09
NA 127.58
ELECTRICAL
1076
ISSUE INQUIRY - DIESEL ENGINE GENERATORS 22-Mar-09 12-Apr-09
NA 67.34
1077
30-Mar-09 20-Apr-09
ISSUE INQUIRY - POWER & DISTRIBUTION TRANSFORMER NA 62.91
1078
RECEIVE BIDS - DIESEL ENGINE GENERATORS 27-Apr-09 3-May-09
NA 33.67
1079 RECEIVE BIDS - POWER & DISTRIBUTION
5-May-09 11-May-09
TRANSFORMER NA 31.45
INSTRUMENTATION
1080 ISSUE INQUIRY - INTEGRATED CONTROL & SAFETY
22-Mar-09 12-Apr-09
SYSTEMS AND SCADA NA 279.98
1081 RECEIVE BIDS - INTEGRATED CONTROL & SAFETY
27-Apr-09 4-May-09
SYSTEMS AND SCADA NA 139.99
CONSTRUCTION
CIVIL
1082
GEOTECHNICAL SURVEY WORK AT SITE 15-Apr-09 14-Jun-09
NA 447.00
1083
TOPOGRAPHY SURVEY WORK AT SITE 15-Apr-09 10-May-09
NA 447.00
1084
1-May-09
START MOBILIZATION - CPF CIVIL WORKS CONTRACTOR NA 0.00

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012 PAGE 32 OF 32
JOB NO. : JI 2008

TECHNICAL DOCUMENT REGISTER


STANDARD REPORT

DOC. ISSUING DISP./ SYS SEQ. BILING. REV. START ISSUE FOR COMPLETE ISSUE FOR RECD. COMMENTS ISSUE FOR RECD. COMMENTS ISSUED FOR MAN HRS. EARNED
PROGRESS ACTIVITY
ASST./W SOURCE DOC. NO. NO. DOC. DESCRIPTION CATEG-O IDC IDC REVIEW/APPROVAL INFORMATION DESIGN/CONST. MAN HRS
BR TYPE TRANS RY
IDENT. DATE
DATE DATE DATE TRANS DATE TRANS CODE DATE TRANS DATE TRANS CODE DATE TRANS

PROCESS
Engineering
P 01-Mar-2011 15/Mar/2011 29/Mar/2011 15/Aug/2011
P HEAT & MATERIAL BALANCE IN SALAH CPF 95.00
HB00 PPCE 00 0500 A 1 F 0134 0219 2 15/Aug/2011 180 E1D03PR 171.00
A 08-Mar-2011 10/Mar/2011 05/Apr/2011
P 21-Apr-2011 30-Nov-2011
HYDRAULICS CALCULATION REPORT FOR IS-CPF
HB00 P PPCE 00 0501 0 3 F 21-Apr-2011 30-Nov-2011 SF-1 95.00 882 E1D03PR 837.90
A 21-Apr-2011 12-Oct-2011
P 15-Apr-2011 15-May-2011
SEPARATOR & SCRUBBER SIZING FOR IS-CPF
HB00 P PPCE 00 0507 0 3 F SF-1 L-11 1 100.00 179 E1D03PR 179.00
A 21-Apr-2011 20-Jul-2011 07-Sep-2011
P 01-Mar-2011 31-Mar-2011
RELIEF VALVE CALCULATION FOR IS-CPF
HB00 P PPCE 00 1000 A 3 F SF-0 100.00 200 E1D03PR 200.00
A 15-Feb-2011 05-Jun-2011
P 15-Mar-2011 29-Apr-2011
P VOLUME CALCULATION FOR BLOWDOWN STUDY IS-CPF 100.00
HB00 PPCE 00 1001 0 3 F SF-1 100 E1D03PR 100.00
A 10-Mar-2011 09-Oct-2011
P 01-Mar-2011 08-Mar-2011
EQUIVALENT LENGTH CALCULATION FOR PSV INLET
HB00 P PPCE 00 1002 A 3 F SF-0 100.00 200 E1D03PR 200.00
LINE - IS-CPF
A 03-Mar-2011 24-May-2011
P 01-Mar-2011 16-Mar-2011
EQUIVALENT LENGTH CALCULATION FOR PSV OUTLET
HB00 P PPCE 00 1003 0 3 F SF-2 100.00 150 E1D03PR 150.00
& BDVS LINE - IS-CPF
A 05-Apr-2011 25-Oct-2011
P 01-Mar-2011 22-Mar-2011
EQUIVALENT LENGTH CALCULATION FOR FLARE
HB00 P PPCE 00 1004 0 3 F SF-2 100.00 150 E1D03PR 150.00
SYSTEM - IS-CPF
A 03-Mar-2011 25-Oct-2011
P 25-Mar-2011 28/Mar/2011 11/Apr/2011 22/Nov/2011
P IS CPF HP FLARE KO DRUM SIZING CALCULATION SF-1 100.00
HB00 PPCE 04 1000 0 1 F 0690 0737 2 68 E1D03C 68.00
A 06-Mar-2011 23/May/2011 14/Jun/2011 14/Jul/2011
P 25-Mar-2011 28/Mar/2011 11/Apr/2011 22/Nov/2011
IS CPF LP FLARE KO DRUM SIZING CALCULATION SF-1
HB00 P PPCE 04 1001 0 1 F 0690 0747 2 100.00 68 E1D03C 68.00
A 13-Mar-2011 23/May/2011 14/Jun/2011 14/Jul/2011
P
HYDRAULIC CALCULATIONS FOR IN SALAH CPF
HB09 P PPCE 03 1001 - 3 F 0.00 1 E1D03PR 0.00
PRODUCED WATER PUMPS H-PA-038001A/B
A
P
HYDRAULIC CALCULATIONS FOR IN SALAH CPF WATER
HB09 P PPCE 03 1002 - 3 F 0.00 1 E1D03PR 0.00
INJECTION PUMPS H-PB-038002A/B/C
A
P 01-Aug-2011 31-Aug-2011
P SIZING FOR IS CPF PRODUCED WATER EVAPORATION 95.00
HB09 PPCE 03 1004 0 3 F SF-1 1 E1D03PR 0.95
POND (H-TP-038001)
A 01-Aug-2011 24-Aug-2011
P 01-Jul-2011 31-Aug-2011
EQUIPMENT SIZING - IN SALAH CPF PLANT WATER
HB09 P PPCE 05 1000 0 3 F SF-1 95.00 1 E1D03PR 0.95
STORAGE TANK H-TA-052001
A 04-Aug-2011 22-Aug-2011
P
HYDRAULIC CALCULATIONS FOR IN SALAH CPF PLANT
HB09 P PPCE 05 1001 - 3 F 0.00 1 E1D03PR 0.00
WATER TRANSFER PUMPS H-PA-052001A/B
A
P
HYDRAULIC CALCULATIONS FOR IN SALAH CPF PLANT
HB09 P PPCE 05 1002 - 3 F 0.00 1 E1D03PR 0.00
WATER LIFT PUMPS H-PS-052002A/B/C
A
P 01-Jul-2011 31-Aug-2011
P EQUIPMENT SIZING - IN SALAH CPF FRESH WATER 95.00
HB09 PPCE 05 1001 0 3 F SF-1 1 E1D03PR 0.95
STORAGE TANK H-TA-053001
A 04-Aug-2011 22-Aug-2011
P
HYDRAULIC CALCULATIONS FOR IN SALAH CPF FRESH
HB09 P PPCE 05 1002 - 3 F 0.00 1 E1D03PR 0.00
WATER PRESSURISATION PUMPS H-PA-053001A/B
A
P
HYDRAULIC CALCULATIONS FOR IN SALAH CPF GLYCOL
HB09 P PPCE 05 1000 - 3 F 0.00 1 E1D03PR 0.00
DRAINS PUMP H-PH-054002
A

LEGEND: APPROVAL CATEGORY: R - REVIEW; A - APPROVAL; I - INFORMATION 1 of 394


DATES: P - PLANNED, F - FORECAST, A - ACTUAL
This document is an uncontrolled copy when printed or saved. Viewed by:
Ahmad Warsi 13-Mar-2012
PROCUREMENT TRACKING REGISTER

ISG PROJECT - IN SALAH GAS SOUTHERN FIELDS DEVELOPMENT PTR TEMPLATE


CONTRACT NO. : 100045/ISG/CON
DOCUMENT NO : 1 7 11 12 13 14 15-Jan-00 23 24-Jan-00 25-Jan-00 26 28-Jan-00 29-Jan-00 30 09-Jan-00
CUT OFF DATE: 29-Oct-11

Issue Inquiry Requisition Receive Bid TBE Complete Place LOI / LOA Place PO Receive / Approve Key Vendor Drawings / Documents Place Sub-orders Receive Raw Materials Fabrication / Mfg. Inspection Release Note Ex-works Delivery Item on Board Shipping/Air Freight/Land Transport (ATA Port) Custom Clearance and Transport to site/store Visual Inspection on Receipt at Site/Store ROS
Inquiry No. Description Discipline INQD_TAG_NO PO_NO Vendor Name PO Delivery Terms PO_CDD
P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog
Supply, Fab & Galv. of Chainlink Fence,
UU00-P-ZATS-107-1000 Palisade Fence & Gates CIVIL & STRUCTURAL LOT : 001 SF0031 LINK MIDDLE EAST LTD FOB DUBAI SEAPORT, UAE 27-Mar-11 27-Mar-11 100 08-Apr-11 08-Apr-11 100 24-May-11 24-May-11 100 05-Jun-11 05-Jun-11 100 20-Jul-11 05-Jun-11 100 20-Aug-11 10-Aug-11 100.00 27-Aug-11 10-Aug-11 100.00 03-Sep-11 10-Aug-11 100.00 10-Sep-11 05-Sep-11 100.00 18-Oct-11 04-Oct-11 100.00 17-Nov-11 17-Oct-11 100.00 02-Dec-11 22-Oct-11 100.00 11-Nov-11
Supply, Fab & Galv. of Chainlink Fence,
UU00-P-ZATS-107-1000 Palisade Fence & Gates CIVIL & STRUCTURAL LOT : 002 SF0031 LINK MIDDLE EAST LTD FOB DUBAI SEAPORT, UAE 30-Oct-11 27-Mar-11 27-Mar-11 100 08-Apr-11 08-Apr-11 100 24-May-11 24-May-11 100 05-Jun-11 05-Jun-11 100 20-Jul-11 05-Jun-11 100 20-Aug-11 18-Sep-11 100.00 27-Aug-11 18-Sep-11 100.00 03-Sep-11 18-Sep-11 100.00 10-Sep-11 26-Sep-11 18-Oct-11 30-Oct-11 17-Nov-11 30-Oct-11 02-Dec-11 30-Oct-11 11-Nov-11
Supply, Fab & Galv. of Chainlink Fence,
UU00-P-ZATS-107-1000 Palisade Fence & Gates CIVIL & STRUCTURAL LOT : 003 SF0031 LINK MIDDLE EAST LTD FOB DUBAI SEAPORT, UAE 30-Oct-11 27-Mar-11 27-Mar-11 100 08-Apr-11 08-Apr-11 100 24-May-11 24-May-11 100 05-Jun-11 05-Jun-11 100 20-Jul-11 05-Jun-11 100 20-Aug-11 02-Oct-11 100.00 27-Aug-11 02-Oct-11 100.00 03-Sep-11 05-Oct-11 100.00 10-Sep-11 17-Oct-11 18-Oct-11 17-Nov-11 17-Nov-11 17-Nov-11 02-Dec-11 17-Nov-11 11-Nov-11
Supply, Fab & Galv. of Chainlink Fence,
UU00-P-ZATS-107-1000 Palisade Fence & Gates CIVIL & STRUCTURAL LOT : 004 SF0031 LINK MIDDLE EAST LTD FOB DUBAI SEAPORT, UAE 30-Oct-11 27-Mar-11 27-Mar-11 100 08-Apr-11 08-Apr-11 100 24-May-11 24-May-11 100 05-Jun-11 05-Jun-11 100 20-Jul-11 05-Jun-11 100 20-Aug-11 18-Sep-11 43.97 27-Aug-11 18-Sep-11 37.21 03-Sep-11 30-Jun-12 10-Sep-11 30-Jun-12 18-Oct-11 30-Jun-12 17-Nov-11 30-Jun-12 02-Dec-11 30-Jun-12 11-Nov-11
TECHNICAL METAL
UU00-P-ZHTS-090-1000 Anchor Bolts CIVIL & STRUCTURAL LOT : 001 SF0007 ESTABLISHMENT FCA SELLERS WORKS, UAE 09-Jun-11 01-Mar-11 02-Mar-11 100 20-Mar-11 13-Mar-11 100 10-Apr-11 07-Apr-11 100 15-Apr-11 14-Apr-11 100 30-May-11 14-Apr-11 100 25-Jun-11 26-Jul-11 100.00 02-Jul-11 26-Jul-11 100.00 09-Jul-11 26-Jul-11 100.00 16-Jul-11 15-Aug-11 23-Aug-11 12-Sep-11 22-Sep-11 12-Sep-11 07-Oct-11 27-Sep-11 07-Oct-11
TECHNICAL METAL
UU00-P-ZHTS-090-1000 Anchor Bolts CIVIL & STRUCTURAL LOT : 002 SF0007 ESTABLISHMENT FCA SELLERS WORKS, UAE 09-Jun-11 01-Mar-11 02-Mar-11 100 20-Mar-11 13-Mar-11 100 10-Apr-11 07-Apr-11 100 15-Apr-11 14-Apr-11 100 30-May-11 14-Apr-11 100 25-Jun-11 01-Jun-11 100.00 02-Jul-11 01-Jun-11 100.00 09-Jul-11 01-Jun-11 100.00 16-Jul-11 27-Jun-11 100.00 23-Aug-11 22-Jul-11 100.00 22-Sep-11 25-Aug-11 100.00 07-Oct-11 01-Sep-11 100.00 07-Oct-11
TECHNICAL METAL
UU00-P-ZHTS-090-1000 Anchor Bolts - 3rd LOT CIVIL & STRUCTURAL LOT : 003 SF0007 ESTABLISHMENT FCA SELLERS WORKS, UAE 05-Sep-11 01-Mar-11 02-Mar-11 100 20-Mar-11 13-Mar-11 100 10-Apr-11 07-Apr-11 100 15-Apr-11 14-Apr-11 100 30-May-11 14-Apr-11 100 25-Jun-11 18-Sep-11 100.00 02-Jul-11 18-Sep-11 100.00 09-Jul-11 19-Sep-11 100.00 16-Jul-11 03-Oct-11 23-Aug-11 03-Nov-11 22-Sep-11 03-Nov-11 07-Oct-11 18-Nov-11 07-Oct-11
TECHNICAL METAL
UU00-P-ZHTS-090-1000 Anchor Bolts - 4th LOT CIVIL & STRUCTURAL LOT : 004 SF0007 ESTABLISHMENT FCA SELLERS WORKS, UAE 01-Mar-11 02-Mar-11 100 20-Mar-11 13-Mar-11 100 10-Apr-11 07-Apr-11 100 15-Apr-11 14-Apr-11 100 30-May-11 14-Apr-11 100 25-Jun-11 05-Nov-11 02-Jul-11 05-Nov-11 09-Jul-11 15-Dec-11 16-Jul-11 15-Dec-11 23-Aug-11 15-Dec-11 22-Sep-11 15-Dec-11 07-Oct-11 15-Dec-11 07-Oct-11
TECHNICAL METAL
UU00-P-ZHTS-090-1000 Anchor Bolts - 4th LOT CIVIL & STRUCTURAL LOT : 005 SF0007 ESTABLISHMENT FCA SELLERS WORKS, UAE 09-Jun-11 01-Mar-11 02-Mar-11 100 20-Mar-11 13-Mar-11 100 10-Apr-11 07-Apr-11 100 15-Apr-11 14-Apr-11 100 30-May-11 14-Apr-11 100 25-Jun-11 31-May-11 02-Jul-11 31-May-11 09-Jul-11 09-Jun-11 16-Jul-11 09-Jun-11 23-Aug-11 09-Jun-11 22-Sep-11 09-Jun-11 07-Oct-11 09-Jun-11 07-Oct-11
Supply of Structural Steel Profiles &
UU00-P-ZHTS-090-1001 Plates CIVIL & STRUCTURAL UU00-P-ZHTS-090-1001-102 23-Feb-11 07-Feb-11 100 23-Mar-11 07-Mar-11 100 05-May-11 19-Apr-11 100 27-May-11 11-May-11 100 11-Jul-11 11-May-11 100 05-Aug-11 13-Jul-11 12-Aug-11 19-Jul-11 19-Aug-11 26-Jul-11 26-Aug-11 02-Aug-11 03-Oct-11 09-Sep-11 02-Nov-11 09-Oct-11 17-Nov-11 24-Oct-11 28-Sep-11
FCA SELLER'S WORKS, MUSSAFAH, ABU
UU00-P-ZHTS-090-1002 Structural Steel Fabrication CIVIL & STRUCTURAL LOT : 003 SF0015 TIGER STEEL ENGINEERING DHABI EMIRATE, UAE 30-Jun-12 22-Feb-11 06-Mar-11 100 15-Mar-11 23-Mar-11 100 05-Apr-11 19-Apr-11 100 12-Apr-11 11-May-11 100 27-May-11 11-May-11 100 23-Aug-11 21-May-12 26.59 30-Aug-11 20-Sep-11 8.60 06-Sep-11 30-Jun-12 13-Sep-11 07-Jul-12 21-Oct-11 14-Aug-12 20-Nov-11 13-Sep-12 05-Dec-11 28-Sep-12 05-Dec-11
FCA SELLER'S WORKS, MUSSAFAH, ABU
UU00-P-ZHTS-090-1002 Structural Steel Fabrication CIVIL & STRUCTURAL LOT : 001 SF0015 TIGER STEEL ENGINEERING DHABI EMIRATE, UAE 30-Jun-12 22-Feb-11 06-Mar-11 100 15-Mar-11 23-Mar-11 100 05-Apr-11 19-Apr-11 100 12-Apr-11 11-May-11 100 27-May-11 11-May-11 100 23-Aug-11 07-Sep-11 100.00 30-Aug-11 19-Sep-11 100.00 06-Sep-11 20-Sep-11 100.00 13-Sep-11 26-Sep-11 21-Oct-11 30-Oct-11 20-Nov-11 30-Oct-11 05-Dec-11 30-Oct-11 05-Dec-11
FCA SELLER'S WORKS, MUSSAFAH, ABU
UU00-P-ZHTS-090-1002 Structural Steel Fabrication CIVIL & STRUCTURAL LOT : 002 SF0015 TIGER STEEL ENGINEERING DHABI EMIRATE, UAE 30-Jun-12 22-Feb-11 06-Mar-11 100 15-Mar-11 23-Mar-11 100 05-Apr-11 19-Apr-11 100 12-Apr-11 11-May-11 100 27-May-11 11-May-11 100 23-Aug-11 01-Oct-11 100.00 30-Aug-11 04-Oct-11 100.00 06-Sep-11 16-Oct-11 100.00 13-Sep-11 10-Oct-11 21-Oct-11 10-Nov-11 20-Nov-11 10-Nov-11 05-Dec-11 10-Nov-11 05-Dec-11

UU00-P-ZHTS-090-1004 Grating, Chq. Plate, Handrail & Ladder CIVIL & STRUCTURAL UU00-P-ZHTS-090-1004-104 16-May-11 23-Aug-11 100 15-Jun-11 03-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 07-Nov-11 09-Mar-12 14-Nov-11 16-Mar-12 21-Nov-11 23-Mar-12 28-Nov-11 30-Mar-12 05-Jan-12 07-May-12 04-Feb-12 06-Jun-12 19-Feb-12 21-Jun-12 19-Feb-12
FOB HOUSTON PORT, USA & JEBEL ALI
UB00-P-MLTS-000-1009 HP Flare Package MECHANICAL STATIC H-FX-043001 SF0071 CALLIDUS TECHNOLOGIES LLC PORT, UAE 17-May-12 16-Apr-11 16-May-11 100 27-Jun-11 09-Jun-11 100 04-Aug-11 07-Sep-11 100 11-Aug-11 08-Sep-11 100 25-Sep-11 08-Sep-11 100 09-Nov-11 04-Dec-11 12 19-Nov-11 14-Dec-11 18-Jan-12 10-Feb-12 16-Jun-12 04-Jul-12 23-Jun-12 11-Jul-12 30-Jun-12 17-Jul-12 07-Jul-12 24-Jul-12 14-Aug-12 31-Aug-12 13-Sep-12 30-Sep-12 28-Sep-12 15-Oct-12 28-Sep-12
FOB HOUSTON PORT, USA & JEBEL ALI
UB00-P-MLTS-000-1009 LP Flare Package MECHANICAL STATIC H-FX-044001 SF0071 CALLIDUS TECHNOLOGIES LLC PORT, UAE 17-May-12 16-Apr-11 16-May-11 100 27-Jun-11 09-Jun-11 100 04-Aug-11 07-Sep-11 100 11-Aug-11 08-Sep-11 100 25-Sep-11 08-Sep-11 100 09-Nov-11 04-Dec-11 12 19-Nov-11 14-Dec-11 18-Jan-12 10-Feb-12 16-Jun-12 04-Jul-12 23-Jun-12 11-Jul-12 30-Jun-12 17-Jul-12 07-Jul-12 24-Jul-12 14-Aug-12 31-Aug-12 13-Sep-12 30-Sep-12 28-Sep-12 15-Oct-12 28-Sep-12
UB09-P-MLTS-000-1010 Fuel Gas Heater MECHANICAL STATIC H-FE-045001 SF0056 CHROMALOX (UK) LTD FOB ANTWERP, BELGIUM 01-Mar-12 25-Mar-11 28-Apr-11 100 24-Apr-11 23-May-11 100 03-Jun-11 28-Jul-11 100 10-Jun-11 04-Aug-11 100 25-Jul-11 04-Aug-11 100 08-Sep-11 29-Oct-11 35 22-Dec-11 06-Feb-12 21-Jan-12 06-Mar-12 06-Mar-12 18-Apr-12 13-Mar-12 25-Apr-12 20-Mar-12 01-May-12 27-Mar-12 08-May-12 04-May-12 15-Jun-12 03-Jun-12 15-Jul-12 18-Jun-12 30-Jul-12 18-Jun-12
UF00-P-MDTS-000-2001 Raw Diesel Storage Tank MECHANICAL STATIC H-TA-062002 15-Mar-11 28-Oct-11 08-Apr-11 21-Nov-11 09-Jun-11 08-Jan-12 16-Jun-11 15-Jan-12 31-Jul-11 29-Feb-12 14-Sep-11 14-Apr-12 25-Oct-11 25-May-12 24-Dec-11 24-Jul-12 23-Jan-12 23-Aug-12 30-Jan-12 30-Aug-12 18-Feb-12 18-Sep-12 25-Feb-12 25-Sep-12 03-Apr-12 02-Nov-12 03-May-12 02-Dec-12 18-May-12 17-Dec-12 18-May-12
UF00-P-MDTS-000-2001 Raw Water Storage Tank MECHANICAL STATIC H-TA-109001 15-Mar-11 28-Oct-11 08-Apr-11 21-Nov-11 09-Jun-11 08-Jan-12 16-Jun-11 15-Jan-12 31-Jul-11 29-Feb-12 14-Sep-11 14-Apr-12 25-Oct-11 25-May-12 24-Dec-11 24-Jul-12 23-Jan-12 23-Aug-12 30-Jan-12 30-Aug-12 18-Feb-12 18-Sep-12 25-Feb-12 25-Sep-12 03-Apr-12 02-Nov-12 03-May-12 02-Dec-12 18-May-12 17-Dec-12 18-May-12
UF00-P-MDTS-000-2001 Fire / Fresh Water Storage Tanks MECHANICAL STATIC H-TA-109002A 15-Mar-11 28-Oct-11 08-Apr-11 21-Nov-11 09-Jun-11 08-Jan-12 16-Jun-11 15-Jan-12 31-Jul-11 29-Feb-12 14-Sep-11 14-Apr-12 25-Oct-11 25-May-12 24-Dec-11 24-Jul-12 23-Jan-12 23-Aug-12 30-Jan-12 30-Aug-12 18-Feb-12 18-Sep-12 25-Feb-12 25-Sep-12 03-Apr-12 02-Nov-12 03-May-12 02-Dec-12 18-May-12 17-Dec-12 18-May-12
UF00-P-MDTS-000-2001 Fire / Fresh Water Storage Tanks MECHANICAL STATIC H-TA-109002B 15-Mar-11 28-Oct-11 08-Apr-11 21-Nov-11 09-Jun-11 08-Jan-12 16-Jun-11 15-Jan-12 31-Jul-11 29-Feb-12 14-Sep-11 14-Apr-12 25-Oct-11 25-May-12 24-Dec-11 24-Jul-12 23-Jan-12 23-Aug-12 30-Jan-12 30-Aug-12 18-Feb-12 18-Sep-12 25-Feb-12 25-Sep-12 03-Apr-12 02-Nov-12 03-May-12 02-Dec-12 18-May-12 17-Dec-12 18-May-12
UF00-P-MDTS-062-2001 Diesel Coalescer MECHANICAL STATIC H-GC-062004 25-Mar-11 02-Nov-11 24-Apr-11 02-Dec-11 28-Jun-11 08-Jan-12 05-Jul-11 15-Jan-12 19-Aug-11 29-Feb-12 03-Oct-11 14-Apr-12 12-Nov-11 24-May-12 11-Jan-12 23-Jul-12 10-Apr-12 21-Oct-12 17-Apr-12 28-Oct-12 24-Apr-12 04-Nov-12 01-May-12 11-Nov-12 08-Jun-12 19-Dec-12 08-Jul-12 18-Jan-13 23-Jul-12 02-Feb-13 23-Jul-12
UF00-P-MDTS-062-2001 Diesel Coalescer Pre-Filter MECHANICAL STATIC H-GC-062003 25-Mar-11 02-Nov-11 24-Apr-11 02-Dec-11 28-Jun-11 08-Jan-12 05-Jul-11 15-Jan-12 19-Aug-11 29-Feb-12 03-Oct-11 14-Apr-12 12-Nov-11 24-May-12 11-Jan-12 23-Jul-12 10-Apr-12 21-Oct-12 17-Apr-12 28-Oct-12 24-Apr-12 04-Nov-12 01-May-12 11-Nov-12 08-Jun-12 19-Dec-12 08-Jul-12 18-Jan-13 23-Jul-12 02-Feb-13 23-Jul-12
INDUSTRIA MECCANICA BASSI FOB MARGHERA PORT (NORTH ITALIAN
UU00-P-EETS-000-1001 Slug Catcher MECHANICAL STATIC H-LD-020001 SF0011 LUIGI & C. SPA PORT), ITALY 03-Apr-12 15-Feb-11 28-Feb-11 100 02-Mar-11 31-Mar-11 100 25-Mar-11 18-Apr-11 100 01-Apr-11 26-Apr-11 100 16-May-11 26-Apr-11 100 04-Aug-11 09-Aug-11 85 11-Apr-12 07-Mar-12 95 26-May-12 14-Apr-12 38 10-Jul-12 22-May-12 18.00 17-Jul-12 28-May-12 24-Jul-12 03-Jun-12 31-Jul-12 10-Jun-12 07-Sep-12 18-Jul-12 07-Oct-12 17-Aug-12 22-Oct-12 01-Sep-12 22-Oct-12
FOB ANTWERP INTERNATIONAL
UU00-P-MCTS-000-1004 Product Gas Cooler - Train 100 MECHANICAL STATIC H-HC-020101 SF0012 HAMON D'HONDT S.A. SEAPORT, BELGIUM 15-Mar-12 20-Feb-11 20-Feb-11 100 22-Mar-11 18-Mar-11 100 08-May-11 21-Apr-11 100 15-May-11 28-Apr-11 100 29-Jun-11 28-Apr-11 100 13-Aug-11 07-Aug-11 65 06-Jan-12 18-Jan-12 10 06-Mar-12 26-Mar-12 05-Apr-12 29-Apr-12 12-Apr-12 07-May-12 19-Apr-12 15-May-12 26-Apr-12 22-May-12 03-Jun-12 29-Jun-12 03-Jul-12 29-Jul-12 18-Jul-12 13-Aug-12 18-Jul-12
FOB ANTWERP INTERNATIONAL
UU00-P-MCTS-000-1004 Product Gas Cooler - Train 200 MECHANICAL STATIC H-HC-020201 SF0012 HAMON D'HONDT S.A. SEAPORT, BELGIUM 15-Mar-12 20-Feb-11 20-Feb-11 100 22-Mar-11 18-Mar-11 100 08-May-11 21-Apr-11 100 15-May-11 28-Apr-11 100 29-Jun-11 28-Apr-11 100 13-Aug-11 07-Aug-11 65 06-Jan-12 18-Jan-12 10 06-Mar-12 26-Mar-12 05-Apr-12 29-Apr-12 12-Apr-12 07-May-12 19-Apr-12 15-May-12 26-Apr-12 22-May-12 03-Jun-12 29-Jun-12 03-Jul-12 29-Jul-12 18-Jul-12 13-Aug-12 18-Jul-12
FOB ANTWERP INTERNATIONAL
UU00-P-MCTS-000-1004 Produced Water Air Cooler MECHANICAL STATIC H-HC-038001 SF0012 HAMON D'HONDT S.A. SEAPORT, BELGIUM 15-Mar-12 20-Feb-11 20-Feb-11 100 22-Mar-11 18-Mar-11 100 08-May-11 21-Apr-11 100 15-May-11 28-Apr-11 100 29-Jun-11 28-Apr-11 100 13-Aug-11 07-Aug-11 65 06-Jan-12 18-Jan-12 10 06-Mar-12 26-Mar-12 05-Apr-12 29-Apr-12 12-Apr-12 07-May-12 19-Apr-12 15-May-12 26-Apr-12 22-May-12 03-Jun-12 29-Jun-12 03-Jul-12 29-Jul-12 18-Jul-12 13-Aug-12 18-Jul-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 LP Flare KO Drum MECHANICAL STATIC H-VD-044001 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-Feb-12 07-Dec-10 01-Feb-11 100 12-Jan-11 20-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 17-Jun-11 92 08-Sep-11 17-Oct-11 95 07-Nov-11 29-Dec-11 75 05-Feb-12 17-Apr-12 18.00 12-Feb-12 26-Apr-12 19-Feb-12 03-May-12 26-Feb-12 10-May-12 04-Apr-12 17-Jun-12 04-May-12 17-Jul-12 19-May-12 01-Aug-12 19-May-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 2nd Stage Scrubber MECHANICAL STATIC J-VT-023152 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-May-12 07-Dec-10 01-Feb-11 100 12-Jan-11 01-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 17-Jun-11 92 08-Sep-11 17-Oct-11 95 07-Nov-11 29-Dec-11 75 05-Feb-12 17-Apr-12 18.00 12-Feb-12 26-Apr-12 19-Feb-12 03-May-12 26-Feb-12 10-May-12 04-Apr-12 17-Jun-12 04-May-12 17-Jul-12 19-May-12 01-Aug-12 19-May-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 Train-1 2nd Stage Scrubber (REG) MECHANICAL STATIC K-VT-023152 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-Mar-12 07-Dec-10 01-Feb-11 100 12-Jan-11 20-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 01-Jun-11 92 08-Sep-11 14-Sep-11 95 07-Nov-11 16-Nov-11 75 05-Feb-12 18-Feb-12 18.00 12-Feb-12 25-Feb-12 19-Feb-12 03-Mar-12 26-Feb-12 10-Mar-12 04-Apr-12 17-Apr-12 04-May-12 17-May-12 19-May-12 01-Jun-12 19-May-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 Train-2 2nd Stage Scrubber (REG) MECHANICAL STATIC K-VT-023252 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-Mar-12 07-Dec-10 01-Feb-11 100 12-Jan-11 20-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 01-Jun-11 92 08-Sep-11 14-Sep-11 95 07-Nov-11 16-Nov-11 75 05-Feb-12 18-Feb-12 18.00 12-Feb-12 25-Feb-12 19-Feb-12 03-Mar-12 26-Feb-12 10-Mar-12 04-Apr-12 17-Apr-12 04-May-12 17-May-12 19-May-12 01-Jun-12 19-May-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 Train-1 2nd Stage Scrubber (TEG) MECHANICAL STATIC L-VT-023152 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-May-12 07-Dec-10 01-Feb-11 100 12-Jan-11 20-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 17-Jun-11 92 08-Sep-11 17-Oct-11 95 07-Nov-11 29-Dec-11 75 05-Feb-12 17-Apr-12 18.00 12-Feb-12 26-Apr-12 19-Feb-12 03-May-12 26-Feb-12 10-May-12 04-Apr-12 17-Jun-12 04-May-12 17-Jul-12 19-May-12 01-Aug-12 19-May-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 Train-2 2nd Stage Scrubber (TEG) MECHANICAL STATIC L-VT-023252 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-May-12 07-Dec-10 01-Feb-11 100 12-Jan-11 20-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 17-Jun-11 92 08-Sep-11 17-Oct-11 95 07-Nov-11 29-Dec-11 75 05-Feb-12 17-Apr-12 18.00 12-Feb-12 26-Apr-12 19-Feb-12 03-May-12 26-Feb-12 10-May-12 04-Apr-12 17-Jun-12 04-May-12 17-Jul-12 19-May-12 01-Aug-12 19-May-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 Closed Drains Degassing Drum MECHANICAL STATIC K-VA-057301 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-Feb-12 07-Dec-10 01-Feb-11 100 12-Jan-11 20-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 17-Jun-11 92 08-Sep-11 17-Oct-11 95 07-Nov-11 29-Dec-11 75 05-Feb-12 17-Apr-12 18.00 12-Feb-12 26-Apr-12 19-Feb-12 03-May-12 26-Feb-12 10-May-12 04-Apr-12 17-Jun-12 04-May-12 17-Jul-12 19-May-12 01-Aug-12 19-May-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 Inlet Separator MECHANICAL STATIC H-VA-020001 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-Mar-12 07-Dec-10 01-Feb-11 100 12-Jan-11 20-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 17-Jun-11 92 08-Sep-11 17-Oct-11 95 07-Nov-11 29-Dec-11 75 05-Feb-12 17-Apr-12 18.00 12-Feb-12 26-Apr-12 2.00 19-Feb-12 03-May-12 2.00 26-Feb-12 10-May-12 04-Apr-12 17-Jun-12 04-May-12 17-Jul-12 19-May-12 01-Aug-12 19-May-12

DOOSAN ENGINEERING & FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1001 Produced Water Degasser MECHANICAL STATIC H-VD-038001 SF0002 CONSTRUCTION CO., LTD. (THE NETHERLANDS/BELGIUM) 03-Feb-12 07-Dec-10 01-Feb-11 100 12-Jan-11 20-Feb-11 100 23-Feb-11 24-Feb-11 100 02-Mar-11 27-Feb-11 100 16-Apr-11 03-Mar-11 100 31-May-11 17-Jun-11 92 08-Sep-11 17-Oct-11 95 07-Nov-11 29-Dec-11 75 05-Feb-12 17-Apr-12 18.00 12-Feb-12 26-Apr-12 19-Feb-12 03-May-12 26-Feb-12 10-May-12 04-Apr-12 17-Jun-12 04-May-12 17-Jul-12 19-May-12 01-Aug-12 19-May-12

FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1003 Vessel Internals MECHANICAL STATIC VES-INT-1 SF0008 CDS SEPARATION SYSTEMS (THE NETHERLANDS/BELGIUM) 04-Sep-11 16-Jan-11 24-Feb-11 100 15-Feb-11 15-Mar-11 100 24-Mar-11 21-Apr-11 100 31-Mar-11 21-Apr-11 100 15-May-11 01-May-11 100 30-May-11 10-Oct-11 100 10-Jun-11 10-Oct-11 100 10-Jul-11 10-Oct-11 100 09-Aug-11 10-Oct-11 100.00 16-Aug-11 10-Oct-11 100.00 23-Aug-11 10-Oct-11 100.00 30-Aug-11 17-Oct-11 07-Oct-11 24-Nov-11 06-Nov-11 24-Dec-11 21-Nov-11 08-Jan-12 21-Nov-11

FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1003 Vessel Internals MECHANICAL STATIC VES-INT-2 SF0008 CDS SEPARATION SYSTEMS (THE NETHERLANDS/BELGIUM) 04-Sep-11 16-Jan-11 24-Feb-11 100 15-Feb-11 15-Mar-11 100 24-Mar-11 21-Apr-11 100 31-Mar-11 21-Apr-11 100 15-May-11 01-May-11 100 30-May-11 10-Oct-11 100 10-Jun-11 10-Oct-11 100 10-Jul-11 10-Oct-11 100 09-Aug-11 10-Oct-11 100.00 16-Aug-11 10-Oct-11 100.00 23-Aug-11 10-Oct-11 100.00 30-Aug-11 17-Oct-11 07-Oct-11 24-Nov-11 06-Nov-11 24-Dec-11 21-Nov-11 08-Jan-12 21-Nov-11

FOB INTERNATIONAL SEAPORT, EUROPE


UU00-P-MDTS-000-1003 Vessel Internals MECHANICAL STATIC VES-INT-3 SF0008 CDS SEPARATION SYSTEMS (THE NETHERLANDS/BELGIUM) 04-Sep-11 16-Jan-11 24-Feb-11 100 15-Feb-11 15-Mar-11 100 24-Mar-11 21-Apr-11 100 31-Mar-11 21-Apr-11 100 15-May-11 01-May-11 100 30-May-11 10-Oct-11 100 10-Jun-11 10-Oct-11 100 10-Jul-11 10-Oct-11 100 09-Aug-11 10-Oct-11 100.00 16-Aug-11 10-Oct-11 100.00 23-Aug-11 10-Oct-11 100.00 30-Aug-11 17-Oct-11 07-Oct-11 24-Nov-11 06-Nov-11 24-Dec-11 21-Nov-11 08-Jan-12 21-Nov-11
UU00-P-MDTS-000-1006 Plant Water Storage Tank MECHANICAL STATIC H-TA-052001 SF0043 CR-METAL EX-WORKS, BLIDA, ALGERIA 05-Nov-11 15-Mar-11 23-Mar-11 100 08-Apr-11 30-Mar-11 100 09-Jun-11 05-Jul-11 100 16-Jun-11 05-Jul-11 100 31-Jul-11 05-Jul-11 100 14-Sep-11 25-Nov-11 3 25-Oct-11 29-Jan-12 24-Dec-11 03-May-12 23-Jan-12 20-Jun-12 30-Jan-12 01-Jul-12 18-Feb-12 31-Jul-12 25-Feb-12 07-Aug-12 03-Apr-12 14-Sep-12 03-May-12 14-Oct-12 18-May-12 29-Oct-12 18-May-12
UU00-P-MDTS-000-1006 Fresh Water Storage Tank MECHANICAL STATIC H-TA-053001 SF0043 CR-METAL EX-WORKS, BLIDA, ALGERIA 05-Nov-11 15-Mar-11 23-Mar-11 100 08-Apr-11 30-Mar-11 100 09-Jun-11 05-Jul-11 100 16-Jun-11 05-Jul-11 100 31-Jul-11 05-Jul-11 100 14-Sep-11 25-Nov-11 3 25-Oct-11 29-Jan-12 24-Dec-11 03-May-12 23-Jan-12 20-Jun-12 30-Jan-12 01-Jul-12 18-Feb-12 31-Jul-12 25-Feb-12 07-Aug-12 03-Apr-12 14-Sep-12 03-May-12 14-Oct-12 18-May-12 29-Oct-12 18-May-12
UU00-P-MDTS-000-1006 Glycol Storage Tank MECHANICAL STATIC H-TA-054001 SF0043 CR-METAL EX-WORKS, BLIDA, ALGERIA 05-Nov-11 15-Mar-11 23-Mar-11 100 08-Apr-11 30-Mar-11 100 09-Jun-11 05-Jul-11 100 16-Jun-11 05-Jul-11 100 31-Jul-11 05-Jul-11 100 14-Sep-11 25-Nov-11 3 25-Oct-11 29-Jan-12 24-Dec-11 03-May-12 23-Jan-12 20-Jun-12 30-Jan-12 01-Jul-12 18-Feb-12 31-Jul-12 25-Feb-12 07-Aug-12 03-Apr-12 14-Sep-12 03-May-12 14-Oct-12 18-May-12 29-Oct-12 18-May-12
UU00-P-MDTS-000-1006 Raw Diesel Storage Tank MECHANICAL STATIC H-TA-062001 SF0043 CR-METAL EX-WORKS, BLIDA, ALGERIA 05-Nov-11 15-Mar-11 23-Mar-11 100 08-Apr-11 30-Mar-11 100 09-Jun-11 05-Jul-11 100 16-Jun-11 05-Jul-11 100 31-Jul-11 05-Jul-11 100 14-Sep-11 25-Nov-11 3 25-Oct-11 29-Jan-12 24-Dec-11 03-May-12 23-Jan-12 20-Jun-12 30-Jan-12 01-Jul-12 18-Feb-12 31-Jul-12 25-Feb-12 07-Aug-12 03-Apr-12 14-Sep-12 03-May-12 14-Oct-12 18-May-12 29-Oct-12 18-May-12
DOOSAN ENGINEERING & FOB MASAN INTERNATIONAL SEAPORT,
UU00-P-MDTS-000-1007 HP Flare KO Drum MECHANICAL STATIC H-VD-043001 SF0009 CONSTRUCTION CO., LTD. KOREA 19-Apr-12 13-Mar-11 13-Mar-11 100 12-Apr-11 28-Mar-11 100 19-May-11 28-Apr-11 100 26-May-11 28-Apr-11 100 10-Jul-11 01-May-11 100 24-Aug-11 10-Sep-11 75 08-Oct-11 16-Nov-11 65 07-Dec-11 14-Feb-12 0.26 06-Mar-12 28-Jun-12 13-Mar-12 08-Jul-12 20-Mar-12 19-Jul-12 27-Mar-12 26-Jul-12 04-May-12 02-Sep-12 03-Jun-12 02-Oct-12 18-Jun-12 17-Oct-12 18-Jun-12
DOOSAN ENGINEERING & FOB MASAN INTERNATIONAL SEAPORT,
UU00-P-MDTS-000-1007 Air Receiver MECHANICAL STATIC H-VL-063001 SF0009 CONSTRUCTION CO., LTD. KOREA 31-Mar-12 13-Mar-11 13-Mar-11 100 12-Apr-11 28-Mar-11 100 19-May-11 28-Apr-11 100 26-May-11 28-Apr-11 100 10-Jul-11 01-May-11 100 24-Aug-11 13-Sep-11 75 08-Oct-11 21-Nov-11 65 07-Dec-11 21-Feb-12 0.26 06-Mar-12 08-Jul-12 2.00 13-Mar-12 19-Jul-12 2.00 20-Mar-12 31-Jul-12 2.00 27-Mar-12 07-Aug-12 04-May-12 14-Sep-12 03-Jun-12 14-Oct-12 18-Jun-12 29-Oct-12 18-Jun-12
UU00-P-MDTS-000-1011 Scraper Launcher MECHANICAL STATIC P-LE-033001 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Launcher MECHANICAL STATIC V-LE-033001 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Launcher MECHANICAL STATIC W-LE-033001 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Launcher MECHANICAL STATIC N-LE-033001 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Receiver MECHANICAL STATIC N-LE-033002 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Receiver MECHANICAL STATIC P-LE-033002 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Launcher MECHANICAL STATIC X-LE-033003 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Receiver MECHANICAL STATIC V-LE-033002 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Receiver MECHANICAL STATIC W-LE-033002 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
UU00-P-MDTS-000-1011 Scraper Receiver MECHANICAL STATIC X-LE-033004 25-May-11 15-May-11 100 24-Jun-11 07-Jun-11 100 01-Aug-11 26-Sep-11 100 08-Aug-11 26-Sep-11 100 22-Sep-11 10-Nov-11 06-Nov-11 25-Dec-11 16-Dec-11 03-Feb-12 30-Jan-12 19-Mar-12 15-Mar-12 03-May-12 22-Mar-12 10-May-12 29-Mar-12 17-May-12 05-Apr-12 24-May-12 13-May-12 01-Jul-12 12-Jun-12 31-Jul-12 27-Jun-12 15-Aug-12 27-Jun-12
FOB DUBAI INTERNATIONAL SEAPORT,
UU00-P-MLTS-000-1008 Water Injection Filters MECHANICAL STATIC H-GC-038001A SF0055 DOLLINGER UAE 25-Mar-11 13-Apr-11 100 24-Apr-11 04-May-11 100 28-Jun-11 31-Jul-11 100 05-Jul-11 15-Aug-11 100 19-Aug-11 15-Aug-11 100 03-Oct-11 04-Nov-11 12-Nov-11 10-Dec-11 11-Jan-12 02-Feb-12 10-Apr-12 23-Apr-12 17-Apr-12 29-Apr-12 04-May-12 16-May-12 11-May-12 23-May-12 18-Jun-12 30-Jun-12 18-Jul-12 30-Jul-12 02-Aug-12 14-Aug-12 02-Aug-12
FOB DUBAI INTERNATIONAL SEAPORT,
UU00-P-MLTS-000-1008 Fuel Gas Filter / Separator MECHANICAL STATIC H-VJ-045001B SF0055 DOLLINGER UAE 25-Mar-11 13-Apr-11 100 24-Apr-11 04-May-11 100 28-Jun-11 31-Jul-11 100 05-Jul-11 15-Aug-11 100 19-Aug-11 15-Aug-11 100 03-Oct-11 13-Nov-11 12-Nov-11 23-Dec-11 11-Jan-12 21-Feb-12 10-Apr-12 21-May-12 17-Apr-12 28-May-12 04-May-12 14-Jun-12 11-May-12 21-Jun-12 18-Jun-12 29-Jul-12 18-Jul-12 28-Aug-12 02-Aug-12 12-Sep-12 02-Aug-12
FOB DUBAI INTERNATIONAL SEAPORT,
UU00-P-MLTS-000-1008 Water Injection Filters MECHANICAL STATIC H-GC-038001B SF0055 DOLLINGER UAE 25-Mar-11 13-Apr-11 100 24-Apr-11 04-May-11 100 28-Jun-11 31-Jul-11 100 05-Jul-11 15-Aug-11 100 19-Aug-11 15-Aug-11 100 03-Oct-11 13-Nov-11 12-Nov-11 23-Dec-11 11-Jan-12 21-Feb-12 10-Apr-12 21-May-12 17-Apr-12 28-May-12 04-May-12 14-Jun-12 11-May-12 21-Jun-12 18-Jun-12 29-Jul-12 18-Jul-12 28-Aug-12 02-Aug-12 12-Sep-12 02-Aug-12
FOB DUBAI INTERNATIONAL SEAPORT,
UU00-P-MLTS-000-1008 Fuel Gas Filter / Separator MECHANICAL STATIC H-VJ-045001A SF0055 DOLLINGER UAE 25-Mar-11 13-Apr-11 100 24-Apr-11 04-May-11 100 28-Jun-11 31-Jul-11 100 05-Jul-11 15-Aug-11 100 19-Aug-11 15-Aug-11 100 03-Oct-11 13-Nov-11 12-Nov-11 23-Dec-11 11-Jan-12 21-Feb-12 10-Apr-12 21-May-12 17-Apr-12 28-May-12 04-May-12 14-Jun-12 11-May-12 21-Jun-12 18-Jun-12 29-Jul-12 18-Jul-12 28-Aug-12 02-Aug-12 12-Sep-12 02-Aug-12
FOB DUBAI INTERNATIONAL SEAPORT,
UU00-P-MLTS-000-1008 Diesel Coalescer Pre-Filter MECHANICAL STATIC H-GC-062001 SF0055 DOLLINGER FILTRATION UAE 30-Apr-12 25-Mar-11 13-Apr-11 100 24-Apr-11 04-May-11 100 28-Jun-11 31-Jul-11 100 05-Jul-11 15-Aug-11 100 19-Aug-11 15-Aug-11 100 03-Oct-11 22-Nov-11 18 12-Nov-11 05-Jan-12 11-Jan-12 11-Mar-12 10-Apr-12 18-Jun-12 17-Apr-12 26-Jun-12 04-May-12 16-Jul-12 11-May-12 23-Jul-12 18-Jun-12 30-Aug-12 18-Jul-12 29-Sep-12 02-Aug-12 14-Oct-12 02-Aug-12
FOB DUBAI INTERNATIONAL SEAPORT,
UU00-P-MLTS-000-1008 Diesel Coalescer MECHANICAL STATIC H-GC-062002 SF0055 DOLLINGER FILTRATION UAE 30-Apr-12 25-Mar-11 13-Apr-11 100 24-Apr-11 04-May-11 100 28-Jun-11 31-Jul-11 100 05-Jul-11 15-Aug-11 100 19-Aug-11 15-Aug-11 100 03-Oct-11 22-Nov-11 18 12-Nov-11 05-Jan-12 11-Jan-12 11-Mar-12 10-Apr-12 18-Jun-12 17-Apr-12 26-Jun-12 04-May-12 16-Jul-12 11-May-12 23-Jul-12 18-Jun-12 30-Aug-12 18-Jul-12 29-Sep-12 02-Aug-12 14-Oct-12 02-Aug-12
FOB DUBAI INTERNATIONAL SEAPORT,
UU00-P-MLTS-000-1008 Glycol Catcher MECHANICAL STATIC K-VD-020301 SF0055 DOLLINGER FILTRATION UAE 30-Apr-12 25-Mar-11 13-Apr-11 100 24-Apr-11 04-May-11 100 28-Jun-11 31-Jul-11 100 05-Jul-11 15-Aug-11 100 19-Aug-11 15-Aug-11 100 03-Oct-11 22-Nov-11 18 12-Nov-11 05-Jan-12 11-Jan-12 11-Mar-12 10-Apr-12 18-Jun-12 17-Apr-12 26-Jun-12 04-May-12 16-Jul-12 11-May-12 23-Jul-12 18-Jun-12 30-Aug-12 18-Jul-12 29-Sep-12 02-Aug-12 14-Oct-12 23-Jul-12
FOB DUBAI INTERNATIONAL SEAPORT,
UU00-P-MLTS-000-1008 Glycol Catcher MECHANICAL STATIC K-VD-024306 SF0055 DOLLINGER FILTRATION UAE 30-Apr-12 25-Mar-11 13-Apr-11 100 24-Apr-11 04-May-11 100 28-Jun-11 31-Jul-11 100 05-Jul-11 15-Aug-11 100 19-Aug-11 15-Aug-11 100 03-Oct-11 22-Nov-11 18 12-Nov-11 05-Jan-12 11-Jan-12 11-Mar-12 10-Apr-12 18-Jun-12 17-Apr-12 26-Jun-12 04-May-12 16-Jul-12 11-May-12 23-Jul-12 18-Jun-12 30-Aug-12 18-Jul-12 29-Sep-12 02-Aug-12 14-Oct-12 23-Jul-12
FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Glycol Regeneration Package MECHANICAL STATIC H-XX-024101-AKER SF0005 AKER PROCESS SYSTEMS SAS ITALY 28-Nov-11 16-Jan-11 29-Jan-11 100 15-Feb-11 15-Feb-11 100 23-Mar-11 28-Apr-11 100 30-Mar-11 28-Apr-11 100 14-May-11 04-May-11 100 28-Jun-11 12-Jul-11 83 07-Nov-11 15-Sep-11 100 06-Jan-12 04-Nov-11 30 05-Apr-12 18-Jan-12 20.00 12-Apr-12 24-Jan-12 19-Apr-12 15-Mar-12 26-Apr-12 22-Mar-12 03-Jun-12 29-Apr-12 03-Jul-12 29-May-12 18-Jul-12 13-Jun-12 18-Jul-12
FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Glycol Regeneration Package MECHANICAL STATIC H-XX-024201-AKER SF0005 AKER PROCESS SYSTEMS SAS ITALY 28-Nov-11 16-Jan-11 29-Jan-11 100 15-Feb-11 15-Feb-11 100 23-Mar-11 28-Apr-11 100 30-Mar-11 28-Apr-11 100 14-May-11 04-May-11 100 28-Jun-11 12-Jul-11 83 07-Nov-11 15-Sep-11 100 06-Jan-12 04-Nov-11 30 05-Apr-12 18-Jan-12 20.00 12-Apr-12 24-Jan-12 19-Apr-12 15-Mar-12 26-Apr-12 22-Mar-12 03-Jun-12 29-Apr-12 03-Jul-12 29-May-12 18-Jul-12 13-Jun-12 18-Jul-12
FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Glycol Regeneration Package MECHANICAL STATIC K-XX-024301-AKER SF0005 AKER PROCESS SYSTEMS SAS ITALY 28-Nov-11 16-Jan-11 29-Jan-11 100 15-Feb-11 15-Feb-11 100 23-Mar-11 28-Apr-11 100 30-Mar-11 28-Apr-11 100 14-May-11 04-May-11 100 28-Jun-11 11-Jul-11 83 07-Nov-11 15-Sep-11 100 06-Jan-12 03-Nov-11 30 05-Apr-12 16-Jan-12 20.00 12-Apr-12 22-Jan-12 25-Apr-12 15-Mar-12 02-May-12 22-Mar-12 09-Jun-12 29-Apr-12 09-Jul-12 29-May-12 24-Jul-12 13-Jun-12 18-Jul-12
Str. Fabrication works - Flash Drum INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (FD101STR) MECHANICAL STATIC 100-A-FD-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping pre-fabrication works - Flash Drum MECHANICAL STATIC 100-A-FD-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
PH Control agent Dozing Pump (H-PD-024 INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 102) fabrication - Flash Drum MECHANICAL STATIC 100-A-DP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
PH Control Agent tamk (H-TX-024 101) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Flash Drum MECHANICAL STATIC 100-A-TK-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 15-Sep-11 75 15-Sep-11 15-Sep-11 15-Sep-11 15-Sep-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol Heat exchanger (H-HA-024 101) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication - Flash Drum MECHANICAL STATIC 100-A-HE-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Flash drum (H-VB-024 102) fabrication - INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Flash Drum MECHANICAL STATIC 100-A-FD-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Flash Drum MECHANICAL STATIC 100-A-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Flash INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum MECHANICAL STATIC 100-A-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Final testing & ex-works - Flash INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum(FD101EW) MECHANICAL STATIC 100-A-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 15-Sep-11 25 15-Sep-11 15-Sep-11 15-Sep-11 15-Sep-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Re-boiler (H-HI-024 103) fabrication INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 works - Reboiler skid MECHANICAL STATIC 100-B-RB-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Reboiler skid MECHANICAL STATIC 100-B-RB-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping pre-fabrication works - Reboiler INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 100-B-RB-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Reboiler INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 100-B-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Reboiler skid MECHANICAL STATIC 100-B-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Final testing & ex-works - Reboiler skid MECHANICAL STATIC 100-B-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 15-Sep-11 25 15-Sep-11 15-Sep-11 15-Sep-11 15-Sep-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol KO Gas KO Pot (H-VD-024 107) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication - Surge Drum skid MECHANICAL STATIC 100-C-GK-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 15-Sep-11 50 15-Sep-11 99 15-Sep-11 15-Sep-11 15-Sep-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Surge drum (H-VL-024 104) fabrication INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 works - Surge Drum skid MECHANICAL STATIC 100-C-SD-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12

Lean Glycol Pumps (H-PB-024 101 A/B) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Surge Drum skid MECHANICAL STATIC 100-C-GP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping pre-fabrication works - Surge INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum skid MECHANICAL STATIC 100-C-SD-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Surge Drum skid MECHANICAL STATIC 100-C-SD-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Surge Drum skid MECHANICAL STATIC 100-C-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Surge INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum skid MECHANICAL STATIC 100-C-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Final testing & ex-works - Surge Drum INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 100-C-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Still Column Overhead Pumps (H-PA-024
103 A/B) fabrication works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 100-D-CP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Still Column Overhead Receiver(H-VA-
024 105) fabrication - Overhead receiver INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 and pumps skid MECHANICAL STATIC 100-D-CR-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Str. Fabrication works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 100-D-OR-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping pre-fabrication works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 100-D-OR-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid
(assembly) - Overhead receiver and INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 pumps skid MECHANICAL STATIC 100-D-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 100-D-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Final testing & ex-works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 100-D-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Skid E MECHANICAL STATIC 100-E-SE-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Stripping Column (H-VE-024 108) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 100-E-SC-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Particle filters (H-GC-024 101 A/B) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 100-E-PF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Charcoal filters (H-GC-024 102) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 100-E-CF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Guard Filter (H-GC-024 103) Fabrication INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 works - Skid E MECHANICAL STATIC 100-E-GF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping pre-fabrication works - Skid E MECHANICAL STATIC 100-E-SE-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Skid E MECHANICAL STATIC 100-E-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping/E&I installation works - Skid E MECHANICAL STATIC 100-E-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Final testing & ex-works -Skid E MECHANICAL STATIC 100-E-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol contactor (H-VB-024 101) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Manufacturing MECHANICAL STATIC 100-L-GC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 75 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
PROCUREMENT TRACKING REGISTER

ISG PROJECT - IN SALAH GAS SOUTHERN FIELDS DEVELOPMENT PTR TEMPLATE


CONTRACT NO. : 100045/ISG/CON
DOCUMENT NO : 1 7 11 12 13 14 15-Jan-00 23 24-Jan-00 25-Jan-00 26 28-Jan-00 29-Jan-00 30 09-Jan-00
CUT OFF DATE: 29-Oct-11

Issue Inquiry Requisition Receive Bid TBE Complete Place LOI / LOA Place PO Receive / Approve Key Vendor Drawings / Documents Place Sub-orders Receive Raw Materials Fabrication / Mfg. Inspection Release Note Ex-works Delivery Item on Board Shipping/Air Freight/Land Transport (ATA Port) Custom Clearance and Transport to site/store Visual Inspection on Receipt at Site/Store ROS
Inquiry No. Description Discipline INQD_TAG_NO PO_NO Vendor Name PO Delivery Terms PO_CDD
P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog
Still column Reflex Condenser (H-HA-024 INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 102) Manufacturing MECHANICAL STATIC 100-L-SC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Blower (H-KE-024 101 A/B) Manufacturing MECHANICAL STATIC 100-L-BL-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Lean Glycol Air Cooler (H-HC-024 104) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication MECHANICAL STATIC 100-L-AC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Still Column Overhead Condenser (H-KEM- INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 024103A/B) - fabrication MECHANICAL STATIC 100-L-OC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Flash Drum MECHANICAL STATIC 200-A-FD-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping pre-fabrication works - Flash Drum MECHANICAL STATIC 200-A-FD-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Flash drum (H-VB-024 201) fabrication - INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Flash Drum MECHANICAL STATIC 200-A-FD-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12

Antifoam Control Agent Tank (H-TX-024 INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 201) fabrication works - Flash Drum MECHANICAL STATIC 200-A-TK-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12

Antifoam Control agent Dozing Pump (H- INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 PD-024 103) fabrication - Flash Drum MECHANICAL STATIC 200-A-DP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Flash INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum MECHANICAL STATIC 200-A-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol Heat exchanger (H-HA-024 201) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication - Flash Drum MECHANICAL STATIC 200-A-HE-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Flash Drum MECHANICAL STATIC 200-A-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Final testing & ex-works - Flash Drum MECHANICAL STATIC 200-A-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 15-Sep-11 25 15-Sep-11 15-Sep-11 15-Sep-11 15-Sep-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Re-boiler (H-HI-024 203) fabrication INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 works - Reboiler skid MECHANICAL STATIC 200-B-RB-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Reboiler skid MECHANICAL STATIC 200-B-RB-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping pre-fabrication works - Reboiler INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 200-B-RB-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Reboiler INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 200-B-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Reboiler skid MECHANICAL STATIC 200-B-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Final testing & ex-works - Reboiler skid MECHANICAL STATIC 200-B-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Surge Drum skid MECHANICAL STATIC 200-C-SD-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol KO Gas KO Pot (H-VD-024 107) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication - Surge Drum skid MECHANICAL STATIC 200-C-GK-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Surge drum (H-VL-024 104) fabrication INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 works - Surge Drum skid MECHANICAL STATIC 200-C-SD-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping pre-fabrication works - Surge INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum skid MECHANICAL STATIC 200-C-SD-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12

Lean Glycol Pumps (H-PB-024 101 A/B) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Surge Drum skid MECHANICAL STATIC 200-C-GP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Surge Drum skid MECHANICAL STATIC 200-C-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Surge INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum skid MECHANICAL STATIC 200-C-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Final testing & ex-works - Surge Drum INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 200-C-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Skid E MECHANICAL STATIC 200-E-SE-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Stripping Column (H-VE-024 206) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 200-E-SC-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Particle filters (H-GC-024 201 A/B) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 200-E-PF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Charcoal filters (H-GC-024 202) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 200-E-CF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping pre-fabrication works - Skid E MECHANICAL STATIC 200-E-SE-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Guard Filter (H-GC-024 203) Fabrication INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 works - Skid E MECHANICAL STATIC 200-E-GF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Skid E MECHANICAL STATIC 200-E-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping/E&I installation works - Skid E MECHANICAL STATIC 200-E-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Final testing & ex-works -Skid E MECHANICAL STATIC 200-E-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol contactor (H-VB-024 101) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Manufacturing MECHANICAL STATIC 200-L-GC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 75 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Blower (H-KE-024 101 A/B) Manufacturing MECHANICAL STATIC 200-L-BL-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Lean Glycol Air Cooler (H-HC-024 104) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication MECHANICAL STATIC 200-L-AC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Flash Drum MECHANICAL STATIC 300-A-FD-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping pre-fabrication works - Flash Drum MECHANICAL STATIC 300-A-FD-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
PH Control agent Dozing Pump (K-PD-024 INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 302) fabrication - Flash Drum MECHANICAL STATIC 300-A-DP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
PH Control Agent tamk (K-TX-024 301) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Flash Drum MECHANICAL STATIC 300-A-TK-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12

Antifoam Control Agent Dozing Pump (K- INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 PD-024 303) fabrication - Flash Drum MECHANICAL STATIC 300-A-AFP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12

Antifoam Control Agent tamk (K-TX-024 INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 302) fabrication works - Flash Drum MECHANICAL STATIC 300-A-AFT-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol Heat exchanger (K-HA-024 301) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication - Flash Drum MECHANICAL STATIC 300-A-HE-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Flash drum (K-VB-024 302) fabrication - INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Flash Drum MECHANICAL STATIC 300-A-FD-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Flash Drum MECHANICAL STATIC 300-A-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Flash INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum MECHANICAL STATIC 300-A-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Final testing & ex-works - Flash Drum MECHANICAL STATIC 300-A-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Reboiler skid MECHANICAL STATIC 300-B-RB-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping pre-fabrication works - Reboiler INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 300-B-RB-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Re-boiler K-HI-024 303) fabrication works INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 - Reboiler skid MECHANICAL STATIC 300-B-RB-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Reboiler INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 300-B-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Reboiler skid MECHANICAL STATIC 300-B-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Final testing & ex-works - Reboiler skid MECHANICAL STATIC 300-B-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Surge Drum skid MECHANICAL STATIC 300-C-SD-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping pre-fabrication works - Surge INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum skid MECHANICAL STATIC 300-C-SD-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Surge drum (K-VL-024 304) fabrication INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 works - Surge Drum skid MECHANICAL STATIC 300-C-SD-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol KO Gas KO Pot (K-VD-024 307) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication - Surge Drum skid MECHANICAL STATIC 300-C-GK-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12

Lean Glycol Pumps (K-PB-024 301 A/B) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Surge Drum skid MECHANICAL STATIC 300-C-GP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Surge Drum skid MECHANICAL STATIC 300-C-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Surge INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Drum skid MECHANICAL STATIC 300-C-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Final testing & ex-works - Surge Drum INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 skid MECHANICAL STATIC 300-C-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Still Column Overhead Receiver(K-VA-024
305) fabrication - Overhead receiver and INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 pumps skid MECHANICAL STATIC 300-D-CR-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Still Column Overhead Pumps (K-PA-024
303 A/B) fabrication works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 300-D-CP-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Str. Fabrication works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 300-D-OR-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping pre-fabrication works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 300-D-OR-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid
(assembly) - Overhead receiver and INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 pumps skid MECHANICAL STATIC 300-D-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Piping/E&I installation works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 300-D-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Final testing & ex-works - Overhead INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 receiver and pumps skid MECHANICAL STATIC 300-D-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Str. Fabrication works - Skid E MECHANICAL STATIC 300-E-SE-STRFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Stripping Column (K-VE-024 308) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 300-E-SC-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Guard Filter (K-GC-024 303) Fabrication INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 works - Skid E MECHANICAL STATIC 300-E-GF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping pre-fabrication works - Skid E MECHANICAL STATIC 300-E-SE-PIPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 30 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Particle filters (K-GC-024 301 A/B) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 300-E-PF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Charcoal filters (K-GC-024 302) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication works - Skid E MECHANICAL STATIC 300-E-CF-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Installation of equipment on skid INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 (assembly) - Skid E MECHANICAL STATIC 300-E-AS-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Piping/E&I installation works - Skid E MECHANICAL STATIC 300-E-OT-INSTALL SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 50 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Final testing & ex-works -Skid E MECHANICAL STATIC 300-E-FT-EXWORK SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 25 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Glycol contactor (K-VB-024 301) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Manufacturing MECHANICAL STATIC 300-L-GC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 75 28-Apr-11 75 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Still column Reflex Condenser (K-HA-024 INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 302) Manufacturing MECHANICAL STATIC 300-L-SC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Blower (K-KE-024 301 A/B) Manufacturing MECHANICAL STATIC 300-L-BL-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Lean Glycol Air Cooler (K-HC-024 304) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 fabrication MECHANICAL STATIC 300-L-AC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Still Column Overhead Condenser (K-HC- INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 024105)fabrication MECHANICAL STATIC 300-L-OC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 29-Jan-11 100 15-Feb-11 100 28-Apr-11 100 28-Apr-11 100 04-May-11 100 28-Apr-11 28-Apr-11 99 28-Apr-11 28-Apr-11 28-Apr-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Forced Draft Burner manufactruing - INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Reboiler skid MECHANICAL STATIC 100-B-FD-EQFAB SF0006 SCARDELLATO SPA ITALY 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11
Glycol Still Column (H-VE-024 103) INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Manufacturing MECHANICAL STATIC 100-L-SN-MNF SF0006 SCARDELLATO SPA ITALY 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Forced Draft Burner fabrication works MECHANICAL STATIC 200-B-FB-EQPFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
Still column Reflex Condenser (H-HA-024 INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 202) Manufacturing MECHANICAL STATIC 200-L-SC-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Still Column Manufacturing MECHANICAL STATIC 200-L-SN-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Forced Draft Burner fabrication works MECHANICAL STATIC 300-B-FB-EQFAB SF0006 SCARDELLATO SPA ITALY 04-Apr-12 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
INDUSTRIE MECCANICHE FOB VENICE INTERNATIONAL SEAPORT,
UU00-P-MLTS-024-1002 Still column Manufacturing MECHANICAL STATIC 300-L-SN-MNF SF0006 SCARDELLATO SPA ITALY 04-Apr-12 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 100 04-May-11 04-May-11 04-May-11 04-May-11 04-May-11 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12 30-Jul-12
FCA INTERNATIONAL SEAPORT -
UU00-P-MLTS-101-1000 Incinerator Package MECHANICAL STATIC H-XX-101008 SF0016 INCINCO LIMITED MARSEILLE, FRANCE 05-Oct-11 20-Feb-11 22-Feb-11 100 22-Mar-11 18-Mar-11 100 23-Apr-11 05-May-11 100 30-Apr-11 12-May-11 100 14-Jun-11 12-May-11 100 29-Jul-11 15-Sep-11 96.67 08-Sep-11 15-Sep-11 100 23-Oct-11 12-Oct-11 98.33 07-Dec-11 25-Oct-11 86.67 14-Dec-11 15-Sep-11 33.33 21-Dec-11 15-Sep-11 33.33 28-Dec-11 01-Oct-11 04-Feb-12 03-Oct-11 05-Mar-12 03-Oct-11 20-Mar-12 18-Oct-11 20-Mar-12

HB09-P-MJTS-038-1000 Produced Water Pumps MECHANICAL ROTATING H-PA-038001A SF0039 WORTHINGTON SRL FOB INTERNATIONAL SEAPORT ITALY 03-May-12 15-Feb-11 28-Feb-11 100 17-Mar-11 05-Apr-11 100 09-May-11 23-Jun-11 100 16-May-11 23-Jun-11 100 30-Jun-11 23-Jun-11 100 14-Aug-11 11-Sep-11 35 23-Nov-11 10-Dec-11 40 22-Jan-12 01-Feb-12 21-Apr-12 21-Apr-12 28-Apr-12 27-Apr-12 05-May-12 03-May-12 12-May-12 10-May-12 19-Jun-12 17-Jun-12 19-Jul-12 17-Jul-12 03-Aug-12 01-Aug-12 03-Aug-12

