You are on page 1of 9

WORK METHOD STATEMENT WATER

TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store

IKEA Jakarta Garden City 2nd Store

Employer PT. Archipelago Property Development Project Number P10065


Engineer PT. AECOM Indonesia Document Number IK2-BAM-GE-SC-W-0020
Contractor BAM International Revision 00
Number of
pages 23 Date:

WORK METHOD STATEMENT


WATER TANK CONSTRUCTION

Reference Sheet
Document Number Description

BMS BAM International Management System


IK2-BAM-GE-QA-Q-0001 Quality Management Plan
IK2-BAM-GE-QA-Q-000S Project Environment Plan
IK2-BAM-GE-SA-Q-0001 Project HSS Plan

Revision History
Revision Date Revision Description

00 9 October 2019 For Construction


Prepared by Checked by Approved by
JUL MRA BHA
Author Eng. Manager Project Manager

Status Definition Total number of pages


(latest revision) (excluding attachments)

For Construction 23
© BAM International BMS-ENG- Rev 00

Table of content

Document Number Page Revision


IK2-BAM-GE-SC-W-0020 of 00
09-Oct-2019
WORK METHOD STATEMENT WATER
TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store

1 INTRODUCTION.................................................................................................................................... 3
2 SCOPE OF WORK................................................................................................................................. 3
3 PERSONS INVOLVED........................................................................................................................... 3
4 RESPONSIBILITIES.............................................................................................................................. 3
5 TECHNICAL ASPECTS (WORK METHODS)........................................................................................ 4
6 TOOLS AND MATERIAL..................................................................................................................... 22
7 MONITORING...................................................................................................................................... 22
8 SAFETY MANAGEMENT.................................................................................................................... 23

Document Number Page Revision

IK2-BAM-GE-SC-W-0020 of 00
09-Oct-2019
WORK METHOD STATEMENT
WATER TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store

1 INTRODUCTION
This method explains the casting work carried out at the Jakarta Garden City IKEA2 project from the
process of land preparation, tools, materials, casting and final work / finish. Casting work is carried out
after the completion of rebar and formwork works. Casting can be carried out manually (using human
power with tools) or using tools (mobile crane tools, concrete buckets with tower cranes and concrete
pumps).

2 SCOPE OF WORK
The scope of work cover following:
 Watertank Rebar installation
 Scaffolding and platform installation
 Watertank Formwork installation
 Watertank Concrete casting

3 PERSONS INVOLVED
Organization shall be put in accordance with work sequence
- Construction Manager
- Surveyor
- Site Engineers
- Construction Supervisor
- QA/QC engineer
- Safety Supervisor/Inspector

4 RESPONSIBILITIES
Construction Manager
In order to ensure effective development and implementation of the safe systems of work, the
construction manager shall nominate a supervisor, who has overall control of works.The construction
manager is required to ensure suitable working conditions site wide, logistic and other facilities for all
operatives

Surveyor
 Conduct and development of site surveying
 Develop reference point and level
 Monitoring the work progress and report to Construction Manager

Site Engineers:
 Prepare work methods that are used as references in the field in the form of tools and materials
 Check the stages of work in the field
 Preparing shop drawings
 Working with supervisors related to monitoring and procuring material
 Technical coordination with subcontractors
Construction Supervisor
 Supervisors must ensure that the installation plan includes:
 Identify the type of work to be done
 Identify work-related hazards
 Carry out risk assessment
 Identify control measures
 Develop a method that will be used with the engineer
 Communicate plans to everyone involved
 Review the plan before starting implementation and inform field data or changes that have
occurred
 Direct workers to find out work and risks
Document Number Page Revision
IK2-BAM-GE-SC-W-0020 3 of 9 00
09-Oct-2019
WORK METHOD STATEMENT
WATER TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store

 Report if there are irregularities and obstacles that occur in the field during implementation
 Provide work implementation solutions if there are deviations and obstacles that occur
 Coordination with Superintendents for problems in the field
 Perform meeting tool-boxes before carrying out work
Safety Supervisor/Inspector
 HSE and the team engineer will help and ensure work follows the occupational safety and
health rules and regulations.
 Provide safety induction to all workers
 Control and hold pre-start meetings / tool-box meetings routinely led by supervisors
 Creating and monitoring a healthy and safe work environment
 Ensure that all equipment is suitable and safe to use
 Ensure all workers comply with safety requirements for work
QA/QC Engineer
 Ensure the implementation of work in accordance with the Implementation Method by controlling
the implementation process
 Coordinating the Work Inspection Request (WIR)
 Carry out inspection of work results in accordance with the stages mentioned in the ITP and ensure
the work results are made and stored properly.
 Make reports of aberration that occur and follow up

5 TECHNICAL ASPECTS (WORK METHODS)

A. Typical Scaffolding and Access installation

1. Install scaffolding to serve as a working platform and safe access in and out of Water Tank;

Fig 3.: Typical plan for Formworks on Column and Walls

Document Number Page Revision


IK2-BAM-GE-SC-W-0020 4 of 9 00
09-Oct-2019
WORK METHOD STATEMENT
WATER TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store

Fig 4.: Typical Elevation for Formworks on Column and Walls with construction joints

2. Ensure all scaffolding has green tags for safe use during rebar and form work installation;
3. Complete scaffolding set-up and access stairs. Proceed to rebar and formwork installation.

