Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah

Kebangsaan Kg. Tanam, Dalat


Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
SK Kampung Tanam (Updated as of 25102022) 940d 17-Sep-20 21-Jun-22 17-Sep-20 A 14-Apr-23 100% 57.29% -317d

PROJECT MILESTONE 940d 17-Sep-20 21-Jun-22 17-Sep-20 A 14-Apr-23 0% 0% -317d

001 Project Commencement 0d 17-Sep-20 17-Sep-20 A 100% 100%

002 Original Completion 0d 16-Mar-22 16-Mar-22 A 100% 100%

002a Revised Completion after EOT No.1 (EIW Year 2020) : 15 Days 0d 31-Mar-22 31-Mar-22 A 100% 100%

002b Revised Completion after EOT No.2 (PKP3.0) : 46 Days 0d 16-May-22 16-May-22 A 100% 100%

002c Revised Completion after EOT No.3 (EIW Year 2021) : 16 Days 0d 01-Jun-22 01-Jun-22 A 100% 100%

002d Revised Completion after EOT No.4 : 20 Days 0d 21-Jun-22 21-Jun-22 A 100% 100%

002e Project Completion 0d 21-Jun-22 14-Apr-23 100% 0% -317d

PRELIMINARIES AND GENERALLY 936d 17-Sep-20 20-Jun-22 17-Sep-20 A 10-Apr-23 100% 94.1% -313d

PRELIMINARIES AND GENERALLY 936d 17-Sep-20 20-Jun-22 17-Sep-20 A 10-Apr-23 100% 94.1% -313d
003 SITE POSSESSION 0d 17-Sep-20 17-Sep-20 A 100% 100%

004 SITE SURVEY SETTING OUT 16d 17-Sep-20 08-Oct-20 17-Sep-20 A 08-Oct-20 A 100% 100%

005 MOBILIZATION 5d 09-Oct-20 15-Oct-20 09-Oct-20 A 15-Oct-20 A 100% 100%

006 SITE OFFICE AND TEMPORARY BUILDINGS 10d 02-Nov-20 13-Nov-20 02-Nov-20 A 13-Nov-20 A 100% 100%

007 SO AND SOR SITE OFFICE 30d 16-Nov-20 25-Dec-20 16-Nov-20 A 25-Dec-20 A 100% 100%

008 ACCESS AND TEMPORARY WORKS 18d 16-Nov-20 09-Dec-20 16-Nov-20 A 09-Dec-20 A 100% 100%

009 SIGN BOARD 2d 10-Dec-20 11-Dec-20 10-Dec-20 A 11-Dec-20 A 100% 100%

010 PRELIMINARIES AND GENERALLY 606d 17-Sep-20 15-May-22 17-Sep-20 A 24-Dec-22 100% 94.1% -206d

011 DEMOBILIZATION 3d 18-Jun-22 20-Jun-22 08-Apr-23 10-Apr-23 100% 0% -313d

CONSTRUCTION WORKS 937d 17-Sep-20 17-Jun-22 17-Sep-20 A 11-Apr-23 100% 55.18% -314d

DEMOLITION 625d 02-Feb-21 07-May-21 01-Feb-21 A 18-Oct-22 A 100% 100%


016 Demolition of Existing Quarters (Wooden House) 40d 02-Feb-21 08-Apr-21 01-Feb-21 A 02-Apr-21 A 100% 100%

017 Demolition of Existing Crossover 7d 09-Apr-21 20-Apr-21 26-Sep-22 A 04-Oct-22 A 100% 100%

018 Demolition of Existing Concrete Ramp 5d 22-Apr-21 29-Apr-21 05-Oct-22 A 11-Oct-22 A 100% 100%

019 Demolition of Existing Concrete Footpath 5d 30-Apr-21 07-May-21 12-Oct-22 A 18-Oct-22 A 100% 100%

PILING WORKS 470d 30-Oct-20 08-Nov-21 28-Nov-20 A 15-Nov-22 100% 99.9% -158d
Driving of Spun Piles 90d 30-Oct-20 09-Mar-21 28-Nov-20 A 19-Apr-21 A 100% 100%
Mobilization of Machineries and Materials 85d 30-Oct-20 01-Mar-21 28-Nov-20 A 31-Mar-21 A 100% 100%
021 Mobilization of piling equipment 1d 30-Oct-20 30-Oct-20 28-Nov-20 A 30-Nov-20 A 100% 100%

022 Pile Point Setting out 7d 02-Nov-20 10-Nov-20 01-Dec-20 A 01-Dec-20 A 100% 100%

023 Delivery of piles - for Spun pile 350mm dia 84d 02-Nov-20 01-Mar-21 28-Nov-20 A 31-Mar-21 A 100% 100%

Test Pile 16d 02-Nov-20 23-Nov-20 02-Dec-20 A 05-Feb-21 A 100% 100%


025 Test Pile no.1 - Driving Test Pile No.1 1d 02-Nov-20 02-Nov-20 02-Dec-20 A 02-Dec-20 A 100% 100%

026 Test Pile No.1 - Static load test no.1 7d 03-Nov-20 11-Nov-20 22-Dec-20 A 30-Dec-20 A 100% 100%

027 Test Pile no.2 - Driving Test Pile No.2 1d 12-Nov-20 12-Nov-20 04-Jan-21 A 04-Jan-21 A 100% 100%

028 Test Pile No.2 - Static load test no.2 7d 13-Nov-20 23-Nov-20 26-Jan-21 A 05-Feb-21 A 100% 100%

Driving of Spun Piles 73d 24-Nov-20 09-Mar-21 09-Jan-21 A 19-Apr-21 A 100% 100%
030 Blok Pentadbiran & Akademik = 219 Point 35d 24-Nov-20 12-Jan-21 09-Jan-21 A 25-Jan-21 A 100% 100%

031 Kantin & Dataran Perhimpunan = 72 Points 14d 13-Jan-21 01-Feb-21 25-Jan-21 A 06-Mar-21 A 100% 100%

032 Pra Sekolah = 30 Points 6d 02-Feb-21 09-Feb-21 08-Mar-21 A 18-Mar-21 A 100% 100%

033 Rumah Guru = 91 Points 18d 10-Feb-21 09-Mar-21 19-Mar-21 A 19-Apr-21 A 100% 100%

Actual Work Critical Remaining Work Summary Primary Baseline Page 1 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
Driving of Square Piles ( 150mm x 150mm ) 250d 02-Feb-21 17-Sep-21 03-May-21 A 23-Feb-22 A 100% 100%
Mobilization of Machineries and Materials 29d 02-Feb-21 18-Mar-21 03-May-21 A 18-Feb-22 A 100% 100%
034 Mobilization of piling equipment 9d 04-Mar-21 18-Mar-21 03-May-21 A 04-May-21 A 100% 100%

035 Pile Point Setting out - Square piles 9d 04-Mar-21 18-Mar-21 03-May-21 A 18-Feb-22 A 100% 100%

036 Delivery of piles - for R.C Square pile 150mm x 150mm 20d 02-Feb-21 02-Mar-21 03-May-21 A 17-Feb-22 A 100% 100%

Driving of Square Piles ( 150mm x 150mm ) 221d 19-Mar-21 17-Sep-21 04-May-21 A 23-Feb-22 A 100% 100%
038 - Pondok Jaga = 21 points 4d 19-Mar-21 25-Mar-21 04-May-21 A 10-May-21 A 100% 100%

039 - Foul Drainage = 91 points 15d 26-Mar-21 22-Apr-21 11-May-21 A 30-Jul-21 A 100% 100%

