ABSTRACT ESTIMATE
Sl.No. Description of Item Quantity Rate (in Rs.) Unit Amount (in Rs.)
1 of 5
6 Supply and erecting of 1.00 HP (25 mm x 25 mm) single phase
ISI Monoblock CI body motor pump set conforming to IS
9079:2002 approved make centrifugal water pump with
impeller, priming funnel cork, companion metallic flanges with
bolts and nuts and mounted on a common shaft of high
1 8175.00 Nos 8,175
coefficient squirrel cage induction motor totally enclosed and
fan cooled tyupe suitable to operate on 230 V single phase 50
HZ , 1440 RPM AC power supply excluding suction/delivery pipe
with nuts duly grouted on existing CC foundation and bolts,
spring washer of requistie size for monoblock motor and pump
7 Brick masonry in CM (1:6) with bricks of traditional size 23 x 11 x
7 cm 2nd class including cost and conveyance of all materials
5.98 4968.48 cum 29,712
and all labour charges etc., complete for finished item of work
for Basement.
8 Plastering with CM 2 coats, 12mm thick, base coat in CM (1:5),
8mm thick and top coat in CM (1:3), 4mm thick with sponze
26 317.39 sqm 8,252
finishing including cost and conveyance of all materials and all
labour charges etc., complete for walls.
9 Supply of 3 Core 2.5 Sqmm Flat Copper cable of ISI for
20 80.00 rmt 1,600
Submersible Motors confirming to IS:694:1990.
10 Supply and fixing of MS clamp set (2 Nos.) suitable for 32 mm
10 853.00 Nos 8,530
diameter pipe with 8 Nos. nuts and bolts including all charges
11 Supplying and fixing NP bib taps of size 12.70mm dia of Indian
make Seiko including cost and conveyance of all materials,
5 351.76 Nos 1,759
labour charges etc., complete for finished item of work in all
floors for 400 Grams
12 Water purifier (Drinking water solution) detailed circular will be
1 25000.00 Nos 25,000
issued later
13 Provision for SEIGNIORAGE CHARGES @ 1.00% Percentag
1 1204.11 1,204
e
14 Provision for PS Charges @ 3.00% Percentag
1 4090.32 4,090
e
15 Provision for Quality Control Charges @ 0.50% Percentag
1 681.72 682
e
16 Provision for NAC Charges @ 0.1% Percentag
1 120.41 120
e
17 Provision for GST @ 12.00% Percentag
1 14608.29 14,608
e
Total - - 1,41,116
2 of 5
DETAILED ESTIMATE
3 of 5
Supply and erecting of 1.00 HP (25 mm x 25 mm) single phase ISI Monoblock CI body motor pump set conforming to IS
9079:2002 approved make centrifugal water pump with impeller, priming funnel cork, companion metallic flanges with
bolts and nuts and mounted on a common shaft of high coefficient squirrel cage induction motor totally enclosed and fan
cooled tyupe suitable to operate on 230 V single phase 50 HZ , 1440 RPM AC power supply excluding suction/delivery pipe
with nuts duly grouted on existing CC foundation and bolts, spring washer of requistie size for monoblock motor and pump
Erecting of 1 HP mono block mator pump set 1 0 0 0 1
Total 1 Nos 8175 8,175
Brick masonry in CM (1:6) with bricks of traditional size 23 x 11 x 7 cm 2nd class including cost and conveyance of all
materials and all labour charges etc., complete for finished item of work for Basement.
Long Walls 2 3.5 0.23 2 3.22
Short Walls 2 3 0.23 2 2.76
Total 5.98 cum 4968.48 29,712
Plastering with CM 2 coats, 12mm thick, base coat in CM (1:5), 8mm thick and top coat in CM (1:3), 4mm thick with sponze
finishing including cost and conveyance of all materials and all labour charges etc., complete for walls.
Long Walls 2 3.5 0 2 14
Short Walls 2 3 0 2 12
Total 26 sqm 317.39 8,252
Supply of 3 Core 2.5 Sqmm Flat Copper cable of ISI for Submersible Motors confirming to IS:694:1990.
Flat Cable Wire 1 20 0 0 20
Total 20 rmt 80 1,600
Supply and fixing of MS clamp set (2 Nos.) suitable for 32 mm diameter pipe with 8 Nos. nuts and bolts including all
charges
MS Clamp Set 10 0 0 0 10
Total 10 Nos 853 8,530
Supplying and fixing NP bib taps of size 12.70mm dia of Indian make Seiko including cost and conveyance of all materials,
labour charges etc., complete for finished item of work in all floors for 400 Grams
NP bib taps of size 12.70mm for 400 Grams 5 0 0 0 5
Total 5 Nos 351.76 1,759
Water purifier (Drinking water solution) detailed circular will be issued later
Water purifier Aquaguard 1 0 0 0 1
Total 1 Nos 25000 25,000
Provision for SEIGNIORAGE CHARGES @ 1.00%
Total 1 Perce 1204.11 1,204
ntage
Provision for PS Charges @ 3.00%
Total 1 Perce 4090.32 4,090
ntage
4 of 5
Provision for Quality Control Charges @ 0.50%
Total 1 Perce 681.72 682
ntage
Provision for NAC Charges @ 0.1%
Total 1 Perce 120.41 120
ntage
Provision for GST @ 12.00%
Total 1 Perce 14608.29 14,608
ntage
5 of 5