HB09-P-MJTS-038-1000 Produced Water Pumps MECHANICAL ROTATING H-PA-038001B SF0039 WORTHINGTON SRL FOB INTERNATIONAL SEAPORT ITALY 03-May-12 15-Feb-11 28-Feb-11 100 17-Mar-11 05-Apr-11 100 09-May-11 23-Jun-11 100 16-May-11 23-Jun-11 100 30-Jun-11 23-Jun-11 100 14-Aug-11 11-Sep-11 35 23-Nov-11 10-Dec-11 40 22-Jan-12 01-Feb-12 21-Apr-12 21-Apr-12 28-Apr-12 27-Apr-12 05-May-12 03-May-12 12-May-12 10-May-12 19-Jun-12 17-Jun-12 19-Jul-12 17-Jul-12 03-Aug-12 01-Aug-12 03-Aug-12
FOB HAMBURG INTERNATIONAL
HB09-P-MJTS-038-1001 Water Injection Pumps MECHANICAL ROTATING H-PB-038002A SF0038 FLOWSERVE HAMBURG GMBH SEAPORT, GERMANY 21-Jun-12 17-Mar-11 02-Mar-11 100 16-Apr-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 23-Jun-11 100 15-Jul-11 23-Jun-11 100 29-Aug-11 25-Nov-11 25 23-Oct-11 28-Feb-12 10 22-Dec-11 11-Jun-12 05-Feb-12 28-Aug-12 12-Feb-12 09-Sep-12 19-Feb-12 21-Sep-12 26-Feb-12 28-Sep-12 04-Apr-12 05-Nov-12 04-May-12 05-Dec-12 19-May-12 20-Dec-12 19-May-12
FOB HAMBURG INTERNATIONAL
HB09-P-MJTS-038-1001 Water Injection Pumps MECHANICAL ROTATING H-PB-038002B SF0038 FLOWSERVE HAMBURG GMBH SEAPORT, GERMANY 21-Jun-12 17-Mar-11 02-Mar-11 100 16-Apr-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 23-Jun-11 100 15-Jul-11 23-Jun-11 100 29-Aug-11 25-Nov-11 25 23-Oct-11 28-Feb-12 10 22-Dec-11 11-Jun-12 05-Feb-12 28-Aug-12 12-Feb-12 09-Sep-12 19-Feb-12 21-Sep-12 26-Feb-12 28-Sep-12 04-Apr-12 05-Nov-12 04-May-12 19-Dec-12 19-May-12 03-Jan-13 19-May-12
FOB HAMBURG INTERNATIONAL
HB09-P-MJTS-038-1001 Water Injection Pumps MECHANICAL ROTATING H-PB-038002C SF0038 FLOWSERVE HAMBURG GMBH SEAPORT, GERMANY 21-Jun-12 17-Mar-11 02-Mar-11 100 16-Apr-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 23-Jun-11 100 15-Jul-11 23-Jun-11 100 29-Aug-11 25-Nov-11 25 23-Oct-11 28-Feb-12 10 22-Dec-11 11-Jun-12 05-Feb-12 28-Aug-12 12-Feb-12 09-Sep-12 19-Feb-12 21-Sep-12 26-Feb-12 28-Sep-12 04-Apr-12 05-Nov-12 04-May-12 19-Dec-12 19-May-12 03-Jan-13 19-May-12
Instrument Air Compressor & Dryer ATLAS COPSO SERVICES MIDDLE FOB INTERNATIONAL SEAPORT -
HB09-P-MLTS-063-1000 Package MECHANICAL ROTATING H-XV-063001 SF0003 EAST FZE ANTWERP, BELGIUM 15-Mar-12 10-Feb-11 10-Feb-11 100 12-Mar-11 28-Feb-11 100 23-Apr-11 07-Mar-11 100 30-Apr-11 14-Mar-11 100 14-Jun-11 20-Mar-11 100 29-Jul-11 27-Jul-11 73 08-Sep-11 27-Sep-11 80 07-Nov-11 26-Dec-11 40 05-Feb-12 09-May-12 10.00 12-Feb-12 20-May-12 19-Feb-12 30-May-12 26-Feb-12 06-Jun-12 04-Apr-12 14-Jul-12 04-May-12 13-Aug-12 19-May-12 28-Aug-12 19-May-12
FOB INTERNATIONAL SEAPORT -
HB09-P-MLTS-064-1000 Nitrogen Generation Package MECHANICAL ROTATING H-XC-064001 SF0025 AIRPACK NEDERLAND BV ANTWERP, BELGIUM 15-Nov-11 15-Feb-11 10-Feb-11 100 17-Mar-11 01-Mar-11 100 18-May-11 17-May-11 100 25-May-11 17-May-11 100 09-Jul-11 21-May-11 100 23-Aug-11 09-Oct-11 80 18-Sep-11 20-Nov-11 80 17-Nov-11 25-Feb-12 65 01-Jan-12 08-May-12 20.00 08-Jan-12 19-May-12 15-Jan-12 30-May-12 22-Jan-12 06-Jun-12 29-Feb-12 14-Jul-12 30-Mar-12 13-Aug-12 14-Apr-12 28-Aug-12 14-Apr-12
Mobile Truck Mounted Nitrogen FOB INTERNATIONAL SEAPORT -
HB09-P-MLTS-064-1000 Generation Package MECHANICAL ROTATING U-XC-064001 SF0025 AIRPACK NEDERLAND BV ANTWERP, BELGIUM 14-Feb-12 15-Feb-11 10-Feb-11 100 17-Mar-11 01-Mar-11 100 18-May-11 17-May-11 100 25-May-11 17-May-11 100 09-Jul-11 21-May-11 100 23-Aug-11 09-Oct-11 80 18-Sep-11 20-Nov-11 80 17-Nov-11 25-Feb-12 60 01-Jan-12 08-May-12 10.00 08-Jan-12 19-May-12 15-Jan-12 30-May-12 22-Jan-12 06-Jun-12 29-Feb-12 14-Jul-12 30-Mar-12 13-Aug-12 14-Apr-12 28-Aug-12 14-Apr-12
HB09-P-MLTS-101-1000 Waste Water Treatment Package MECHANICAL ROTATING H-XF-101001 SF0040 OVIVO UK LIMITED FOB INTERNATIONAL SEAPORT UK 06-Dec-11 15-Apr-11 04-Apr-11 100 15-May-11 22-Apr-11 100 30-Jun-11 27-Jun-11 100 07-Jul-11 29-Jun-11 100 21-Aug-11 05-Jul-11 100 05-Oct-11 10-Oct-11 10 14-Nov-11 25-Nov-11 13-Jan-12 02-Feb-12 12-Apr-12 15-May-12 19-Apr-12 23-May-12 21-Apr-12 25-May-12 28-Apr-12 01-Jun-12 05-Jun-12 09-Jul-12 05-Jul-12 08-Aug-12 20-Jul-12 23-Aug-12 20-Jul-12

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
PROCUREMENT TRACKING REGISTER

ISG PROJECT - IN SALAH GAS SOUTHERN FIELDS DEVELOPMENT PTR TEMPLATE


CONTRACT NO. : 100045/ISG/CON
DOCUMENT NO : 1 7 11 12 13 14 15-Jan-00 23 24-Jan-00 25-Jan-00 26 28-Jan-00 29-Jan-00 30 09-Jan-00
CUT OFF DATE: 29-Oct-11

Issue Inquiry Requisition Receive Bid TBE Complete Place LOI / LOA Place PO Receive / Approve Key Vendor Drawings / Documents Place Sub-orders Receive Raw Materials Fabrication / Mfg. Inspection Release Note Ex-works Delivery Item on Board Shipping/Air Freight/Land Transport (ATA Port) Custom Clearance and Transport to site/store Visual Inspection on Receipt at Site/Store ROS
Inquiry No. Description Discipline INQD_TAG_NO PO_NO Vendor Name PO Delivery Terms PO_CDD
P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog
SOLAR TURBINES
HB09-P-MUTS-081-1000 Gas Turbine Generator - Train 2 MECHANICAL ROTATING H-XM-081201 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 29-Mar-12 65 24-May-12 04-Jun-12 11 20-Jul-12 31-Jul-12 27-Jul-12 07-Aug-12 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 Gas Turbine Generator - Train 1 MECHANICAL ROTATING H-XM-081101 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 29-Mar-12 65 24-May-12 04-Jun-12 11 20-Jul-12 31-Jul-12 27-Jul-12 07-Aug-12 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 Gas Turbine Generator - Train 1 (LER MECHANICAL ROTATING H-XM-081101-LER SF0014 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 29-Mar-12 65 24-May-12 04-Jun-12 11 20-Jul-12 31-Jul-12 27-Jul-12 07-Aug-12 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 Gas Turbine Generator - Train 2 (LER) MECHANICAL ROTATING H-XM-081201-LER SF0014 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 29-Mar-12 65 24-May-12 04-Jun-12 11 20-Jul-12 31-Jul-12 27-Jul-12 07-Aug-12 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 NER - Train 1 MECHANICAL ROTATING H-XM-081101-5 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 13-Aug-11 65 24-May-12 13-Aug-11 11 20-Jul-12 13-Aug-11 27-Jul-12 13-Aug-11 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 CO2 Bottles - Train 1 MECHANICAL ROTATING H-XM-081101-6 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 13-Aug-11 65 24-May-12 13-Aug-11 11 20-Jul-12 13-Aug-11 27-Jul-12 13-Aug-11 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 Lube Oil Cooler - Train 1 MECHANICAL ROTATING H-XM-081101-7 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 13-Aug-11 65 24-May-12 13-Aug-11 11 20-Jul-12 13-Aug-11 27-Jul-12 13-Aug-11 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 Fuel Gas Treatment - Train 1 MECHANICAL ROTATING H-XM-081101-8 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 13-Aug-11 65 24-May-12 13-Aug-11 11 20-Jul-12 13-Aug-11 27-Jul-12 13-Aug-11 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 Fuel Gas Treatment - Train 2 MECHANICAL ROTATING H-XM-081201-9 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 13-Aug-11 65 24-May-12 13-Aug-11 11 20-Jul-12 13-Aug-11 27-Jul-12 13-Aug-11 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 NER - Train 2 MECHANICAL ROTATING H-XM-081201-10 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 13-Aug-11 65 24-May-12 13-Aug-11 11 20-Jul-12 13-Aug-11 27-Jul-12 13-Aug-11 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 CO2 Bottles - Train 2 MECHANICAL ROTATING H-XM-081201-11 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 13-Aug-11 65 24-May-12 13-Aug-11 11 20-Jul-12 13-Aug-11 27-Jul-12 13-Aug-11 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
SOLAR TURBINES
HB09-P-MUTS-081-1000 Lube Oil Cooler - Train 2 MECHANICAL ROTATING H-XM-081201-12 SF0013 INTERNATIONAL COMPANY FCA SELLER'S WORK, USA 04-Jun-12 10-Feb-11 23-Jan-11 100 03-Mar-11 01-Feb-11 100 19-May-11 26-May-11 100 26-May-11 05-Jun-11 100 12-Jun-11 05-Jun-11 100 03-Aug-11 13-Aug-11 50 18-Mar-12 13-Aug-11 65 24-May-12 13-Aug-11 11 20-Jul-12 13-Aug-11 27-Jul-12 13-Aug-11 03-Aug-12 15-Aug-12 10-Aug-12 22-Aug-12 17-Sep-12 29-Sep-12 17-Oct-12 29-Oct-12 01-Nov-12 13-Nov-12 01-Nov-12
HU00-P-MJTS-000-1000 Mobile Pump MECHANICAL ROTATING H-PF-054004 16-May-11 28-Oct-11 15-Jun-11 23-Nov-11 23-Jul-11 21-Dec-11 30-Jul-11 28-Dec-11 13-Sep-11 11-Feb-12 28-Oct-11 27-Mar-12 22-Nov-11 21-Apr-12 21-Jan-12 20-Jun-12 06-Mar-12 04-Aug-12 13-Mar-12 11-Aug-12 20-Mar-12 18-Aug-12 27-Mar-12 25-Aug-12 04-May-12 02-Oct-12 03-Jun-12 01-Nov-12 18-Jun-12 16-Nov-12 18-Jun-12
HU00-P-MJTS-000-1000 Pneumatic Pump MECHANICAL ROTATING H-PF-054003 16-May-11 28-Oct-11 15-Jun-11 23-Nov-11 23-Jul-11 21-Dec-11 30-Jul-11 28-Dec-11 13-Sep-11 11-Feb-12 28-Oct-11 27-Mar-12 22-Nov-11 21-Apr-12 21-Jan-12 20-Jun-12 06-Mar-12 04-Aug-12 13-Mar-12 11-Aug-12 20-Mar-12 18-Aug-12 27-Mar-12 25-Aug-12 04-May-12 02-Oct-12 03-Jun-12 01-Nov-12 18-Jun-12 16-Nov-12 18-Jun-12
HU00-P-MJTS-000-1000 Pneumatic Pump MECHANICAL ROTATING K-PF-054302 16-May-11 28-Oct-11 15-Jun-11 23-Nov-11 23-Jul-11 21-Dec-11 30-Jul-11 28-Dec-11 13-Sep-11 11-Feb-12 28-Oct-11 27-Mar-12 22-Nov-11 21-Apr-12 21-Jan-12 20-Jun-12 06-Mar-12 04-Aug-12 13-Mar-12 11-Aug-12 20-Mar-12 18-Aug-12 27-Mar-12 25-Aug-12 04-May-12 02-Oct-12 03-Jun-12 01-Nov-12 18-Jun-12 16-Nov-12 18-Jun-12
JB00-P-MUTS-023-1000 Compressor Revamp (KRECHBA) MECHANICAL ROTATING J-XT-023150 25-Mar-11 04-Apr-11 100 27-Jun-11 09-Jun-11 100 27-Jul-11 24-May-12 03-Aug-11 31-May-12 17-Sep-11 15-Jul-12 01-Nov-11 12-Nov-12 05-Dec-12 08-Sep-13 03-Feb-13 07-Nov-13 04-Apr-13 20-Feb-14 11-Apr-13 27-Feb-14 18-Apr-13 06-Mar-14 25-Apr-13 13-Mar-14 02-Jun-13 20-Apr-14 02-Jul-13 20-May-14 17-Jul-13 04-Jun-14 17-Jul-13
UB00-P-MLTS-101-1000 Pump Station Package MECHANICAL ROTATING H-XF-101002 15-Apr-11 02-May-11 100 24-Jun-11 24-Jul-11 100 24-Jul-11 23-Nov-11 31-Jul-11 30-Nov-11 14-Sep-11 14-Jan-12 29-Oct-11 13-Feb-12 24-Nov-11 05-Mar-12 23-Jan-12 26-Mar-12 08-Mar-12 02-May-12 15-Mar-12 09-May-12 19-Mar-12 16-May-12 26-Mar-12 23-May-12 03-May-12 30-Jun-12 02-Jun-12 30-Jul-12 17-Jun-12 14-Aug-12 17-Jun-12
UB00-P-MLTS-101-1000 Pump Station Package MECHANICAL ROTATING K-XF-101XXX 15-Apr-11 02-May-11 100 24-Jun-11 24-Jul-11 100 24-Jul-11 23-Nov-11 31-Jul-11 30-Nov-11 14-Sep-11 14-Jan-12 29-Oct-11 13-Feb-12 24-Nov-11 05-Mar-12 23-Jan-12 26-Mar-12 08-Mar-12 02-May-12 15-Mar-12 09-May-12 19-Mar-12 16-May-12 26-Mar-12 23-May-12 03-May-12 30-Jun-12 02-Jun-12 30-Jul-12 17-Jun-12 14-Aug-12 17-Jun-12
UB00-P-MUTS-023-1000 Compressor Revamp-TEG Train-1 MECHANICAL ROTATING L-XT-023150 SF0001 NUOVO PIGNONE SPA FOB ITALIAN PORT BASIS 30-Apr-13 17-Feb-11 01-Feb-11 100 03-Mar-11 01-Feb-11 100 24-Mar-11 17-May-11 100 17-Jun-11 14-Jul-11 100 01-Aug-11 14-Jul-11 100 15-Sep-11 07-Nov-11 5 20-Oct-12 09-Apr-13 4 19-Dec-12 26-Jun-13 17-Feb-13 12-Sep-13 24-Feb-13 21-Sep-13 03-Mar-13 30-Sep-13 10-Mar-13 07-Oct-13 17-Apr-13 14-Nov-13 17-May-13 14-Dec-13 01-Jun-13 29-Dec-13 01-Jun-13
UB00-P-MUTS-023-1000 Compressor Revamp-REG Train-1 MECHANICAL ROTATING K-XT-023150 SF0001 NUOVO PIGNONE SPA FOB ITALIAN PORT BASIS 30-Apr-13 17-Feb-11 01-Feb-11 100 03-Mar-11 01-Feb-11 100 24-Mar-11 17-May-11 100 17-Jun-11 14-Jul-11 100 01-Aug-11 14-Jul-11 100 15-Sep-11 07-Nov-11 5 20-Oct-12 09-Apr-13 4 19-Dec-12 26-Jun-13 17-Feb-13 12-Sep-13 24-Feb-13 21-Sep-13 03-Mar-13 30-Sep-13 10-Mar-13 07-Oct-13 17-Apr-13 14-Nov-13 17-May-13 14-Dec-13 01-Jun-13 29-Dec-13 01-Jun-13
UB00-P-MUTS-023-1000 Compressor Revamp-REG Train-2 MECHANICAL ROTATING K-XT-023250 SF0001 NUOVO PIGNONE SPA FOB ITALIAN PORT BASIS 30-Apr-13 17-Feb-11 01-Feb-11 100 03-Mar-11 01-Feb-11 100 24-Mar-11 17-May-11 100 17-Jun-11 14-Jul-11 100 01-Aug-11 14-Jul-11 100 15-Sep-11 07-Nov-11 5 20-Oct-12 09-Apr-13 4 19-Dec-12 26-Jun-13 17-Feb-13 12-Sep-13 24-Feb-13 21-Sep-13 03-Mar-13 30-Sep-13 10-Mar-13 07-Oct-13 17-Apr-13 14-Nov-13 17-May-13 14-Dec-13 01-Jun-13 29-Dec-13 01-Jun-13
UB00-P-MUTS-023-1000 Compressor Revamp-TEG Train-2 MECHANICAL ROTATING L-XT-023250 SF0001 NUOVO PIGNONE SPA FOB ITALIAN PORT BASIS 30-Apr-13 17-Feb-11 01-Feb-11 100 03-Mar-11 01-Feb-11 100 24-Mar-11 17-May-11 100 17-Jun-11 14-Jul-11 100 01-Aug-11 14-Jul-11 100 15-Sep-11 07-Nov-11 5 20-Oct-12 09-Apr-13 4 19-Dec-12 26-Jun-13 17-Feb-13 12-Sep-13 24-Feb-13 21-Sep-13 03-Mar-13 30-Sep-13 10-Mar-13 07-Oct-13 17-Apr-13 14-Nov-13 17-May-13 14-Dec-13 01-Jun-13 29-Dec-13 01-Jun-13

SOCIETE FRANCAISE D'ETUDES


UB09-P-MLTS-053-1000 Fresh Water Package MECHANICAL ROTATING H-XX-053001 SF0041 ET COMMERCIALISATION FOB MARSEILLE, FRANCE 26-Nov-11 07-Mar-11 15-Mar-11 100 06-Apr-11 05-Apr-11 100 21-Jun-11 23-Jun-11 100 28-Jun-11 28-Jun-11 100 12-Aug-11 28-Jun-11 100 26-Sep-11 20-Oct-11 45 04-Nov-11 08-Dec-11 03-Jan-12 22-Feb-12 02-Apr-12 15-Jun-12 09-Apr-12 24-Jun-12 13-Apr-12 30-Jun-12 20-Apr-12 07-Jul-12 28-May-12 14-Aug-12 27-Jun-12 13-Sep-12 12-Jul-12 28-Sep-12 12-Jul-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013004 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013008 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING I-XR-013001 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING I-XR-013005 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013001 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 12-Aug-12 14-May-12 11-Sep-12 29-May-12 26-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013002 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013003 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013005 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013006 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013007 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013009 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013010 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING E-XR-013011 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING I-XR-013002 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING I-XR-013003 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING I-XR-013004 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING I-XR-013006 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING I-XR-013007 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
Wellhead Chemical Injection (Scale FOB GENOVA INTERNATIONAL SEAPORT,
UC00-P-MLTS-013-1000 Inhibitor) MECHANICAL ROTATING I-XR-013008 SF0047 LEWA SRL ITALY 28-Feb-12 04-Apr-11 03-Apr-11 100 04-May-11 28-Apr-11 100 03-Jun-11 13-Jun-11 100 10-Jun-11 10-Jul-11 100 25-Jul-11 10-Jul-11 100 08-Sep-11 08-Nov-11 45 18-Sep-11 21-Nov-11 25 17-Nov-11 09-Feb-12 15-Feb-12 09-Jun-12 22-Feb-12 18-Jun-12 29-Feb-12 28-Jun-12 07-Mar-12 05-Jul-12 14-Apr-12 03-Aug-12 14-May-12 02-Sep-12 29-May-12 17-Sep-12 29-May-12
UF00-P-MJTS-000-2001 Mobile Pump MECHANICAL ROTATING H-PF-062003 16-May-11 28-Oct-11 15-Jun-11 27-Nov-11 23-Jul-11 08-Jan-12 30-Jul-11 15-Jan-12 13-Sep-11 29-Feb-12 28-Oct-11 14-Apr-12 22-Nov-11 09-May-12 21-Jan-12 08-Jul-12 06-Mar-12 22-Aug-12 13-Mar-12 29-Aug-12 20-Mar-12 05-Sep-12 27-Mar-12 12-Sep-12 04-May-12 20-Oct-12 03-Jun-12 19-Nov-12 18-Jun-12 04-Dec-12 18-Jun-12
UF00-P-MJTS-000-2002 Fresh Water Pressurisation Pumps MECHANICAL ROTATING H-PA-109002A 15-Mar-11 20-Nov-11 14-Apr-11 11-Dec-11 28-Jun-11 08-Jan-12 05-Jul-11 15-Jan-12 19-Aug-11 29-Feb-12 03-Oct-11 14-Apr-12 28-Oct-11 09-May-12 27-Dec-11 08-Jul-12 10-Feb-12 22-Aug-12 17-Feb-12 29-Aug-12 22-Feb-12 03-Sep-12 29-Feb-12 10-Sep-12 07-Apr-12 18-Oct-12 07-May-12 17-Nov-12 22-May-12 02-Dec-12 22-May-12
UF00-P-MJTS-000-2002 Diesel Transfer Pump MECHANICAL ROTATING H-PA-062002 15-Mar-11 20-Nov-11 14-Apr-11 11-Dec-11 28-Jun-11 08-Jan-12 05-Jul-11 15-Jan-12 19-Aug-11 29-Feb-12 03-Oct-11 14-Apr-12 28-Oct-11 09-May-12 27-Dec-11 08-Jul-12 10-Feb-12 22-Aug-12 17-Feb-12 29-Aug-12 22-Feb-12 03-Sep-12 29-Feb-12 10-Sep-12 07-Apr-12 18-Oct-12 07-May-12 17-Nov-12 22-May-12 02-Dec-12 22-May-12
UF00-P-MJTS-000-2002 Fresh Water Pressurisation Pumps MECHANICAL ROTATING H-PA-109002B 15-Mar-11 20-Nov-11 14-Apr-11 11-Dec-11 28-Jun-11 08-Jan-12 05-Jul-11 15-Jan-12 19-Aug-11 29-Feb-12 03-Oct-11 14-Apr-12 28-Oct-11 09-May-12 27-Dec-11 08-Jul-12 10-Feb-12 22-Aug-12 17-Feb-12 29-Aug-12 22-Feb-12 03-Sep-12 29-Feb-12 10-Sep-12 07-Apr-12 18-Oct-12 07-May-12 17-Nov-12 22-May-12 02-Dec-12 22-May-12
UF00-P-MJTS-000-2002 Raw Water Transfer Pumps MECHANICAL ROTATING H-PA-109001A 15-Mar-11 20-Nov-11 14-Apr-11 11-Dec-11 28-Jun-11 08-Jan-12 05-Jul-11 15-Jan-12 19-Aug-11 29-Feb-12 03-Oct-11 14-Apr-12 28-Oct-11 09-May-12 27-Dec-11 08-Jul-12 10-Feb-12 22-Aug-12 17-Feb-12 29-Aug-12 22-Feb-12 03-Sep-12 29-Feb-12 10-Sep-12 07-Apr-12 18-Oct-12 07-May-12 17-Nov-12 22-May-12 02-Dec-12 22-May-12
UF00-P-MJTS-000-2002 Raw Water Transfer Pumps MECHANICAL ROTATING H-PA-109001B 15-Mar-11 20-Nov-11 14-Apr-11 11-Dec-11 28-Jun-11 08-Jan-12 05-Jul-11 15-Jan-12 19-Aug-11 29-Feb-12 03-Oct-11 14-Apr-12 28-Oct-11 09-May-12 27-Dec-11 08-Jul-12 10-Feb-12 22-Aug-12 17-Feb-12 29-Aug-12 22-Feb-12 03-Sep-12 29-Feb-12 10-Sep-12 07-Apr-12 18-Oct-12 07-May-12 17-Nov-12 22-May-12 02-Dec-12 22-May-12
UF00-P-MJTS-000-2002 Diesel Dispensing Pump MECHANICAL ROTATING H-PZ-062001 15-Mar-11 20-Nov-11 14-Apr-11 11-Dec-11 28-Jun-11 08-Jan-12 05-Jul-11 15-Jan-12 19-Aug-11 29-Feb-12 03-Oct-11 14-Apr-12 28-Oct-11 09-May-12 27-Dec-11 08-Jul-12 10-Feb-12 22-Aug-12 17-Feb-12 29-Aug-12 22-Feb-12 03-Sep-12 29-Feb-12 10-Sep-12 07-Apr-12 18-Oct-12 07-May-12 17-Nov-12 22-May-12 02-Dec-12 22-May-12
UF00-P-MJTS-071-2001 Fire Water Pumps MECHANICAL ROTATING H-PA-071001A 30-May-11 20-Nov-11 29-Jun-11 11-Dec-11 07-Aug-11 08-Jan-12 14-Aug-11 15-Jan-12 28-Sep-11 29-Feb-12 12-Nov-11 14-Apr-12 17-Nov-11 19-Apr-12 22-Dec-11 24-May-12 21-Jan-12 23-Jun-12 28-Jan-12 30-Jun-12 12-Feb-12 15-Jul-12 19-Feb-12 22-Jul-12 28-Mar-12 29-Aug-12 27-Apr-12 28-Sep-12 12-May-12 13-Oct-12 12-May-12
UF00-P-MJTS-071-2001 Fire Water Pumps MECHANICAL ROTATING H-PA-071001B 30-May-11 20-Nov-11 29-Jun-11 11-Dec-11 07-Aug-11 08-Jan-12 14-Aug-11 15-Jan-12 28-Sep-11 29-Feb-12 12-Nov-11 14-Apr-12 17-Nov-11 19-Apr-12 22-Dec-11 24-May-12 21-Jan-12 23-Jun-12 28-Jan-12 30-Jun-12 12-Feb-12 15-Jul-12 19-Feb-12 22-Jul-12 28-Mar-12 29-Aug-12 27-Apr-12 28-Sep-12 12-May-12 13-Oct-12 12-May-12
UF00-P-MJTS-071-2001 Fire Water Jockey Pumps MECHANICAL ROTATING H-PA-071002 30-May-11 20-Nov-11 29-Jun-11 11-Dec-11 07-Aug-11 08-Jan-12 14-Aug-11 15-Jan-12 28-Sep-11 29-Feb-12 12-Nov-11 14-Apr-12 17-Nov-11 19-Apr-12 22-Dec-11 24-May-12 21-Jan-12 23-Jun-12 28-Jan-12 30-Jun-12 12-Feb-12 15-Jul-12 19-Feb-12 22-Jul-12 28-Mar-12 29-Aug-12 27-Apr-12 28-Sep-12 12-May-12 13-Oct-12 12-May-12

UF00-P-MJTS-091-2001 Overhead Travelling Cranes & Monorails MECHANICAL ROTATING H-XX-XXXXX 30-Jun-11 28-Oct-11 30-Jul-11 27-Nov-11 06-Sep-11 08-Jan-12 13-Sep-11 15-Jan-12 28-Oct-11 29-Feb-12 12-Dec-11 14-Apr-12 06-Jan-12 09-May-12 06-Mar-12 08-Jul-12 20-Apr-12 22-Aug-12 27-Apr-12 29-Aug-12 05-May-12 06-Sep-12 12-May-12 13-Sep-12 19-Jun-12 21-Oct-12 19-Jul-12 20-Nov-12 03-Aug-12 05-Dec-12 03-Aug-12
Military Camp Waste Water Treatment
UF00-P-MJTS-101-2001 Package MECHANICAL ROTATING H-XF-101005 15-Apr-11 28-Oct-11 15-May-11 27-Nov-11 30-Jun-11 08-Jan-12 07-Jul-11 15-Jan-12 21-Aug-11 29-Feb-12 05-Oct-11 14-Apr-12 14-Nov-11 24-May-12 13-Jan-12 23-Jul-12 12-Apr-12 21-Oct-12 19-Apr-12 28-Oct-12 21-Apr-12 30-Oct-12 28-Apr-12 06-Nov-12 05-Jun-12 14-Dec-12 05-Jul-12 13-Jan-13 20-Jul-12 28-Jan-13 20-Jul-12

UF00-P-MJTS-101-2001 BdV Waste Water Treatment Package MECHANICAL ROTATING H-XF-101004 15-Apr-11 28-Oct-11 15-May-11 27-Nov-11 30-Jun-11 08-Jan-12 07-Jul-11 15-Jan-12 21-Aug-11 29-Feb-12 05-Oct-11 14-Apr-12 14-Nov-11 24-May-12 13-Jan-12 23-Jul-12 12-Apr-12 21-Oct-12 19-Apr-12 28-Oct-12 21-Apr-12 30-Oct-12 28-Apr-12 06-Nov-12 05-Jun-12 14-Dec-12 05-Jul-12 13-Jan-13 20-Jul-12 28-Jan-13 20-Jul-12
UF00-P-MJTS-101-2002 Waste Water Pump Package MECHANICAL ROTATING H-XF-101007 15-Apr-11 20-Nov-11 24-Jun-11 11-Dec-11 24-Jul-11 08-Jan-12 31-Jul-11 15-Jan-12 14-Sep-11 29-Feb-12 29-Oct-11 14-Apr-12 24-Nov-11 10-May-12 23-Jan-12 09-Jul-12 08-Mar-12 23-Aug-12 15-Mar-12 30-Aug-12 19-Mar-12 03-Sep-12 26-Mar-12 10-Sep-12 03-May-12 18-Oct-12 02-Jun-12 17-Nov-12 17-Jun-12 02-Dec-12 17-Jun-12
UF00-P-MJTS-101-2002 Waste Water Pump Package MECHANICAL ROTATING H-XF-101006 15-Apr-11 20-Nov-11 24-Jun-11 11-Dec-11 24-Jul-11 08-Jan-12 31-Jul-11 15-Jan-12 14-Sep-11 29-Feb-12 29-Oct-11 14-Apr-12 24-Nov-11 10-May-12 23-Jan-12 09-Jul-12 08-Mar-12 23-Aug-12 15-Mar-12 30-Aug-12 19-Mar-12 03-Sep-12 26-Mar-12 10-Sep-12 03-May-12 18-Oct-12 02-Jun-12 17-Nov-12 17-Jun-12 02-Dec-12 17-Jun-12
UF00-P-MJTS-101-2002 Waste Water Pump Package MECHANICAL ROTATING H-XF-101008 15-Apr-11 20-Nov-11 24-Jun-11 11-Dec-11 24-Jul-11 08-Jan-12 31-Jul-11 15-Jan-12 14-Sep-11 29-Feb-12 29-Oct-11 14-Apr-12 24-Nov-11 10-May-12 23-Jan-12 09-Jul-12 08-Mar-12 23-Aug-12 15-Mar-12 30-Aug-12 19-Mar-12 03-Sep-12 26-Mar-12 10-Sep-12 03-May-12 18-Oct-12 02-Jun-12 17-Nov-12 17-Jun-12 02-Dec-12 17-Jun-12
UF00-P-MJTS-101-2002 Waste Water Pump Package MECHANICAL ROTATING H-XF-101009 15-Apr-11 20-Nov-11 24-Jun-11 11-Dec-11 24-Jul-11 08-Jan-12 31-Jul-11 15-Jan-12 14-Sep-11 29-Feb-12 29-Oct-11 14-Apr-12 24-Nov-11 10-May-12 23-Jan-12 09-Jul-12 08-Mar-12 23-Aug-12 15-Mar-12 30-Aug-12 19-Mar-12 03-Sep-12 26-Mar-12 10-Sep-12 03-May-12 18-Oct-12 02-Jun-12 17-Nov-12 17-Jun-12 02-Dec-12 17-Jun-12
UF00-P-MJTS-109-2001 Fresh Water Package MECHANICAL ROTATING H-XX-109001 07-Mar-11 28-Oct-11 06-Apr-11 27-Nov-11 21-Jun-11 08-Jan-12 28-Jun-11 15-Jan-12 12-Aug-11 29-Feb-12 26-Sep-11 14-Apr-12 04-Nov-11 23-May-12 03-Jan-12 22-Jul-12 02-Apr-12 20-Oct-12 09-Apr-12 27-Oct-12 10-Apr-12 28-Oct-12 17-Apr-12 04-Nov-12 25-May-12 12-Dec-12 24-Jun-12 11-Jan-13 09-Jul-12 26-Jan-13 09-Jul-12
UF00-P-MJTS-109-2001 Fresh Water Package MECHANICAL ROTATING H-XX-109002 07-Mar-11 28-Oct-11 06-Apr-11 27-Nov-11 21-Jun-11 08-Jan-12 28-Jun-11 15-Jan-12 12-Aug-11 29-Feb-12 26-Sep-11 14-Apr-12 04-Nov-11 23-May-12 03-Jan-12 22-Jul-12 02-Apr-12 20-Oct-12 09-Apr-12 27-Oct-12 10-Apr-12 28-Oct-12 17-Apr-12 04-Nov-12 25-May-12 12-Dec-12 24-Jun-12 11-Jan-13 09-Jul-12 26-Jan-13 09-Jul-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Diesel Transfer Pump MECHANICAL ROTATING H-PA-062001 SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Apr-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 21-Oct-11 35 28-Oct-11 20-Nov-11 25 27-Dec-11 30-Jan-12 10-Feb-12 23-Mar-12 17-Feb-12 31-Mar-12 22-Feb-12 06-Apr-12 29-Feb-12 13-Apr-12 07-Apr-12 21-May-12 07-May-12 20-Jun-12 22-May-12 05-Jul-12 22-May-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Glycol Transfer Pump MECHANICAL ROTATING H-PA-054001 SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Feb-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 18-Oct-11 35 28-Oct-11 16-Nov-11 25 27-Dec-11 25-Jan-12 10-Feb-12 17-Mar-12 17-Feb-12 25-Mar-12 27-Feb-12 06-Apr-12 05-Mar-12 13-Apr-12 12-Apr-12 21-May-12 12-May-12 20-Jun-12 27-May-12 05-Jul-12 27-May-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Plant Water Transfer Pumps MECHANICAL ROTATING H-PA-052001A SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Feb-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 18-Oct-11 35 28-Oct-11 16-Nov-11 25 27-Dec-11 25-Jan-12 10-Feb-12 17-Mar-12 17-Feb-12 25-Mar-12 27-Feb-12 06-Apr-12 05-Mar-12 13-Apr-12 12-Apr-12 21-May-12 12-May-12 20-Jun-12 27-May-12 05-Jul-12 27-May-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Closed Drains Pump MECHANICAL ROTATING K-PH-057301 SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Feb-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 18-Oct-11 35 28-Oct-11 16-Nov-11 25 27-Dec-11 25-Jan-12 10-Feb-12 17-Mar-12 17-Feb-12 25-Mar-12 27-Feb-12 06-Apr-12 05-Mar-12 13-Apr-12 12-Apr-12 21-May-12 12-May-12 20-Jun-12 27-May-12 05-Jul-12 27-May-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Fresh Water Pressurisation Pumps MECHANICAL ROTATING H-PA-053001A SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Feb-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 18-Oct-11 35 28-Oct-11 16-Nov-11 25 27-Dec-11 25-Jan-12 10-Feb-12 17-Mar-12 17-Feb-12 25-Mar-12 27-Feb-12 06-Apr-12 05-Mar-12 13-Apr-12 12-Apr-12 21-May-12 12-May-12 20-Jun-12 27-May-12 05-Jul-12 27-May-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Fresh Water Pressurisation Pumps MECHANICAL ROTATING H-PA-053001B SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Feb-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 18-Oct-11 35 28-Oct-11 16-Nov-11 25 27-Dec-11 25-Jan-12 10-Feb-12 17-Mar-12 17-Feb-12 25-Mar-12 27-Feb-12 06-Apr-12 05-Mar-12 13-Apr-12 12-Apr-12 21-May-12 12-May-12 20-Jun-12 27-May-12 05-Jul-12 27-May-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Glycol Drains Pump MECHANICAL ROTATING K-PH-054301 SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Feb-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 18-Oct-11 35 28-Oct-11 16-Nov-11 25 27-Dec-11 25-Jan-12 10-Feb-12 17-Mar-12 17-Feb-12 25-Mar-12 27-Feb-12 06-Apr-12 05-Mar-12 13-Apr-12 12-Apr-12 21-May-12 12-May-12 20-Jun-12 27-May-12 05-Jul-12 27-May-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Glycol Drains Pump MECHANICAL ROTATING H-PH-054002 SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Feb-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 21-Oct-11 35 28-Oct-11 20-Nov-11 25 27-Dec-11 30-Jan-12 10-Feb-12 23-Mar-12 17-Feb-12 31-Mar-12 22-Feb-12 06-Apr-12 29-Feb-12 13-Apr-12 07-Apr-12 21-May-12 07-May-12 20-Jun-12 22-May-12 05-Jul-12 22-May-12

