Professional Documents
Culture Documents
No: WI-SAI-PCON-003-E
WORK INSTRUCTION
Rev. 03 Date: 19/OCT/09
ENGINEERING PLANNING,
PROGRESS MONITORING, AND REPORTING
Page 2 of 11
Revision Summary
Table of Contents
1. PURPOSE/SCOPE.................................................................................................................................... 4
2. REFERENCES .......................................................................................................................................... 4
3. DEFINITIONS ............................................................................................................................................ 4
4. ACTIVITIES/DESCRIPTION ..................................................................................................................... 5
4.1. GENERAL ............................................................................................................................................. 5
4.2. RESPONSIBILITIES ............................................................................................................................. 5
4.3. DOCUMENT PROGRESS REGISTER PREPARATION AND WORK BREAKDOWN STRUCTURE
DEFINITION..................................................................................................................................................... 7
4.4. ENGINEERING ACTIVITIES PLANNING ............................................................................................. 7
4.5. ENGINEERING PROGRESS MONITORING ....................................................................................... 7
4.6. ENGINEERING PROGRESS REPORTING ......................................................................................... 8
5. FORMS .................................................................................................................................................... 10
5.1. COST BREAKDOWN STRUCTURE (FORM-SAI-PCON-003-E) ....................................................... 10
5.2. PROGRESS S-CURVES (ENGINEERING OVERALL) (FORM-SAI-PCON-005-E) .......................... 10
5.3. ENGINEERING PERFORMANCE (FORM-SAI-PCON-007-E) .......................................................... 10
5.4. ENGINEERING PROGRESS BY PHASES (FORM-SAI-PCON-009-E) ............................................ 10
5.5. ENGINEERING MANHOURS FORECAST OR STATUS (FORM-SAI-PCON-010-E)....................... 10
5.6. MASTER DOCUMENT REGISTER (FORM-SAI-ENG-006-E) ........................................................... 10
5.7. DOCUMENT PROGRESS REGISTER (FORM-SAI-ENG-030-E) ...................................................... 10
5.8. MEETING ATTENDEES (FORM-SAI-ADM-011-E) ............................................................................ 10
5.9. MINUTES OF MEETING (FORM-SAI-ADM-015-E)............................................................................ 10
6. EXHIBITS/FLOWCHARTS...................................................................................................................... 10
6.1. EXHIBIT 1 – ENGINEERING PLANNING, PROGRESS MONITORING, AND REPORTING
FLOWCHART ................................................................................................................................................ 10
Doc. No: WI-SAI-PCON-003-E
WORK INSTRUCTION
Rev. 03 Date: 19/OCT/09
ENGINEERING PLANNING,
PROGRESS MONITORING, AND REPORTING
Page 4 of 11
1. PURPOSE/SCOPE
The purpose of this document is to define the planning of engineering activities, their progress
monitoring, and reporting.
This document shall be applicable for all projects with engineering activities performed by Saipem
America.
2. REFERENCES
2.1. PROJECT CONTROL (GL-COR-PCON-001-E)
2.9. PROJECT MANAGER, PROJECT LEVEL, AND JOB NUMBER ASSIGNMENT (WI-SAI-
PROJ-003-E)
3. DEFINITIONS
3.1. Company: In the context of this document, Company shall be interpreted as Saipem America
Inc.
3.14. WBS: Work Breakdown Structure which organizes project scope of work.
3.15. Weight Values: Values used to evaluate deliverables hierarchy within WBS.
4. ACTIVITIES/DESCRIPTION
4.1. GENERAL
Engineering activities are defined per General Procedure Engineering Activities (GP-SAI-
ENG-002-E).
4.2. RESPONSIBILITIES
It is the ultimate responsibility of the Project Control Manager to plan engineering activities
and to monitor and report their progress but this process involves the whole Project Team.
Every Project Team member’s role and responsibilities are described below. Some of the
described roles may be grouped or eliminated according to the project complexity as defined
in Work Instruction Project Manager, Project Level, and Job Number Assignment (WI-SAI-
PROJ-003-E).
The preparation of the Document Progress Register and definition of the Work Breakdown
Structure must be performed per Work Instruction Preparation of the Initial Project
Coordination Plan and Original Control Budget (WI-SAI-PROJ-005-E) in accordance with the
following documents:
• Project Control (GL-COR-PCON-001-E).
• Project Control Standards And Reports (STD-COR-PCON-001-E).
• Project Cost Control (WI-SAI-PCON-002-E).
• Work Breakdown Structure (FORM-SAI-PCON-013-E).
• Cost Breakdown Structure (FORM-SAI-PCON-003-E).
• Master Document Register (FORM-SAI-ENG-006-E).
• Document Progress Register (FORM-SAI-ENG-030-E).
In order to have a homogeneous basis to estimate the actual progress status of the
works, the PM with the support of Project Team, must establish relative weight
allotted to each document produced by Engineering. The weight of each
drawing/document shall be based on the estimated quantity of manhours required for
preparation.
The Document Progress Register forecast dates of each document shall be used to
plan the project initial schedule (baseline) by the Project Manager, the Planning
Engineer, or the Project Control Manager depending on project complexity and
organization.
The following scheduling software shall be used to plan the project progress:
• Primavera;
• Microsoft Project; or
• Other software can also be used if approved per Policy Software/Hardware
Policy (POL-SAI-ICT-004-E).
