Professional Documents
Culture Documents
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
EPCC -01 PACKAGE FOR CDU/VDU UNIT_HRRL BARMER, RAJASTHAN 992
MS1035 Site Mobilization and Setting of Site office with posting of 0 Site Mobilization and Setting of Site office with posting of RCM
RCM
MS1135 UG Pipe 1st MTO Ordering Complete 0 UG Pipe 1st MTO Ordering Complete
MS1325 Place Order- Switchgears & Transformers 0 Place Order- Switchgears & Transformers
MS1720 AG Piping 1st MTO Ordering Complete 0 AG Piping 1st MTO Ordering Complete
Actual Work Critical Remaining Work Page 1 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
MS1905 Start Steel Str. Fabricati on Work 0 Start Steel Str. Fabricati on Work
MS1700 Start Heater Field Erection Work 0 Start Heater Field Erection Work
MS1475 Start Issue A/G Piping Isometrics- AFC 0 Start Issue A/G Piping Isometrics- AFC
MS1915 Start Steel Str. Erection Work 0 Start Steel Str. Erection Work
MS1425 Completion of Foundation for CDU/VDU Column 0 Completion of Foundation for CDU/VDU Column
MS1885 Substn. Building Ready for Panel Erection 0 Substn. Building Ready for Panel Erection
MS1635 Start DCS Installation in SRR Bldg. ( By Others ) 0 Start DCS Installation in SRR Bldg. ( By Others )
MS1575 Completion Erection of CDU / VDU Column 0 Completion Erection of CDU / VDU Column
MS1020 Start Precommissioning flushing and blowing work 0 Start Precommissioning flushing and blowing work
MS1775 Start Instrument Loop & Functoin Test 0 Start Instrument Loop & Functoin Test
Actual Work Critical Remaining Work Page 2 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
MS1675 Heater Package Erection & Refractory Work Completion 0 Heater Package Erection & Refractory Work Completion
MS1650 Completion of Motor Solo Run test 0 Completion of Motor Solo Run test
MS1800 Completion of Piping Flushing, Blowing and ReinStatement 0 Completion of Piping Flushing, Blowing and Rein
Engineering 0 Engineering
OOE1000 CDU/VDU Column Loading Information for Civil Design 0 CDU/VDU Column Loading Information for Civil Design
OOE1010 Availability of Native Files ( P&ID, MFD, PFD, Equipment 0 Availability of Native Files ( P&ID, MFD, PFD, Equipment Data Sheet Etc.)
Data Sheet Etc.)
Free Issue Material 61 Free Issue Material
FIM1000 Crude Distillation Column (CDU) from EIL/Owner (In Two 0 Crude Distillation Column (CDU) from EIL/Owner (In Two Parts field welding at Site in vertical position by o
Parts field welding at Site in vertical position by others)
FIM1255 Vacuum Distillation Column (VDU) from EIL/Owner ( In 0 Vacuum Distillation Column (VDU) from EIL/Owner ( In Three Parts , field welding in vertical position at site
Three Parts , field welding in vertical position at site by
FIM1100 FIM ( Substn ) : Detector, Hooters , Sirens etc. 0 FIM ( Substn ) : Detector, Hooters , Sirens etc.
FIM1265 FIM ( SRR) : Detector, Hooters, Sirects Etc. 0 FIM ( SRR) : Detector, Hooters, Sirects Etc.