040 - External Staircase = 6 points 1d 23-Apr-21 23-Apr-21 19-Feb-22 A 23-Feb-22 A 100% 100%

041 - Bin Center = 22 points 4d 26-Apr-21 30-Apr-21 02-Aug-21 A 07-Aug-21 A 100% 100%

042 - Suction & Reel Tank = 30 points 5d 03-May-21 10-May-21 09-Aug-21 A 19-Aug-21 A 100% 100%

043 - Flag Pole = 3 points 1d 11-May-21 11-May-21 19-Feb-22 A 23-Feb-22 A 100% 100%

044 - Footpath = 32 points 5d 17-May-21 24-May-21 19-Feb-22 A 23-Feb-22 A 100% 100%

045 - Covered Walkway = 129 points 20d 25-May-21 05-Jul-21 10-Jul-21 A 30-Aug-21 A 100% 100%

046 - Surface Water Drainage = 203 points 33d 06-Jul-21 17-Sep-21 20-Aug-21 A 23-Feb-22 A 100% 100%

Driving of Timber Pile ( Belian Pile ) 118d 06-Jul-21 08-Nov-21 07-Feb-22 A 10-Nov-22 100% 97.4% -204d
Mobilization of Machineries and Materials 57d 06-Jul-21 27-Oct-21 07-Feb-22 A 07-Oct-22 A 100% 100%
047 Mobilization of equipment 2d 06-Jul-21 09-Jul-21 07-Feb-22 A 08-Feb-22 A 100% 100%

048 Pile Delivery and Pile Point Setting out 55d 12-Jul-21 27-Oct-21 09-Feb-22 A 07-Oct-22 A 100% 100%

Driving of Timber Pile ( Belian Pile ) 72d 12-Jul-21 08-Nov-21 23-Jul-22 A 10-Nov-22 100% 76.5% -204d
050 - Roadworks = 3 points 1d 12-Jul-21 12-Jul-21 26-Oct-22 26-Oct-22 100% 0% -220d

051 - Surface water Drainage = 977 points 55d 13-Jul-21 28-Oct-21 23-Jul-22 A 10-Nov-22 100% 79.69% -204d

052 - Water Recticulation = 38 points 7d 29-Oct-21 08-Nov-21 26-Oct-22 03-Nov-22 100% 0% -204d

Driving of Bakau Pile 40d 13-Jul-21 04-Nov-21 01-Apr-22 A 15-Nov-22 100% 91.55% -158d
053 Pile Delivery and Pile Point Setting out - Bakau Pile 20d 13-Jul-21 25-Aug-21 01-Apr-22 A 03-Aug-22 A 100% 100%

054 - Fencing = 356 points 40d 26-Aug-21 04-Nov-21 20-May-22 A 15-Nov-22 100% 64.95% -158d

BLOK PENTADBIRAN & AKADEMIK 544d 10-Dec-20 17-Jun-22 19-Mar-21 A 28-Mar-23 100% 46.03% -217d
Work Below Lowest Floor Finish 72d 10-Dec-20 29-Mar-21 19-Mar-21 A 30-Jul-21 A 100% 100%
058 Excavation for Pile Cap 12d 10-Dec-20 25-Dec-20 19-Mar-21 A 19-May-21 A 100% 100%

059 Cutting Of Piles 10d 28-Dec-20 11-Jan-21 31-Mar-21 A 31-May-21 A 100% 100%

060 Lean Concrete 5d 28-Dec-20 04-Jan-21 31-Mar-21 A 19-Jun-21 A 100% 100%

061 Pile Cap Rebar & Formworks 20d 05-Jan-21 01-Feb-21 03-May-21 A 19-Jun-21 A 100% 100%

062 Pile Cap Concreting Works 20d 05-Jan-21 01-Feb-21 08-May-21 A 01-Jul-21 A 100% 100%

063 Stump Rebar & Formworks 15d 02-Feb-21 23-Feb-21 15-May-21 A 12-Jul-21 A 100% 100%

064 Stump Concreting Works 15d 24-Feb-21 19-Mar-21 22-May-21 A 15-Jul-21 A 100% 100%
065 Stump Remove Formworks 2d 22-Mar-21 23-Mar-21 26-May-21 A 24-Jun-21 A 100% 100%

066 Backfill pilecap 3d 25-Mar-21 29-Mar-21 25-Jun-21 A 30-Jul-21 A 100% 100%

Ground floor 121d 30-Mar-21 21-May-21 02-Aug-21 A 15-Apr-22 A 100% 100%


068 Beam rebar & Formwork 9d 30-Mar-21 15-Apr-21 02-Aug-21 A 24-Nov-21 A 100% 100%

069 Beam Concreting works 2d 16-Apr-21 19-Apr-21 13-Sep-21 A 24-Nov-21 A 100% 100%

070 Beam Remove Formworks 2d 20-Apr-21 22-Apr-21 20-Sep-21 A 24-Nov-21 A 100% 100%

071 Slab and Staircase Rebar & Formworks 6d 23-Apr-21 03-May-21 13-Sep-21 A 03-Feb-22 A 100% 100%

072 Slab and Staircase Concreting Works 1d 04-May-21 04-May-21 20-Sep-21 A 09-Apr-22 A 100% 100%

Actual Work Critical Remaining Work Summary Primary Baseline Page 2 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
073 Slab and Staircase Remove Formworks 1d 06-May-21 06-May-21 16-Oct-21 A 15-Apr-22 A 100% 100%