FOB SOUTHAMPTON OR FELIXSTOWE


UU00-P-MJTS-000-1000 Plant Water Transfer Pumps MECHANICAL ROTATING H-PA-052001B SF0018 FLOWSERVE GB LIMITED INTERNATIONAL SEAPORT 06-Feb-12 15-Mar-11 29-Mar-11 100 14-Apr-11 24-Apr-11 100 28-Jun-11 03-Jul-11 100 05-Jul-11 06-Jul-11 100 19-Aug-11 06-Jul-11 100 03-Oct-11 18-Oct-11 35 28-Oct-11 16-Nov-11 25 27-Dec-11 25-Jan-12 10-Feb-12 17-Mar-12 17-Feb-12 25-Mar-12 27-Feb-12 06-Apr-12 05-Mar-12 13-Apr-12 12-Apr-12 21-May-12 12-May-12 20-Jun-12 27-May-12 05-Jul-12 27-May-12
UU00-P-MJTS-052-1000 Well Water Lift Pump MECHANICAL ROTATING D-PS-052001 16-May-11 02-May-11 100 15-Jun-11 12-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 28-Oct-11 13-Feb-12 22-Nov-11 09-Mar-12 21-Jan-12 08-Apr-12 06-Mar-12 16-May-12 13-Mar-12 23-May-12 20-Mar-12 30-May-12 27-Mar-12 06-Jun-12 04-May-12 14-Jul-12 03-Jun-12 13-Aug-12 18-Jun-12 28-Aug-12 18-Jun-12
UU00-P-MJTS-052-1000 Well Water Lift Pump MECHANICAL ROTATING E-PS-052001 16-May-11 02-May-11 100 15-Jun-11 12-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 28-Oct-11 13-Feb-12 22-Nov-11 09-Mar-12 21-Jan-12 08-Apr-12 06-Mar-12 16-May-12 13-Mar-12 23-May-12 20-Mar-12 30-May-12 27-Mar-12 06-Jun-12 04-May-12 14-Jul-12 03-Jun-12 13-Aug-12 18-Jun-12 28-Aug-12 18-Jun-12
UU00-P-MJTS-052-1000 Well Water Lift Pump MECHANICAL ROTATING F-PS-052001 16-May-11 02-May-11 100 15-Jun-11 12-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 28-Oct-11 13-Feb-12 22-Nov-11 09-Mar-12 21-Jan-12 08-Apr-12 06-Mar-12 16-May-12 13-Mar-12 23-May-12 20-Mar-12 30-May-12 27-Mar-12 06-Jun-12 04-May-12 14-Jul-12 03-Jun-12 13-Aug-12 18-Jun-12 28-Aug-12 18-Jun-12
UU00-P-MJTS-052-1000 Well Water Lift Pump MECHANICAL ROTATING I-PS-052001 16-May-11 02-May-11 100 15-Jun-11 12-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 28-Oct-11 13-Feb-12 22-Nov-11 09-Mar-12 21-Jan-12 08-Apr-12 06-Mar-12 16-May-12 13-Mar-12 23-May-12 20-Mar-12 30-May-12 27-Mar-12 06-Jun-12 04-May-12 14-Jul-12 03-Jun-12 13-Aug-12 18-Jun-12 28-Aug-12 18-Jun-12
UU00-P-MJTS-052-1000 Plant Water Lift Pump MECHANICAL ROTATING H-PS-052002A 16-May-11 02-May-11 100 15-Jun-11 12-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 28-Oct-11 13-Feb-12 22-Nov-11 09-Mar-12 21-Jan-12 08-Apr-12 06-Mar-12 16-May-12 13-Mar-12 23-May-12 20-Mar-12 30-May-12 27-Mar-12 06-Jun-12 04-May-12 14-Jul-12 03-Jun-12 13-Aug-12 18-Jun-12 28-Aug-12 18-Jun-12
UU00-P-MJTS-052-1000 Plant Water Lift Pump MECHANICAL ROTATING H-PS-052002B 16-May-11 02-May-11 100 15-Jun-11 12-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 28-Oct-11 13-Feb-12 22-Nov-11 09-Mar-12 21-Jan-12 08-Apr-12 06-Mar-12 16-May-12 13-Mar-12 23-May-12 20-Mar-12 30-May-12 27-Mar-12 06-Jun-12 04-May-12 14-Jul-12 03-Jun-12 13-Aug-12 18-Jun-12 28-Aug-12 18-Jun-12
UU00-P-MJTS-052-1000 Plant Water Lift Pump MECHANICAL ROTATING H-PS-052002C 16-May-11 02-May-11 100 15-Jun-11 12-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 28-Oct-11 13-Feb-12 22-Nov-11 09-Mar-12 21-Jan-12 08-Apr-12 06-Mar-12 16-May-12 13-Mar-12 23-May-12 20-Mar-12 30-May-12 27-Mar-12 06-Jun-12 04-May-12 14-Jul-12 03-Jun-12 13-Aug-12 18-Jun-12 28-Aug-12 18-Jun-12
UU00-P-MLTS-000-1000 Monorail MECHANICAL ROTATING XX-XX-XX 25-Aug-11 100 22-Sep-11 100 23-Nov-11 30-Nov-11 14-Jan-12 19-Feb-12 11-Mar-12 01-Apr-12 16-May-12 23-May-12 30-May-12 06-Jun-12 14-Jul-12 13-Aug-12 28-Aug-12 22-Oct-12
UU00-P-MLTS-069-1000 Lubricating Oil MECHANICAL ROTATING xxxxx 10-Feb-12 10-Feb-12 11-Mar-12 11-Mar-12 18-Apr-12 18-Apr-12 25-Apr-12 25-Apr-12 09-Jun-12 09-Jun-12 24-Jul-12 24-Jul-12 19-Jun-12 19-Jun-12 09-Jul-12 09-Jul-12 03-Aug-12 03-Aug-12 10-Aug-12 10-Aug-12 17-Aug-12 17-Aug-12 24-Aug-12 24-Aug-12 01-Oct-12 01-Oct-12 31-Oct-12 31-Oct-12 15-Nov-12 15-Nov-12 15-Nov-12
UU00-P-SSTS-097-1000 Equipment & Controls HVAC UU00-P-SSTS-097-1000-106 15-May-11 28-Oct-11 13-Jun-11 27-Nov-11 21-Jul-11 08-Jan-12 28-Jul-11 15-Jan-12 11-Sep-11 29-Feb-12 06-Mar-12 24-Aug-12 13-Mar-12 31-Aug-12 20-Mar-12 07-Sep-12 27-Mar-12 14-Sep-12 04-May-12 22-Oct-12 03-Jun-12 21-Nov-12 18-Jun-12 06-Dec-12 18-Jun-12
UU00-P-SSTS-097-1001 Ventilation Equipment HVAC UU00-P-SSTS-097-1001-107 15-May-11 28-Oct-11 13-Jun-11 27-Nov-11 21-Jul-11 08-Jan-12 28-Jul-11 15-Jan-12 11-Sep-11 29-Feb-12 06-Mar-12 24-Aug-12 13-Mar-12 31-Aug-12 20-Mar-12 07-Sep-12 27-Mar-12 14-Sep-12 04-May-12 22-Oct-12 03-Jun-12 21-Nov-12 18-Jun-12 06-Dec-12 18-Jun-12
UU00-P-SSTS-097-1002 Chilled & Hot Water Pumps HVAC UU00-P-SSTS-097-1002-108 18-Apr-11 28-Oct-11 18-May-11 27-Nov-11 20-Jun-11 08-Jan-12 27-Jun-11 15-Jan-12 11-Aug-11 29-Feb-12 31-Jan-12 20-Aug-12 07-Feb-12 27-Aug-12 14-Feb-12 03-Sep-12 21-Feb-12 10-Sep-12 30-Mar-12 18-Oct-12 29-Apr-12 17-Nov-12 15-May-12 03-Dec-12 15-May-12
UU00-P-SSTS-097-1003 Ducting and Duct Accessories HVAC UU00-P-SSTS-097-1003-109 17-Apr-11 28-Oct-11 17-May-11 27-Nov-11 20-Jun-11 08-Jan-12 27-Jun-11 15-Jan-12 11-Aug-11 29-Feb-12 02-Oct-11 21-Apr-12 09-Oct-11 28-Apr-12 16-Oct-11 05-May-12 23-Oct-11 12-May-12 30-Nov-11 19-Jun-12 30-Dec-11 19-Jul-12 14-Jan-12 03-Aug-12 14-Jan-12

UU00-P-SSTS-097-1004 Chilled Water Line Ancillary Equipment HVAC UU00-P-SSTS-097-1004-110 20-Mar-11 28-Oct-11 19-Apr-11 27-Nov-11 22-May-11 08-Jan-12 29-May-11 15-Jan-12 13-Jul-11 29-Feb-12 03-Dec-11 21-Jul-12 10-Dec-11 28-Jul-12 17-Dec-11 04-Aug-12 24-Dec-11 11-Aug-12 31-Jan-12 18-Sep-12 01-Mar-12 18-Oct-12 16-Mar-12 02-Nov-12 16-Mar-12
UU00-P-SSTS-097-1005 Consumables HVAC UU00-P-SSTS-097-1005-111 16-May-11 28-Oct-11 15-Jun-11 27-Nov-11 23-Jul-11 08-Jan-12 30-Jul-11 15-Jan-12 13-Oct-11 30-Mar-12 08-Nov-11 25-Apr-12 15-Nov-11 02-May-12 22-Nov-11 09-May-12 29-Nov-11 16-May-12 06-Jan-12 23-Jun-12 05-Feb-12 23-Jul-12 20-Feb-12 07-Aug-12 20-Feb-12

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) PIPING LOT : 001 SF0020 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 30-Jun-11 31-Jan-11 09-Feb-11 100 02-Mar-11 10-Mar-11 100 25-Mar-11 05-May-11 100 01-Apr-11 12-May-11 100 16-May-11 12-May-11 100 08-Sep-11 28-Jul-11 100.00 15-Sep-11 28-Jul-11 100.00 22-Sep-11 08-Aug-11 100.00 29-Sep-11 22-Aug-11 100.00 06-Nov-11 17-Sep-11 100.00 06-Dec-11 04-Oct-11 100.00 21-Dec-11 08-Oct-11 100.00 21-Dec-11

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) PIPING LOT : 002 SF0020 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 17-Oct-11 31-Jan-11 09-Feb-11 100 02-Mar-11 10-Mar-11 100 25-Mar-11 05-May-11 100 01-Apr-11 12-May-11 100 16-May-11 12-May-11 100 08-Sep-11 14-Nov-11 25.36 15-Sep-11 22-Nov-11 22-Sep-11 30-Nov-11 29-Sep-11 07-Dec-11 06-Nov-11 14-Jan-12 06-Dec-11 13-Feb-12 21-Dec-11 28-Feb-12 21-Dec-11

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) PIPING LOT : 003 SF0020 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 31-Aug-11 31-Jan-11 09-Feb-11 100 02-Mar-11 10-Mar-11 100 25-Mar-11 05-May-11 100 01-Apr-11 12-May-11 100 16-May-11 12-May-11 100 08-Sep-11 28-Sep-11 100.00 15-Sep-11 28-Sep-11 100.00 22-Sep-11 10-Oct-11 100.00 29-Sep-11 24-Oct-11 06-Nov-11 24-Nov-11 06-Dec-11 25-Nov-11 21-Dec-11 25-Nov-11 21-Dec-11

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) PIPING LOT : 004 SF0020 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 31-Aug-11 31-Jan-11 09-Feb-11 100 02-Mar-11 10-Mar-11 100 25-Mar-11 05-May-11 100 01-Apr-11 12-May-11 100 16-May-11 12-May-11 100 08-Sep-11 20-Oct-11 100.00 15-Sep-11 20-Oct-11 100.00 22-Sep-11 27-Oct-11 100.00 29-Sep-11 27-Oct-11 06-Nov-11 27-Oct-11 06-Dec-11 27-Oct-11 21-Dec-11 27-Oct-11 21-Dec-11

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) - TOP UP-2 PIPING UU00-P-LMTS-000-1000-142-14 FCA SELLER'S WORKS, JEBEL ALI 03-Oct-11 13-Apr-12 20-Apr-12 27-Apr-12 04-May-12 11-Jun-12 11-Jul-12 26-Jul-12 26-Jul-12

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) PIPING LOT : 005 SF0020 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 31-Jan-12 31-Jan-11 09-Feb-11 100 02-Mar-11 10-Mar-11 100 25-Mar-11 05-May-11 100 01-Apr-11 12-May-11 100 16-May-11 12-May-11 100 08-Sep-11 14-Nov-11 0.07 15-Sep-11 14-Nov-11 22-Sep-11 30-Nov-11 29-Sep-11 30-Nov-11 06-Nov-11 30-Nov-11 06-Dec-11 30-Nov-11 21-Dec-11 30-Nov-11 21-Dec-11

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) PIPING LOT : 006 SF0020 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 30-Nov-11 31-Jan-11 09-Feb-11 100 02-Mar-11 10-Mar-11 100 25-Mar-11 05-May-11 100 01-Apr-11 12-May-11 100 16-May-11 12-May-11 100 08-Sep-11 28-Sep-11 100.00 15-Sep-11 28-Sep-11 100.00 22-Sep-11 10-Oct-11 100.00 29-Sep-11 24-Oct-11 06-Nov-11 24-Nov-11 06-Dec-11 25-Nov-11 21-Dec-11 25-Nov-11 21-Dec-11

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) - TOP UP-1 PIPING LOT : 007 SF0076 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 31-Jan-12 14-Sep-11 100 14-Sep-11 100 14-Sep-11 100 14-Sep-11 100 03-Oct-11 14-Sep-11 100 13-Apr-12 14-Sep-11 5.00 20-Apr-12 14-Sep-11 27-Apr-12 31-Jan-12 04-May-12 31-Jan-12 11-Jun-12 31-Jan-12 11-Jul-12 31-Jan-12 26-Jul-12 31-Jan-12 26-Jul-12

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) - TOP UP-1 PIPING LOT : 008 SF0076 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 28-Sep-11 14-Sep-11 100 14-Sep-11 100 14-Sep-11 100 14-Sep-11 100 03-Oct-11 14-Sep-11 100 13-Apr-12 28-Sep-11 100.00 20-Apr-12 28-Sep-11 100.00 27-Apr-12 11-Oct-11 100.00 04-May-12 24-Oct-11 11-Jun-12 24-Nov-11 11-Jul-12 25-Nov-11 26-Jul-12 25-Nov-11 26-Jul-12

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) - TOP UP-1 PIPING LOT : 009 SF0076 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 28-Sep-11 14-Sep-11 100 14-Sep-11 100 14-Sep-11 100 14-Sep-11 100 03-Oct-11 14-Sep-11 100 13-Apr-12 14-Sep-11 5.00 20-Apr-12 14-Sep-11 27-Apr-12 28-Sep-11 04-May-12 28-Sep-11 11-Jun-12 28-Sep-11 11-Jul-12 28-Sep-11 26-Jul-12 28-Sep-11 26-Jul-12

UU00-P-LMTS-000-1000 CS & LTCS Pipes (Seamless) - TOP UP-1 PIPING LOT : 010 SF0076 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI 31-Dec-11 14-Sep-11 100 14-Sep-11 100 14-Sep-11 100 14-Sep-11 100 03-Oct-11 14-Sep-11 100 13-Apr-12 14-Sep-11 5.00 20-Apr-12 14-Sep-11 27-Apr-12 31-Dec-11 04-May-12 31-Dec-11 11-Jun-12 31-Dec-11 11-Jul-12 31-Dec-11 26-Jul-12 31-Dec-11 26-Jul-12
FOB PUSAN / MASAN / KWANGYANG,
UU00-P-LMTS-000-1001 CS & LTCS Pipes (Welded) - TOP UP PIPING UU00-P-LMTS-000-1001-143 KOREA 03-Oct-11 03-Oct-11 13-Apr-12 13-Apr-12 20-Apr-12 20-Apr-12 27-Apr-12 27-Apr-12 04-May-12 04-May-12 11-Jun-12 11-Jun-12 11-Jul-12 11-Jul-12 26-Jul-12 26-Jul-12 26-Jul-12
ERNDTEBRÜCKER EISENWERK FOB PUSAN / MASAN / KWANGYANG,
UU00-P-LMTS-000-1001 CS & LTCS Pipes (Welded) - Lot-1 PIPING LOT : 001 SF0036 GMBH & CO. KG KOREA 26-Oct-11 14-Feb-11 09-Feb-11 100 16-Mar-11 10-Mar-11 100 08-Apr-11 19-May-11 100 15-Apr-11 22-Jun-11 100 30-May-11 22-Jun-11 100 23-Sep-11 15-Dec-11 35.00 30-Sep-11 23-Dec-11 07-Oct-11 30-Dec-11 14-Oct-11 06-Jan-12 21-Nov-11 13-Feb-12 21-Dec-11 14-Mar-12 05-Jan-12 29-Mar-12 05-Jan-12
ERNDTEBRÜCKER EISENWERK FOB PUSAN / MASAN / KWANGYANG,
UU00-P-LMTS-000-1001 CS & LTCS Pipes (Welded) - Lot-2 PIPING LOT : 002 SF0036 GMBH & CO. KG KOREA 16-Feb-12 14-Feb-11 09-Feb-11 100 16-Mar-11 10-Mar-11 100 08-Apr-11 19-May-11 100 15-Apr-11 22-Jun-11 100 30-May-11 22-Jun-11 100 23-Sep-11 28-Jan-12 15.00 30-Sep-11 28-Jan-12 07-Oct-11 16-Feb-12 14-Oct-11 16-Feb-12 21-Nov-11 16-Feb-12 21-Dec-11 16-Feb-12 05-Jan-12 16-Feb-12 05-Jan-12
ERNDTEBRÜCKER EISENWERK FOB PUSAN / MASAN / KWANGYANG,
UU00-P-LMTS-000-1001 CS & LTCS Pipes (Welded) - Lot-2 PIPING LOT : 003 SF0036 GMBH & CO. KG KOREA 16-Feb-12 14-Feb-11 09-Feb-11 100 16-Mar-11 10-Mar-11 100 08-Apr-11 19-May-11 100 15-Apr-11 22-Jun-11 100 30-May-11 22-Jun-11 100 23-Sep-11 28-Jan-12 25.00 30-Sep-11 28-Jan-12 07-Oct-11 16-Feb-12 14-Oct-11 16-Feb-12 21-Nov-11 16-Feb-12 21-Dec-11 16-Feb-12 05-Jan-12 16-Feb-12 05-Jan-12
UU00-P-LMTS-000-1003 SS Pipes (Seamless) - TOP UP PIPING UU00-P-LMTS-000-1003-145 FOB ANTWERP PORT 03-Oct-11 03-Oct-11 13-Apr-12 13-Apr-12 20-Apr-12 20-Apr-12 27-Apr-12 27-Apr-12 04-May-12 04-May-12 11-Jun-12 11-Jun-12 11-Jul-12 11-Jul-12 26-Jul-12 26-Jul-12 26-Jul-12

SALZGITTER MANNESMANN
UU00-P-LMTS-000-1003 SS Pipes (Seamless) PIPING LOT : 001 SF0019 STAINLESS TUBES FRANCE SAS FOB ANTWERP PORT 30-Sep-11 14-Feb-11 01-Mar-11 100 07-Mar-11 20-Mar-11 100 08-Apr-11 12-May-11 100 25-May-11 12-May-11 100 09-Jul-11 12-May-11 100 23-Oct-11 10-Dec-11 70.00 30-Oct-11 20-Dec-11 06-Nov-11 30-Dec-11 13-Nov-11 06-Jan-12 21-Dec-11 13-Feb-12 20-Jan-12 14-Mar-12 04-Feb-12 29-Mar-12 04-Feb-12

SALZGITTER MANNESMANN
UU00-P-LMTS-000-1003 SS Pipes (Seamless) PIPING LOT : 002 SF0067 STAINLESS TUBES FRANCE SAS FOB ANTWERP PORT 11-Dec-11 14-Feb-11 01-Mar-11 100 07-Mar-11 20-Mar-11 100 08-Apr-11 12-May-11 100 25-May-11 12-May-11 100 09-Jul-11 12-May-11 100 23-Oct-11 10-Dec-11 25.00 30-Oct-11 20-Dec-11 06-Nov-11 30-Dec-11 13-Nov-11 06-Jan-12 21-Dec-11 13-Feb-12 20-Jan-12 14-Mar-12 04-Feb-12 29-Mar-12 04-Feb-12

SALZGITTER MANNESMANN
UU00-P-LMTS-000-1003 SS Pipes (Seamless) PIPING LOT : 004 SF0019 STAINLESS TUBES FRANCE SAS FOB ANTWERP PORT 30-Sep-11 14-Feb-11 01-Mar-11 100 07-Mar-11 20-Mar-11 100 08-Apr-11 12-May-11 100 25-May-11 12-May-11 100 09-Jul-11 12-May-11 100 23-Oct-11 04-Oct-11 100.00 30-Oct-11 26-Sep-11 100.00 06-Nov-11 17-Oct-11 100.00 13-Nov-11 17-Oct-11 21-Dec-11 17-Oct-11 20-Jan-12 17-Oct-11 04-Feb-12 17-Oct-11 04-Feb-12

SALZGITTER MANNESMANN
UU00-P-LMTS-000-1003 SS Pipes (Seamless) PIPING LOT : 003 SF0019 STAINLESS TUBES FRANCE SAS FOB ANTWERP PORT 30-Sep-11 14-Feb-11 01-Mar-11 100 07-Mar-11 20-Mar-11 100 08-Apr-11 12-May-11 100 25-May-11 12-May-11 100 09-Jul-11 12-May-11 100 23-Oct-11 09-Oct-11 100.00 30-Oct-11 11-Oct-11 100.00 06-Nov-11 23-Oct-11 100.00 13-Nov-11 23-Oct-11 21-Dec-11 23-Oct-11 20-Jan-12 23-Oct-11 04-Feb-12 23-Oct-11 04-Feb-12
UU00-P-LMTS-000-1004 SS Pipes (Welded) PIPING LOT : 001 SF0049 BSL PIPES & FITTINGS FOB VENICE SEAPORT, ITALY 20-Dec-11 14-Feb-11 01-Mar-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 01-May-11 100 15-Apr-11 12-Jul-11 100 30-May-11 12-Jul-11 100 23-Sep-11 05-Jan-12 42.00 30-Sep-11 13-Jan-12 07-Oct-11 20-Jan-12 14-Oct-11 27-Jan-12 21-Nov-11 05-Mar-12 21-Dec-11 04-Apr-12 05-Jan-12 19-Apr-12 05-Jan-12
UU00-P-LMTS-000-1004 SS Pipes (Welded) - TOP UP-3 PIPING UU00-P-LMTS-000-1004-146-4-5 FOB VENICE SEAPORT, ITALY 03-Oct-11 13-Apr-12 20-Apr-12 27-Apr-12 04-May-12 11-Jun-12 11-Jul-12 26-Jul-12 26-Jul-12
UU00-P-LMTS-000-1004 SS Pipes (Welded) - TOP UP-1 PIPING LOT : 002 SF0062 BSL PIPES & FITTINGS FOB VENICE SEAPORT, ITALY 25-Dec-11 14-Aug-11 100 14-Aug-11 100 14-Aug-11 100 14-Aug-11 100 03-Oct-11 14-Aug-11 100 13-Apr-12 14-Aug-11 7.00 20-Apr-12 14-Aug-11 27-Apr-12 25-Dec-11 04-May-12 25-Dec-11 11-Jun-12 25-Dec-11 11-Jul-12 25-Dec-11 26-Jul-12 25-Dec-11 26-Jul-12
UU00-P-LMTS-000-1004 SS Pipes (Welded) - TOP UP-1 PIPING LOT : 003 SF0062 BSL PIPES & FITTINGS FOB VENICE SEAPORT, ITALY 02-Jan-12 14-Aug-11 100 14-Aug-11 100 14-Aug-11 100 14-Aug-11 100 03-Oct-11 14-Aug-11 100 13-Apr-12 14-Aug-11 7.00 20-Apr-12 14-Aug-11 27-Apr-12 02-Jan-12 04-May-12 02-Jan-12 11-Jun-12 02-Jan-12 11-Jul-12 02-Jan-12 26-Jul-12 02-Jan-12 26-Jul-12
UU00-P-LMTS-000-1004 SS Pipes (Welded) - TOP UP-2 PIPING LOT : 004 SF0075 SOSTA BV FOB VENICE SEAPORT, ITALY 10-Jan-12 13-Sep-11 100 13-Sep-11 100 13-Sep-11 100 13-Sep-11 100 03-Oct-11 13-Sep-11 100 13-Apr-12 13-Sep-11 3.00 20-Apr-12 13-Sep-11 27-Apr-12 10-Jan-12 04-May-12 10-Jan-12 11-Jun-12 10-Jan-12 11-Jul-12 10-Jan-12 26-Jul-12 10-Jan-12 26-Jul-12
UU00-P-LMTS-000-1005 DSS Pipes - (Seamless) TOP UP-2 PIPING UU00-P-LMTS-000-1005-147 FOB HAMBURG, GERMANY. 03-Oct-11 03-Oct-11 13-Apr-12 13-Apr-12 20-Apr-12 20-Apr-12 27-Apr-12 27-Apr-12 04-May-12 04-May-12 11-Jun-12 11-Jun-12 11-Jul-12 11-Jul-12 26-Jul-12 26-Jul-12 26-Jul-12

SALZGITTER MANNESMANN
UU00-P-LMTS-000-1005 DSS Pipes (Seamless) PIPING LOT : 001 SF0017 STAINLESS TUBES FRANCE SAS FOB HAMBURG, GERMANY. 23-Oct-11 14-Feb-11 21-Feb-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 05-May-11 100 15-Apr-11 12-May-11 100 30-May-11 12-May-11 100 23-Sep-11 11-Dec-11 75.00 30-Sep-11 20-Dec-11 07-Oct-11 30-Dec-11 14-Oct-11 06-Jan-12 21-Nov-11 13-Feb-12 21-Dec-11 14-Mar-12 05-Jan-12 29-Mar-12 05-Jan-12
UU00-P-LMTS-000-1005 DSS Pipes (Welded) PIPING LOT : 002 SF0023 H. BUTTING GMBH & CO. KG FOB HAMBURG, GERMANY. 27-Oct-11 14-Feb-11 21-Feb-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 05-May-11 100 15-Apr-11 12-May-11 100 30-May-11 12-May-11 100 23-Sep-11 11-Dec-11 82.00 30-Sep-11 20-Dec-11 07-Oct-11 30-Dec-11 14-Oct-11 06-Jan-12 21-Nov-11 13-Feb-12 21-Dec-11 14-Mar-12 05-Jan-12 29-Mar-12 05-Jan-12

SALZGITTER MANNESMANN
UU00-P-LMTS-000-1005 DSS Pipes (Seamless) PIPING LOT : 003 SF0017 STAINLESS TUBES FRANCE SAS FOB HAMBURG, GERMANY. 23-Oct-11 14-Feb-11 21-Feb-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 05-May-11 100 15-Apr-11 12-May-11 100 30-May-11 12-May-11 100 23-Sep-11 29-Sep-11 100.00 30-Sep-11 29-Sep-11 100.00 07-Oct-11 11-Oct-11 100.00 14-Oct-11 11-Oct-11 21-Nov-11 11-Oct-11 21-Dec-11 11-Oct-11 05-Jan-12 11-Oct-11 05-Jan-12

SALZGITTER MANNESMANN
UU00-P-LMTS-000-1005 DSS Pipes (Seamless) PIPING LOT : 004 SF0017 STAINLESS TUBES FRANCE SAS FOB HAMBURG, GERMANY. 25-Sep-11 14-Feb-11 21-Feb-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 05-May-11 100 15-Apr-11 12-May-11 100 30-May-11 12-May-11 100 23-Sep-11 19-Oct-11 100.00 30-Sep-11 19-Oct-11 100.00 07-Oct-11 26-Oct-11 100.00 14-Oct-11 26-Oct-11 21-Nov-11 26-Oct-11 21-Dec-11 26-Oct-11 05-Jan-12 26-Oct-11 05-Jan-12
UU00-P-LMTS-000-1005 DSS Pipes - (Welded) TOP UP PIPING UU00-P-LMTS-000-1005-147-10 FOB HAMBURG, GERMANY. 03-Oct-11 13-Apr-12 20-Apr-12 27-Apr-12 04-May-12 11-Jun-12 11-Jul-12 26-Jul-12 26-Jul-12
UU00-P-LMTS-000-1005 DSS Pipes (Welded) PIPING LOT : 005 SF0023 H. BUTTING GMBH & CO. KG FOB HAMBURG, GERMANY. 22-Feb-12 14-Feb-11 21-Feb-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 05-May-11 100 15-Apr-11 12-May-11 100 30-May-11 12-May-11 100 23-Sep-11 11-Dec-11 82.00 30-Sep-11 11-Dec-11 07-Oct-11 30-Dec-11 14-Oct-11 30-Dec-11 21-Nov-11 30-Dec-11 21-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 05-Jan-12

SALZGITTER MANNESMANN
UU00-P-LMTS-000-1005 DSS Pipes - (Seamless) TOP UP-1 PIPING LOT : 006 SF0063 STAINLESS TUBES FRANCE SAS FOB HAMBURG, GERMANY. 27-Nov-11 17-Aug-11 100 17-Aug-11 100 17-Aug-11 100 17-Aug-11 100 03-Oct-11 17-Aug-11 100 13-Apr-12 17-Aug-11 20.00 20-Apr-12 17-Aug-11 27-Apr-12 27-Nov-11 04-May-12 27-Nov-11 11-Jun-12 27-Nov-11 11-Jul-12 27-Nov-11 26-Jul-12 27-Nov-11 26-Jul-12

UU00-P-LMTS-000-1006 HDPE Pipes, Fittings & Flanges - TOP UP PIPING UU00-P-LMTS-000-1006-223 FOB INTERNATIONAL SEA PORT, UK 03-Oct-11 03-Oct-11 19-Jan-12 19-Jan-12 26-Jan-12 26-Jan-12 02-Feb-12 02-Feb-12 09-Feb-12 09-Feb-12 18-Mar-12 18-Mar-12 17-Apr-12 17-Apr-12 02-May-12 02-May-12 02-May-12
RADIUSENAAT PIPING AND
UU00-P-LMTS-000-1006 HDPE Pipes, Fittings & Flanges PIPING LOT : 001 SF0050 FITTINGS LLC FOB INTERNATIONAL SEA PORT, UK 12-Sep-11 02-Mar-11 25-Apr-11 100 23-Mar-11 16-May-11 100 18-May-11 11-Jul-11 100 25-May-11 18-Jul-11 100 09-Jul-11 18-Jul-11 100 02-Oct-11 09-Jan-12 10.00 09-Oct-11 18-Jan-12 18-Oct-11 30-Jan-12 25-Oct-11 06-Feb-12 02-Dec-11 15-Mar-12 01-Jan-12 14-Apr-12 16-Jan-12 29-Apr-12 16-Jan-12
RADIUSENAAT PIPING AND
UU00-P-LMTS-000-1006 HDPE Pipes, Fittings & Flanges PIPING LOT : 002 SF0050 FITTINGS LLC FOB INTERNATIONAL SEA PORT, UK 10-Oct-11 02-Mar-11 25-Apr-11 100 23-Mar-11 16-May-11 100 18-May-11 11-Jul-11 100 25-May-11 18-Jul-11 100 09-Jul-11 18-Jul-11 100 02-Oct-11 09-Jan-12 10.00 09-Oct-11 09-Jan-12 18-Oct-11 30-Jan-12 25-Oct-11 30-Jan-12 02-Dec-11 30-Jan-12 01-Jan-12 30-Jan-12 16-Jan-12 30-Jan-12 16-Jan-12

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
PROCUREMENT TRACKING REGISTER

ISG PROJECT - IN SALAH GAS SOUTHERN FIELDS DEVELOPMENT PTR TEMPLATE


CONTRACT NO. : 100045/ISG/CON
DOCUMENT NO : 1 7 11 12 13 14 15-Jan-00 23 24-Jan-00 25-Jan-00 26 28-Jan-00 29-Jan-00 30 09-Jan-00
CUT OFF DATE: 29-Oct-11

Issue Inquiry Requisition Receive Bid TBE Complete Place LOI / LOA Place PO Receive / Approve Key Vendor Drawings / Documents Place Sub-orders Receive Raw Materials Fabrication / Mfg. Inspection Release Note Ex-works Delivery Item on Board Shipping/Air Freight/Land Transport (ATA Port) Custom Clearance and Transport to site/store Visual Inspection on Receipt at Site/Store ROS
Inquiry No. Description Discipline INQD_TAG_NO PO_NO Vendor Name PO Delivery Terms PO_CDD
P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog

UU00-P-LMTS-000-1007 CS & LTCS Fittings (Wrought) - TOP UP PIPING UU00-P-LMTS-000-1007-148 FOB NORTH ITALIAN SEAPORT, ITALY 03-Oct-11 03-Oct-11 13-Apr-12 13-Apr-12 20-Apr-12 20-Apr-12 27-Apr-12 27-Apr-12 04-May-12 04-May-12 11-Jun-12 11-Jun-12 11-Jul-12 11-Jul-12 26-Jul-12 26-Jul-12 26-Jul-12

UU00-P-LMTS-000-1007 CS & LTCS Fittings (Wrought) - 1st Lot PIPING LOT : 001 SF0021 TECTUBI RACCORDI SPA FOB NORTH ITALIAN SEAPORT, ITALY 11-Oct-11 14-Feb-11 09-Feb-11 100 16-Mar-11 09-Mar-11 100 08-Apr-11 01-May-11 100 25-May-11 12-May-11 100 09-Jul-11 12-May-11 100 28-Oct-11 18-Dec-11 76.55 30-Oct-11 21-Dec-11 06-Nov-11 31-Dec-11 13-Nov-11 07-Jan-12 21-Dec-11 14-Feb-12 20-Jan-12 15-Mar-12 04-Feb-12 30-Mar-12 04-Feb-11

UU00-P-LMTS-000-1007 CS & LTCS Fittings (Wrought) - 2nd Lot PIPING LOT : 002 SF0093 TECTUBI RACCORDI SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Feb-12 14-Feb-11 09-Feb-11 100 16-Mar-11 09-Mar-11 100 08-Apr-11 01-May-11 100 15-Apr-11 16-Oct-11 100 30-May-11 16-Oct-11 100 23-Sep-11 07-Mar-12 30-Sep-11 07-Mar-12 07-Oct-11 19-Mar-12 14-Oct-11 19-Mar-12 21-Nov-11 19-Mar-12 21-Dec-11 19-Mar-12 05-Jan-12 19-Mar-12 05-Jan-12

UU00-P-LMTS-000-1008 DSS Fittings (Wrought) - TOP UP PIPING UU00-P-LMTS-000-1008-149 FOB NORTH ITALIAN SEAPORT, ITALY 03-Oct-11 03-Oct-11 23-Feb-12 23-Feb-12 01-Mar-12 01-Mar-12 08-Mar-12 08-Mar-12 15-Mar-12 15-Mar-12 22-Apr-12 22-Apr-12 22-May-12 22-May-12 06-Jun-12 06-Jun-12 06-Jun-12

UU00-P-LMTS-000-1008 DSS Fittings (Wrought) - 1st Lot PIPING LOT : 001 SF0022 TECTUBI RACCORDI SPA FOB NORTH ITALIAN SEAPORT, ITALY 03-Oct-11 14-Feb-11 22-Feb-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 05-May-11 100 15-Apr-11 12-May-11 100 30-May-11 12-May-11 100 23-Sep-11 11-Dec-11 65.14 30-Sep-11 11-Dec-11 07-Oct-11 30-Dec-11 14-Oct-11 30-Dec-11 21-Nov-11 30-Dec-11 21-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 05-Jan-12

UU00-P-LMTS-000-1008 DSS Fittings (Wrought) - 2nd lot PIPING LOT : 002 SF0094 TECTUBI RACCORDI SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Feb-12 14-Feb-11 22-Feb-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 05-May-11 100 15-Apr-11 16-Oct-11 100 30-May-11 16-Oct-11 100 23-Sep-11 07-Mar-12 30-Sep-11 07-Mar-12 07-Oct-11 19-Mar-12 14-Oct-11 19-Mar-12 21-Nov-11 19-Mar-12 21-Dec-11 19-Mar-12 05-Jan-12 19-Mar-12 05-Jan-12

UU00-P-LMTS-000-1008 DSS Fittings (Wrought) - 1st Lot PIPING LOT : 003 SF0022 TECTUBI RACCORDI SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Feb-12 14-Feb-11 22-Feb-11 100 07-Mar-11 16-Mar-11 100 08-Apr-11 05-May-11 100 15-Apr-11 12-May-11 100 30-May-11 12-May-11 100 23-Sep-11 27-Jan-12 30-Sep-11 27-Jan-12 07-Oct-11 19-Feb-12 14-Oct-11 19-Feb-12 21-Nov-11 19-Feb-12 21-Dec-11 19-Feb-12 05-Jan-12 19-Feb-12 05-Jan-12
UU00-P-LMTS-000-1009 All Forged Fittings - TOP UP PIPING UU00-P-LMTS-000-1009-150 FOB GENOA, ITALY 03-Oct-11 03-Oct-11 23-May-12 23-May-12 30-May-12 30-May-12 06-Jun-12 06-Jun-12 13-Jun-12 13-Jun-12 21-Jul-12 21-Jul-12 20-Aug-12 20-Aug-12 04-Sep-12 04-Sep-12 04-Sep-12
UU00-P-LMTS-000-1009 All Forged Fittings - 2nd Lot PIPING UU00-P-LMTS-000-1009-120-3 FOB GENOA, ITALY 14-Feb-11 27-Feb-11 100 07-Mar-11 22-Mar-11 100 08-Apr-11 16-May-11 100 15-Apr-11 05-Nov-11 30-May-11 20-Dec-11 22-Nov-11 05-Jun-12 29-Nov-11 12-Jun-12 06-Dec-11 19-Jun-12 13-Dec-11 26-Jun-12 20-Jan-12 03-Aug-12 19-Feb-12 02-Sep-12 05-Mar-12 17-Sep-12 05-Mar-12
UU00-P-LMTS-000-1009 All Forged Fittings - 1st Lot PIPING LOT : 001 SF0029 M.E.G.A. SPA FOB GENOA, ITALY 31-Aug-11 14-Feb-11 27-Feb-11 100 07-Mar-11 22-Mar-11 100 08-Apr-11 16-May-11 100 25-May-11 25-May-11 100 09-Jul-11 25-May-11 100 11-Jan-12 09-Dec-11 75.49 28-Jan-12 24-Dec-11 04-Feb-12 30-Dec-11 11-Feb-12 06-Jan-12 20-Mar-12 13-Feb-12 19-Apr-12 14-Mar-12 04-May-12 29-Mar-12 04-May-12
UU00-P-LMTS-000-1009 All Forged Fittings - 1st Lot PIPING LOT : 002 SF0029 M.E.G.A. SPA FOB GENOA, ITALY 31-Aug-11 14-Feb-11 27-Feb-11 100 07-Mar-11 22-Mar-11 100 08-Apr-11 16-May-11 100 25-May-11 25-May-11 100 09-Jul-11 25-May-11 100 11-Jan-12 11-Oct-11 100.00 28-Jan-12 11-Oct-11 100.00 04-Feb-12 16-Oct-11 100.00 11-Feb-12 16-Oct-11 20-Mar-12 16-Oct-11 19-Apr-12 16-Oct-11 04-May-12 16-Oct-11 04-May-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1010 CS & LTCS Flanges & Spectacle Blinds PIPING LOT : 001 SF0026 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Oct-11 14-Feb-11 09-Feb-11 100 16-Mar-11 08-Mar-11 100 08-Apr-11 19-May-11 100 25-May-11 19-May-11 100 09-Jul-11 19-May-11 100 28-Oct-11 19-Sep-11 100.00 30-Oct-11 19-Sep-11 100.00 06-Nov-11 04-Oct-11 100.00 13-Nov-11 11-Oct-11 21-Dec-11 18-Nov-11 20-Jan-12 18-Dec-11 04-Feb-12 02-Jan-12 04-Feb-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1010 CS & LTCS Flanges & Spectacle Blinds PIPING LOT : 002 SF0026 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Oct-11 14-Feb-11 09-Feb-11 100 16-Mar-11 08-Mar-11 100 08-Apr-11 19-May-11 100 25-May-11 19-May-11 100 09-Jul-11 19-May-11 100 28-Oct-11 27-Sep-11 100.00 30-Oct-11 27-Sep-11 100.00 06-Nov-11 05-Oct-11 100.00 13-Nov-11 12-Oct-11 21-Dec-11 19-Nov-11 20-Jan-12 19-Dec-11 04-Feb-12 03-Jan-12 04-Feb-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1010 CS & LTCS Flanges & Spectacle Blinds PIPING LOT : 005 SF0026 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Oct-11 14-Feb-11 09-Feb-11 100 16-Mar-11 08-Mar-11 100 08-Apr-11 19-May-11 100 25-May-11 19-May-11 100 09-Jul-11 19-May-11 100 28-Oct-11 12-Feb-12 60.00 30-Oct-11 12-Feb-12 06-Nov-11 28-Feb-12 13-Nov-11 28-Feb-12 21-Dec-11 28-Feb-12 20-Jan-12 28-Feb-12 04-Feb-12 28-Feb-12 04-Feb-12
CS & LTCS Flanges & Spectacle Blinds -
UU00-P-LMTS-000-1010 TOP UP-3 PIPING UU00-P-LMTS-000-1010-151-11 FOB NORTH ITALIAN SEAPORT, ITALY 03-Oct-11 23-Feb-12 01-Mar-12 08-Mar-12 15-Mar-12 22-Apr-12 22-May-12 06-Jun-12 06-Jun-12
CS & LTCS Flanges & Spectacle Blinds - OFFICINE AMBROGIO MELESI &
UU00-P-LMTS-000-1010 TOP UP-1 PIPING LOT : 003 SF0098 C. SRL FOB NORTH ITALIAN SEAPORT, ITALY 08-Mar-12 20-Oct-11 100 20-Oct-11 100 20-Oct-11 100 20-Oct-11 100 03-Oct-11 20-Oct-11 100 23-Feb-12 20-Oct-11 01-Mar-12 20-Oct-11 08-Mar-12 08-Mar-12 15-Mar-12 08-Mar-12 22-Apr-12 08-Mar-12 22-May-12 08-Mar-12 06-Jun-12 08-Mar-12 06-Jun-12
CS & LTCS Flanges & Spectacle Blinds - FAD FLANGE ACCIAIO E DERIVATI
UU00-P-LMTS-000-1010 TOP UP-2 PIPING LOT : 004 SF0100 SPA FOB NORTH ITALIAN SEAPORT, ITALY 01-Dec-11 20-Oct-11 100 20-Oct-11 100 20-Oct-11 100 20-Oct-11 100 03-Oct-11 20-Oct-11 100 23-Feb-12 20-Oct-11 01-Mar-12 20-Oct-11 08-Mar-12 01-Dec-11 15-Mar-12 01-Dec-11 22-Apr-12 01-Dec-11 22-May-12 01-Dec-11 06-Jun-12 01-Dec-11 06-Jun-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1010 CS & LTCS Flanges & Spectacle Blinds PIPING LOT : 006 SF0026 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Oct-11 14-Feb-11 09-Feb-11 100 16-Mar-11 08-Mar-11 100 08-Apr-11 19-May-11 100 25-May-11 19-May-11 100 09-Jul-11 19-May-11 100 28-Oct-11 11-Oct-11 30-Oct-11 11-Oct-11 06-Nov-11 19-Oct-11 13-Nov-11 19-Oct-11 21-Dec-11 19-Oct-11 20-Jan-12 19-Oct-11 04-Feb-12 19-Oct-11 04-Feb-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1010 CS & LTCS Flanges & Spectacle Blinds PIPING LOT : 007 SF0026 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 14-Feb-11 09-Feb-11 100 16-Mar-11 08-Mar-11 100 08-Apr-11 19-May-11 100 25-May-11 19-May-11 100 09-Jul-11 19-May-11 100 28-Oct-11 12-Feb-12 60.00 30-Oct-11 12-Feb-12 06-Nov-11 28-Feb-12 13-Nov-11 28-Feb-12 21-Dec-11 28-Feb-12 20-Jan-12 28-Feb-12 04-Feb-12 28-Feb-12 04-Feb-12
CS & LTCS Flanges & Spectacle Blinds - FAD FLANGE ACCIAIO E DERIVATI
UU00-P-LMTS-000-1010 TOP UP-2 PIPING LOT : 008 SF0100 SPA FOB NORTH ITALIAN SEAPORT, ITALY 23-Nov-11 20-Oct-11 100 20-Oct-11 100 20-Oct-11 100 20-Oct-11 100 03-Oct-11 20-Oct-11 100 23-Feb-12 20-Oct-11 01-Mar-12 20-Oct-11 08-Mar-12 23-Nov-11 15-Mar-12 23-Nov-11 22-Apr-12 23-Nov-11 22-May-12 23-Nov-11 06-Jun-12 23-Nov-11 06-Jun-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1011 SS & DSS Flanges & Spectacle Blinds PIPING LOT : 002 SF0027 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Oct-11 02-Mar-11 22-Feb-11 100 01-Apr-11 14-Mar-11 100 24-Apr-11 19-May-11 100 18-May-11 19-May-11 100 02-Jul-11 19-May-11 100 23-Oct-11 20-Sep-11 100.00 28-Oct-11 20-Sep-11 100.00 04-Nov-11 04-Oct-11 100.00 11-Nov-11 11-Oct-11 19-Dec-11 18-Nov-11 18-Jan-12 18-Dec-11 02-Feb-12 02-Jan-12 02-Feb-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1011 SS & DSS Flanges & Spectacle Blinds PIPING LOT : 001 SF0027 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Oct-11 02-Mar-11 22-Feb-11 100 01-Apr-11 14-Mar-11 100 24-Apr-11 19-May-11 100 18-May-11 19-May-11 100 02-Jul-11 19-May-11 100 23-Oct-11 27-Sep-11 100.00 28-Oct-11 27-Sep-11 100.00 04-Nov-11 06-Oct-11 100.00 11-Nov-11 13-Oct-11 19-Dec-11 20-Nov-11 18-Jan-12 20-Dec-11 02-Feb-12 04-Jan-12 02-Feb-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1011 SS & DSS Flanges & Spectacle Blinds PIPING LOT : 005 SF0027 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Oct-11 02-Mar-11 22-Feb-11 100 01-Apr-11 14-Mar-11 100 24-Apr-11 19-May-11 100 18-May-11 19-May-11 100 02-Jul-11 19-May-11 100 23-Oct-11 08-Feb-12 60.00 28-Oct-11 08-Feb-12 04-Nov-11 28-Feb-12 11-Nov-11 28-Feb-12 19-Dec-11 28-Feb-12 18-Jan-12 28-Feb-12 02-Feb-12 28-Feb-12 02-Feb-12
OFFICINE NICOLA GALPERTI &
UU00-P-LMTS-000-1011 SS & DSS Flanges & Spectacle Blinds PIPING LOT : 006 SF0027 FIGLIO SPA FOB NORTH ITALIAN SEAPORT, ITALY 19-Oct-11 02-Mar-11 22-Feb-11 100 01-Apr-11 14-Mar-11 100 24-Apr-11 19-May-11 100 18-May-11 19-May-11 100 02-Jul-11 19-May-11 100 23-Oct-11 17-Oct-11 100.00 28-Oct-11 17-Oct-11 100.00 04-Nov-11 23-Oct-11 100.00 11-Nov-11 23-Oct-11 19-Dec-11 23-Oct-11 18-Jan-12 23-Oct-11 02-Feb-12 23-Oct-11 02-Feb-12
SS & DSS Flanges & Spectacle Blinds -
UU00-P-LMTS-000-1011 TOP UP-3 PIPING UU00-P-LMTS-000-1011-77-17 FOB NORTH ITALIAN SEAPORT, ITALY 03-Oct-11 24-Mar-12 31-Mar-12 07-Apr-12 14-Apr-12 22-May-12 21-Jun-12 06-Jul-12 06-Jul-12
SS & DSS Flanges & Spectacle Blinds - OFFICINE AMBROGIO MELESI &
UU00-P-LMTS-000-1011 TOP UP-1 PIPING LOT : 003 SF0099 C. SRL FOB NORTH ITALIAN SEAPORT, ITALY 08-Mar-12 20-Oct-11 100 20-Oct-11 100 20-Oct-11 100 20-Oct-11 100 03-Oct-11 20-Oct-11 100 24-Mar-12 20-Oct-11 31-Mar-12 20-Oct-11 07-Apr-12 08-Mar-12 14-Apr-12 08-Mar-12 22-May-12 08-Mar-12 21-Jun-12 08-Mar-12 06-Jul-12 08-Mar-12 06-Jul-12
SS & DSS Flanges & Spectacle Blinds - OFFICINE AMBROGIO MELESI &
UU00-P-LMTS-000-1011 TOP UP-2 PIPING LOT : 004 SF0102 C. SRL FOB NORTH ITALIAN SEAPORT, ITALY 11-Mar-12 23-Oct-11 100 23-Oct-11 100 23-Oct-11 100 23-Oct-11 100 03-Oct-11 23-Oct-11 100 24-Mar-12 23-Oct-11 31-Mar-12 23-Oct-11 07-Apr-12 11-Mar-12 14-Apr-12 11-Mar-12 22-May-12 11-Mar-12 21-Jun-12 11-Mar-12 06-Jul-12 11-Mar-12 06-Jul-12

UU00-P-LMTS-000-1012 Ball Valves (Floating)-Lot-2 PIPING UU00-P-LMTS-000-1012-122-2 FOB INTERNATIONAL SEAPORT, ITALY 01-Apr-11 09-Mar-11 100 01-May-11 23-Mar-11 100 24-May-11 07-Jul-11 100 31-May-11 05-Nov-11 15-Jul-11 20-Dec-11 05-Feb-12 04-Jul-12 12-Feb-12 11-Jul-12 19-Feb-12 18-Jul-12 26-Feb-12 25-Jul-12 04-Apr-12 01-Sep-12 04-May-12 01-Oct-12 19-May-12 16-Oct-12 19-May-12

UU00-P-LMTS-000-1012 Ball Valves (Floating)-Lot-1 PIPING LOT : 001 SF0048 OMB VALVES SPA FOB INTERNATIONAL SEAPORT, ITALY 02-Feb-12 01-Apr-11 09-Mar-11 100 01-May-11 23-Mar-11 100 24-May-11 07-Jul-11 100 31-May-11 07-Jul-11 100 15-Jul-11 07-Jul-11 100 05-Feb-12 19-Mar-12 8.00 12-Feb-12 19-Mar-12 19-Feb-12 02-Apr-12 26-Feb-12 02-Apr-12 04-Apr-12 02-Apr-12 04-May-12 02-Apr-12 19-May-12 02-Apr-12 19-May-12

UU00-P-LMTS-000-1012 Ball Valves (Floating)-Lot-1 PIPING LOT : 002 SF0048 OMB VALVES SPA FOB INTERNATIONAL SEAPORT, ITALY 20-May-12 01-Apr-11 09-Mar-11 100 01-May-11 23-Mar-11 100 24-May-11 07-Jul-11 100 31-May-11 07-Jul-11 100 15-Jul-11 07-Jul-11 100 05-Feb-12 03-May-12 8.00 12-Feb-12 03-May-12 19-Feb-12 20-May-12 26-Feb-12 20-May-12 04-Apr-12 20-May-12 04-May-12 20-May-12 19-May-12 20-May-12 19-May-12

UU00-P-LMTS-000-1012 Ball Valves (Floating)-Lot-1 PIPING LOT : 003 SF0048 OMB VALVES SPA FOB INTERNATIONAL SEAPORT, ITALY 29-Feb-12 01-Apr-11 09-Mar-11 100 01-May-11 23-Mar-11 100 24-May-11 07-Jul-11 100 31-May-11 07-Jul-11 100 15-Jul-11 07-Jul-11 100 05-Feb-12 19-Mar-12 8.00 12-Feb-12 19-Mar-12 19-Feb-12 02-Apr-12 26-Feb-12 02-Apr-12 04-Apr-12 02-Apr-12 04-May-12 02-Apr-12 19-May-12 02-Apr-12 19-May-12

UU00-P-LMTS-000-1013 Ball Valves (Trunion Mounted) Lot - 2 PIPING UU00-P-LMTS-000-1013-123-2 FOB NORTH ITALIAN SEAPORT, ITALY 01-Apr-11 14-Mar-11 100 01-May-11 09-Apr-11 100 24-May-11 21-Jul-11 100 31-May-11 20-Nov-11 15-Jul-11 04-Jan-12 06-Mar-12 26-Aug-12 13-Mar-12 02-Sep-12 20-Mar-12 09-Sep-12 27-Mar-12 16-Sep-12 04-May-12 24-Oct-12 03-Jun-12 23-Nov-12 18-Jun-12 08-Dec-12 18-Jun-12

UU00-P-LMTS-000-1013 Ball Valves (Trunion Mounted) - Lot-1 PIPING LOT : 001 SF0044 OMS SALERI SPA FOB NORTH ITALIAN SEAPORT, ITALY 30-Sep-12 01-Apr-11 14-Mar-11 100 01-May-11 09-Apr-11 100 24-May-11 21-Jul-11 100 31-May-11 21-Jul-11 100 15-Jul-11 21-Jul-11 100 06-Mar-12 09-Sep-12 7.00 13-Mar-12 19-Sep-12 20-Mar-12 30-Sep-12 27-Mar-12 07-Oct-12 04-May-12 14-Nov-12 03-Jun-12 14-Dec-12 18-Jun-12 29-Dec-12 18-Jun-12

UU00-P-LMTS-000-1013 Ball Valves (Trunion Mounted) - Lot-1 PIPING LOT : 002 SF0044 OMS SALERI SPA FOB NORTH ITALIAN SEAPORT, ITALY 31-Jul-12 01-Apr-11 14-Mar-11 100 01-May-11 09-Apr-11 100 24-May-11 21-Jul-11 100 31-May-11 21-Jul-11 100 15-Jul-11 21-Jul-11 100 06-Mar-12 12-Aug-12 7.00 13-Mar-12 22-Aug-12 20-Mar-12 31-Aug-12 27-Mar-12 07-Sep-12 04-May-12 15-Oct-12 03-Jun-12 14-Nov-12 18-Jun-12 29-Nov-12 18-Jun-12

UU00-P-LMTS-000-1013 Ball Valves (Trunion Mounted) - Lot-1 PIPING LOT : 003 SF0044 OMS SALERI SPA FOB NORTH ITALIAN SEAPORT, ITALY 04-Nov-12 01-Apr-11 14-Mar-11 100 01-May-11 09-Apr-11 100 24-May-11 21-Jul-11 100 31-May-11 21-Jul-11 100 15-Jul-11 21-Jul-11 100 06-Mar-12 13-Oct-12 7.00 13-Mar-12 13-Oct-12 20-Mar-12 04-Nov-12 27-Mar-12 04-Nov-12 04-May-12 04-Nov-12 03-Jun-12 04-Nov-12 18-Jun-12 04-Nov-12 18-Jun-12

UU00-P-LMTS-000-1013 Ball Valves (Trunion Mounted) - Lot-1 PIPING LOT : 004 SF0044 OMS SALERI SPA FOB NORTH ITALIAN SEAPORT, ITALY 31-Jul-12 01-Apr-11 14-Mar-11 100 01-May-11 09-Apr-11 100 24-May-11 21-Jul-11 100 31-May-11 21-Jul-11 100 15-Jul-11 21-Jul-11 100 06-Mar-12 12-Aug-12 7.00 13-Mar-12 12-Aug-12 20-Mar-12 31-Aug-12 27-Mar-12 31-Aug-12 04-May-12 31-Aug-12 03-Jun-12 31-Aug-12 18-Jun-12 31-Aug-12 18-Jun-12

UU00-P-LMTS-000-1013 Ball Valves (Trunion Mounted) - Lot-1 PIPING LOT : 005 SF0044 OMS SALERI SPA FOB NORTH ITALIAN SEAPORT, ITALY 30-Sep-12 01-Apr-11 14-Mar-11 100 01-May-11 09-Apr-11 100 24-May-11 21-Jul-11 100 31-May-11 21-Jul-11 100 15-Jul-11 21-Jul-11 100 06-Mar-12 09-Sep-12 7.00 13-Mar-12 09-Sep-12 20-Mar-12 30-Sep-12 27-Mar-12 30-Sep-12 04-May-12 30-Sep-12 03-Jun-12 30-Sep-12 18-Jun-12 30-Sep-12 18-Jun-12
GALPERTI ENGINEERING AND
UU00-P-LMTS-000-1014 Block & Bleed Valves PIPING LOT : 001 SF0060 FLOW CONTROL SPA FOB GENOA, ITALY 20-Apr-12 01-Apr-11 21-Mar-11 100 01-May-11 09-Apr-11 100 24-May-11 25-Aug-11 100 31-May-11 04-Sep-11 100 15-Jul-11 04-Sep-11 100 05-Feb-12 03-Jul-12 3.00 12-Feb-12 11-Jul-12 19-Feb-12 20-Jul-12 26-Feb-12 27-Jul-12 04-Apr-12 03-Sep-12 04-May-12 03-Oct-12 19-May-12 18-Oct-12 19-May-12
Dual Plate Check Valves & Wafer Check FOB NEAREST INTERNATIONAL
UU00-P-LMTS-000-1015 Valves-Lot-2 PIPING UU00-P-LMTS-000-1015-72-2 SEAPORT, UK 01-Apr-11 23-Mar-11 100 01-May-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 04-Jul-11 100 15-Jul-11 18-Aug-11 05-Feb-12 05-Feb-12 12-Feb-12 11-Feb-12 19-Feb-12 18-Feb-12 26-Feb-12 25-Feb-12 04-Apr-12 03-Apr-12 04-May-12 03-May-12 19-May-12 18-May-12 19-May-12
Dual Plate Check Valves & Wafer Check FOB NEAREST INTERNATIONAL
UU00-P-LMTS-000-1015 Valves-Lot-1 PIPING LOT : 001 SF0045 GOODWIN INTERNATIONAL LTD SEAPORT, UK 01-Apr-11 23-Mar-11 100 01-May-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 04-Jul-11 100 15-Jul-11 04-Jul-11 100 05-Feb-12 21-Dec-11 25.11 12-Feb-12 21-Dec-11 19-Feb-12 21-Dec-11 26-Feb-12 21-Dec-11 04-Apr-12 21-Dec-11 04-May-12 21-Dec-11 19-May-12 21-Dec-11 19-May-12
Dual Plate Check Valves & Wafer Check FOB NEAREST INTERNATIONAL
UU00-P-LMTS-000-1015 Valves-Lot-1 PIPING LOT : 002 SF0045 GOODWIN INTERNATIONAL LTD SEAPORT, UK 01-Apr-11 23-Mar-11 100 01-May-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 04-Jul-11 100 15-Jul-11 04-Jul-11 100 05-Feb-12 21-Dec-11 25.00 12-Feb-12 21-Dec-11 19-Feb-12 21-Dec-11 26-Feb-12 21-Dec-11 04-Apr-12 21-Dec-11 04-May-12 21-Dec-11 19-May-12 21-Dec-11 19-May-12
Dual Plate Check Valves & Wafer Check FOB NEAREST INTERNATIONAL
UU00-P-LMTS-000-1015 Valves-Lot-1 PIPING LOT : 003 SF0045 GOODWIN INTERNATIONAL LTD SEAPORT, UK 07-Jan-12 01-Apr-11 23-Mar-11 100 01-May-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 04-Jul-11 100 15-Jul-11 04-Jul-11 100 05-Feb-12 28-Dec-11 25.00 12-Feb-12 28-Dec-11 19-Feb-12 07-Jan-12 26-Feb-12 07-Jan-12 04-Apr-12 07-Jan-12 04-May-12 07-Jan-12 19-May-12 07-Jan-12 19-May-12
Dual Plate Check Valves & Wafer Check FOB NEAREST INTERNATIONAL
UU00-P-LMTS-000-1015 Valves-Lot-1 PIPING LOT : 004 SF0045 GOODWIN INTERNATIONAL LTD SEAPORT, UK 01-Apr-11 23-Mar-11 100 01-May-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 04-Jul-11 100 15-Jul-11 04-Jul-11 100 05-Feb-12 21-Dec-11 26.26 12-Feb-12 21-Dec-11 19-Feb-12 21-Dec-11 26-Feb-12 21-Dec-11 04-Apr-12 21-Dec-11 04-May-12 21-Dec-11 19-May-12 21-Dec-11 19-May-12
Dual Plate Check Valves & Wafer Check FOB NEAREST INTERNATIONAL
UU00-P-LMTS-000-1015 Valves-Lot-1 PIPING LOT : 005 SF0045 GOODWIN INTERNATIONAL LTD SEAPORT, UK 07-Jan-12 01-Apr-11 23-Mar-11 100 01-May-11 13-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 04-Jul-11 100 15-Jul-11 04-Jul-11 100 05-Feb-12 28-Dec-11 25.00 12-Feb-12 28-Dec-11 19-Feb-12 07-Jan-12 26-Feb-12 07-Jan-12 04-Apr-12 07-Jan-12 04-May-12 07-Jan-12 19-May-12 07-Jan-12 19-May-12
UU00-P-LMTS-000-1016 GCC Valves - 1st Lot PIPING LOT : 001 SF0052 MALBRANQUE FOB ANTWERPEN, BELGIUM PORT 26-Feb-12 01-Apr-11 14-Mar-11 100 01-May-11 08-Apr-11 100 24-May-11 06-Jul-11 100 31-May-11 26-Jul-11 100 15-Jul-11 26-Jul-11 100 05-Feb-12 10-May-12 9.00 12-Feb-12 18-May-12 19-Feb-12 26-May-12 26-Feb-12 02-Jun-12 04-Apr-12 10-Jul-12 04-May-12 09-Aug-12 19-May-12 24-Aug-12 19-May-12
UU00-P-LMTS-000-1016 GCC Valves - 3rd Lot PIPING UU00-P-LMTS-000-1016-125-2-4 FOB ANTWERPEN, BELGIUM PORT 01-Apr-11 14-Mar-11 100 01-May-11 08-Apr-11 100 24-May-11 06-Jul-11 100 31-May-11 15-Jul-11 05-Feb-12 12-Feb-12 19-Feb-12 26-Feb-12 04-Apr-12 04-May-12 19-May-12 19-May-12
UU00-P-LMTS-000-1016 GCC Valves - 2nd Lot PIPING LOT : 002 SF0052 MALBRANQUE FOB ANTWERPEN, BELGIUM PORT 11-Apr-12 01-Apr-11 14-Mar-11 100 01-May-11 08-Apr-11 100 24-May-11 06-Jul-11 100 31-May-11 26-Jul-11 100 15-Jul-11 26-Jul-11 100 05-Feb-12 10-May-12 9.00 12-Feb-12 10-May-12 19-Feb-12 26-May-12 26-Feb-12 26-May-12 04-Apr-12 26-May-12 04-May-12 26-May-12 19-May-12 26-May-12 19-May-12
UU00-P-LMTS-000-1016 GCC Valves - 2nd Lot PIPING LOT : 003 SF0052 MALBRANQUE FOB ANTWERPEN, BELGIUM PORT 17-Mar-12 01-Apr-11 14-Mar-11 100 01-May-11 08-Apr-11 100 24-May-11 06-Jul-11 100 31-May-11 26-Jul-11 100 15-Jul-11 26-Jul-11 100 05-Feb-12 10-May-12 9.00 12-Feb-12 10-May-12 19-Feb-12 26-May-12 26-Feb-12 26-May-12 04-Apr-12 26-May-12 04-May-12 26-May-12 19-May-12 26-May-12 19-May-12
TYCO VALVES & CONTROLS FOB NEAREST INTERNATIONAL
UU00-P-LMTS-000-1017 Butterfly Valves PIPING LOT : 001 SF0042 MIDDLE EAST SEAPORT, UK 10-Nov-11 01-Apr-11 21-Mar-11 100 01-May-11 08-Apr-11 100 24-May-11 23-Jun-11 100 31-May-11 23-Jun-11 100 15-Jul-11 23-Jun-11 100 06-Jan-12 04-Dec-11 70.00 13-Jan-12 09-Dec-11 30.00 20-Jan-12 14-Dec-11 27-Jan-12 21-Dec-11 05-Mar-12 28-Jan-12 04-Apr-12 27-Feb-12 19-Apr-12 13-Mar-12 19-Apr-12
FOB NEAREST INTERNATIONAL
UU00-P-LMTS-000-1018 Bronze Valves PIPING LOT : 001 SF0053 SHIPHAM VALVES LTD SEAPORT, UK 13-Dec-11 01-Apr-11 05-May-11 100 01-May-11 09-Jun-11 100 24-May-11 31-Jul-11 100 31-May-11 02-Aug-11 100 15-Jul-11 02-Aug-11 100 06-Jan-12 29-Feb-12 3.00 13-Jan-12 07-Mar-12 20-Jan-12 13-Mar-12 27-Jan-12 20-Mar-12 05-Mar-12 27-Apr-12 04-Apr-12 27-May-12 19-Apr-12 11-Jun-12 19-Apr-12
BARTON FIRTOP ENGINEERING
UU00-P-LMTS-000-1019 Strainers PIPING LOT : 001 SF0105 CO. LTD FOB UK PORT 24-May-12 25-May-11 01-Jun-11 100 24-Jun-11 27-Jun-11 100 17-Jul-11 27-Oct-11 100 24-Jul-11 27-Oct-11 100 07-Sep-11 27-Oct-11 100 28-Mar-12 24-Apr-12 02-May-12 24-Apr-12 09-May-12 24-May-12 16-May-12 24-May-12 23-Jun-12 24-May-12 23-Jul-12 24-May-12 07-Aug-12 24-May-12 07-Aug-12
UU00-P-LMTS-000-1020 Air Trap PIPING UU00-P-LMTS-000-1020-128 SF0097 SPIRAX-SARCO LTD 25-May-11 09-Jun-11 100 24-Jun-11 10-Jul-11 100 17-Jul-11 17-Oct-11 100 24-Jul-11 24-Oct-11 100 07-Sep-11 08-Dec-11 31-Dec-11 16-Jan-12 07-Jan-12 23-Jan-12 14-Jan-12 30-Jan-12 21-Jan-12 06-Feb-12 28-Feb-12 15-Mar-12 29-Mar-12 14-Apr-12 13-Apr-12 29-Apr-12 13-Apr-12
UU00-P-LMTS-000-1021 Bird Screen PIPING UU00-P-LMTS-000-1021-129 25-May-11 30-Oct-11 24-Jun-11 29-Nov-11 17-Jul-11 22-Dec-11 24-Jul-11 29-Dec-11 07-Sep-11 12-Feb-12 31-Dec-11 06-Jun-12 07-Jan-12 13-Jun-12 14-Jan-12 20-Jun-12 21-Jan-12 27-Jun-12 28-Feb-12 04-Aug-12 29-Mar-12 03-Sep-12 13-Apr-12 18-Sep-12 13-Apr-12