OOCO1000 Handing Over of Site for Construction Work 0 Handing Over of Site for Construction Work
Actual Work Critical Remaining Work Page 3 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
OOCO1025 Handing Over of land at site for setting up Project Office, 0 Handing Over of land at site for setting up Project Office, Fabrication and Stoage Yard
Fabrication and Stoage Yard
OOCO1035 CDU & VDU COLUMN release for Piping Work 0 CDU & VDU COLUMN release for Piping Work
A6670 Availabiity of Raw Water , Plant water , Plant Air 0 Availabiity of Raw Water , Plant water , Plant Air
FIM1285 Availability of Incoming Power Supply for Substn 0 Availability of Incoming Power Supply for Substn Energization (66 Kv)
Energization (66 Kv)
A6330 Availability of DCS, ESD, F&G PLC : FIM (Ready for loop 0 Availability of DCS, ESD, F&G PLC : FIM (Ready for loop check)
check)
A6690 Avaiabiity of Nitrogen 0 Avaiabiity of Nitrogen
A6730 Availability of Fuel Gas / Fuel Oil / Flushing Oil 0 Availability of Fuel Gas / Fuel Oil / Flushing Oil
Actual Work Critical Remaining Work Page 4 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
PID5 P&ID AF D ( With 60% Model Review Tag Resolution + 14
Hazop Resolution )
PID2 P&ID - AFC ( For 90% Model Review) 20
PDS - Vessel, Heat Exchangers, Pu mps 10 PDS - Vessel, Heat Exchangers, Pumps
Actual Work Critical Remaining Work Page 5 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
EP1260 Process List and Documents (Balance) 251
EP1175 HAZOP 12
A5420 Loading Data from Owner for VDU Column + Toyo - Piping 26
Team
A5470 Loading Data ( Others) 130
A5430 Loading Data from Air Cooler Vendor (Main Pipe Rack ) 14
Pile and Foundation Location Plan - AFC Category 205 Pile and Foundation Location Plan - AFC Category
Critical - Pile and Foundation Location Plan 149 Critical - Pile and Foundation Location Plan
Actual Work Critical Remaining Work Page 6 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
ENGPILE1000 CDU Column - Pile & Fdn. Location Plan 56
UG Composite 85 UG Composite
Actual Work Critical Remaining Work Page 7 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A5380 Conceptual UG Composite Plan-IFR 40
Actual Work Critical Remaining Work Page 8 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
EPIPE1175 90 % Model Review 7
A5860 Main Cable Route & Layout Plan: Overall & Key Plan - AFR 15
A5890 Main Cable Route & Layout Plan: Overall & Key Plan - AFC 20
Actual Work Critical Remaining Work Page 9 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A5840 Equip Sizing: Load Analysis/ Eqpt Sizing Calculations- AFR 21
EINST1075 Input to Owner: DCS Hardware Finalization for DCS ( 0 Input to Owner: DCS Hardware Finalization for DCS ( Indicative Only))
Indicative Only))
EINST1110 Instrument Layout - AFC 40
Towers (CS, CS+Clad, Site Joint) 130 Towers (CS, CS+Clad, Site Joint)
Actual Work Critical Remaining Work Page 10 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A2770 Technical Querry / TBE 14
SS Clad, Solid SS & Brass Exchanger_AXEA002 135 SS Clad, Solid SS & Brass Exchanger_AXEA002
Actual Work Critical Remaining Work Page 11 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A6620 Key Vendor Data Approval 55
Big Vessels (More than 2m Dia) 142 Big Vessels (More than 2m Dia)
Small Vessels ( Less than 2m Dia) 142 Small Vessels (Less than 2m Dia)
HTAT _Fired Heaters ( Crud e Heater101- F-101A/B an d Vacuum Heater 101-F-102) 169 HTAT _Fired Heaters ( Crude Heater101-F-101A/B and Vacuum Heater 101-F-102)
Actual Work Critical Remaining Work Page 12 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A5140 Prepare & Issue MR 5
Pumps ( Crude Charge, Crude Booster, HVGO PDT, Demulsifier Injection Pump, VR 189
PDT + Quench Pump, RCO Pumps ( Crude Charge, Crude Booster, HVGO PDT, Demulsifier Injection Pump, VR PDT + Quench Pump, RCO
Centrifugal Pumps Remaining All (API) 177 Centrifugal Pumps Remaining All (API)
High speed Centrifugal Pumps (SUNDYNE) 178 High speed Centrifugal Pumps (SUNDYNE)
Actual Work Critical Remaining Work Page 13 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A7360 Technical Querry / TBE 25
Actual Work Critical Remaining Work Page 14 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Reciprocating Air Compressor 173 Reciprocating Air Compressor
Actual Work Critical Remaining Work Page 15 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A3110 Receipt of Quotation 15
Fire Fighting Equipment / Clean Agent/ Others 156 Fire Fighting Equipment / Clean Agent/ Others
Actual Work Critical Remaining Work Page 16 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A3840 Key Vendor Data Approval 90
Piping 63 Piping
A3620 TBE/CBE 5
A3670 TBE/CBE 8
Actual Work Critical Remaining Work Page 17 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A4080 Key Vendor Data Reci ept 25
66 KV GIS (Gas Insulated S/gear) Eqpt 183 66 KV GIS (Gas Insulated S/gear) Eqpt