074 Column Rebar & Formworks 4d 07-May-21 17-May-21 05-Oct-21 A 04-Dec-21 A 100% 100%

075 Column Concreting Works 1d 18-May-21 18-May-21 12-Oct-21 A 23-Dec-21 A 100% 100%

076 Column Remove Formworks 2d 20-May-21 21-May-21 16-Oct-21 A 30-Dec-21 A 100% 100%

First floor 61d 24-May-21 23-Jul-21 20-Oct-21 A 09-Aug-22 A 100% 100%


078 Beam rebar & Formwork 12d 24-May-21 18-Jun-21 20-Oct-21 A 19-Jan-22 A 100% 100%

079 Beam Concreting works 2d 21-Jun-21 24-Jun-21 30-Nov-21 A 21-Jan-22 A 100% 100%

080 Slab and Staircase Rebar & Formworks 3d 25-Jun-21 29-Jun-21 20-Oct-21 A 25-May-22 A 100% 100%

081 Slab and Staircase Concreting Works 1d 30-Jun-21 30-Jun-21 30-Nov-21 A 02-Aug-22 A 100% 100%

082 Slab and staircase Remove Formworks 2d 01-Jul-21 02-Jul-21 20-Dec-21 A 09-Aug-22 A 100% 100%

083 Column Rebar & Formworks 3d 05-Jul-21 09-Jul-21 06-Dec-21 A 08-Feb-22 A 100% 100%

084 Column Concreting Works 3d 12-Jul-21 16-Jul-21 29-Dec-21 A 04-May-22 A 100% 100%

085 Column Remove Formworks 3d 19-Jul-21 23-Jul-21 06-Jan-22 A 16-May-22 A 100% 100%

Second floor 85d 26-Jul-21 13-Oct-21 12-Jan-22 A 20-Aug-22 A 100% 100%


087 Beam rebar & Formwork 12d 26-Jul-21 19-Aug-21 12-Jan-22 A 18-Jul-22 A 100% 100%

088 Beam Concreting works 2d 20-Aug-21 23-Aug-21 12-Jan-22 A 21-Jul-22 A 100% 100%

089 Slab and Staircase Rebar & Formworks 4d 25-Aug-21 30-Aug-21 15-Mar-22 A 18-Jul-22 A 100% 100%

090 Slab and Staircase Concreting Works 10d 02-Sep-21 24-Sep-21 19-Mar-22 A 21-Jul-22 A 100% 100%

091 Slab and staircase Remove Formworks 2d 27-Sep-21 30-Sep-21 24-Mar-22 A 20-Aug-22 A 100% 100%

092 Column Rebar & Formworks 3d 01-Oct-21 05-Oct-21 22-Mar-22 A 25-Jul-22 A 100% 100%

093 Column Concreting Works 3d 06-Oct-21 08-Oct-21 15-Apr-22 A 25-Jul-22 A 100% 100%

094 Column Remove Formworks 3d 11-Oct-21 13-Oct-21 05-May-22 A 11-Aug-22 A 100% 100%

Roof Level 14d 14-Oct-21 02-Nov-21 10-Jun-22 A 20-Sep-22 A 100% 100%


096 Beam rebar & Formwork 10d 14-Oct-21 27-Oct-21 10-Jun-22 A 12-Sep-22 A 100% 100%

097 Beam Concreting works 2d 28-Oct-21 29-Oct-21 23-Jun-22 A 13-Sep-22 A 100% 100%

098 Beam Remove Formworks 2d 01-Nov-21 02-Nov-21 14-Jul-22 A 20-Sep-22 A 100% 100%

Architectural Works 233d 03-Nov-21 17-Jun-22 04-Apr-22 A 28-Mar-23 100% 15.08% -217d
099 Roofing and Roof Plumbing 60d 03-Nov-21 28-Jan-22 08-Aug-22 A 06-Dec-22 100% 50% -220d

100 External Wall 62d 03-Nov-21 03-Feb-22 04-Apr-22 A 03-Nov-22 100% 90% -196d

101 Internal Wall & Partition 62d 03-Nov-21 03-Feb-22 07-Apr-22 A 31-Oct-22 100% 94% -194d

102 Windows 40d 31-Jan-22 01-Apr-22 07-Dec-22 31-Jan-23 100% 0% -220d

103 Doors 20d 04-Feb-22 03-Mar-22 07-Dec-22 03-Jan-23 100% 0% -220d

104 Floor Finishes 45d 31-Jan-22 08-Apr-22 07-Dec-22 07-Feb-23 100% 0% -217d
105 Wall Finishes 45d 31-Jan-22 08-Apr-22 07-Dec-22 07-Feb-23 100% 0% -217d

106 Ceiling Finishes 45d 31-Jan-22 08-Apr-22 07-Dec-22 07-Feb-23 100% 0% -217d

107 Staircase Finishes 20d 11-Apr-22 17-May-22 08-Feb-23 07-Mar-23 100% 0% -217d

108 Sanitary Wares & Fittings 20d 11-Apr-22 17-May-22 08-Feb-23 07-Mar-23 100% 0% -217d

109 Builder's Work in Connection with Services 15d 18-May-22 17-Jun-22 08-Mar-23 28-Mar-23 100% 0% -217d

110 Furniture 15d 11-Apr-22 17-Jun-22 08-Mar-23 28-Mar-23 100% 0% -217d

KANTIN 470d 22-Mar-21 16-Jun-22 08-May-21 A 17-Mar-23 100% 71.25% -210d


Work Below Lowest Floor Finish 73d 22-Mar-21 18-Aug-21 08-May-21 A 30-Jul-21 A 100% 100%
112 Excavation for Pile Cap 7d 22-Mar-21 01-Apr-21 08-May-21 A 19-May-21 A 100% 100%

Actual Work Critical Remaining Work Summary Primary Baseline Page 3 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
113 Cutting Of Piles 7d 05-Apr-21 15-Apr-21 15-May-21 A 31-May-21 A 100% 100%

114 Lean Concrete 6d 16-Apr-21 26-Apr-21 19-May-21 A 19-Jun-21 A 100% 100%

115 Pile Cap Rebar & Formworks 10d 27-Apr-21 17-May-21 24-May-21 A 19-Jun-21 A 100% 100%

116 Pile Cap Concreting Works 10d 18-May-21 04-Jun-21 29-May-21 A 01-Jul-21 A 100% 100%

117 Stump Rebar & Formworks 10d 10-Jun-21 29-Jun-21 10-Jun-21 A 12-Jul-21 A 100% 100%

118 Stump Concreting Works 10d 30-Jun-21 19-Jul-21 12-Jun-21 A 12-Jul-21 A 100% 100%

119 Stump Remove Formworks 8d 20-Jul-21 06-Aug-21 16-Jun-21 A 24-Jul-21 A 100% 100%

120 Backfill pilecap 5d 09-Aug-21 18-Aug-21 25-Jun-21 A 30-Jul-21 A 100% 100%

Ground floor 344d 19-Aug-21 21-Feb-22 01-Jul-21 A 03-Jan-23 100% 91.06% -197d
122 Beam rebar & Formwork 7d 19-Aug-21 30-Aug-21 01-Jul-21 A 05-Jan-22 A 100% 100%

123 Beam Concreting works 2d 02-Sep-21 03-Sep-21 12-Jul-21 A 08-Jan-22 A 100% 100%

124 Beam Remove Formwoorks 2d 06-Sep-21 09-Sep-21 15-Jul-21 A 15-Jan-22 A 100% 100%

125 Slab and Staircase Rebar & Formworks 3d 10-Sep-21 17-Sep-21 24-Jul-21 A 05-Mar-22 A 100% 100%

126 Slab and Staircase Concreting Works 1d 20-Sep-21 20-Sep-21 30-Jul-21 A 10-Mar-22 A 100% 100%

127 Slab and staircase Remove Formworks 2d 23-Sep-21 24-Sep-21 15-Oct-21 A 12-Mar-22 A 100% 100%

128 Column Rebar & Formworks 5d 27-Sep-21 05-Oct-21 12-Oct-21 A 14-Mar-22 A 100% 100%

129 Column Concreting Works 2d 06-Oct-21 07-Oct-21 24-Nov-21 A 14-Mar-22 A 100% 100%

130 Column Remove Formworks 2d 08-Oct-21 11-Oct-21 02-Dec-21 A 25-Apr-22 A 100% 100%

131 Structural Steel Works 50d 12-Oct-21 20-Dec-21 26-Oct-22 03-Jan-23 100% 0% -197d

135 Stage Construction 40d 21-Dec-21 21-Feb-22 11-Oct-21 A 23-Oct-21 A 100% 100%

Roof Level 8d 12-Oct-21 25-Oct-21 03-Feb-22 A 17-Jun-22 A 100% 100%


136 Beam rebar & Formwork 7d 12-Oct-21 20-Oct-21 03-Feb-22 A 20-May-22 A 100% 100%

137 Beam Concreting works 1d 21-Oct-21 21-Oct-21 10-Feb-22 A 27-May-22 A 100% 100%

138 Beam Remove Formworks 2d 22-Oct-21 25-Oct-21 02-Mar-22 A 17-Jun-22 A 100% 100%

Architectural Works 185d 22-Oct-21 16-Jun-22 13-Jun-22 A 17-Mar-23 100% 59% -210d
139 Roofing and Roof Plumbing 30d 05-Nov-21 16-Dec-21 13-Jun-22 A 28-Oct-22 100% 90% -210d