4.5.1. General
To ensure that the project Engineering activities are progressing as planned, the
current progress status and trend shall be periodically reviewed (monthly as a
general rule) in comparison with the schedule and the following forms:
• Master Document Register (FORM-SAI-ENG-006-E).
Doc. No: WI-SAI-PCON-003-E
WORK INSTRUCTION
Rev. 03 Date: 19/OCT/09
ENGINEERING PLANNING,
PROGRESS MONITORING, AND REPORTING
Page 8 of 11
The Document Progress Register is a key tool in obtaining confirmation about the
engineering progress status and it is indispensable for assessing the work progress
trend. The progress status and an issue forecast shall be reported in the Document
Progress Register that shall be constantly kept up-to-date, in consideration of the
design development.
In order to correctly monitor the engineering progress, the following data needs to be
collected regularly and calculated by the Project Manager, the Planning Engineer, or
the Project Control Manager depending on project complexity and organization.
Budget Hours Work Scheduled are the total budgeted manhours split by WBS,
according to Work Instruction Preparation of the Initial Project Plan (WI-SAI-PROJ-
005-E).
Actual Hours Work Performed are the total amount of spent manhours, split by WBS.
Physical Progress is related to Budget Hours Work Performed (BHWP) - also called
Earned Value (EV) - as per the following formula:
The Productivity Index is calculated between the spent manhours, the foreseen ones,
and the physical progress as per the following formula:
The normal project reporting cut-off date is every end of month. The Project
Manager, the Planning Engineer, or the Project Control Manager, depending on
project complexity and organization, shall then collect all the information and issue
the monthly engineering progress report which gives a clear situation regarding the
achieved progress and the trend maintained.
Doc. No: WI-SAI-PCON-003-E
WORK INSTRUCTION
Rev. 03 Date: 19/OCT/09
ENGINEERING PLANNING,
PROGRESS MONITORING, AND REPORTING
Page 9 of 11
The monthly engineering progress data shall be used to activate corrective actions
when needed or as lessons learned for future projects.
The periodicity for the project engineering activities reporting is usually agreed with
the Client and included with contract documentation.
The Project Manager, the Planning Engineer, or the Project Control Manager,
depending on project complexity and organization, supported by project team
members if required, shall review and report the following information:
• General summary: The overall work progress status is briefly analyzed;
• Remarks: The major events of the months, such as: meetings, shifting of dates,
etc.;
• Criticalities: The conditions, affecting or likely to affect the regular work progress
and the fulfillment of the final objectives, are indicated;
• Corrective actions: The main corrective actions undertaken, or to be undertaken
in order to solve current or potential criticalities, are highlighted;
• Summary of work progress status: The comparison among the new scheduled
dates and those initially forecasted in the baseline shall be reviewed;
• Status of activities: A list of completed activities shall be reviewed, as well as, a
forecast of all activities still to be completed;
• Document Progress Register, “S-curves” and histograms; and
• Conclusion: Any discrepancy between the current situation and the scheduled
one shall be reported and explained, with reference to Area and Discipline.
5. FORMS
5.1. WORK BREAKDOWN STRUCTURE (FORM-SAI-PCON-013-E)
6. EXHIBITS/FLOWCHARTS
6.1. EXHIBIT 1 – ENGINEERING PLANNING, PROGRESS MONITORING, AND REPORTING
FLOWCHART
Doc. No: WI-SAI-PCON-003-E
WORK INSTRUCTION
Rev. 03 Date: 19/OCT/09
ENGINEERING PLANNING,
PROGRESS MONITORING, AND REPORTING
Page 11 of 11
EXHIBIT 1
ENGINEERING PLANNING, PROGRESS MONITORING, AND REPORTING
FLOWCHART
FORM-SAI-PCON-003-E
START
Cost Breakdown
Structure
GP-SAI-ENG-002-E
GL-COR-PCON-001-E
Engineering
Revision Control
Activities
FORM-SAI-ENG-006-E
Master Document
Register
WI-SAI-PROJ-005-E PM/PLE/PCM
STD-COR-PCON-001-E
Preparation of the Prepare DPR FORM-SAI-ENG-030-E
Revision Control
Initial Project & define WBS Document Progress
Register
WI-SAI-DSSM-002-E PM/PLE/PCM
Identification and Project
Plan WI-SAI-PCON-001-E
Numbering of Schedule
Engineering Progress Measurement
Company (baseline)
activities
Documents
PM/PLE/PCM
WI-SAI-DSSM-003-E Monitor WI-SAI-PCON-002-E
Revision Control Engineering Project Cost Control
activities
progress
MONTHLY
FORM-SAI-PCON-003-E
POL-SAI-ICT-004-E PM/PLE/PCM Cost Breakdown
Software/Hardware Report Structure
Policy Engineering FORM-SAI-PCON-009-E
activities Engineering Progress By
progress Phases
FORM-SAI-PCON-005-E
Progress S-Curves
WI-SAI-PROJ-003-E
Project Manager and FORM-SAI-PCON-010-E
Job Number Engineering Man-Hours
Assignment Forecast or Status
FORM-SAI-PCON-007-E
Engineering
Performance
PROJECT MONTHLY
REPORT
FORM-SAI-ADM-015-E
Minutes of Meeting
FORM-SAI-ADM-011-E
END Meeting Attendees