Actual Work Critical Remaining Work Page 18 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A7040 Prepare & Issue MR 30
AC & DC UPS and Battery Charger 282 AC & DC UPS and Battery Charger
Actual Work Critical Remaining Work Page 19 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A4470 Technical Querry / TBE 14
Actual Work Critical Remaining Work Page 20 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
In-line Instruments 168 In-line Instruments
Instrument Cable Duct/Trays/ Fittings / Others 148 Instrument Cable Duct/Trays/ Fittings / Others
Fired Heaters ( Crude Heater101-F-101A/B and Vacuum Heater 101-F -102) 425 Fired Heaters ( Crude Heater101-F-101A/B and Vacuum Heater 101-F-102)
Actual Work Critical Remaining Work Page 21 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
PM2801 Ordering / LOI ISsue 5
Towers (CS, CS+Clad, Site Joint) 316 Towers (CS, CS+Clad, Site Joint)
Actual Work Critical Remaining Work Page 22 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Air Cooler 395 Air Cooler
Big Vessels (More than 2m Dia) 384 Big Vessels (More than 2m Dia)
Small Vessels ( Less than 2m Dia) 384 Small Vessels (Less than 2m Dia)
Pumps ( Crude Charge, Crude Booster, HVGO PDT, Demulsifier Injection Pump, VR PDT
329+ Quench Pump, RCO Pumps ( Crude Charge, Crude Booster, HVGO PDT, Demulsifier Injection Pump, VR PDT +
Centrifugal Pumps Remaining All (API) 273 Centrifugal Pumps Remaining All (API)
High speed Centrifugal Pumps (SUNDYNE) 273 High speed Centrifugal Pumps (SUNDYNE)
Actual Work Critical Remaining Work Page 23 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
PM3302 Manufacturing & Delivery to Site 258
Actual Work Critical Remaining Work Page 24 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
PM2702 Ordering / LOI ISsue 12
Fire Fighting Equipment / Clean Agent/ Others 195 Fire Fighting Equipment / Clean Agent/ Others
Actual Work Critical Remaining Work Page 25 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
EHV & HV Switchgear (ICOG) 218 EHV & HV Switchgear (ICOG)
66 KV GIS (Gas Insulated S/gear) Eqpt 218 66 KV GIS (Gas Insulated S/gear) Eqpt
AC & DC UPS and Battery Charger 207 AC & DC UPS and Battery Charger
Actual Work Critical Remaining Work Page 26 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Cathodic Protection System 237 Cathodic Protection System
Actual Work Critical Remaining Work Page 27 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
PM2032 Manufacturing & Delivery to Site 250
Instrument Cable Duct/Trays/ Fittings / Other remain 200 Instrument Cable Duct/Trays/ Fittings / Other remain
Mechanical and PIping Work Subcontractor 60 Mechanical and PIping Work Subcontractor
Actual Work Critical Remaining Work Page 28 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A6240 Electrical Work Subcontract Mobilization 45
66 Kv SubStation Building (Building Size 110 M x 31 M ) 590 66 Kv SubStation Building (Building Size 110 M x 31 M )
CC500 1st Part Sub-station ( Excavation for Fdn , Pile treatment 170
upto 1st Floor Slab Casting )
Actual Work Critical Remaining Work Page 29 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
CC510 2nd Part Sub-station ( Excavation for Fdn , Pile treatment 190
upto 1st Floor Slab Casting plus stair case upto top level )
CC840 Finishing Item 208
CC740 Sub-station Bldg Ready for Panel Installation 0 Sub-station Bldg Ready for Panel Installation
Sattelite Rack Room Building (Building Size 35 M x 36 M ) 597 Sattelite Rack Room Building (Building Size 35 M x 36 M )
CC675 SRR bldg Final Paint/ Finish work/ Stone Clad ( if Sated in 80
ITB)
CC645 SRR bldg Ready for Instrument Eqpt /Panel Installation 0 SRR bldg Ready for Instrument Eqpt /Panel Installation
Actual Work Critical Remaining Work Page 30 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
CC685 Roof Treatment 60
TS # 2 530 TS # 2
Actual Work Critical Remaining Work Page 31 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A6400 Stair, Ladder, Platform, Grating, Handrail etc. 90
TS # 5 551 TS # 5
Heater (CDU Heater : 2 Nos; VDU Heater : 1 Nos; Common Stack ~85 Meter) 535 Heater (CDU Heater : 2 Nos; VDU Heater : 1 Nos; Common S
Actual Work Critical Remaining Work Page 32 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
A6110 Heater-Equip. Fdn. 90
Actual Work Critical Remaining Work Page 33 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone
EPCC-01 PACKAGE FOR CDU/VDU WITH HWOG TREATMENT UNIT, SAT. LPG TREATING UNIT & SAT.
FUEL GAS TREATING UNIT FOR HPCL RAJASTHAN REFINERY LIMITED (HRRL) & RAJASTHAN
REFINERY PROJECT (RRP) AT PACHPADRA TEHSIL, BARMER DISTRICT, RAJASTHAN, INDIA.
PROJECT SCHEDULE
Activity ID Activity Name Original
Duration Month
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
CONPIP1050 UG Pipe : Fabrication and Laying 250
Commissioning 52 Commissioning
A6350 Commissioning 60
Actual Work Critical Remaining Work Page 34 of 34 Date Revision Checked Approved
01-Jun-19 ISSUE FOR PROPOSAL UCY RC
Remaining Work Milestone