UU00-P-LMTS-000-1022 Flame Arrestor PIPING LOT : 001 SF0104 HYDROPNEUMATICS PVT. LTD. FOB MUMBAI PORT, INDIA 17-Jan-12 25-May-11 19-Jul-11 100 24-Jun-11 06-Aug-11 100 17-Jul-11 25-Oct-11 100 24-Jul-11 25-Oct-11 100 07-Sep-11 25-Oct-11 100 01-Dec-11 09-Jan-12 08-Dec-11 09-Jan-12 15-Dec-11 17-Jan-12 22-Dec-11 17-Jan-12 29-Jan-12 17-Jan-12 28-Feb-12 17-Jan-12 14-Mar-12 17-Jan-12 14-Mar-12
UU00-P-LMTS-000-1023 Sample Cooler PIPING UU00-P-LMTS-000-1023-74 25-May-11 07-Aug-11 100 30-Jun-11 31-Oct-11 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 06-Jan-12 27-Jun-12 13-Jan-12 04-Jul-12 20-Jan-12 11-Jul-12 27-Jan-12 18-Jul-12 05-Mar-12 25-Aug-12 04-Apr-12 24-Sep-12 19-Apr-12 09-Oct-12 19-Apr-12

UU00-P-LMTS-000-1024 Access Fittings with Corrosion Probe PIPING UU00-P-LMTS-000-1024-131 31-May-11 26-Sep-11 100 30-Jun-11 10-Oct-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 06-Mar-12 13-Feb-12 13-Mar-12 20-Feb-12 20-Mar-12 27-Feb-12 27-Mar-12 05-Mar-12 04-May-12 12-Apr-12 03-Jun-12 12-May-12 18-Jun-12 27-May-12 18-Jun-12
UU00-P-LMTS-000-1025 Hose & Hose Coupling PIPING UU00-P-LMTS-000-1025-132 31-May-11 21-Sep-11 100 30-Jun-11 06-Oct-11 100 23-Jul-11 06-Nov-11 30-Jul-11 13-Nov-11 13-Sep-11 28-Dec-11 06-Mar-12 04-Mar-12 13-Mar-12 11-Mar-12 20-Mar-12 18-Mar-12 27-Mar-12 25-Mar-12 04-May-12 02-May-12 03-Jun-12 01-Jun-12 18-Jun-12 16-Jun-12 18-Jun-12
UU00-P-LMTS-000-1026 Gasket PIPING LOT : 001 SF0101 KLINGER LTD FCA SELLER'S WORKS, UK 29-Jan-12 30-Jun-11 09-Jun-11 100 30-Jul-11 09-Jul-11 100 22-Aug-11 16-Oct-11 100 29-Aug-11 23-Oct-11 100 13-Oct-11 23-Oct-11 100 07-Nov-11 13-Jan-12 14-Nov-11 13-Jan-12 21-Nov-11 29-Jan-12 28-Nov-11 29-Jan-12 05-Jan-12 29-Jan-12 04-Feb-12 29-Jan-12 19-Feb-12 29-Jan-12 19-Feb-12
INDUSTRIAL MATERIAL SUPPLY
UU00-P-LMTS-000-1027 Galvanised Pipe Fittings & Flanges PIPING LOT : 002 SF0046 FZCO FCA SELLER'S WORKS, JEBEL ALI, UAE 18-Jul-11 31-May-11 26-Apr-11 100 30-Jun-11 12-Jun-11 100 23-Jul-11 23-Jun-11 100 30-Jul-11 04-Jul-11 100 13-Sep-11 04-Jul-11 100 07-Dec-11 13-Dec-11 60.00 14-Dec-11 22-Dec-11 21-Dec-11 30-Dec-11 28-Dec-11 06-Jan-12 04-Feb-12 13-Feb-12 05-Mar-12 14-Mar-12 20-Mar-12 29-Mar-12 20-Mar-12

UU00-P-LMTS-000-1027 Galvanised Pipe Fittings & Flanges PIPING LOT : 001 SF0064 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI, UAE 12-Sep-11 31-May-11 26-Apr-11 100 30-Jun-11 12-Jun-11 100 23-Jul-11 23-Jun-11 100 30-Jul-11 04-Jul-11 100 13-Sep-11 22-Aug-11 100 07-Dec-11 13-Dec-11 21.60 14-Dec-11 22-Dec-11 21-Dec-11 30-Dec-11 28-Dec-11 06-Jan-12 04-Feb-12 13-Feb-12 05-Mar-12 14-Mar-12 20-Mar-12 29-Mar-12 20-Mar-12

UU00-P-LMTS-000-1027 Galvanised Pipe Fittings & Flanges PIPING LOT : 003 SF0064 GERAB NATIONAL ENTERPRISES FCA SELLER'S WORKS, JEBEL ALI, UAE 12-Sep-11 31-May-11 26-Apr-11 100 30-Jun-11 12-Jun-11 100 23-Jul-11 23-Jun-11 100 30-Jul-11 04-Jul-11 100 13-Sep-11 22-Aug-11 100 07-Dec-11 20-Oct-11 100.00 14-Dec-11 20-Oct-11 100.00 21-Dec-11 27-Oct-11 100.00 28-Dec-11 27-Oct-11 04-Feb-12 27-Oct-11 05-Mar-12 27-Oct-11 20-Mar-12 27-Oct-11 20-Mar-12
UU00-P-LMTS-000-1028 Insulating Gasket PIPING UU00-P-LMTS-000-1028-134 31-May-11 13-Jul-11 100 30-Jun-11 01-Aug-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 06-Jan-12 13-Feb-12 13-Jan-12 20-Feb-12 20-Jan-12 27-Feb-12 27-Jan-12 05-Mar-12 05-Mar-12 12-Apr-12 04-Apr-12 12-May-12 19-Apr-12 27-May-12 19-Apr-12
UU00-P-LMTS-000-1029 Fastners PIPING LOT : 001 SF0080 OME METALLURGICA ERBESE FOB GENOVA PORT, ITALY 23-Nov-11 30-Jun-11 12-Jun-11 100 30-Jul-11 27-Jun-11 100 22-Aug-11 25-Sep-11 100 29-Aug-11 28-Sep-11 100 13-Oct-11 28-Sep-11 100 07-Nov-11 15-Dec-11 14-Nov-11 15-Dec-11 21-Nov-11 30-Dec-11 28-Nov-11 30-Dec-11 05-Jan-12 30-Dec-11 04-Feb-12 30-Dec-11 19-Feb-12 30-Dec-11 19-Feb-12

UU00-P-LMTS-000-1030 Spring Hangers, Strut & ROD Hangers PIPING UU00-P-LMTS-000-1030-136 30-Jun-11 30-Oct-11 30-Jul-11 29-Nov-11 22-Aug-11 22-Dec-11 29-Aug-11 29-Dec-11 13-Oct-11 12-Feb-12 05-Apr-12 05-Aug-12 12-Apr-12 12-Aug-12 19-Apr-12 19-Aug-12 26-Apr-12 26-Aug-12 03-Jun-12 03-Oct-12 03-Jul-12 02-Nov-12 18-Jul-12 17-Nov-12 18-Jul-12
UU00-P-LMTS-000-1031 Pipe Support Bought-out Items PIPING UU00-P-LMTS-000-1031-76 01-May-11 10-Nov-11 31-May-11 10-Dec-11 23-Jun-11 02-Jan-12 30-Jun-11 09-Jan-12 14-Aug-11 23-Feb-12 07-Dec-11 17-Jun-12 14-Dec-11 24-Jun-12 21-Dec-11 01-Jul-12 28-Dec-11 08-Jul-12 04-Feb-12 15-Aug-12 05-Mar-12 14-Sep-12 20-Mar-12 29-Sep-12 20-Mar-12
UU00-P-LMTS-000-1032 Choke Valves PIPING UU00-P-LMTS-000-1032-137 01-May-11 04-Dec-11 31-May-11 03-Jan-12 23-Jun-11 26-Jan-12 30-Jun-11 02-Feb-12 14-Aug-11 18-Mar-12 07-Dec-11 11-Jul-12 14-Dec-11 18-Jul-12 21-Dec-11 25-Jul-12 28-Dec-11 01-Aug-12 04-Feb-12 08-Sep-12 05-Mar-12 08-Oct-12 20-Mar-12 23-Oct-12 20-Mar-12
UU00-P-LMTS-000-1033 Thermal Insulation PIPING UU00-P-LMTS-000-1033-138 30-Jun-11 11-Dec-11 30-Jul-11 10-Jan-12 22-Aug-11 02-Feb-12 29-Aug-11 09-Feb-12 13-Oct-11 25-Mar-12 07-Dec-11 19-May-12 14-Dec-11 26-May-12 21-Dec-11 02-Jun-12 28-Dec-11 09-Jun-12 04-Feb-12 17-Jul-12 05-Mar-12 16-Aug-12 20-Mar-12 31-Aug-12 20-Mar-12
Supply & Fabrication of Standard Pipe
UU00-P-LMTS-000-1034 Supports PIPING UU00-P-LMTS-000-1034-139 01-May-11 27-Nov-11 31-May-11 27-Dec-11 23-Jun-11 19-Jan-12 30-Jun-11 26-Jan-12 14-Aug-11 11-Mar-12 05-Feb-12 02-Sep-12 12-Feb-12 09-Sep-12 19-Feb-12 16-Sep-12 26-Feb-12 23-Sep-12 04-Apr-12 31-Oct-12 04-May-12 30-Nov-12 19-May-12 15-Dec-12 19-May-12
UU00-P-LMTS-000-1035 Monolithic Insulating Joint PIPING UU00-P-LMTS-000-1035-140 01-May-11 28-Oct-11 31-May-11 27-Nov-11 23-Jun-11 20-Dec-11 30-Jun-11 27-Dec-11 14-Aug-11 10-Feb-12 07-Dec-11 04-Jun-12 14-Dec-11 11-Jun-12 21-Dec-11 18-Jun-12 28-Dec-11 25-Jun-12 04-Feb-12 02-Aug-12 05-Mar-12 01-Sep-12 20-Mar-12 16-Sep-12 20-Mar-12
UU00-P-LMTS-000-1036 Sweepolet (2nd Lot) PIPING UU00-P-LMTS-000-1036-141-3 FOB GENOVA PORT, ITALY 01-May-11 29-Mar-11 100 31-May-11 12-Apr-11 100 23-Jun-11 08-Aug-11 100 30-Jun-11 05-Nov-11 14-Aug-11 20-Dec-11 05-Feb-12 04-Jun-12 12-Feb-12 11-Jun-12 19-Feb-12 18-Jun-12 26-Feb-12 25-Jun-12 04-Apr-12 02-Aug-12 04-May-12 01-Sep-12 19-May-12 16-Sep-12 19-May-12
UU00-P-LMTS-000-1036 Extruded Tee(1st Lot) PIPING LOT : 001 SF0058 VALVITALIA SPA FOB GENOVA PORT, ITALY 09-Jan-12 01-May-11 29-Mar-11 100 31-May-11 12-Apr-11 100 23-Jun-11 08-Aug-11 100 30-Jun-11 08-Aug-11 100 14-Aug-11 08-Aug-11 100 05-Feb-12 31-Dec-11 3.00 12-Feb-12 05-Jan-12 19-Feb-12 09-Jan-12 26-Feb-12 16-Jan-12 04-Apr-12 23-Feb-12 04-May-12 24-Mar-12 19-May-12 08-Apr-12 19-May-12
UU00-P-LMTS-000-1036 Extruded Tee(1st Lot) PIPING LOT : 002 SF0058 VALVITALIA SPA FOB GENOVA PORT, ITALY 28-Nov-11 01-May-11 29-Mar-11 100 31-May-11 12-Apr-11 100 23-Jun-11 08-Aug-11 100 30-Jun-11 08-Aug-11 100 14-Aug-11 08-Aug-11 100 05-Feb-12 21-Dec-11 3.00 12-Feb-12 25-Dec-11 19-Feb-12 30-Dec-11 26-Feb-12 06-Jan-12 04-Apr-12 13-Feb-12 04-May-12 14-Mar-12 19-May-12 29-Mar-12 19-May-12
UU00-P-LMTS-000-1036 Sweepolet (1st Lot) PIPING LOT : 003 SF0059 M.E.G.A. SPA FOB GENOVA PORT, ITALY 28-Nov-11 01-May-11 29-Mar-11 100 31-May-11 12-Apr-11 100 23-Jun-11 08-Aug-11 100 30-Jun-11 08-Aug-11 100 14-Aug-11 08-Aug-11 100 05-Feb-12 23-Nov-11 25.00 12-Feb-12 26-Nov-11 19-Feb-12 30-Nov-11 26-Feb-12 07-Dec-11 04-Apr-12 14-Jan-12 04-May-12 13-Feb-12 19-May-12 28-Feb-12 19-May-12
UU00-P-LMTS-000-1036 Extruded Tee (3rd Lot) PIPING UU00-P-LMTS-000-1036-141-4-9 FOB GENOVA PORT, ITALY 01-May-11 31-May-11 23-Jun-11 30-Jun-11 14-Aug-11 05-Feb-12 12-Feb-12 19-Feb-12 26-Feb-12 04-Apr-12 04-May-12 19-May-12 19-May-12
UU00-P-LMTS-000-1036 Extruded Tee (2nd Lot) PIPING LOT : 004 SF0058 VALVITALIA SPA FOB GENOVA PORT, ITALY 09-Jan-12 01-May-11 29-Mar-11 100 31-May-11 12-Apr-11 100 23-Jun-11 08-Aug-11 100 30-Jun-11 08-Aug-11 100 14-Aug-11 08-Aug-11 100 05-Feb-12 31-Dec-11 12-Feb-12 31-Dec-11 19-Feb-12 09-Jan-12 26-Feb-12 09-Jan-12 04-Apr-12 09-Jan-12 04-May-12 09-Jan-12 19-May-12 09-Jan-12 19-May-12
UU00-P-LMTS-000-1036 Sweepolet (1st Lot) PIPING LOT : 005 SF0059 M.E.G.A. SPA FOB GENOVA PORT, ITALY 22-Dec-11 01-May-11 29-Mar-11 100 31-May-11 12-Apr-11 100 23-Jun-11 08-Aug-11 100 30-Jun-11 08-Aug-11 100 14-Aug-11 08-Aug-11 100 05-Feb-12 14-Dec-11 25.00 12-Feb-12 14-Dec-11 19-Feb-12 22-Dec-11 26-Feb-12 22-Dec-11 04-Apr-12 22-Dec-11 04-May-12 22-Dec-11 19-May-12 22-Dec-11 19-May-12
SERCK AUDCO VALVES
UU00-P-LMTS-000-1037 Plug Valves PIPING LOT : 001 SF0066 (FLOWSERVE) FOB INTERNATIONAL SEAPORT UK 18-Apr-12 05-May-11 05-May-11 100 26-May-11 18-Jun-11 100 25-Jun-11 24-Aug-11 100 01-Jul-11 24-Aug-11 100 15-Aug-11 24-Aug-11 100 18-Nov-11 24-May-12 10.00 25-Nov-11 07-Jun-12 01-Dec-11 18-Jun-12 08-Dec-11 25-Jun-12 15-Jan-12 02-Aug-12 14-Feb-12 01-Sep-12 29-Feb-12 16-Sep-12 29-Feb-12
UU00-P-LMTS-000-1038 Special Globe Valves PIPING UU00-P-LMTS-000-1038-1 09-Jun-11 09-Jun-11 100 09-Jul-11 05-Jul-11 100 30-Jul-11 23-Nov-11 06-Aug-11 30-Nov-11 20-Sep-11 14-Jan-12 04-Mar-12 30-May-12 11-Mar-12 06-Jun-12 18-Mar-12 13-Jun-12 25-Mar-12 20-Jun-12 02-May-12 28-Jul-12 01-Jun-12 27-Aug-12 16-Jun-12 11-Sep-12 16-Jun-12
UU00-P-LMTS-000-1039 Valve Interlocking System PIPING UU00-P-LMTS-000-1039-1 05-Oct-11 100 04-Nov-11 24-Dec-11 31-Dec-11 14-Feb-12 30-Mar-12 06-Apr-12 13-Apr-12 20-Apr-12 28-May-12 27-Jun-12 12-Jul-12 06-Oct-11
UU00-P-LMTS-000-1041 Sight Glass PIPING UU00-P-LMTS-000-1041-1 18-Oct-11 100 17-Nov-11 17-Dec-11 24-Dec-11 07-Feb-12 07-Apr-12 14-Apr-12 21-Apr-12 28-Apr-12 05-Jun-12 05-Jul-12 20-Jul-12 23-Oct-11
PL-13CR-LOGISTICS 6" Pipe Logistics PIPELINE PL-13CR-LOGISTICS-1
PL-13CR-LOGISTICS 16" Pipe Logistics - 1st Lot PIPELINE PL-13CR-LOGISTICS-2
PL-13CR-LOGISTICS 16" Pipe Logistics - 2nd Lot PIPELINE PL-13CR-LOGISTICS-3
PL-13CR-LOGISTICS 16" Pipe Logistics - 3rd Lot PIPELINE PL-13CR-LOGISTICS-4
PL-13CR-LOGISTICS 16" Pipe Logistics - 4th Lot PIPELINE PL-13CR-LOGISTICS-5
PL-13CR-LOGISTICS 16" Pipe Logistics - 5thLot PIPELINE PL-13CR-LOGISTICS-6
PL-13CR-LOGISTICS 16" Pipe Logistics - 6th. Lot PIPELINE PL-13CR-LOGISTICS-7
PL-13CR-LOGISTICS 16" Pipe Logistics - 7th. Lot PIPELINE PL-13CR-LOGISTICS-8
PL-13CR-LOGISTICS 16" Pipe Logistics - 8th. Lot PIPELINE PL-13CR-LOGISTICS-9
PL-13CR-LOGISTICS 12" Pipe Logistics - 1st Lot PIPELINE PL-13CR-LOGISTICS-10
PL-13CR-LOGISTICS 12" Pipe Logistics - 2nd Lot PIPELINE PL-13CR-LOGISTICS-11
PL-13CR-LOGISTICS 12" Pipe Logistics - 3rd Lot PIPELINE PL-13CR-LOGISTICS-12
PL-13CR-LOGISTICS 12" Pipe Logistics - 4th Lot PIPELINE PL-13CR-LOGISTICS-13
PL-13CR-LOGISTICS 8" Pipe Logistics - 1st Lot PIPELINE PL-13CR-LOGISTICS-14
PL-13CR-LOGISTICS 8" Pipe Logistics - 2nd Lot PIPELINE PL-13CR-LOGISTICS-15
PL-13CR-LOGISTICS 8" Pipe Logistics - 3rd Lot PIPELINE PL-13CR-LOGISTICS-16
PL-13CR-LOGISTICS 8" Pipe Logistics - 4th Lot PIPELINE PL-13CR-LOGISTICS-17
UT00-P-EETS-000-1040 Globe Valves PIPELINE UT00-P-EETS-000-1040-1 26-Jul-11 26-Jul-11 100 25-Aug-11 30-Oct-11 24-Sep-11 24-Dec-11 01-Oct-11 31-Dec-11 15-Nov-11 14-Feb-12 15-Mar-12 01-Sep-12 22-Mar-12 08-Sep-12 29-Mar-12 15-Sep-12 05-Apr-12 22-Sep-12 13-May-12 30-Oct-12 12-Jun-12 29-Nov-12 27-Jun-12 14-Dec-12 27-Jun-12
Manufac. (Upto Ex-works)-Coated & Bare
24" API-5L Gr.X70 CS Line Pipe (1st Lot- SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 14Km) PIPELINE LOT : 001 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 15-Jan-12 30.00 15-Oct-11 15-Jan-12 22-Oct-11 30-Jan-12 29-Oct-11 30-Jan-12 06-Dec-11 30-Jan-12 05-Jan-12 30-Jan-12 20-Jan-12 30-Jan-12
Coating of 24" API-5L Gr.X70 CS Line Pipe SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 (2nd Lot-18Km) PIPELINE LOT : 002 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 15-Jan-12 15-Oct-11 15-Jan-12 22-Oct-11 30-Jan-12 29-Oct-11 30-Jan-12 06-Dec-11 30-Jan-12 05-Jan-12 30-Jan-12 20-Jan-12 30-Jan-12
Manufac. Bare 32" API-5L Gr.X70 CS Line SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 Pipe (4th Lot-1.636Km) PIPELINE LOT : 003 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 30.00 15-Oct-11 17-Dec-11 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11

Manufac. Bare 32" API-5L Gr.X70 CS Line SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 Pipe (2nd Lot-13.8Km) - WT-11.9 mm PIPELINE LOT : 004 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 99.00 15-Oct-11 17-Dec-11 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11
Manufac. (Upto Ex-works)-Coated & Bare
24" API-5L Gr.X70 CS Line Pipe (2nd Lot- SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 18Km) PIPELINE LOT : 005 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 15-Jan-12 30.00 15-Oct-11 15-Jan-12 22-Oct-11 30-Jan-12 29-Oct-11 30-Jan-12 06-Dec-11 30-Jan-12 05-Jan-12 30-Jan-12 20-Jan-12 30-Jan-12
Manufac. (Upto Ex-works)-Coated & Bare
24" API-5L Gr.X70 CS Line Pipe (3rd Lot- SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 21.6Km) PIPELINE LOT : 006 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 15-Jan-12 30.00 15-Oct-11 15-Jan-12 22-Oct-11 30-Jan-12 29-Oct-11 30-Jan-12 06-Dec-11 30-Jan-12 05-Jan-12 30-Jan-12 20-Jan-12 30-Jan-12
Coating (Upto Ex-works)- 32" API-5L
Gr.X70 CS Line Pipe (2nd Lot-13.8Km) SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 WT-11.9 mm PIPELINE LOT : 007 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 98.93 15-Oct-11 17-Dec-11 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11
Manufac. Bare 32" API-5L Gr.X70 CS Line SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 Pipe (3rd Lot-33.467Km) PIPELINE LOT : 008 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 54.00 15-Oct-11 17-Dec-11 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11

Coating (Upto Ex-works)- 32"API-5L SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 Gr.X70 CS Line Pipe (4th Lot-1.636Km) PIPELINE LOT : 009 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 15-Oct-11 17-Dec-11 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11
Coating of 24" API-5L Gr.X70 CS Line Pipe SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 (4th Lot-9.866Km) PIPELINE LOT : 010 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 15-Jan-12 15-Oct-11 15-Jan-12 22-Oct-11 30-Jan-12 29-Oct-11 30-Jan-12 06-Dec-11 30-Jan-12 05-Jan-12 30-Jan-12 20-Jan-12 30-Jan-12

Manufac. Bare 32" API-5L Gr.X70 CS Line SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 Pipe (1st Lot-21.6Km) - WT-11.9 mm PIPELINE LOT : 011 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 99.00 15-Oct-11 17-Dec-11 99.00 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11
Manufac. (Upto Ex-works)-Coated & Bare
24" API-5L Gr.X70 CS Line Pipe (4th Lot- SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 9.866Km) PIPELINE LOT : 012 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 30.00 15-Oct-11 17-Dec-11 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11
Coating of 24" API-5L Gr.X70 CS Line Pipe SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 (3rd Lot-21.6Km) PIPELINE LOT : 013 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 15-Jan-12 15-Oct-11 15-Jan-12 22-Oct-11 30-Jan-12 29-Oct-11 30-Jan-12 06-Dec-11 30-Jan-12 05-Jan-12 30-Jan-12 20-Jan-12 30-Jan-12
Coating of 24" API-5L Gr.X70 CS Line Pipe SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 (1st Lot-14Km) PIPELINE LOT : 014 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 15-Jan-12 15-Oct-11 15-Jan-12 22-Oct-11 30-Jan-12 29-Oct-11 30-Jan-12 06-Dec-11 30-Jan-12 05-Jan-12 30-Jan-12 20-Jan-12 30-Jan-12
Coating (Upto Ex-works)- 32" API-5L
Gr.X70 CS Line Pipe (1st Lot-21.6Km) - SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 WT -11.9 mm PIPELINE LOT : 015 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 98.93 15-Oct-11 17-Dec-11 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11

Coating (Upto Ex-works)- 32" API-5L SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 Gr.X70 CS Line Pipe (3rd Lot-33.467Km) PIPELINE LOT : 016 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 17-Dec-11 19.99 15-Oct-11 17-Dec-11 22-Oct-11 30-Dec-11 29-Oct-11 30-Dec-11 06-Dec-11 30-Dec-11 05-Jan-12 30-Dec-11 20-Jan-12 30-Dec-11
SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 CS Welded Pipelines Bare & Coated PIPELINE LOT : 017 SF0034 INTERNATIONAL GMBH SECTION-1) 30-Dec-11 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 15-Jan-12 38.35 15-Oct-11 15-Jan-12 22-Oct-11 30-Jan-12 29-Oct-11 30-Jan-12 06-Dec-11 30-Jan-12 05-Jan-12 30-Jan-12 20-Jan-12 30-Jan-12 20-Jan-12

Manufac. Bare 32" API-5L Gr.X70 CS Line SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 Pipe (1st Lot-21.6Km) - WT-11.9 mm PIPELINE LOT : 018 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 10-Oct-11 100.00 15-Oct-11 04-Oct-11 100.00 22-Oct-11 18-Oct-11 100.00 29-Oct-11 17-Oct-11 06-Dec-11 19-Oct-11 05-Jan-12 19-Oct-11 20-Jan-12 19-Oct-11
Manufac. Bare 32" API-5L Gr.X70 CS Line SALZGITTER MANNESMANN CFR ALGERIAN PORT (REFER A6 IN
UU00-P-EETS-000-1000 Pipe (3rd Lot-33.467Km) PIPELINE LOT : 019 SF0034 INTERNATIONAL GMBH SECTION-1) 15-Feb-11 03-Mar-11 100 02-Mar-11 19-Mar-11 100 25-Mar-11 22-Jun-11 100 01-Apr-11 22-Jun-11 100 16-May-11 22-Jun-11 100 08-Oct-11 18-Oct-11 100.00 15-Oct-11 18-Oct-11 100.00 22-Oct-11 27-Oct-11 100.00 29-Oct-11 22-Oct-11 06-Dec-11 28-Oct-11 05-Jan-12 29-Oct-11 20-Jan-12 29-Oct-11
UU00-P-EETS-000-1002 Tie In Ball Valves PIPELINE LOT : 001 SF0037 VALVITALIA SPA FOB NORTH ITALIAN PORT, ITALY 23-Feb-12 01-Apr-11 23-Mar-11 100 01-May-11 08-Apr-11 100 24-May-11 09-Jun-11 100 31-May-11 16-Jun-11 100 15-Jul-11 16-Jun-11 100 07-Nov-11 29-Mar-12 8.00 14-Nov-11 29-Mar-12 21-Nov-11 23-Apr-12 28-Nov-11 23-Apr-12 05-Jan-12 23-Apr-12 04-Feb-12 23-Apr-12 19-Feb-12 23-Apr-12 19-Feb-12

UU00-P-EETS-000-1003 CS Seamless Linepipes Bare & Coated PIPELINE LOT : 001 SF0051 TENARIS GLOBAL SERVICES SA CFR SKIKDA PORT, ALGERIA 26-Jan-12 01-Apr-11 23-Mar-11 100 01-May-11 07-Apr-11 100 24-May-11 20-Jul-11 100 31-May-11 20-Jul-11 100 15-Jul-11 20-Jul-11 100 07-Nov-11 08-Feb-12 3.00 14-Nov-11 17-Feb-12 21-Nov-11 26-Feb-12 28-Nov-11 04-Mar-12 05-Jan-12 11-Apr-12 04-Feb-12 11-May-12 19-Feb-12 26-May-12 19-Feb-12
UU00-P-EETS-000-1004 Monolithic Insulating Joints PIPELINE UU00-P-EETS-000-1004-80 SF0089 ZUNT ITALIANA SRL 15-Apr-11 28-Apr-11 100 15-May-11 18-May-11 100 07-Jun-11 04-Oct-11 100 14-Jun-11 05-Oct-11 100 29-Jul-11 19-Nov-11 21-Jan-12 13-May-12 28-Jan-12 20-May-12 04-Feb-12 27-May-12 11-Feb-12 03-Jun-12 20-Mar-12 11-Jul-12 19-Apr-12 10-Aug-12 04-May-12 25-Aug-12 04-May-12
UU00-P-EETS-000-1005 Ball Valves PIPELINE UU00-P-EETS-000-1005-158 01-Apr-11 28-Jun-11 100 01-May-11 27-Jul-11 100 24-May-11 30-Oct-11 31-May-11 06-Nov-11 15-Jul-11 21-Dec-11 06-Mar-12 16-Dec-12 13-Mar-12 23-Dec-12 20-Mar-12 30-Dec-12 27-Mar-12 06-Jan-13 04-May-12 13-Feb-13 03-Jun-12 15-Mar-13 18-Jun-12 30-Mar-13 18-Jun-12
SERCK AUDCO VALVES
UU00-P-EETS-000-1006 Plug Valves PIPELINE UU00-P-EETS-000-1006-159 SF0096 (FLOWSERVE) 05-Apr-11 09-Jun-11 100 05-May-11 09-Jul-11 100 28-May-11 12-Oct-11 100 04-Jun-11 19-Oct-11 100 19-Jul-11 03-Dec-11 06-Jan-12 22-May-12 13-Jan-12 29-May-12 20-Jan-12 05-Jun-12 27-Jan-12 12-Jun-12 05-Mar-12 20-Jul-12 04-Apr-12 19-Aug-12 19-Apr-12 03-Sep-12 19-Apr-12
UU00-P-EETS-000-1008 Barred Tee PIPELINE LOT : 001 SF0069 VALVITALIA SPA FOB GENOA PORT, ITALY 09-Feb-12 25-Apr-11 10-May-11 100 25-May-11 14-Jul-11 100 17-Jun-11 25-Aug-11 100 24-Jun-11 08-Sep-11 100 08-Aug-11 08-Sep-11 100 30-Jan-12 20-Apr-12 5.00 06-Feb-12 20-Apr-12 13-Feb-12 04-May-12 20-Feb-12 04-May-12 29-Mar-12 04-May-12 28-Apr-12 04-May-12 13-May-12 04-May-12 13-May-12
UU00-P-EETS-000-1009 DSS Flanges & Fittings (Wrought) PIPELINE UU00-P-EETS-000-1009-157 25-May-11 01-Nov-11 24-Jun-11 15-Nov-11 17-Jul-11 23-Nov-11 24-Jul-11 30-Nov-11 07-Sep-11 14-Jan-12 31-Dec-11 16-May-12 07-Jan-12 23-May-12 14-Jan-12 30-May-12 21-Jan-12 06-Jun-12 28-Feb-12 14-Jul-12 29-Mar-12 13-Aug-12 13-Apr-12 28-Aug-12 13-Apr-12
UU00-P-EETS-000-1010 CS & LTCS Flanges, Blanks & Fittings PIPELINE UU00-P-EETS-000-1010-156 25-May-11 06-Jul-11 100 24-Jun-11 28-Jul-11 100 17-Jul-11 23-Nov-11 24-Jul-11 30-Nov-11 07-Sep-11 14-Jan-12 31-Dec-11 16-May-12 07-Jan-12 23-May-12 14-Jan-12 30-May-12 21-Jan-12 06-Jun-12 28-Feb-12 14-Jul-12 29-Mar-12 13-Aug-12 13-Apr-12 28-Aug-12 13-Apr-12
UU00-P-EETS-000-1011 Hot Induction Bends PIPELINE UU00-P-EETS-000-1011-161 16-May-11 11-Apr-11 100 15-Jun-11 19-May-11 100 08-Jul-11 23-Nov-11 15-Jul-11 30-Nov-11 29-Aug-11 14-Jan-12 01-Jan-12 30-May-12 08-Jan-12 06-Jun-12 15-Jan-12 13-Jun-12 22-Jan-12 20-Jun-12 29-Feb-12 28-Jul-12 30-Mar-12 27-Aug-12 14-Apr-12 11-Sep-12 14-Apr-12

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
PROCUREMENT TRACKING REGISTER

ISG PROJECT - IN SALAH GAS SOUTHERN FIELDS DEVELOPMENT PTR TEMPLATE


CONTRACT NO. : 100045/ISG/CON
DOCUMENT NO : 1 7 11 12 13 14 15-Jan-00 23 24-Jan-00 25-Jan-00 26 28-Jan-00 29-Jan-00 30 09-Jan-00
CUT OFF DATE: 29-Oct-11

Issue Inquiry Requisition Receive Bid TBE Complete Place LOI / LOA Place PO Receive / Approve Key Vendor Drawings / Documents Place Sub-orders Receive Raw Materials Fabrication / Mfg. Inspection Release Note Ex-works Delivery Item on Board Shipping/Air Freight/Land Transport (ATA Port) Custom Clearance and Transport to site/store Visual Inspection on Receipt at Site/Store ROS
Inquiry No. Description Discipline INQD_TAG_NO PO_NO Vendor Name PO Delivery Terms PO_CDD
P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog

UU00-P-EETS-000-1012 PE Liner for Water injection pipeline PIPELINE UU00-P-EETS-000-1012-162 15-May-11 11-Jul-11 100 14-Jun-11 29-Jul-11 100 07-Jul-11 24-Dec-11 14-Jul-11 31-Dec-11 28-Aug-11 14-Feb-12 22-Nov-11 10-May-12 29-Nov-11 17-May-12 06-Dec-11 24-May-12 13-Dec-11 31-May-12 20-Jan-12 08-Jul-12 19-Feb-12 07-Aug-12 05-Mar-12 22-Aug-12 05-Mar-12
FOB PUSAN / MASAN / KWANGYANG,
UU00-P-EETS-000-1014 LTCS Pipes for Terminals PIPELINE UU00-P-EETS-000-1014-153-3 KOREA 25-May-11 27-Jun-11 100 24-Jun-11 13-Jul-11 100 17-Jul-11 24-Oct-11 100 24-Jul-11 07-Sep-11 25-Dec-11 01-Jan-12 08-Jan-12 15-Jan-12 22-Feb-12 23-Mar-12 07-Apr-12 07-Apr-12
ERNDTEBRÜCKER EISENWERK FOB PUSAN / MASAN / KWANGYANG,
UU00-P-EETS-000-1014 LTCS Pipes for Terminals - Lot-1 PIPELINE LOT : 001 SF0082 GMBH & CO. KG KOREA 09-Apr-12 25-May-11 27-Jun-11 100 24-Jun-11 13-Jul-11 100 17-Jul-11 24-Oct-11 100 24-Jul-11 24-Oct-11 100 07-Sep-11 24-Oct-11 100 25-Dec-11 26-Mar-12 01-Jan-12 26-Mar-12 08-Jan-12 09-Apr-12 15-Jan-12 09-Apr-12 22-Feb-12 09-Apr-12 23-Mar-12 09-Apr-12 07-Apr-12 09-Apr-12 07-Apr-12
FOB PUSAN / MASAN / KWANGYANG,
UU00-P-EETS-000-1014 LTCS Pipes for Terminals - Lot-2 PIPELINE LOT : 002 SF0103 GERAB NATIONAL ENTERPRISES KOREA 07-Nov-11 25-May-11 24-Oct-11 100 24-Jun-11 24-Oct-11 100 17-Jul-11 24-Oct-11 100 24-Jul-11 24-Oct-11 100 07-Sep-11 24-Oct-11 100 25-Dec-11 06-Nov-11 01-Jan-12 06-Nov-11 08-Jan-12 07-Nov-11 15-Jan-12 07-Nov-11 22-Feb-12 07-Nov-11 23-Mar-12 07-Nov-11 07-Apr-12 07-Nov-11 07-Apr-12
UU00-P-EETS-000-1015 DSS pipes for Terminals - Lot-3 PIPELINE UU00-P-EETS-000-1022-154-3 FOB EUROPEAN PORT 25-May-11 27-Jun-11 100 24-Jun-11 17-Jul-11 100 17-Jul-11 24-Jul-11 07-Sep-11 25-Dec-11 01-Jan-12 08-Jan-12 15-Jan-12 22-Feb-12 23-Mar-12 07-Apr-12 07-Apr-12
UU00-P-EETS-000-1015 DSS pipes for Terminals - Lot-1 PIPELINE LOT : 001 SF0106 H. BUTTING GMBH & CO. KG FOB EUROPEAN PORT 28-Mar-12 25-May-11 27-Jun-11 100 24-Jun-11 17-Jul-11 100 17-Jul-11 26-Oct-11 100 24-Jul-11 26-Oct-11 100 07-Sep-11 26-Oct-11 100 25-Dec-11 15-Mar-12 01-Jan-12 15-Mar-12 08-Jan-12 28-Mar-12 15-Jan-12 04-Apr-12 22-Feb-12 12-May-12 23-Mar-12 11-Jun-12 07-Apr-12 26-Jun-12 07-Apr-12
UU00-P-EETS-000-1015 DSS pipes for Terminals - Lot-2 PIPELINE LOT : 002 SF0108 SCHULZ EXPORT GMBH FOB EUROPEAN PORT 10-Nov-11 25-May-11 26-Oct-11 100 24-Jun-11 26-Oct-11 100 17-Jul-11 26-Oct-11 100 24-Jul-11 26-Oct-11 100 07-Sep-11 26-Oct-11 100 25-Dec-11 09-Nov-11 01-Jan-12 09-Nov-11 08-Jan-12 10-Nov-11 15-Jan-12 17-Nov-11 22-Feb-12 25-Dec-11 23-Mar-12 24-Jan-12 07-Apr-12 08-Feb-12 07-Apr-12