140 External Wall 45d 22-Oct-21 23-Dec-21 04-Jul-22 A 25-Jul-22 A 100% 100%

141 Internal Wall & Partition 45d 22-Oct-21 23-Dec-21 04-Jul-22 A 29-Jul-22 A 100% 100%

142 Windows 30d 24-Dec-21 10-Feb-22 31-Oct-22 09-Dec-22 100% 0% -210d

143 Doors 30d 24-Dec-21 17-Feb-22 31-Oct-22 09-Dec-22 100% 0% -210d

144 Floor Finishes 30d 24-Dec-21 17-Feb-22 03-Oct-22 A 25-Nov-22 100% 24.97% -200d

145 Wall Finishes 30d 24-Dec-21 10-Feb-22 30-Jul-22 A 04-Nov-22 100% 75% -190d

146 Ceiling Finishes 30d 22-Feb-22 07-Apr-22 12-Dec-22 20-Jan-23 100% 0% -210d
147 Sanitary Wares & Fittings 30d 08-Apr-22 30-May-22 23-Jan-23 03-Mar-23 100% 0% -210d

148 Builder's Work in Connection with Services 10d 31-May-22 16-Jun-22 06-Mar-23 17-Mar-23 100% 0% -210d

149 Furniture 40d 08-Apr-22 16-Jun-22 23-Jan-23 17-Mar-23 100% 0% -210d

PRA SEKOLAH 270d 03-Nov-21 17-Jun-22 21-Dec-21 A 11-Apr-23 100% 64.96% -227d
Work Below Lowest Floor Finish 30d 03-Nov-21 06-Jan-22 21-Dec-21 A 19-Mar-22 A 100% 100%
152 Excavation for Pile Cap 5d 03-Nov-21 09-Nov-21 21-Dec-21 A 15-Mar-22 A 100% 100%

153 Cutting Of Piles 5d 10-Nov-21 16-Nov-21 22-Dec-21 A 15-Mar-22 A 100% 100%

154 Lean Concrete 5d 17-Nov-21 23-Nov-21 22-Dec-21 A 15-Mar-22 A 100% 100%

Actual Work Critical Remaining Work Summary Primary Baseline Page 4 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
155 Pile Cap Rebar & Formworks 5d 24-Nov-21 30-Nov-21 23-Dec-21 A 15-Mar-22 A 100% 100%

156 Pile Cap Concreting Works 5d 01-Dec-21 07-Dec-21 24-Dec-21 A 15-Mar-22 A 100% 100%

157 Stump Rebar & Formworks 10d 08-Dec-21 21-Dec-21 27-Dec-21 A 15-Mar-22 A 100% 100%

158 Stump Concreting Works 5d 22-Dec-21 28-Dec-21 29-Dec-21 A 15-Mar-22 A 100% 100%

159 Stump Remove Formworks 2d 29-Dec-21 30-Dec-21 06-Jan-22 A 15-Mar-22 A 100% 100%

160 Backfill pilecap 5d 31-Dec-21 06-Jan-22 08-Jan-22 A 19-Mar-22 A 100% 100%

Ground floor 54d 07-Jan-22 21-Feb-22 16-Mar-22 A 27-Jun-22 A 100% 100%


162 Beam rebar & Formwork 5d 07-Jan-22 14-Jan-22 16-Mar-22 A 16-May-22 A 100% 100%

163 Beam Concreting works 2d 17-Jan-22 18-Jan-22 05-Apr-22 A 17-May-22 A 100% 100%

164 Beam Remove Formworks 1d 20-Jan-22 27-Jan-22 20-May-22 A 27-Jun-22 A 100% 100%

165 Slab Rebar & Formworks 3d 28-Jan-22 03-Feb-22 11-Apr-22 A 14-May-22 A 100% 100%

166 Slab Concreting Works 1d 04-Feb-22 04-Feb-22 27-Apr-22 A 17-May-22 A 100% 100%

167 Slab Remove Formworks 2d 07-Feb-22 08-Feb-22 20-May-22 A 27-Jun-22 A 100% 100%

168 Column Rebar & Formworks 5d 09-Feb-22 15-Feb-22 29-Apr-22 A 19-May-22 A 100% 100%

169 Column Concreting Works 2d 16-Feb-22 17-Feb-22 30-Apr-22 A 20-May-22 A 100% 100%

170 Column Remove Formworks 2d 18-Feb-22 21-Feb-22 05-May-22 A 25-May-22 A 100% 100%

Roof Level 9d 22-Feb-22 04-Mar-22 13-Jun-22 A 25-Jul-22 A 100% 100%


172 Beam rebar & Formwork 5d 22-Feb-22 28-Feb-22 13-Jun-22 A 05-Jul-22 A 100% 100%

173 Beam Concreting works 2d 01-Mar-22 02-Mar-22 15-Jun-22 A 07-Jul-22 A 100% 100%

174 Beam Remove Formworks 2d 03-Mar-22 04-Mar-22 20-Jun-22 A 25-Jul-22 A 100% 100%

Architectural Works 206d 09-Feb-22 17-Jun-22 13-Jun-22 A 11-Apr-23 100% 46.51% -227d
175 Roofing and Roof Plumbing 30d 07-Mar-22 22-Apr-22 01-Jul-22 A 28-Oct-22 100% 90% -172d

176 External Wall 30d 09-Feb-22 24-Mar-22 13-Jun-22 A 27-Sep-22 A 100% 100%

177 Internal Wall & Partition 50d 09-Feb-22 27-Apr-22 01-Jul-22 A 03-Aug-22 A 100% 100%

178 Windows 60d 25-Mar-22 17-May-22 26-Oct-22 17-Jan-23 100% 0% -227d

179 Doors 60d 25-Mar-22 17-May-22 27-Sep-22 A 03-Jan-23 100% 18.18% -216d

180 Floor Finishes 60d 25-Mar-22 17-May-22 26-Oct-22 17-Jan-23 100% 0% -227d

181 Wall Finishes 30d 25-Mar-22 17-May-22 05-Aug-22 A 02-Nov-22 100% 80% -143d

182 Ceiling Finishes 30d 28-Apr-22 17-Jun-22 18-Jan-23 28-Feb-23 100% 0% -227d

183 Sanitary Wares & Fittings 30d 18-May-22 17-Jun-22 01-Mar-23 11-Apr-23 100% 0% -227d

184 Builder's Work in Connection with Services 30d 18-May-22 17-Jun-22 01-Mar-23 11-Apr-23 100% 0% -227d

185 Furniture 30d 28-Apr-22 17-Jun-22 18-Jan-23 28-Feb-23 100% 0% -197d

186 Step Construction 20d 18-May-22 17-Jun-22 01-Sep-22 A 07-Sep-22 A 100% 100%

RUMAH GURU 432d 30-Jun-21 08-Jun-22 11-Jun-21 A 04-Apr-23 100% 44.74% -222d
Work Below Lowest Floor Finish 56d 30-Jun-21 13-Oct-21 11-Jun-21 A 03-Dec-21 A 100% 100%
188 Excavation for Pile Cap 5d 30-Jun-21 06-Jul-21 11-Jun-21 A 17-Nov-21 A 100% 100%

189 Cutting Of Piles 5d 09-Jul-21 19-Jul-21 19-Jun-21 A 19-Nov-21 A 100% 100%

190 Lean Concrete 5d 20-Jul-21 30-Jul-21 15-Jul-21 A 22-Nov-21 A 100% 100%

191 Pile Cap Rebar & Formworks 10d 02-Aug-21 20-Aug-21 17-Jul-21 A 24-Nov-21 A 100% 100%

192 Pile Cap Concreting Works 10d 23-Aug-21 10-Sep-21 23-Jul-21 A 25-Nov-21 A 100% 100%

193 Stump Rebar & Formworks 10d 13-Sep-21 05-Oct-21 30-Jul-21 A 25-Nov-21 A 100% 100%

Actual Work Critical Remaining Work Summary Primary Baseline Page 5 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
194 Stump Concreting Works 2d 06-Oct-21 07-Oct-21 11-Aug-21 A 26-Nov-21 A 100% 100%