B. Rebar and Formwork Installation on water tanks

1. Rebar shall installed as per approved shop drawing.

Fig 1.: Typical Wall/Column Rebar upstand installation

2. Starter bar shall prepared on the concrete slab (e.g. B2 & B1 cast-in-situ slab)
3. Any opening shall prepared using block out or pipe sleeves
4. Rebar that has been cut shall be compensated with trimmer bar as mention on IFC structural
drawing.
5. After rebar installed, all constructin joint location shall be installed with WATERSTOP as per
Cemenaid’s recommendation.

Document Number Page Revision


IK2-BAM-GE-SC-W-0020 5 of 9 00
09-Oct-2019
WORK METHOD STATEMENT
WATER TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store

Fig 2.: Typical Wall Penetration detail with compensation rebars

6. Install block out for manholes provision and install MEP pipe sleeves;
7. Inspection shall be done by QC team;
8. Formwork closing.
9. Can proceed to concrete casting.

C. Concrete Casting

1. Prepare concrete casting tools and equipment at designated working area (e.g. concrete
vibrator).
2. The casting sequence shall follow as per agreed with construction and qaqc.

Fig 5.: Casting sequence

3. Concreting using waterproofing concrete f’c 55 MPa (e.g. Cementaid’s 3CC water proofing
concrete)
4. While concreting is on-going, ensure to monitor the surrounding supports and joints;
5. Ensure to use concrete vibrator to avoid honeycomb and segregation.
6. Concrete casting will be completed when it reach the construction joint level.
7. Proceed to next step of casting.

Document Number Page Revision


IK2-BAM-GE-SC-W-0020 6 of 9 00
09-Oct-2019
WORK METHOD STATEMENT
WATER TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store

Fig 5.: Concrete outline of water tank

Fig 6.: Construction joint levels on Water tank (Typical)

6 TOOLS AND MATERIAL


In this works, the tools and material used is:

A. Tools
No Resources
1 Tower Crane
2 Concrete Pump
3 Total Station and Waterpass
4 Concrete bucket cap 1.0 m3 / 0.8 m3
5 Air compressor
6 Electric concrete vibrator +needle
7 External Vibrator for wall
8 Cutting wheel
9 Plastic chute H = 5.0 m

Document Number Page Revision


IK2-BAM-GE-SC-W-0020 7 of 9 00
09-Oct-2019
WORK METHOD STATEMENT
WATER TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store

10 Jet washer
11 Welding trafo
12 Wheel barrow
13 Water drum
14 Steel pipe

B. Material

No Material References
1 Readymix concrete Fç=32MPa, 35 MPa, 55 MPa
2 Tarpaulin plastic cover
3 Admixture-concrete waterproofing 3CC ex cementaid
4 Curing compound
5 Formoil
6 Waterstop
7 Clean water
8 Portland cement
9 Bonding agent
10 Styrofoam
111 Chicken mesh

7 MONITORING

A. Quality Assurance
1. Ensure the method statement has been approved and every works done as per method
statement, contract, and vendor document.
2. Method statement must be known by every person involved in this works
3. Hand the Inspection Test Plan (ITP) and ensure internal checklist has been fulfilled before work
done.
4. Execute identification on every material, tools, procedure, resources and management to
ensure every works finished properly.
B. Quality Control
1. Work permit should be approved as per method statement, area, material, and tools
2. Execute ITP control and ensure it can be done
3. Execute ITP update to improve work quality
4. Prepare plan, procedure, and document related to the works
5. Every step should follow the method statement including finishing.
6. Execute quality control on every works as per ITP and ensure quality record properly stored

8 SAFETY MANAGEMENT

1. The introduction of work safety must be introduced to everyone involved in the project before the
construction work begins through safety induction
2. Work order, the potential that can cause work accidents both equipment, material and work methods
must be explained in the initial stages and at the pre-start meeting. This was stated in detail in the
job safety analysis (JSA).
3. All people involved in work must wear personal protective equipment in the project area. The
provision of security signs and work safety is always placed in the appropriate location.
4. Mechanics along with safety must always check the equipment that is being used and which will be
used in the construction process periodically.
5. Special things that require attention:
 Material placement
 Inspection of transportation access
 Lifting equipment does not experience overload
 Use slings in good condition, planned length, and according to the load lifted

Document Number Page Revision


IK2-BAM-GE-SC-W-0020 8 of 9 00
09-Oct-2019
WORK METHOD STATEMENT
WATER TANK CONSTRUCTION
IKEA Jakarta Garden City 2nd Store


Attention is directed specifically to chemical material (admixture), give a special place with
special marks
 Every supporting material must have an MSDS
6. Work protection equipment that must be used is:
 Helmet
 Safety shoes
 Safety gloves
 Fullbody harness
 Safety vest
 Safety glasses

Document Number Page Revision


IK2-BAM-GE-SC-W-0020 9 of 9 00
09-Oct-2019

You might also like