UU00-P-EETS-000-1016 Access Fittings with Corrosion Probe PIPELINE UU00-P-EETS-000-1015-160 07-May-11 20-Jun-11 100 06-Jun-11 22-Sep-11 100 29-Jun-11 23-Nov-11 06-Jul-11 30-Nov-11 20-Aug-11 14-Jan-12 07-Dec-11 13-Feb-12 14-Dec-11 20-Feb-12 21-Dec-11 27-Feb-12 28-Dec-11 05-Mar-12 04-Feb-12 12-Apr-12 05-Mar-12 12-May-12 20-Mar-12 27-May-12 20-Mar-12
UU00-P-EETS-000-1017 Pig Signaler (Local / Remote) PIPELINE UU00-P-EETS-000-1017-82 13-Jul-11 14-Nov-11 12-Aug-11 14-Dec-11 19-Sep-11 21-Jan-12 26-Sep-11 28-Jan-12 10-Nov-11 13-Mar-12 04-Jun-12 05-Sep-12 11-Jun-12 12-Sep-12 18-Jun-12 19-Sep-12 25-Jun-12 26-Sep-12 02-Aug-12 03-Nov-12 01-Sep-12 03-Dec-12 16-Sep-12 18-Dec-12 16-Sep-12
UU00-P-EETS-000-1018 Key Interlocking System PIPELINE UU00-P-EETS-000-1018-164 30-Jun-11 20-Jun-11 100 01-Aug-11 07-Jul-11 100 24-Aug-11 24-Dec-11 31-Aug-11 31-Dec-11 15-Oct-11 14-Feb-12 14-Feb-12 30-Mar-12 21-Feb-12 06-Apr-12 28-Feb-12 13-Apr-12 06-Mar-12 20-Apr-12 13-Apr-12 28-May-12 13-May-12 27-Jun-12 28-May-12 12-Jul-12 28-May-12
UU00-P-EETS-000-1019 Sphere Tee PIPELINE LOT : 001 SF0070 VALVITALIA SPA FOB GENOA PORT, ITALY 23-Feb-12 25-Apr-11 15-May-11 100 25-May-11 17-Jun-11 100 17-Jun-11 08-Sep-11 100 24-Jun-11 08-Sep-11 100 08-Aug-11 08-Sep-11 100 30-Jan-12 20-Apr-12 5.00 06-Feb-12 20-Apr-12 13-Feb-12 04-May-12 20-Feb-12 04-May-12 29-Mar-12 04-May-12 28-Apr-12 04-May-12 13-May-12 04-May-12 13-May-12
UU00-P-EETS-000-1021 Scrapper Traps (Permanent) PIPELINE UU00-P-EETS-000-1021-163 SF0079 VALVITALIA SPA 30-Jun-11 15-May-11 100 01-Aug-11 07-Jun-11 100 24-Aug-11 26-Sep-11 100 31-Aug-11 26-Sep-11 100 15-Oct-11 10-Nov-11 14-Feb-12 11-Mar-12 21-Feb-12 18-Mar-12 28-Feb-12 25-Mar-12 06-Mar-12 01-Apr-12 13-Apr-12 09-May-12 13-May-12 08-Jun-12 28-May-12 23-Jun-12 28-May-12
UU00-P-EETS-000-1023 Gaskets PIPELINE UU00-P-EETS-000-1023-1 31-May-11 27-Jun-11 100 30-Jun-11 13-Jul-11 100 23-Jul-11 24-Dec-11 30-Jul-11 31-Dec-11 13-Sep-11 14-Feb-12 08-Oct-11 21-Apr-12 15-Oct-11 28-Apr-12 22-Oct-11 05-May-12 29-Oct-11 12-May-12 06-Dec-11 19-Jun-12 05-Jan-12 19-Jul-12 20-Jan-12 03-Aug-12 20-Jan-12
UU00-P-EETS-000-1024 Fasteners PIPELINE UU00-P-EETS-000-1024-1 31-May-11 06-Jul-11 100 30-Jun-11 01-Aug-11 100 23-Jul-11 24-Dec-11 30-Jul-11 31-Dec-11 13-Sep-11 14-Feb-12 08-Oct-11 10-Mar-12 15-Oct-11 17-Mar-12 22-Oct-11 24-Mar-12 29-Oct-11 31-Mar-12 06-Dec-11 08-May-12 05-Jan-12 07-Jun-12 20-Jan-12 22-Jun-12 20-Jan-12
UU00-P-EETS-000-1025 Pipeline Construction Services PIPELINE UU00-P-EETS-000-1025-1
UU00-P-EETS-000-1026 Choke Valves PIPELINE UU00-P-EETS-000-1026-1 25-May-11 25-Dec-11 24-Jun-11 24-Jan-12 17-Jul-11 16-Feb-12 24-Jul-11 23-Feb-12 07-Sep-11 08-Apr-12 25-Feb-12 26-Sep-12 03-Mar-12 03-Oct-12 10-Mar-12 10-Oct-12 17-Mar-12 17-Oct-12 24-Apr-12 24-Nov-12 24-May-12 24-Dec-12 08-Jun-12 08-Jan-13 08-Jun-12
UU00-P-EETS-000-1027 Check Valves PIPELINE UU00-P-EETS-000-1027-1 SF0091 AMPO 25-May-11 20-Jun-11 100 24-Jun-11 08-Aug-11 100 17-Jul-11 04-Oct-11 100 24-Jul-11 11-Oct-11 100 07-Sep-11 25-Nov-11 25-Feb-12 14-May-12 03-Mar-12 21-May-12 10-Mar-12 28-May-12 17-Mar-12 04-Jun-12 24-Apr-12 12-Jul-12 24-May-12 11-Aug-12 08-Jun-12 26-Aug-12 08-Jun-12
UU00-P-EETS-000-1028 Block & Bleed Valves PIPELINE UU00-P-EETS-000-1028-1 25-May-11 20-Jun-11 100 24-Jun-11 09-Jul-11 100 17-Jul-11 23-Nov-11 24-Jul-11 30-Nov-11 07-Sep-11 14-Jan-12 25-Feb-12 27-Jun-12 03-Mar-12 04-Jul-12 10-Mar-12 11-Jul-12 17-Mar-12 18-Jul-12 24-Apr-12 25-Aug-12 24-May-12 24-Sep-12 08-Jun-12 09-Oct-12 08-Jun-12
OFFICINE AMBROGIO MELESI &
UU00-P-EETS-000-1030 Anchor Flange PIPELINE LOT : 001 SF0072 C. SRL FOB NORTH ITALIAN PORT, ITALY 09-Feb-12 05-Jun-11 07-Jun-11 100 07-Jul-11 20-Jun-11 100 30-Jul-11 08-Sep-11 100 06-Aug-11 08-Sep-11 100 20-Sep-11 08-Sep-11 100 13-Jan-12 15-Apr-12 3.00 20-Jan-12 15-Apr-12 27-Jan-12 04-May-12 03-Feb-12 04-May-12 12-Mar-12 04-May-12 11-Apr-12 04-May-12 26-Apr-12 04-May-12 13-Apr-12
UU00-P-EETS-000-1101 Cathodic Protection System METALLURGY LOT : 001 SF0035 HOCKWAY MIDDLE EAST FZC FOB UK SEAPORT 31-Jan-12 17-Mar-11 24-Mar-11 100 16-Apr-11 06-Apr-11 100 24-May-11 09-Jun-11 100 31-May-11 15-Jun-11 100 15-Jul-11 15-Jun-11 100 07-Nov-11 30-Apr-12 22.00 14-Nov-11 30-Apr-12 21-Nov-11 28-May-12 28-Nov-11 28-May-12 05-Jan-12 28-May-12 04-Feb-12 28-May-12 19-Feb-12 28-May-12 19-Feb-12
SCHNEIDER ELECTRIC ENERGY FOB INTERNATIONAL SEAPORT, UK /
UB00-P-NNTS-000-1001 Substation Package SS-2 ELECTRICAL H-ZE-091010 SF0004 UK LTD TURKEY 23-Mar-12 16-Jan-11 01-Feb-11 100 17-Feb-11 14-Mar-11 100 24-Mar-11 16-Mar-11 100 31-Mar-11 16-Mar-11 100 15-May-11 23-Mar-11 100 29-Jun-11 28-Jun-11 49 07-Nov-11 26-Sep-11 100 06-Jan-12 05-Dec-11 38 05-Apr-12 18-Mar-12 25.00 12-Apr-12 26-Mar-12 19-Apr-12 05-Jun-12 26-Apr-12 12-Jun-12 03-Jun-12 20-Jul-12 03-Jul-12 19-Aug-12 18-Jul-12 03-Sep-12 18-Jul-12
SCHNEIDER ELECTRIC ENERGY FOB INTERNATIONAL SEAPORT, UK /
UB00-P-NNTS-000-1001 Substation Package SS-3 ELECTRICAL H-ZE-091011 SF0004 UK LTD TURKEY 23-Mar-12 16-Jan-11 01-Feb-11 100 17-Feb-11 14-Mar-11 100 24-Mar-11 16-Mar-11 100 31-Mar-11 16-Mar-11 100 15-May-11 23-Mar-11 100 29-Jun-11 04-Jul-11 49 07-Dec-11 26-Sep-11 100 05-Feb-12 08-Dec-11 38 05-May-12 27-Mar-12 25.00 12-May-12 05-Apr-12 19-May-12 05-Aug-12 26-May-12 12-Aug-12 03-Jul-12 19-Sep-12 02-Aug-12 19-Oct-12 17-Aug-12 03-Nov-12 17-Aug-12
SCHNEIDER ELECTRIC ENERGY FOB INTERNATIONAL SEAPORT, UK /
UB00-P-NNTS-000-1001 Substation Package SS-5 ELECTRICAL K-ZE-091901 SF0004 UK LTD TURKEY 23-Mar-12 16-Jan-11 01-Feb-11 100 17-Feb-11 14-Mar-11 100 24-Mar-11 16-Mar-11 100 31-Mar-11 16-Mar-11 100 15-May-11 23-Mar-11 100 29-Jun-11 13-Jul-11 49 07-Nov-11 26-Sep-11 100 06-Jan-12 14-Dec-11 38 05-Apr-12 11-Apr-12 25.00 12-Apr-12 20-Apr-12 19-Apr-12 05-Aug-12 26-Apr-12 12-Aug-12 03-Jun-12 19-Sep-12 03-Jul-12 19-Oct-12 18-Jul-12 03-Nov-12 18-Jul-12
SCHNEIDER ELECTRIC ENERGY FOB INTERNATIONAL SEAPORT, UK /
UB00-P-NNTS-000-1001 Substation Package SS-6 ELECTRICAL K-ZE-091902 SF0004 UK LTD TURKEY 23-Jun-12 16-Jan-11 01-Feb-11 100 17-Feb-11 14-Mar-11 100 24-Mar-11 16-Mar-11 100 31-Mar-11 16-Mar-11 100 15-May-11 23-Mar-11 100 29-Jun-11 13-Jul-11 49 07-Dec-11 26-Sep-11 100 05-Feb-12 14-Dec-11 38 05-May-12 11-Apr-12 25.00 12-May-12 20-Apr-12 19-May-12 15-Sep-12 26-May-12 22-Sep-12 03-Jul-12 30-Oct-12 02-Aug-12 29-Nov-12 17-Aug-12 14-Dec-12 17-Aug-12
SCHNEIDER ELECTRIC ENERGY FOB INTERNATIONAL SEAPORT, UK /
UB00-P-NNTS-000-1001 Substation Package SS-7 ELECTRICAL K-ZE-091903 SF0004 UK LTD TURKEY 23-Jun-12 16-Jan-11 01-Feb-11 100 17-Feb-11 14-Mar-11 100 24-Mar-11 16-Mar-11 100 31-Mar-11 16-Mar-11 100 15-May-11 23-Mar-11 100 29-Jun-11 13-Jul-11 49 07-Dec-11 26-Sep-11 100 05-Feb-12 14-Dec-11 38 05-May-12 11-Apr-12 25.00 12-May-12 20-Apr-12 19-May-12 15-Sep-12 26-May-12 22-Sep-12 03-Jul-12 30-Oct-12 02-Aug-12 29-Nov-12 17-Aug-12 14-Dec-12 17-Aug-12
SCHNEIDER ELECTRIC ENERGY FOB INTERNATIONAL SEAPORT, UK /
UB00-P-NNTS-000-1001 Substation Package SS-1 ELECTRICAL H-ZE-091005 SF0004 UK LTD TURKEY 23-Mar-12 16-Jan-11 01-Feb-11 100 17-Feb-11 14-Mar-11 100 24-Mar-11 16-Mar-11 100 31-Mar-11 16-Mar-11 100 15-May-11 23-Mar-11 100 29-Jun-11 28-Jun-11 49 07-Nov-11 26-Sep-11 100 06-Jan-12 05-Dec-11 38 05-Apr-12 18-Mar-12 25.00 12-Apr-12 26-Mar-12 19-Apr-12 05-Jun-12 26-Apr-12 12-Jun-12 03-Jun-12 20-Jul-12 03-Jul-12 19-Aug-12 18-Jul-12 03-Sep-12 18-Jul-12
SCHNEIDER ELECTRIC ENERGY FOB INTERNATIONAL SEAPORT, UK /
UB00-P-NNTS-000-1001 Substation Package SS-4 ELECTRICAL H-ZE-091012 SF0004 UK LTD TURKEY 23-Mar-12 16-Jan-11 01-Feb-11 100 17-Feb-11 14-Mar-11 100 24-Mar-11 16-Mar-11 100 31-Mar-11 16-Mar-11 100 15-May-11 23-Mar-11 100 29-Jun-11 13-Jul-11 49 07-Nov-11 26-Sep-11 100 06-Jan-12 14-Dec-11 38 05-Apr-12 11-Apr-12 25.00 12-Apr-12 20-Apr-12 19-Apr-12 05-Aug-12 26-Apr-12 12-Aug-12 03-Jun-12 19-Sep-12 03-Jul-12 19-Oct-12 18-Jul-12 03-Nov-12 18-Jul-12
SCHNEIDER ELECTRIC ENERGY FOB INTERNATIONAL SEAPORT, UK /
UB00-P-NNTS-000-1001 Substation Package SS-8 ELECTRICAL L-ZE-091901 SF0004 UK LTD TURKEY 23-Jun-12 16-Jan-11 01-Feb-11 100 17-Feb-11 14-Mar-11 100 24-Mar-11 16-Mar-11 100 31-Mar-11 16-Mar-11 100 15-May-11 23-Mar-11 100 29-Jun-11 13-Jul-11 49 07-Dec-11 26-Sep-11 100 05-Feb-12 14-Dec-11 38 05-May-12 11-Apr-12 25.00 12-May-12 20-Apr-12 19-May-12 15-Sep-12 26-May-12 22-Sep-12 03-Jul-12 30-Oct-12 02-Aug-12 29-Nov-12 17-Aug-12 14-Dec-12 17-Aug-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL H-ET-081001A SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL H-ET-081001B SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL H-ET-081002 SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL H-ET-081007 SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL H-ET-081003 SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL H-ET-081008 SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL L-ET-081905 SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL L-ET-081904 SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL K-ET-081901A SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL K-ET-081901B SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL K-ET-081904 SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL K-ET-081903 SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL K-ET-081902A SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1002 Power & Distribution Transformers ELECTRICAL K-ET-081902B SF0004 UK LTD 24-Jan-12 17-Mar-11 01-Feb-11 100 26-Apr-11 14-Mar-11 100 24-May-11 16-Mar-11 100 31-May-11 16-Mar-11 100 15-Jul-11 23-Mar-11 100 29-Aug-11 28-Jul-11 49 08-Sep-11 26-Sep-11 100 08-Oct-11 10-Nov-11 38 06-Jan-12 23-Mar-12 25.00 13-Jan-12 02-Apr-12 20-Jan-12 28-Feb-12 27-Jan-12 06-Mar-12 05-Mar-12 13-Apr-12 04-Apr-12 13-May-12 19-Apr-12 28-May-12 19-Apr-12
SCHNEIDER ELECTRIC ENERGY
UB00-P-NNTS-000-1003 Modification of MV Switchgear ELECTRICAL K-EJ-081701 SF0030 UK LTD FOB SUR MER FRANCE BASIS 04-Jan-12 16-Apr-11 02-Mar-11 100 16-May-11 06-Apr-11 100 23-Jun-11 16-May-11 100 30-Jun-11 16-May-11 100 14-Aug-11 16-May-11 100 28-Sep-11 10-Sep-11 25 03-Oct-11 20-Oct-11 100 07-Nov-11 20-Oct-11 20 05-Feb-12 14-Feb-12 12-Feb-12 23-Feb-12 19-Feb-12 15-Mar-12 26-Feb-12 22-Mar-12 04-Apr-12 29-Apr-12 04-May-12 29-May-12 19-May-12 13-Jun-12 19-May-12

UB00-P-NNTS-000-1004 Emergency Diesel Generators ELECTRICAL H-XN-084003 SF0024 CUMMINS MIDDLE EAST FZE FOB INTERNATIONAL SEAPORT, ITALY 15-May-12 16-Jan-11 09-Feb-11 100 17-Feb-11 22-Mar-11 100 18-May-11 07-Jun-11 100 25-May-11 18-Jul-11 100 09-Jul-11 25-Jul-11 100 23-Aug-11 27-Oct-11 16.5 02-Nov-11 15-Jan-12 32 31-Dec-11 21-Mar-12 25 30-Mar-12 30-Jun-12 06-Apr-12 08-Jul-12 13-Apr-12 15-Jul-12 20-Apr-12 22-Jul-12 28-May-12 29-Aug-12 27-Jun-12 28-Sep-12 12-Jul-12 23-Oct-12 12-Jul-12

UB00-P-NNTS-000-1004 Emergency Diesel Generators ELECTRICAL H-XN-084002 SF0024 CUMMINS MIDDLE EAST FZE FOB INTERNATIONAL SEAPORT, ITALY 15-May-12 16-Jan-11 09-Feb-11 100 17-Feb-11 22-Mar-11 100 18-May-11 07-Jun-11 100 25-May-11 18-Jul-11 100 09-Jul-11 25-Jul-11 100 23-Aug-11 27-Oct-11 16.5 02-Nov-11 15-Jan-12 32 31-Dec-11 21-Mar-12 25 30-Mar-12 30-Jun-12 06-Apr-12 08-Jul-12 13-Apr-12 15-Jul-12 20-Apr-12 22-Jul-12 28-May-12 29-Aug-12 27-Jun-12 28-Sep-12 12-Jul-12 23-Oct-12 12-Jul-12

UB00-P-NNTS-000-1004 Emergency Diesel Generators ELECTRICAL H-XN-084001 SF0024 CUMMINS MIDDLE EAST FZE FOB INTERNATIONAL SEAPORT, ITALY 13-Jun-12 16-Jan-11 09-Feb-11 100 17-Feb-11 22-Mar-11 100 18-May-11 07-Jun-11 100 25-May-11 18-Jul-11 100 09-Jul-11 25-Jul-11 100 23-Aug-11 27-Oct-11 16.5 02-Nov-11 15-Jan-12 32 31-Dec-11 21-Mar-12 25 30-Mar-12 30-Jun-12 06-Apr-12 08-Jul-12 13-Apr-12 15-Jul-12 20-Apr-12 22-Jul-12 28-May-12 29-Aug-12 27-Jun-12 28-Sep-12 12-Jul-12 13-Oct-12 12-Jul-12
UB00-P-NNTS-000-1005 Modification of LV Switchgear ELECTRICAL L-EL-082701 16-Apr-11 02-Mar-11 100 16-May-11 06-Apr-11 100 23-Jun-11 24-Dec-11 30-Jun-11 31-Dec-11 14-Aug-11 14-Feb-12 28-Sep-11 14-Apr-12 03-Oct-11 14-May-12 07-Nov-11 13-Jun-12 05-Feb-12 17-Aug-12 12-Feb-12 24-Aug-12 19-Feb-12 31-Aug-12 26-Feb-12 07-Sep-12 04-Apr-12 15-Oct-12 04-May-12 14-Nov-12 19-May-12 29-Nov-12 19-May-12
UB00-P-NNTS-000-1006 Solar System ELECTRICAL UB00-P-NNTS-000-1006-169 30-May-11 07-Jun-11 100 29-Jun-11 08-Jul-11 100 06-Aug-11 24-Dec-11 13-Aug-11 31-Dec-11 27-Sep-11 14-Feb-12 22-Feb-12 12-Dec-12 03-Mar-12 22-Dec-12 10-Mar-12 29-Dec-12 17-Mar-12 05-Jan-13 24-Apr-12 12-Feb-13 24-May-12 14-Mar-13 08-Jun-12 29-Mar-13 08-Jun-12
UB00-P-NNTS-000-1007 AC UPS System ELECTRICAL UB00-P-NNTS-000-1007-170 SF0085 GUTOR ELECTRONIC LLC 16-May-11 20-Jun-11 100 15-Jun-11 07-Jul-11 100 23-Jul-11 27-Sep-11 100 30-Jul-11 02-Oct-11 100 13-Sep-11 16-Nov-11 06-Jan-12 10-Mar-12 13-Jan-12 17-Mar-12 20-Jan-12 24-Mar-12 27-Jan-12 31-Mar-12 05-Mar-12 08-May-12 04-Apr-12 07-Jun-12 19-Apr-12 22-Jun-12 19-Apr-12
MV/LV Power, Control & Earthing Cables -
UB00-P-NNTS-000-1008 TOP UP ELECTRICAL UB00-P-NNTS-000-1008-8 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
TURK PRYSMIAN KABLO VE
UB00-P-NNTS-000-1008 MV/LV Power, Control & Earthing Cables ELECTRICAL LOT : 001 SF0032 SISTEMLERI AS FCA MUDANYA, BURSA, TURKEY 13-Nov-11 06-Mar-11 20-Mar-11 100 05-Apr-11 02-Apr-11 100 13-May-11 23-Jun-11 100 20-May-11 14-Jul-11 100 04-Jul-11 14-Jul-11 100 27-Oct-11 10-Feb-12 43.20 03-Nov-11 19-Feb-12 10-Nov-11 28-Feb-12 17-Nov-11 06-Mar-12 25-Dec-11 13-Apr-12 24-Jan-12 13-May-12 08-Feb-12 28-May-12 08-Feb-12

UB00-P-NNTS-000-1009 Lighting Fixtures (Safe Area) - TOP UP ELECTRICAL UB00-P-NNTS-000-1009-9 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
UB00-P-NNTS-000-1009 Lighting Fixtures (Safe Area) ELECTRICAL UB00-P-NNTS-000-1009-171 SF0092 ATX-EGS ELECTRICAL GROUP 16-May-11 21-Jun-11 100 15-Jun-11 11-Jul-11 100 23-Jul-11 09-Oct-11 100 30-Jul-11 12-Oct-11 100 13-Sep-11 26-Nov-11 07-Dec-11 19-Feb-12 14-Dec-11 26-Feb-12 21-Dec-11 04-Mar-12 28-Dec-11 11-Mar-12 04-Feb-12 18-Apr-12 05-Mar-12 18-May-12 20-Mar-12 02-Jun-12 20-Mar-12
UB00-P-NNTS-000-1010 Junction Boxes - TOP UP ELECTRICAL UB00-P-NNTS-000-1010-10 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
UB00-P-NNTS-000-1010 Junction Boxes ELECTRICAL UB00-P-NNTS-000-1010-172 SF0081 R. STAHL MIDDLE EAST FZE 16-May-11 18-Jul-11 100 15-Jun-11 10-Aug-11 100 23-Jul-11 14-Oct-11 100 30-Jul-11 20-Oct-11 100 13-Sep-11 04-Dec-11 07-Dec-11 27-Feb-12 14-Dec-11 05-Mar-12 21-Dec-11 12-Mar-12 28-Dec-11 19-Mar-12 04-Feb-12 26-Apr-12 05-Mar-12 26-May-12 20-Mar-12 10-Jun-12 20-Mar-12
UB00-P-NNTS-000-1011 Lighting Poles - TOP UP ELECTRICAL UB00-P-NNTS-000-1011-11 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
VALMONT - MITAS POLES
UB00-P-NNTS-000-1011 Lighting Poles ELECTRICAL LOT : 001 SF0090 INDUSTRIES FOB MERSIN PORT, TURKEY 16-Dec-11 16-May-11 20-Jun-11 100 15-Jun-11 07-Jul-11 100 23-Jul-11 27-Sep-11 100 30-Jul-11 05-Oct-11 100 13-Sep-11 26-Oct-11 100 07-Dec-11 09-Dec-11 14-Dec-11 09-Dec-11 21-Dec-11 16-Dec-11 28-Dec-11 16-Dec-11 04-Feb-12 16-Dec-11 05-Mar-12 16-Dec-11 20-Mar-12 16-Dec-11 20-Mar-12
Earthing & Lightning Protection Materials
UB00-P-NNTS-000-1012 - TOP UP ELECTRICAL UB00-P-NNTS-084-1012-12 FCA SELLER'S WORKS, PINXTON, UK 05-Jan-12 05-Jan-12 16-Jul-12 16-Jul-12 23-Jul-12 23-Jul-12 30-Jul-12 30-Jul-12 06-Aug-12 06-Aug-12 13-Sep-12 13-Sep-12 13-Oct-12 13-Oct-12 28-Oct-12 28-Oct-12 28-Oct-12

UB00-P-NNTS-000-1012 Earthing & Lightning Protection Materials ELECTRICAL LOT : 001 SF0084 KINGSMILL INDUSTRIES (UK) LTD FCA SELLER'S WORKS, PINXTON, UK 29-Nov-11 16-May-11 20-Jun-11 100 15-Jun-11 05-Jul-11 100 23-Jul-11 29-Sep-11 100 30-Jul-11 03-Oct-11 100 13-Sep-11 03-Oct-11 100 07-Dec-11 23-Nov-11 13.00 14-Dec-11 23-Nov-11 21-Dec-11 29-Nov-11 28-Dec-11 29-Nov-11 04-Feb-12 29-Nov-11 05-Mar-12 29-Nov-11 20-Mar-12 29-Nov-11 20-Mar-12
Welding & Convenience Sockets -
UB00-P-NNTS-000-1013 Hazardous Area ELECTRICAL LOT : 002 SF0074 ATX-EGS ELECTRICAL GROUP NOT APPLICABLE 06-Nov-11 16-May-11 05-Jun-11 100 15-Jun-11 14-Jun-11 100 23-Jul-11 29-Aug-11 100 30-Jul-11 11-Sep-11 100 13-Sep-11 11-Sep-11 100 07-Dec-11 10-Mar-12 13.00 14-Dec-11 10-Mar-12 21-Dec-11 30-Mar-12 28-Dec-11 30-Mar-12 04-Feb-12 30-Mar-12 05-Mar-12 30-Mar-12 20-Mar-12 30-Mar-12 20-Mar-12
Welding & Convenience Sockets -
UB00-P-NNTS-000-1013 Hazardous Area ELECTRICAL LOT : 001 SF1015 COOPER CROUSE-HINDS LLC NOT APPLICABLE 16-May-11 05-Jun-11 100 15-Jun-11 14-Jun-11 100 23-Jul-11 29-Aug-11 100 30-Jul-11 11-Sep-11 100 13-Sep-11 03-Oct-11 100 07-Dec-11 02-Oct-11 14-Dec-11 02-Oct-11 21-Dec-11 02-Oct-11 28-Dec-11 02-Oct-11 04-Feb-12 02-Oct-11 05-Mar-12 02-Oct-11 20-Mar-12 02-Oct-11 20-Mar-12
Welding & Convenience Sockets -
UB00-P-NNTS-000-1013 Hazardous Area ELECTRICAL LOT : 003 SF6006 HOCKWAY MIDDLE EAST FZC NOT APPLICABLE 16-May-11 05-Jun-11 100 15-Jun-11 14-Jun-11 100 23-Jul-11 29-Aug-11 100 30-Jul-11 11-Sep-11 100 13-Sep-11 11-Sep-11 100 07-Dec-11 20-Nov-11 14-Dec-11 20-Nov-11 21-Dec-11 20-Nov-11 28-Dec-11 20-Nov-11 04-Feb-12 20-Nov-11 05-Mar-12 20-Nov-11 20-Mar-12 20-Nov-11 20-Mar-12
UB00-P-NNTS-000-1015 Remote Control Units ELECTRICAL UB00-P-NNTS-084-1015-3 SF0095 R. STAHL MIDDLE EAST FZE 16-May-11 19-Jul-11 100 15-Jun-11 08-Aug-11 100 23-Jul-11 11-Oct-11 100 30-Jul-11 17-Oct-11 100 13-Sep-11 01-Dec-11 07-Dec-11 24-Feb-12 14-Dec-11 02-Mar-12 21-Dec-11 09-Mar-12 28-Dec-11 16-Mar-12 04-Feb-12 23-Apr-12 05-Mar-12 23-May-12 20-Mar-12 07-Jun-12 20-Mar-12
UB00-P-NNTS-000-1016 Termination Kits ELECTRICAL LOT : 001 SF0077 DANWAY LLC FCA JEBEL ALI SEAPORT, UAE 15-Jun-11 12-Jun-11 100 15-Jul-11 05-Jul-11 100 22-Aug-11 15-Sep-11 100 29-Aug-11 22-Sep-11 100 13-Oct-11 22-Sep-11 100 06-Jan-12 12-Mar-12 13.00 13-Jan-12 12-Mar-12 20-Jan-12 30-Mar-12 27-Jan-12 30-Mar-12 05-Mar-12 30-Mar-12 04-Apr-12 30-Mar-12 19-Apr-12 30-Mar-12 19-Apr-12
Welding & Convenience Socket (Safe
UB00-P-NNTS-000-1017 Area) ELECTRICAL UB00-P-NNTS-084-1017-5 16-May-11 06-Nov-11 15-Jun-11 06-Dec-11 23-Jul-11 13-Jan-12 30-Jul-11 20-Jan-12 13-Sep-11 05-Mar-12 07-Dec-11 06-May-12 14-Dec-11 13-May-12 21-Dec-11 20-May-12 28-Dec-11 27-May-12 04-Feb-12 04-Jul-12 05-Mar-12 03-Aug-12 20-Mar-12 18-Aug-12 20-Mar-12
Welding & Convenience Socket (Safe
UB00-P-NNTS-000-1017 Area) - TOP UP ELECTRICAL UB00-P-NNTS-084-1017-13 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
UB00-P-NNTS-000-1018 Cable Glands ELECTRICAL UB00-P-NNTS-084-1018-6 16-May-11 14-Sep-11 100 15-Jun-11 29-Sep-11 100 23-Jul-11 24-Dec-11 30-Jul-11 31-Dec-11 13-Sep-11 14-Feb-12 07-Dec-11 21-Apr-12 14-Dec-11 28-Apr-12 21-Dec-11 05-May-12 28-Dec-11 12-May-12 04-Feb-12 19-Jun-12 05-Mar-12 19-Jul-12 20-Mar-12 03-Aug-12 20-Mar-12
UB00-P-NNTS-000-1019 Heat Tracing System ELECTRICAL UB00-P-NNTS-084-1019-7 13-Oct-11 05-Nov-11 12-Nov-11 05-Dec-11 20-Dec-11 20-Dec-11 27-Dec-11 27-Dec-11 10-Feb-12 10-Feb-12 05-May-12 05-May-12 12-May-12 12-May-12 19-May-12 19-May-12 26-May-12 26-May-12 03-Jul-12 03-Jul-12 02-Aug-12 02-Aug-12 17-Aug-12 17-Aug-12 17-Aug-12
YOKOGAWA EUROPE SOLUTIONS FOB INTERNATIONAL SEAPORT, THE
UU00-P-KKTS-000-1001 Integrated Control System (ICS) INSTRUMENTATION ICS-2 SF0010 B.V. NETHERLANDS 28-Aug-12 15-Feb-11 28-Feb-11 100 17-Mar-11 13-Mar-11 100 23-Apr-11 24-Apr-11 100 30-Apr-11 25-Apr-11 100 14-Jun-11 06-May-11 100 29-Jul-11 17-Aug-11 54 06-Jan-12 07-Mar-12 42 06-Mar-12 22-May-12 04-Jun-12 13-Sep-12 11-Jun-12 22-Sep-12 18-Jun-12 30-Sep-12 25-Jun-12 07-Oct-12 02-Aug-12 14-Nov-12 01-Sep-12 14-Dec-12 16-Sep-12 29-Dec-12 16-Sep-12
YOKOGAWA EUROPE SOLUTIONS FOB INTERNATIONAL SEAPORT, THE
UU00-P-KKTS-000-1001 Integrated Control System (ICS) INSTRUMENTATION ICS-1 SF0010 B.V. NETHERLANDS 07-Sep-12 15-Feb-11 28-Feb-11 100 17-Mar-11 13-Mar-11 100 23-Apr-11 24-Apr-11 100 30-Apr-11 25-Apr-11 100 14-Jun-11 06-May-11 100 29-Jul-11 17-Aug-11 54 06-Jan-12 07-Mar-12 42 06-Mar-12 22-May-12 04-Jun-12 13-Sep-12 11-Jun-12 22-Sep-12 18-Jun-12 30-Sep-12 25-Jun-12 07-Oct-12 02-Aug-12 14-Nov-12 01-Sep-12 14-Dec-12 16-Sep-12 29-Dec-12 16-Sep-12
YOKOGAWA EUROPE SOLUTIONS FOB INTERNATIONAL SEAPORT, THE
UU00-P-KKTS-000-1001 RTU for WHCP - ICSS INSTRUMENTATION ICS-RTU SF0010 B.V. NETHERLANDS 28-Aug-12 06-May-11 100 06-May-11 100 06-May-11 100 06-May-11 100 06-May-11 100 06-May-11 54 06-May-11 42 06-May-11 06-May-11 06-May-11 30-Sep-12 07-Oct-12 14-Nov-12 14-Dec-12 29-Dec-12
WEATHERFORD OIL TOOLS
UU00-P-KKTS-000-1002 Wellhead Control/Solar/Hydraulic Panels INSTRUMENTATION LOT : 001 SF0057 MIDDLE EAST LTD CAC INC. FCA SELLER'S WORKS, JEBEL ALI, UAE 08-Jul-12 17-Mar-11 13-Mar-11 100 16-Apr-11 28-Mar-11 100 24-May-11 28-Jul-11 100 31-May-11 11-Aug-11 100 15-Jul-11 21-Aug-11 100 07-Dec-11 04-Aug-12 7.00 14-Dec-11 04-Aug-12 21-Dec-11 30-Aug-12 28-Dec-11 30-Aug-12 04-Feb-12 30-Aug-12 05-Mar-12 30-Aug-12 20-Mar-12 30-Aug-12 20-Mar-12
Leak Detection System (LDS) & Fibre SENSOR HIGHWAY LIMITED
Optics Pipeline Integrity Monitoring (SCHLUMBERGER),ATMOS
UU00-P-KKTS-000-1003 System (FOPIMS) INSTRUMENTATION UU00-P-KKTS-000-1003-15 INTERNATIONAL LIMITED
SF1016,SF0083,SF0086 16-Apr-11 15-May-11 100 16-May-11 14-Jun-11 100 23-Jun-11 26-Sep-11 100 30-Jun-11 02-Oct-11 100 14-Aug-11 16-Nov-11 07-Dec-11 10-Mar-12 14-Dec-11 17-Mar-12 21-Dec-11 24-Mar-12 28-Dec-11 31-Mar-12 04-Feb-12 08-May-12 05-Mar-12 07-Jun-12 20-Mar-12 22-Jun-12 20-Mar-12
Condition Performance Monitoring
UU00-P-KKTS-000-1004 System (CPMS) INSTRUMENTATION UU00-P-KKTS-000-1004-16 15-Jul-11 07-Aug-11 100 14-Aug-11 30-Oct-11 21-Sep-11 07-Dec-11 28-Sep-11 14-Dec-11 12-Nov-11 28-Jan-12 06-Mar-12 30-May-12 13-Mar-12 06-Jun-12 20-Mar-12 13-Jun-12 27-Mar-12 20-Jun-12 04-May-12 28-Jul-12 03-Jun-12 27-Aug-12 18-Jun-12 11-Sep-12 18-Jun-12
UU00-P-KKTS-000-1005 Flow Computer INSTRUMENTATION UU00-P-KKTS-000-1005-17 15-Jun-11 17-Aug-11 100 15-Jul-11 14-Sep-11 100 22-Aug-11 24-Dec-11 29-Aug-11 31-Dec-11 13-Oct-11 14-Feb-12 05-Feb-12 22-Sep-12 12-Feb-12 29-Sep-12 19-Feb-12 06-Oct-12 26-Feb-12 13-Oct-12 04-Apr-12 20-Nov-12 04-May-12 20-Dec-12 19-May-12 04-Jan-13 19-May-12
UU00-P-KKTS-000-1006 Control Valves INSTRUMENTATION UU00-P-KKTS-000-1006-84 SF0078 KOSO KENT INTROL LIMITED 16-May-11 31-May-11 100 15-Jun-11 27-Jun-11 100 23-Jul-11 25-Aug-11 100 30-Jul-11 09-Oct-11 100 13-Sep-11 23-Nov-11 04-Jun-12 14-Aug-12 11-Jun-12 21-Aug-12 18-Jun-12 28-Aug-12 25-Jun-12 04-Sep-12 02-Aug-12 12-Oct-12 01-Sep-12 11-Nov-12 16-Sep-12 26-Nov-12 16-Sep-12
UU00-P-KKTS-000-1007 Actuated Isolation Valves INSTRUMENTATION UU00-P-KKTS-000-1007-18 16-Apr-11 16-May-11 100 16-May-11 16-Jun-11 100 23-Jun-11 31-Oct-11 30-Jun-11 07-Nov-11 14-Aug-11 22-Dec-11 06-Jan-12 17-Dec-12 13-Jan-12 24-Dec-12 20-Jan-12 31-Dec-12 27-Jan-12 07-Jan-13 05-Mar-12 14-Feb-13 04-Apr-12 16-Mar-13 19-Apr-12 31-Mar-13 19-Apr-12