195 Stump Remove Formworks 2d 08-Oct-21 11-Oct-21 13-Sep-21 A 03-Dec-21 A 100% 100%

196 Backfill pilecap 2d 12-Oct-21 13-Oct-21 07-Oct-21 A 03-Dec-21 A 100% 100%

Ground floor 88d 14-Oct-21 15-Nov-21 07-Dec-21 A 28-Sep-22 A 100% 100%


198 Beam rebar & Formwork 5d 14-Oct-21 20-Oct-21 07-Dec-21 A 18-Mar-22 A 100% 100%

199 Beam Concreting works 2d 21-Oct-21 22-Oct-21 05-Jan-22 A 18-Mar-22 A 100% 100%

200 Beam Remove Formworks 2d 25-Oct-21 26-Oct-21 12-Jan-22 A 19-Sep-22 A 100% 100%

201 Slab and Staircase Rebar & Formworks 5d 27-Oct-21 02-Nov-21 07-Dec-21 A 20-Sep-22 A 100% 100%

202 Slab and Staircase Concreting Works 1d 03-Nov-21 03-Nov-21 12-Jan-22 A 24-Sep-22 A 100% 100%

203 Slab and staircase Remove Formworks 1d 04-Nov-21 04-Nov-21 18-Dec-21 A 28-Sep-22 A 100% 100%

204 Column Rebar & Formworks 4d 05-Nov-21 10-Nov-21 15-Jan-22 A 01-Jul-22 A 100% 100%

205 Column Concreting Works 1d 11-Nov-21 11-Nov-21 19-Jan-22 A 02-Jul-22 A 100% 100%

206 Column Remove Formworks 2d 12-Nov-21 15-Nov-21 22-Jan-22 A 16-Jul-22 A 100% 100%

First floor 19d 16-Nov-21 16-Dec-21 03-Feb-22 A 30-Sep-22 A 100% 100%


208 Beam rebar & Formwork 5d 16-Nov-21 22-Nov-21 03-Feb-22 A 19-Jul-22 A 100% 100%

209 Beam Concreting works 2d 23-Nov-21 24-Nov-21 21-Feb-22 A 20-Jul-22 A 100% 100%

210 Beam Remove Formworks 3d 25-Nov-21 29-Nov-21 02-Apr-22 A 01-Aug-22 A 100% 100%

211 Slab and Staircase Rebar & Formworks 1d 30-Nov-21 30-Nov-21 03-Feb-22 A 30-Sep-22 A 100% 100%

212 Slab and Staircase Concreting Works 2d 01-Dec-21 02-Dec-21 21-Feb-22 A 30-Sep-22 A 100% 100%

213 Slab and staircase Remove Formworks 3d 03-Dec-21 07-Dec-21 09-Mar-22 A 30-Sep-22 A 100% 100%

214 Column Rebar & Formworks 3d 08-Dec-21 10-Dec-21 23-Feb-22 A 22-Jul-22 A 100% 100%

215 Column Concreting Works 3d 13-Dec-21 15-Dec-21 25-Feb-22 A 23-Jul-22 A 100% 100%

216 Column Remove Formworks 1d 16-Dec-21 16-Dec-21 01-Mar-22 A 25-Jul-22 A 100% 100%

Second floor 21d 17-Dec-21 20-Jan-22 22-Mar-22 A 24-Aug-22 A 100% 100%


218 Beam rebar & Formwork 5d 17-Dec-21 23-Dec-21 22-Mar-22 A 08-Aug-22 A 100% 100%

219 Beam Concreting works 2d 24-Dec-21 27-Dec-21 13-Apr-22 A 11-Aug-22 A 100% 100%

220 Beam Remove Formwoorks 3d 28-Dec-21 30-Dec-21 20-Apr-22 A 24-Aug-22 A 100% 100%

221 Slab and Staircase Rebar & Formworks 1d 31-Dec-21 31-Dec-21 22-Mar-22 A 08-Aug-22 A 100% 100%

222 Slab and Staircase Concreting Works 2d 03-Jan-22 04-Jan-22 13-Apr-22 A 11-Aug-22 A 100% 100%

223 Slab and staircase Remove Formworks 3d 05-Jan-22 07-Jan-22 23-Apr-22 A 24-Aug-22 A 100% 100%

224 Column Rebar & Formworks 3d 10-Jan-22 13-Jan-22 16-Apr-22 A 12-Aug-22 A 100% 100%

225 Column Concreting Works 3d 14-Jan-22 18-Jan-22 19-Apr-22 A 13-Aug-22 A 100% 100%

226 Column Remove Formworks 1d 20-Jan-22 20-Jan-22 23-Apr-22 A 20-Aug-22 A 100% 100%
Roof Level 9d 21-Jan-22 08-Feb-22 26-Aug-22 A 24-Sep-22 A 100% 100%
228 Beam rebar & Formwork 4d 21-Jan-22 28-Jan-22 26-Aug-22 A 06-Sep-22 A 100% 100%

229 Beam Concreting works 2d 31-Jan-22 03-Feb-22 07-Sep-22 A 19-Sep-22 A 100% 100%

230 Beam Remove Formwoorks 3d 04-Feb-22 08-Feb-22 23-Sep-22 A 24-Sep-22 A 100% 100%

Architectural Works 221d 10-Jan-22 08-Jun-22 20-May-22 A 04-Apr-23 100% 15.15% -222d
231 Roofing and Roof Plumbing 10d 09-Feb-22 22-Feb-22 07-Sep-22 A 08-Nov-22 100% 5% -222d

232 External Wall 30d 10-Jan-22 25-Feb-22 20-May-22 A 02-Nov-22 100% 80% -203d

233 Internal Wall & Partition 30d 23-Feb-22 08-Apr-22 20-May-22 A 02-Nov-22 100% 83% -187d

234 Windows 30d 23-Feb-22 08-Apr-22 08-Nov-22 20-Dec-22 100% 0% -222d

Actual Work Critical Remaining Work Summary Primary Baseline Page 6 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
235 Doors 30d 23-Feb-22 08-Apr-22 08-Nov-22 20-Dec-22 100% 0% -222d

236 Floor Finishes 30d 23-Feb-22 08-Apr-22 08-Nov-22 20-Dec-22 100% 0% -222d

237 Wall Finishes 30d 28-Feb-22 13-Apr-22 07-Sep-22 A 23-Nov-22 100% 30% -203d

238 Ceiling Finishes 75d 14-Apr-22 08-Jun-22 20-Dec-22 04-Apr-23 100% 0% -222d

239 Sanitary Wares & Fittings 75d 14-Apr-22 08-Jun-22 20-Dec-22 04-Apr-23 100% 0% -222d

240 Builder's Work in Connection with Services 75d 14-Apr-22 08-Jun-22 20-Dec-22 04-Apr-23 100% 0% -222d

241 Furniture 75d 14-Apr-22 08-Jun-22 20-Dec-22 04-Apr-23 100% 0% -222d

PONDOK JAGA & MSB 143d 20-Dec-21 15-Jun-22 12-Aug-22 A 09-Feb-23 100% 46.99% -184d
Work Below Lowest Floor Finish 16d 20-Dec-21 10-Jan-22 12-Aug-22 A 20-Aug-22 A 100% 100%
244 Excavation for Pile Cap 2d 20-Dec-21 21-Dec-21 12-Aug-22 A 13-Aug-22 A 100% 100%

245 Cutting Of Piles 1d 22-Dec-21 22-Dec-21 15-Aug-22 A 15-Aug-22 A 100% 100%

246 Lean Concrete 2d 23-Dec-21 24-Dec-21 15-Aug-22 A 15-Aug-22 A 100% 100%

247 Pile Cap Rebar & Formworks 3d 27-Dec-21 29-Dec-21 16-Aug-22 A 16-Aug-22 A 100% 100%

248 Pile Cap Concreting Works 1d 30-Dec-21 30-Dec-21 17-Aug-22 A 17-Aug-22 A 100% 100%

249 Stump Rebar & Formworks 1d 31-Dec-21 31-Dec-21 18-Aug-22 A 18-Aug-22 A 100% 100%

250 Stump Concreting Works 3d 03-Jan-22 05-Jan-22 18-Aug-22 A 18-Aug-22 A 100% 100%

251 Stump Remove Formworks 1d 06-Jan-22 06-Jan-22 19-Aug-22 A 19-Aug-22 A 100% 100%

252 Backfill pilecap 2d 07-Jan-22 10-Jan-22 20-Aug-22 A 20-Aug-22 A 100% 100%

Ground floor 10d 11-Jan-22 27-Jan-22 22-Aug-22 A 02-Sep-22 A 100% 100%


253 Ground floor 10d 11-Jan-22 27-Jan-22 22-Aug-22 A 02-Sep-22 A 100% 100%

Roof Level 7d 28-Jan-22 09-Feb-22 26-Sep-22 A 04-Oct-22 A 100% 100%


254 Roof Beam 7d 28-Jan-22 09-Feb-22 26-Sep-22 A 04-Oct-22 A 100% 100%

Architectural Works 92d 10-Feb-22 15-Jun-22 05-Oct-22 A 09-Feb-23 100% 15.28% -184d
255 Roofing and Roof Plumbing 20d 10-Feb-22 09-Mar-22 26-Oct-22 22-Nov-22 100% 0% -184d

256 External Wall 20d 10-Feb-22 09-Mar-22 05-Oct-22 A 25-Oct-22 A 100% 100%

257 Internal Wall & Partition 20d 10-Feb-22 09-Mar-22 05-Oct-22 A 25-Oct-22 A 100% 100%

258 Doors 20d 12-Apr-22 18-May-22 21-Dec-22 17-Jan-23 100% 0% -182d

259 Floor Finishes 20d 12-Apr-22 18-May-22 21-Dec-22 17-Jan-23 100% 0% -182d

260 Wall Finishes 20d 10-Mar-22 11-Apr-22 23-Nov-22 20-Dec-22 100% 0% -184d

261 Windows 10d 06-May-22 20-May-22 06-Jan-23 19-Jan-23 100% 0% -184d

262 Ceiling Finishes 12d 12-Apr-22 05-May-22 21-Dec-22 05-Jan-23 100% 0% -184d

263 Sanitary Wares & Fittings 10d 23-May-22 08-Jun-22 20-Jan-23 02-Feb-23 100% 0% -184d

264 Builder's Work in Connection with Services 5d 09-Jun-22 15-Jun-22 03-Feb-23 09-Feb-23 100% 0% -184d
265 Furniture 15d 19-May-22 13-Jun-22 18-Jan-23 07-Feb-23 100% 0% -182d

BIN CENTER 133d 14-Oct-21 25-Jan-22 16-Jul-22 A 28-Dec-22 100% 23.59% -205d
Work Below Lowest Floor Finish 16d 14-Oct-21 04-Nov-21 16-Jul-22 A 25-Jul-22 A 100% 100%
268 Excavation for Pile Cap 2d 14-Oct-21 15-Oct-21 16-Jul-22 A 18-Jul-22 A 100% 100%

269 Cutting Of Piles 1d 18-Oct-21 18-Oct-21 20-Jul-22 A 20-Jul-22 A 100% 100%

270 Lean Concrete 2d 19-Oct-21 20-Oct-21 21-Jul-22 A 21-Jul-22 A 100% 100%

271 Pile Cap Rebar & Formworks 3d 21-Oct-21 25-Oct-21 16-Jul-22 A 22-Jul-22 A 100% 100%

272 Pile Cap Concreting Works 1d 26-Oct-21 26-Oct-21 23-Jul-22 A 23-Jul-22 A 100% 100%

273 Stump Rebar & Formworks 1d 27-Oct-21 27-Oct-21 16-Jul-22 A 23-Jul-22 A 100% 100%

Actual Work Critical Remaining Work Summary Primary Baseline Page 7 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
274 Stump Concreting Works 3d 28-Oct-21 01-Nov-21 23-Jul-22 A 23-Jul-22 A 100% 100%

275 Stump Remove Formworks 1d 02-Nov-21 02-Nov-21 25-Jul-22 A 25-Jul-22 A 100% 100%

276 Backfill pilecap 2d 03-Nov-21 04-Nov-21 25-Jul-22 A 25-Jul-22 A 100% 100%

Ground floor 10d 05-Nov-21 18-Nov-21 22-Aug-22 A 30-Sep-22 A 100% 100%


277 Ground floor 10d 05-Nov-21 18-Nov-21 22-Aug-22 A 30-Sep-22 A 100% 100%

Roof Level 7d 19-Nov-21 29-Nov-21 26-Oct-22 03-Nov-22 100% 0% -205d


278 Roof Beam 7d 19-Nov-21 29-Nov-21 26-Oct-22 03-Nov-22 100% 0% -205d

Architectural Works 39d 30-Nov-21 25-Jan-22 04-Nov-22 28-Dec-22 100% 0% -205d


279 Structural Steel / Roofing and Roof Plumbing 0d 30-Nov-21 30-Nov-21 04-Nov-22 04-Nov-22 100% 0% -195d

280 External Wall 10d 30-Nov-21 13-Dec-21 04-Nov-22 17-Nov-22 100% 0% -205d

281 Internal Wall & Partition 10d 14-Dec-21 27-Dec-21 18-Nov-22 01-Dec-22 100% 0% -205d

282 Doors 5d 28-Dec-21 03-Jan-22 02-Dec-22 08-Dec-22 100% 0% -205d

283 Floor Finishes 5d 28-Dec-21 03-Jan-22 02-Dec-22 08-Dec-22 100% 0% -205d

284 Wall Finishes 5d 04-Jan-22 10-Jan-22 09-Dec-22 15-Dec-22 100% 0% -205d

285 Sanitary 5d 11-Jan-22 18-Jan-22 16-Dec-22 22-Dec-22 100% 0% -205d

286 Misc 4d 20-Jan-22 25-Jan-22 23-Dec-22 28-Dec-22 100% 0% -205d

SUCTION & HOSE REEL TANK 137d 14-Oct-21 25-Jan-22 18-Jul-22 A 03-Jan-23 100% 20.97% -157d
Work Below Lowest Floor Finish 34d 14-Oct-21 05-Nov-21 18-Jul-22 A 22-Aug-22 A 100% 100%
288 Excavation for Pile Cap 2d 14-Oct-21 15-Oct-21 18-Jul-22 A 15-Aug-22 A 100% 100%