UU00-P-KKTS-000-1008 Choke Valve with Hydraulic Actuators INSTRUMENTATION UU00-P-KKTS-000-1008-19 01-Sep-11 23-Oct-11 100 01-Oct-11 22-Nov-11 08-Nov-11 24-Jan-12 15-Nov-11 31-Jan-12 30-Dec-11 16-Mar-12 24-Mar-12 09-Jun-12 31-Mar-12 16-Jun-12 07-Apr-12 23-Jun-12 14-Apr-12 30-Jun-12 22-May-12 07-Aug-12 21-Jun-12 06-Sep-12 06-Jul-12 21-Sep-12 06-Jul-12
UU00-P-KKTS-000-1009 Ball Control Valves INSTRUMENTATION LOT : 001 SF0068 PIBIVIESSE SRL FOB GENOA PORT, ITALY 10-Jun-12 16-May-11 29-May-11 100 15-Jun-11 14-Jun-11 100 23-Jul-11 25-Aug-11 100 30-Jul-11 04-Sep-11 100 13-Sep-11 04-Sep-11 100 05-Apr-12 24-Jun-12 7.00 12-Apr-12 02-Jul-12 19-Apr-12 10-Jul-12 26-Apr-12 17-Jul-12 03-Jun-12 24-Aug-12 03-Jul-12 23-Sep-12 18-Jul-12 08-Oct-12 18-Jul-12
UU00-P-KKTS-000-1010 Shutdown Valves INSTRUMENTATION UU00-P-KKTS-000-1010-85 14-Apr-11 05-May-11 100 14-May-11 05-Nov-11 07-Jun-11 29-Nov-11 14-Jun-11 06-Dec-11 29-Jul-11 20-Jan-12 05-Feb-12 29-Jul-12 12-Feb-12 05-Aug-12 19-Feb-12 12-Aug-12 26-Feb-12 19-Aug-12 04-Apr-12 26-Sep-12 04-May-12 26-Oct-12 19-May-12 10-Nov-12 19-May-12
SERCK AUDCO VALVES
UU00-P-KKTS-000-1011 Motor Operated Valve (Plug Type) INSTRUMENTATION LOT : 001 SF0061 (FLOWSERVE) FOB INTERNATIONAL SEAPORT UK 19-Apr-12 16-Apr-11 20-Apr-11 100 16-May-11 18-May-11 100 23-Jun-11 01-Sep-11 100 30-Jun-11 01-Sep-11 100 14-Aug-11 01-Sep-11 100 05-May-12 06-Jun-12 17.00 12-May-12 12-Jun-12 19-May-12 19-Jun-12 26-May-12 26-Jun-12 03-Jul-12 03-Aug-12 02-Aug-12 02-Sep-12 17-Aug-12 17-Sep-12 17-Aug-12
Block / Gas Over Oil Valves - (N033-BV-
UU00-P-KKTS-000-1012 065)-32" INSTRUMENTATION UU00-P-KKTS-000-1012-22 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
Block / Gas Over Oil Valves - (X033-BV-
UU00-P-KKTS-000-1012 171)-24" INSTRUMENTATION UU00-P-KKTS-000-1012-22-2 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
Block / Gas Over Oil Valves - (X033-BV-
UU00-P-KKTS-000-1012 191)-32" INSTRUMENTATION UU00-P-KKTS-000-1012-22-3 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
Block / Gas Over Oil Valves - (X033-BV-
UU00-P-KKTS-000-1012 192)-32" INSTRUMENTATION UU00-P-KKTS-000-1012-22-4 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
Block / Gas Over Oil Valves - (X033-BV-
UU00-P-KKTS-000-1012 193)-32" INSTRUMENTATION UU00-P-KKTS-000-1012-22-5 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
Block / Gas Over Oil Valves - (X033-BV-
UU00-P-KKTS-000-1012 141)-24" INSTRUMENTATION UU00-P-KKTS-000-1012-22-6 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
Block / Gas Over Oil Valves - (X033-BV-
UU00-P-KKTS-000-1012 131)-24" INSTRUMENTATION UU00-P-KKTS-000-1012-22-7 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
Block / Gas Over Oil Valves - (X033-BV-
UU00-P-KKTS-000-1012 045)-32" INSTRUMENTATION UU00-P-KKTS-000-1012-22-8 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
Block / Gas Over Oil Valves - (X033-BV-
UU00-P-KKTS-000-1012 035)-32" INSTRUMENTATION UU00-P-KKTS-000-1012-22-9 17-Mar-11 02-May-11 100 16-Apr-11 20-May-11 100 24-May-11 25-Oct-11 100 31-May-11 01-Nov-11 15-Jul-11 16-Dec-11 05-Feb-12 18-Sep-12 12-Feb-12 25-Sep-12 19-Feb-12 02-Oct-12 26-Feb-12 09-Oct-12 04-Apr-12 16-Nov-12 04-May-12 16-Dec-12 19-May-12 31-Dec-12 19-May-12
UU00-P-KKTS-000-1013 Pressure Relief Valves INSTRUMENTATION UU00-P-KKTS-000-1013-23 14-Jun-11 07-Jul-11 100 14-Jul-11 27-Jul-11 100 21-Aug-11 22-Dec-11 30-Aug-11 31-Dec-11 14-Oct-11 14-Feb-12 26-Apr-12 22-Sep-12 03-May-12 29-Sep-12 10-May-12 06-Oct-12 17-May-12 13-Oct-12 24-Jun-12 20-Nov-12 24-Jul-12 20-Dec-12 08-Aug-12 04-Jan-13 08-Aug-12
UU00-P-KKTS-000-1014 Pressure / DP Gauges INSTRUMENTATION UU00-P-KKTS-000-1014-86 13-Sep-11 15-Dec-11 13-Oct-11 14-Jan-12 20-Nov-11 21-Feb-12 27-Nov-11 28-Feb-12 11-Jan-12 13-Apr-12 05-May-12 06-Aug-12 12-May-12 13-Aug-12 19-May-12 20-Aug-12 26-May-12 27-Aug-12 03-Jul-12 04-Oct-12 02-Aug-12 03-Nov-12 17-Aug-12 18-Nov-12 17-Aug-12
UU00-P-KKTS-000-1015 Temperature Gauges & Thermowells INSTRUMENTATION UU00-P-KKTS-000-1015-222 13-Sep-11 15-Dec-11 13-Oct-11 14-Jan-12 20-Nov-11 21-Feb-12 27-Nov-11 28-Feb-12 11-Jan-12 13-Apr-12 05-May-12 06-Aug-12 12-May-12 13-Aug-12 19-May-12 20-Aug-12 26-May-12 27-Aug-12 03-Jul-12 04-Oct-12 02-Aug-12 03-Nov-12 17-Aug-12 18-Nov-12 17-Aug-12
UU00-P-KKTS-000-1016 Level Gauges INSTRUMENTATION UU00-P-KKTS-000-1016-24 SF0087 CESARE BONETTI SPA 13-Sep-11 07-Jul-11 100 13-Oct-11 04-Aug-11 100 20-Nov-11 27-Sep-11 100 27-Nov-11 03-Oct-11 100 11-Jan-12 17-Nov-11 05-May-12 11-Mar-12 12-May-12 18-Mar-12 19-May-12 25-Mar-12 26-May-12 01-Apr-12 03-Jul-12 09-May-12 02-Aug-12 08-Jun-12 17-Aug-12 23-Jun-12 17-Aug-12

UU00-P-KKTS-000-1017 Electronic Transmitters & Rotameters INSTRUMENTATION UU00-P-KKTS-000-1017-25 11-Sep-11 14-Nov-11 11-Oct-11 14-Dec-11 18-Nov-11 24-Jan-12 25-Nov-11 31-Jan-12 09-Jan-12 16-Mar-12 05-May-12 28-Jul-12 12-May-12 04-Aug-12 19-May-12 11-Aug-12 26-May-12 18-Aug-12 03-Jul-12 25-Sep-12 02-Aug-12 25-Oct-12 17-Aug-12 09-Nov-12 17-Aug-12
UU00-P-KKTS-000-1018 Level Transmitter Radar Type INSTRUMENTATION LOT : 001 SF0073 EMERSON FZE FOB JEBEL ALI SEAPORT, UAE 20-Dec-11 16-May-11 23-May-11 100 15-Jun-11 14-Jun-11 100 23-Jul-11 12-Sep-11 100 30-Jul-11 13-Sep-11 100 13-Sep-11 13-Sep-11 100 06-Jan-12 19-Jan-12 13.00 13-Jan-12 19-Jan-12 20-Jan-12 30-Jan-12 27-Jan-12 30-Jan-12 05-Mar-12 30-Jan-12 04-Apr-12 30-Jan-12 19-Apr-12 30-Jan-12 19-Apr-12
UU00-P-KKTS-000-1021 Flow Assemblies INSTRUMENTATION UU00-P-KKTS-000-1021-28 16-May-11 01-Sep-11 100 15-Jun-11 22-Sep-11 100 23-Jul-11 24-Dec-11 30-Jul-11 31-Dec-11 13-Sep-11 14-Feb-12 06-Jan-12 28-Jul-12 13-Jan-12 04-Aug-12 20-Jan-12 11-Aug-12 27-Jan-12 18-Aug-12 05-Mar-12 25-Sep-12 04-Apr-12 25-Oct-12 19-Apr-12 09-Nov-12 19-Apr-12
UU00-P-KKTS-000-1022 Ultrasonic Flow Meters INSTRUMENTATION UU00-P-KKTS-000-1022-88 15-Jul-11 25-Jul-11 100 14-Aug-11 17-Aug-11 100 21-Sep-11 24-Dec-11 28-Sep-11 31-Dec-11 12-Nov-11 14-Feb-12 05-May-12 25-Aug-12 12-May-12 01-Sep-12 19-May-12 08-Sep-12 26-May-12 15-Sep-12 03-Jul-12 23-Oct-12 02-Aug-12 22-Nov-12 17-Aug-12 07-Dec-12 17-Aug-12
UU00-P-KKTS-000-1023 Turbine Flow Meters INSTRUMENTATION UU00-P-KKTS-000-1023-29 15-Jul-11 30-Oct-11 14-Aug-11 24-Nov-11 21-Sep-11 24-Dec-11 28-Sep-11 31-Dec-11 12-Nov-11 14-Feb-12 05-May-12 07-Aug-12 12-May-12 14-Aug-12 19-May-12 21-Aug-12 26-May-12 28-Aug-12 03-Jul-12 05-Oct-12 02-Aug-12 04-Nov-12 17-Aug-12 19-Nov-12 17-Aug-12
UU00-P-KKTS-000-1024 Vortex Flow Meters INSTRUMENTATION UU00-P-KKTS-000-1024-30 15-Jul-11 30-Oct-11 14-Aug-11 24-Nov-11 21-Sep-11 24-Dec-11 28-Sep-11 31-Dec-11 12-Nov-11 14-Feb-12 04-Jun-12 06-Sep-12 11-Jun-12 13-Sep-12 18-Jun-12 20-Sep-12 25-Jun-12 27-Sep-12 02-Aug-12 04-Nov-12 01-Sep-12 04-Dec-12 16-Sep-12 19-Dec-12 16-Sep-12
UU00-P-KKTS-000-1025 V-Cone Flow Meters INSTRUMENTATION UU00-P-KKTS-000-1025-31 15-Jul-11 07-Aug-11 100 14-Aug-11 27-Aug-11 100 21-Sep-11 24-Dec-11 28-Sep-11 31-Dec-11 12-Nov-11 14-Feb-12 05-Feb-12 25-Aug-12 12-Feb-12 01-Sep-12 19-Feb-12 08-Sep-12 26-Feb-12 15-Sep-12 04-Apr-12 23-Oct-12 04-May-12 22-Nov-12 19-May-12 07-Dec-12 19-May-12
UU00-P-KKTS-000-1026 Magnetic Flow Meters INSTRUMENTATION UU00-P-KKTS-000-1026-89 15-Jul-11 26-Jul-11 100 14-Aug-11 01-Sep-11 100 21-Sep-11 24-Dec-11 28-Sep-11 31-Dec-11 12-Nov-11 14-Feb-12 06-Jan-12 05-May-12 13-Jan-12 12-May-12 20-Jan-12 19-May-12 27-Jan-12 26-May-12 05-Mar-12 03-Jul-12 04-Apr-12 02-Aug-12 19-Apr-12 17-Aug-12 19-Apr-12
YOKOGAWA EUROPE SOLUTIONS FOB INTERNATIONAL SEAPORT, THE
UU00-P-KKTS-000-1028 Fire & Gas Detectors INSTRUMENTATION UU00-P-KKTS-000-1028-33 SF0010 B.V. NETHERLANDS 28-Aug-12 16-Apr-11 28-Feb-11 100 16-May-11 13-Mar-11 100 23-Jun-11 24-Apr-11 100 30-Jun-11 25-Apr-11 100 14-Aug-11 06-May-11 100 07-Dec-11 19-Jul-12 14-Dec-11 08-Aug-12 21-Dec-11 28-Aug-12 28-Dec-11 04-Sep-12 04-Feb-12 12-Oct-12 05-Mar-12 11-Nov-12 20-Mar-12 26-Nov-12 20-Mar-12
UU00-P-KKTS-000-1030 Instrument Cables - TOP UP INSTRUMENTATION UU00-P-KKTS-000-1030-42 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
UU00-P-KKTS-000-1030 Instrument Cables - Lot 2 INSTRUMENTATION UU00-P-KKTS-000-1030-90-4 17-Mar-11 20-Mar-11 100 16-Apr-11 31-Mar-11 100 24-May-11 29-May-11 100 31-May-11 05-Nov-11 15-Jul-11 20-Dec-11 07-Dec-11 05-May-12 14-Dec-11 12-May-12 21-Dec-11 19-May-12 28-Dec-11 26-May-12 04-Feb-12 03-Jul-12 05-Mar-12 02-Aug-12 20-Mar-12 17-Aug-12 20-Mar-12
UU00-P-KKTS-000-1030 Instrument Cables- Lot 1 INSTRUMENTATION LOT : 001 SF0033 LEONI KERPEN GMBH FOB ANTWERP PORT, BELGIUM 30-Nov-11 17-Mar-11 20-Mar-11 100 16-Apr-11 31-Mar-11 100 24-May-11 29-May-11 100 31-May-11 09-Jun-11 100 15-Jul-11 09-Jun-11 100 07-Dec-11 14-Jan-12 50.00 14-Dec-11 22-Jan-12 21-Dec-11 30-Jan-12 28-Dec-11 06-Feb-12 04-Feb-12 15-Mar-12 05-Mar-12 14-Apr-12 20-Mar-12 29-Apr-12 20-Mar-12
UU00-P-KKTS-000-1031 Instrument Junction Boxes INSTRUMENTATION UU00-P-KKTS-000-1031-35 15-Jul-11 23-Aug-11 100 14-Aug-11 06-Sep-11 100 21-Sep-11 31-Oct-11 28-Sep-11 07-Nov-11 12-Nov-11 22-Dec-11 06-Jan-12 24-Mar-12 13-Jan-12 31-Mar-12 20-Jan-12 07-Apr-12 27-Jan-12 14-Apr-12 05-Mar-12 22-May-12 04-Apr-12 21-Jun-12 19-Apr-12 06-Jul-12 19-Apr-12
UU00-P-KKTS-000-1031 Instrument Junction Boxes - TOP UP INSTRUMENTATION UU00-P-KKTS-000-1031-43 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
UU00-P-KKTS-000-1032 Cable Glands INSTRUMENTATION UU00-P-KKTS-000-1032-36 02-May-11 14-Sep-11 100 23-May-11 25-Nov-11 21-Jun-11 24-Dec-11 28-Jun-11 31-Dec-11 12-Aug-11 14-Feb-12 07-Dec-11 10-Jun-12 14-Dec-11 17-Jun-12 21-Dec-11 24-Jun-12 28-Dec-11 01-Jul-12 04-Feb-12 08-Aug-12 05-Mar-12 07-Sep-12 20-Mar-12 22-Sep-12 20-Mar-12
UU00-P-KKTS-000-1032 Cable Glands - TOP UP INSTRUMENTATION UU00-P-KKTS-000-1032-44 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
UU00-P-KKTS-000-1033 Instrument Tubes & Fittings INSTRUMENTATION UU00-P-KKTS-000-1033-37 14-Aug-11 30-Oct-11 13-Sep-11 29-Nov-11 21-Oct-11 06-Jan-12 28-Oct-11 13-Jan-12 12-Dec-11 27-Feb-12 05-Feb-12 22-Apr-12 12-Feb-12 29-Apr-12 19-Feb-12 06-May-12 26-Feb-12 13-May-12 04-Apr-12 20-Jun-12 04-May-12 20-Jul-12 19-May-12 04-Aug-12 19-May-12

UU00-P-KKTS-000-1033 Instrument Tubes & Fittings - TOP UP INSTRUMENTATION UU00-P-KKTS-000-1033-45 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
UU00-P-KKTS-000-1034 Instrument Bulk Material INSTRUMENTATION UU00-P-KKTS-000-1034-38 14-Aug-11 10-Dec-11 13-Sep-11 09-Jan-12 21-Oct-11 16-Feb-12 28-Oct-11 23-Feb-12 12-Dec-11 08-Apr-12 06-Jan-12 03-May-12 13-Jan-12 10-May-12 20-Jan-12 17-May-12 27-Jan-12 24-May-12 05-Mar-12 01-Jul-12 04-Apr-12 31-Jul-12 19-Apr-12 15-Aug-12 19-Apr-12
UU00-P-KKTS-000-1034 Instrument Bulk Material - TOP UP INSTRUMENTATION UU00-P-KKTS-000-1034-46 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
UU00-P-KKTS-000-1035 Instrument Sunshades INSTRUMENTATION UU00-P-KKTS-000-1035-39 14-Aug-11 10-Dec-11 13-Sep-11 09-Jan-12 21-Oct-11 16-Feb-12 28-Oct-11 23-Feb-12 12-Dec-11 08-Apr-12 06-Jan-12 03-May-12 13-Jan-12 10-May-12 20-Jan-12 17-May-12 27-Jan-12 24-May-12 05-Mar-12 01-Jul-12 04-Apr-12 31-Jul-12 19-Apr-12 15-Aug-12 19-Apr-12
UU00-P-KKTS-000-1036 Instrument Tag Plates INSTRUMENTATION UU00-P-KKTS-000-1036-40 14-Aug-11 31-Jan-12 13-Sep-11 01-Mar-12 21-Oct-11 08-Apr-12 28-Oct-11 15-Apr-12 12-Dec-11 30-May-12 06-Jan-12 24-Jun-12 13-Jan-12 01-Jul-12 20-Jan-12 08-Jul-12 27-Jan-12 15-Jul-12 05-Mar-12 22-Aug-12 04-Apr-12 21-Sep-12 19-Apr-12 06-Oct-12 19-Apr-12
Cable Ladders, Trays & Accessories - TOP
UU00-P-KKTS-000-1037 UP INSTRUMENTATION UU00-P-KKTS-000-1037-47 05-Jan-12 05-Jan-12 26-Jun-12 26-Jun-12 03-Jul-12 03-Jul-12 10-Jul-12 10-Jul-12 17-Jul-12 17-Jul-12 24-Aug-12 24-Aug-12 23-Sep-12 23-Sep-12 08-Oct-12 08-Oct-12 08-Oct-12
TEKOM-PUK
ELECTROMECHANICAL INDUSTRY FOB (INTERNATIONAL) IZMIR SEAPORT,
UU00-P-KKTS-000-1037 Cable Ladders, Trays & Accessories INSTRUMENTATION LOT : 001 SF0028 AND TRADE INC. TURKEY 30-Jun-11 06-Mar-11 20-Mar-11 100 05-Apr-11 01-Apr-11 100 13-May-11 29-May-11 100 20-May-11 31-May-11 100 04-Jul-11 31-May-11 100 27-Sep-11 09-Sep-11 100.00 04-Oct-11 09-Sep-11 100.00 11-Oct-11 27-Sep-11 100.00 18-Oct-11 01-Oct-11 25-Nov-11 20-Oct-11 25-Dec-11 20-Oct-11 09-Jan-12 04-Nov-11 09-Jan-12
UU00-P-KKTS-000-1038 VESDA System INSTRUMENTATION UU00-P-KKTS-000-1038-1 01-Aug-11 100 19-Aug-11 100 24-Dec-11 31-Dec-11 14-Feb-12 25-Mar-12 01-Apr-12 08-Apr-12 15-Apr-12 23-May-12 22-Jun-12 07-Jul-12 24-Aug-12
PETROFAC FACILITIES
MANAGEMENT INTERNATIONAL
UU00-P-XXTS-000-1000 RAM Study HSE UU00-P-XXTS-000-1000-232 SF4002 LIMITED DDP PETROFAC SHARJAH OFFICE, UAE 31-Jan-11 31-Jan-11 100 02-Mar-11 28-Feb-11 100 12-Mar-11 31-Mar-11 100 14-Mar-11 31-Mar-11 100

UU00-P-XXTS-000-1001 Explosion Overpressure Study HSE UU00-P-XXTS-000-1001-233 SF4001 BMT FLUID MECHANICS LIMITED DDP PETROFAC SHARJAH OFFICE, UAE 03-Feb-11 06-Feb-11 100 05-Mar-11 17-Feb-11 100 15-Mar-11 31-Mar-11 100 17-Mar-11 31-Mar-11 100

UU00-P-XXTS-000-1002 FHA, MAR and Safety Design Case Study HSE UU00-P-XXTS-000-1002-228 SF4003 ABBOT RISK CONSULTING LTD DDP PETROFAC SHARJAH OFFICE, UAE 03-Feb-11 09-Feb-11 100 05-Mar-11 28-Feb-11 100 15-Mar-11 06-Apr-11 100 17-Mar-11 06-Apr-11 100

UU00-P-XXTS-000-1003 Environmental Impact Assessment Study HSE UU00-P-XXTS-000-1003-229 03-Aug-11 02-Sep-11 12-Sep-11 14-Sep-11

UU00-P-XXTS-000-1004 Energy Efficiency Study HSE UU00-P-XXTS-000-1004-235 SF4008 WORLEY PARSONS DDP PETROFAC SHARJAH OFFICE, UAE 14-Mar-11 20-Mar-11 100 13-Apr-11 19-Apr-11 100 23-Apr-11 17-Jun-11 100 25-Apr-11 23-Jun-11 100
HU-TECH ERGONOMICS AND
UU00-P-XXTS-000-1005 Human Factor Engineering Study HSE UU00-P-XXTS-000-1005-231 SF4009 HUMAN FACTORS DDP PETROFAC SHARJAH OFFICE, UAE 31-Mar-11 28-Mar-11 100 30-Apr-11 14-Apr-11 100 10-May-11 12-Jul-11 100 12-May-11 12-Jul-11 100

DOME OILFIELD ENGINEERING &


UU00-P-XXTS-000-1009 Functional Safety Assessment HSE UU00-P-XXTS-000-1009-234 SF4019 SERVICES LLC DDP PETROFAC SHARJAH OFFICE, UAE 03-Aug-11 05-May-11 100 02-Sep-11 21-May-11 100 12-Sep-11 03-Oct-11 100 14-Sep-11 03-Oct-11 100
VANGUARD SOLUTIONS (MIDDLE
UU00-P-XXTS-000-1010 HAZOP Study Chairman HSE UU00-P-XXTS-000-1010-225 SF4005 EAST ) FZ LLC DDP PETROFAC SHARJAH OFFICE, UAE 31-Mar-11 18-Apr-11 100 30-Apr-11 27-Apr-11 100 10-May-11 12-May-11 100 12-May-11 19-May-11 100

SAFE CONTROLS ENGINEERING


UU00-P-XXTS-000-1012 SIL Study HSE UU00-P-XXTS-000-1012-227 SF4014 CONSULTANCY FZE DDP PETROFAC SHARJAH OFFICE, UAE 03-Apr-11 05-May-11 100 03-May-11 22-May-11 100 13-May-11 13-Jul-11 100 15-May-11 13-Jul-11 100
UU00-P-XXTS-000-1013 PHSER Chairman HSE UU00-P-XXTS-000-1013-230 03-Aug-11 02-Sep-11 12-Sep-11 14-Sep-11
UU00-P-XXTS-073-1007 Emergency Response Vehicles HSE UU00-P-XXTS-073-1007-49 30-May-11 12-Jun-11 100 07-Jul-11 25-Jul-11 100 05-Sep-11 24-Dec-11 12-Sep-11 31-Dec-11 27-Oct-11 14-Feb-12 19-Feb-12 14-Jul-12 26-Feb-12 21-Jul-12 04-Mar-12 28-Jul-12 11-Mar-12 04-Aug-12 18-Apr-12 11-Sep-12 18-May-12 11-Oct-12 02-Jun-12 26-Oct-12 02-Jun-12

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012
PROCUREMENT TRACKING REGISTER

ISG PROJECT - IN SALAH GAS SOUTHERN FIELDS DEVELOPMENT PTR TEMPLATE


CONTRACT NO. : 100045/ISG/CON
DOCUMENT NO : 1 7 11 12 13 14 15-Jan-00 23 24-Jan-00 25-Jan-00 26 28-Jan-00 29-Jan-00 30 09-Jan-00
CUT OFF DATE: 29-Oct-11

Issue Inquiry Requisition Receive Bid TBE Complete Place LOI / LOA Place PO Receive / Approve Key Vendor Drawings / Documents Place Sub-orders Receive Raw Materials Fabrication / Mfg. Inspection Release Note Ex-works Delivery Item on Board Shipping/Air Freight/Land Transport (ATA Port) Custom Clearance and Transport to site/store Visual Inspection on Receipt at Site/Store ROS
Inquiry No. Description Discipline INQD_TAG_NO PO_NO Vendor Name PO Delivery Terms PO_CDD
P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog P F A % Prog
UU00-P-XXTS-076-1006 Fire Fighting & Safety Equipment HSE UU00-P-XXTS-076-1006-48 16-Apr-11 14-Jun-11 100 24-May-11 04-Jul-11 100 23-Jul-11 24-Dec-11 30-Jul-11 31-Dec-11 13-Sep-11 14-Feb-12 06-Mar-12 07-Apr-12 13-Mar-12 14-Apr-12 20-Mar-12 21-Apr-12 27-Mar-12 28-Apr-12 04-May-12 05-Jun-12 03-Jun-12 05-Jul-12 18-Jun-12 20-Jul-12 18-Jun-12
UU00-P-XXTS-076-1008 Safety Signs HSE UU00-P-XXTS-076-1008-50 20-Jun-11 14-Jun-11 100 20-Jul-11 06-Jul-11 100 22-Aug-11 24-Dec-11 29-Aug-11 31-Dec-11 13-Oct-11 14-Feb-12 06-Jan-12 07-Apr-12 13-Jan-12 14-Apr-12 20-Jan-12 21-Apr-12 27-Jan-12 28-Apr-12 05-Mar-12 05-Jun-12 04-Apr-12 05-Jul-12 19-Apr-12 20-Jul-12 19-Apr-12
UU00-P-TTTS-086-1001 Telecom System TELECOM UU00-P-TTTS-086-1001-51 25-Apr-11 18-Apr-11 100 25-May-11 07-Jun-11 100 17-Jul-11 08-Aug-11 100 24-Jul-11 25-Aug-11 100 07-Sep-11 13-Nov-11 29-May-12 19-Jul-12 05-Jun-12 26-Jul-12 12-Jun-12 02-Aug-12 19-Jun-12 09-Aug-12 27-Jul-12 16-Sep-12 26-Aug-12 16-Oct-12 10-Sep-12 31-Oct-12 10-Sep-12
UU00-P-TTTS-086-1002 Passive Cooling Shelters TELECOM UU00-P-TTTS-086-1002-52 01-May-11 23-May-11 100 31-May-11 07-Jul-11 100 08-Jul-11 23-Nov-11 15-Jul-11 30-Nov-11 29-Aug-11 14-Jan-12 20-Feb-12 13-Jun-12 27-Feb-12 20-Jun-12 05-Mar-12 27-Jun-12 12-Mar-12 04-Jul-12 19-Apr-12 11-Aug-12 19-May-12 10-Sep-12 03-Jun-12 25-Sep-12 03-Jun-12
UU00-P-TTTS-086-1003 Telecom Cables & Bulks TELECOM LOT : 001 SF0054 DRAKA COMTEQ IBERICA SL FOB SANTANDER, SPAIN 25-Apr-11 16-May-11 100 04-Jul-11 15-Jun-11 100 11-Aug-11 28-Jul-11 100 18-Aug-11 09-Aug-11 100 02-Oct-11 09-Aug-11 100 25-Jan-12 07-Mar-12 15.00 01-Feb-12 07-Mar-12 08-Feb-12 25-Mar-12 15-Feb-12 25-Mar-12 24-Mar-12 25-Mar-12 23-Apr-12 25-Mar-12 08-May-12 25-Mar-12 29-Mar-12
UU00-P-TTTS-086-1004 Radio & Tower TELECOM UU00-P-TTTS-086-1004-54 SF0110 MITAS TELECOM SYSTEMS 16-May-11 18-May-11 100 15-Jun-11 02-Jun-11 100 23-Jul-11 23-Nov-11 30-Jul-11 30-Nov-11 13-Sep-11 14-Jan-12 06-Jan-12 18-Apr-12 13-Jan-12 25-Apr-12 20-Jan-12 02-May-12 27-Jan-12 09-May-12 05-Mar-12 16-Jun-12 04-Apr-12 16-Jul-12 19-Apr-12 31-Jul-12 19-Apr-12
UU00-P-TTTS-086-1005 Telecom Copper Cables TELECOM UU00-P-TTTS-086-1005-1 31-Jul-11 100 15-Sep-11 100 07-Nov-11 14-Nov-11 29-Dec-11 02-Apr-12 09-Apr-12 16-Apr-12 23-Apr-12 31-May-12 30-Jun-12 15-Jul-12 22-Sep-12

This document is an uncontrolled copy when printed or saved. Viewed by:


Ahmad Warsi 13-Mar-2012