289 Cutting Of Piles 2d 18-Oct-21 19-Oct-21 19-Jul-22 A 15-Aug-22 A 100% 100%

290 Lean Concrete 2d 20-Oct-21 21-Oct-21 20-Jul-22 A 16-Aug-22 A 100% 100%

291 Pile Cap & Stump Rebar & Formworks 3d 22-Oct-21 26-Oct-21 21-Jul-22 A 17-Aug-22 A 100% 100%

292 Pile Cap & Stump Concreting Works 1d 27-Oct-21 27-Oct-21 23-Jul-22 A 18-Aug-22 A 100% 100%

293 Remove Formworks 1d 28-Oct-21 28-Oct-21 25-Jul-22 A 19-Aug-22 A 100% 100%

294 Ground Beam Rebar & Formwork 3d 29-Oct-21 02-Nov-21 19-Aug-22 A 19-Aug-22 A 100% 100%

295 Ground Beam Concreting works 1d 03-Nov-21 03-Nov-21 20-Aug-22 A 20-Aug-22 A 100% 100%

296 Filling 2d 04-Nov-21 05-Nov-21 22-Aug-22 A 22-Aug-22 A 100% 100%

Structural Works 62d 08-Nov-21 09-Dec-21 20-Aug-22 A 21-Nov-22 100% 7.61% -157d
297 Slab Rebar & Formworks 1d 08-Nov-21 08-Nov-21 20-Aug-22 A 24-Aug-22 A 100% 100%

298 Slab Concreting Works 1d 09-Nov-21 09-Nov-21 25-Aug-22 A 03-Sep-22 A 100% 100%

299 Slab Remove Formworks 2d 10-Nov-21 11-Nov-21 08-Sep-22 A 08-Sep-22 A 100% 100%

300 Plinth formwork & concreting 1d 12-Nov-21 12-Nov-21 26-Sep-22 A 26-Sep-22 A 100% 100%

301 Damp proof Membrane 5d 03-Dec-21 09-Dec-21 15-Nov-22 21-Nov-22 100% 0% -157d

302 Structural Steel Works 14d 15-Nov-21 02-Dec-21 26-Oct-22 14-Nov-22 100% 0% -157d
Architectural Works 31d 10-Dec-21 25-Jan-22 22-Nov-22 03-Jan-23 100% 0% -157d
303 External Wall 10d 10-Dec-21 23-Dec-21 22-Nov-22 05-Dec-22 100% 0% -157d

304 Door & Ironmongeries 3d 24-Dec-21 28-Dec-21 06-Dec-22 08-Dec-22 100% 0% -157d

305 Window 1d 29-Dec-21 29-Dec-21 09-Dec-22 09-Dec-22 100% 0% -157d

306 Wall Finishes 10d 30-Dec-21 13-Jan-22 12-Dec-22 23-Dec-22 100% 0% -157d

307 Floor Finishes 5d 14-Jan-22 21-Jan-22 26-Dec-22 30-Dec-22 100% 0% -157d

308 Sanitary Installation 2d 24-Jan-22 25-Jan-22 02-Jan-23 03-Jan-23 100% 0% -157d

SUNDRIES 32d 27-Jan-22 14-Mar-22 06-Oct-22 A 18-Jan-23 0% 0% -205d

Actual Work Critical Remaining Work Summary Primary Baseline Page 8 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
310 Water Tank Support 3d 27-Jan-22 31-Jan-22 06-Oct-22 A 08-Oct-22 A 100% 100%

311 Water Tank & Piping Delivery & Installation 7d 03-Feb-22 11-Feb-22 10-Oct-22 A 27-Oct-22 100% 75% -161d

312 Valves Delivery & Installation 14d 14-Feb-22 03-Mar-22 29-Dec-22 17-Jan-23 100% 0% -205d

313 Test & Commissioning 1d 14-Mar-22 14-Mar-22 18-Jan-23 18-Jan-23 100% 0% -205d

EXTERNAL WORKS 604d 17-Sep-20 09-Jun-22 17-Sep-20 A 28-Mar-23 100% 56.8% -217d
315 SITE PREPARATION, CLEARANCE 14d 17-Sep-20 06-Oct-20 17-Sep-20 A 06-Oct-20 A 100% 100%

315a EARTHWORK - STAGE 1 (BUILDING PLATFORM) 17d 07-Oct-20 29-Oct-20 07-Oct-20 A 05-Feb-21 A 100% 100%

315b EARTHWORK - STAGE 2 (REMAINING AREA) 220d 30-Oct-20 15-Nov-21 06-Feb-21 A 01-Nov-22 100% 83.5% -224d

316a CROSS OVER 61d 20-Sep-21 17-Dec-21 18-Jun-22 A 09-Jul-22 A 100% 100%

316b ROAD, CARPARK AND FOOTPATH 105d 20-Dec-21 08-Jun-22 02-Nov-22 28-Mar-23 100% 0% -224d

317 SURFACE WATER DRAINAGE 75d 20-Dec-21 13-Apr-22 11-Aug-22 A 17-Jan-23 100% 20.61% -204d

318 SEWERAGE WORKS 124d 16-Nov-21 27-May-22 05-Jun-21 A 02-Nov-22 100% 95.4% -120d

319 WATER RETICULATION 90d 09-Nov-21 23-May-22 26-Oct-22 28-Feb-23 100% 0% -204d

320 COVERED WALKWAY 120d 16-Nov-21 23-May-22 20-Apr-22 A 23-Jan-23 100% 47.22% -177d

321 FENCING AND GATES 125d 16-Nov-21 30-May-22 11-Jun-22 A 26-Dec-22 100% 64.95% -158d

322 FOOTBALLL FIELD 40d 16-Nov-21 10-Jan-22 06-Mar-21 A 08-Nov-22 100% 75% -170d

323 WORK BEYOND LOT BOUNDARIES / MISC 90d 11-Jan-22 09-Jun-22 10-Jun-22 A 20-Jan-23 100% 30.02% -170d

TURFING AND LANDSCAPING 30d 14-Apr-22 08-Jun-22 17-Jan-23 28-Feb-23 100% 0% -204d
Turfing 30d 14-Apr-22 08-Jun-22 17-Jan-23 28-Feb-23 100% 0% -204d
324 Spot Turfing 30d 14-Apr-22 08-Jun-22 17-Jan-23 28-Feb-23 100% 0% -204d

Landscaping 30d 14-Apr-22 08-Jun-22 17-Jan-23 28-Feb-23 100% 0% -204d


326 Tree 30d 14-Apr-22 08-Jun-22 17-Jan-23 28-Feb-23 100% 0% -204d

327 Shrubs 30d 14-Apr-22 08-Jun-22 17-Jan-23 28-Feb-23 100% 0% -204d

SAFETY MEASURE COMPLIANCE 384d 21-Sep-20 16-Jun-22 21-Sep-20 A 25-Oct-22 A 100% 100%
012 PPE PREPARATION 1d 21-Sep-20 21-Sep-20 21-Sep-20 A 21-Sep-20 A 100% 100%

013 SAFETY, TRAFFIC, WARNING SIGN AND LIGHTS 24d 22-Sep-20 23-Oct-20 22-Sep-20 A 23-Oct-20 A 100% 100%

014a TRAFFIC CONTROL & SIGNAGES 359d 26-Oct-20 16-Jun-22 26-Oct-20 A 25-Oct-22 A 100% 100%

014b SESCO SHUT DOWN FOR PILING WORKS 5d 25-Aug-21 02-Sep-21 13-Aug-21 A 28-Feb-22 A 100% 100%

MECHANICAL & ELECTRICAL WORKS 283d 11-Oct-21 13-Apr-22 13-Sep-21 A 15-Feb-23 100% 14.6% -225d
A - ELECTRICAL SYSTEM 211d 11-Oct-21 06-Apr-22 11-Apr-22 A 14-Feb-23 100% 11.24% -224d
330 EXTERNAL HV/LV ELECTRICAL DISTRIBUTION 60d 28-Oct-21 09-Mar-22 26-Oct-22 17-Jan-23 100% 0% -224d

331 INTERNAL LIGHTING & POWER INSTALLATION 60d 11-Oct-21 06-Apr-22 11-Apr-22 A 14-Feb-23 100% 18.24% -224d

332 LIGHTNING PROTECTION AND EARTHING SYSTEM 105d 18-Oct-21 21-Mar-22 18-Jul-22 A 17-Jan-23 100% 0.75% -224d

333 STREET & COMPOUND LIGHTING SYSTEM 80d 09-Nov-21 07-Mar-22 26-Oct-22 14-Feb-23 100% 0% -224d
334 STANDBY GENERATOR SET SYSTEM 60d 16-Nov-21 31-Mar-22 26-Oct-22 17-Jan-23 100% 0% -204d

B - EXTRA LOW VOLTAGE SYSTEM 198d 11-Oct-21 11-Apr-22 18-Apr-22 A 14-Feb-23 100% 0.45% -224d
336 EXTERNAL TELECOMMUNICATION SYSTEM 60d 17-Nov-21 08-Apr-22 26-Oct-22 17-Jan-23 100% 0% -204d

337 INTERNAL TELECOMMUNICATION SYSTEM 72d 03-Nov-21 17-Feb-22 18-Apr-22 A 30-Dec-22 100% 5.8% -222d

338 ICT 30d 18-Feb-22 05-Apr-22 02-Jan-23 10-Feb-23 100% 0% -222d

339 SMATV SYSTEM 40d 11-Oct-21 07-Jan-22 26-Oct-22 20-Dec-22 100% 0% -224d

340 AUDIO VISUAL SYSTEM 48d 19-Oct-21 18-Jan-22 26-Oct-22 30-Dec-22 100% 0% -222d

341 SOUND REINFORCEMENT SYSTEM 48d 03-Nov-21 28-Jan-22 26-Oct-22 30-Dec-22 100% 0% -222d

Actual Work Critical Remaining Work Summary Primary Baseline Page 9 of 10      TASK filter: All Activities
Remaining Work Milestone Baseline Milestone © Oracle Corporation
Pembinaan Gantian Penuh 12 Bilik Darjah Dan (10 Unit) Rumah Guru Dan Lain Lain Kemudahan Di Sekolah Kebangsaan Kg. Tanam, Dalat
Work Programme
Activity ID Activity Name Duration BL Project BL Project Start Finish Schedule % Performance % Total 2021 2022 2023
Start Finish Complete Complete Float A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
342 STAGE LIGHTING SYSTEM 40d 10-Jan-22 11-Apr-22 21-Dec-22 14-Feb-23 100% 0% -224d

C - MECHANICAL SYSTEM 283d 11-Oct-21 13-Apr-22 13-Sep-21 A 15-Feb-23 100% 23.54% -225d
COLD WATER SUPPLY SYSTEM 283d 11-Oct-21 13-Apr-22 13-Sep-21 A 27-Jan-23 100% 13.37% -212d
345 Pondok Jaga 30d 27-Oct-21 07-Dec-21 05-Sep-22 A 23-Nov-22 100% 30.7% -204d

346 Pentadbiran & Akademik 60d 11-Oct-21 13-Apr-22 13-Sep-21 A 17-Jan-23 100% 13.26% -225d

347 Rumah Guru 125d 11-Oct-21 13-Apr-22 18-Apr-22 A 17-Jan-23 100% 19.66% -222d

348 Kantin & Dataran Perhimpunan 125d 11-Oct-21 13-Apr-22 18-Apr-22 A 17-Jan-23 100% 52% -222d

349 Pra Sekolah 70d 11-Oct-21 17-Jan-22 04-Jul-22 A 27-Jan-23 100% 3% -212d

350 Pump Room 110d 27-Oct-21 08-Apr-22 05-Sep-22 A 17-Jan-23 100% 0.07% -204d

351 Bin Center 30d 08-Dec-21 20-Jan-22 05-Sep-22 A 05-Dec-22 100% 3.75% -173d

SANITARY PLUMBING SERVICES 283d 11-Oct-21 13-Apr-22 20-Sep-21 A 10-Feb-23 100% 45.33% -222d
353 Pondok Jaga 30d 27-Oct-21 07-Dec-21 05-Sep-22 A 28-Nov-22 100% 23.1% -167d

354 Pentadbiran & Akademik 125d 11-Oct-21 13-Apr-22 20-Sep-21 A 27-Jan-23 100% 45.83% -212d

355 Rumah Guru 125d 11-Oct-21 13-Apr-22 18-Apr-22 A 10-Feb-23 100% 37.89% -222d

356 Kantin & Dataran Perhimpunan 125d 11-Oct-21 13-Apr-22 18-Apr-22 A 12-Dec-22 100% 73% -181d

357 Pra Sekolah 70d 11-Oct-21 17-Jan-22 18-Apr-22 A 16-Dec-22 100% 47% -181d

358 Pump Room 110d 27-Oct-21 08-Apr-22 05-Sep-22 A 22-Dec-22 100% 62% -186d

359 Bin Center 30d 08-Dec-21 20-Jan-22 05-Sep-22 A 15-Nov-22 100% 52.5% -158d

AIR CON, MECHANICAL VENTILATION 276d 11-Oct-21 18-Feb-22 20-Sep-21 A 15-Feb-23 100% 30.71% -225d
361 Pentadbiran & Akademik 90d 11-Oct-21 18-Feb-22 20-Sep-21 A 17-Jan-23 100% 33.33% -225d

362 Kantin & Dataran Perhimpunan 81d 22-Oct-21 18-Feb-22 26-Oct-22 15-Feb-23 100% 0% -225d

363 MSB 75d 01-Nov-21 18-Feb-22 03-Nov-22 15-Feb-23 100% 0% -225d

FIRE FIGHTING & PROTECTION SYSTEM 258d 14-Oct-21 18-Feb-22 20-Sep-21 A 24-Jan-23 100% 13.38% -209d
365 Pondok Jaga 87d 14-Oct-21 18-Feb-22 05-Sep-22 A 17-Jan-23 100% 31.03% -204d

366 Pentadbiran & Akademik 70d 14-Oct-21 21-Jan-22 20-Sep-21 A 19-Jan-23 100% 12.24% -209d

367 Rumah Guru 65d 14-Oct-21 13-Jan-22 26-Oct-22 24-Jan-23 100% 0% -209d

368 Kantin & Dataran Perhimpunan 63d 17-Nov-21 18-Feb-22 18-Jul-22 A 16-Jan-23 100% 7.35% -204d

369 Pra Sekolah 20d 22-Nov-21 17-Dec-21 26-Oct-22 22-Nov-22 100% 0% -164d

370 Pump Room 55d 22-Nov-21 11-Feb-22 05-Sep-22 A 06-Jan-23 100% 4.13% -197d

PROVISIONAL SUM 46d 04-Mar-22 20-May-22 04-Jan-23 08-Mar-23 100% 0% -210d


372 Lab Furniture 26d 04-Mar-22 13-Apr-22 04-Jan-23 08-Feb-23 100% 0% -220d

373 Signages 20d 14-Apr-22 20-May-22 09-Feb-23 08-Mar-23 100% 0% -210d

HANDOVER 58d 14-Apr-22 21-Jun-22 16-Feb-23 14-Apr-23 0% 0% -317d

374 TEST AND COMMISSIONING 30d 14-Apr-22 08-Jun-22 16-Feb-23 29-Mar-23 100% 0% -225d
375 AUTHORITY INSPECTION 7d 09-Jun-22 17-Jun-22 30-Mar-23 07-Apr-23 100% 0% -225d

376 HANDING OVER 3d 18-Jun-22 21-Jun-22 12-Apr-23 14-Apr-23 100% 0% -317d

Actual Work Critical Remaining Work Summary Primary Baseline Page 10 of 10      TASK filter: All Activities