You are on page 1of 9

CSM TRAINERS & CONSULTANTS

LABOUR & EQUIPMENT PRODUCTIVITY DETAILS

8HRS
RESOURCES - LABOUR AND EQUIPMENT
SR. NO. ITEM PRODUCTIVITY
UNIT QTY LABOUR EQUIPMENT
COM
OPER- HELP- LABO- MAS- SHOV- DIGG- ROLL-
EXCAVATION & EARTHWORKS PACT-
ATOR ER UR ON EL ER ER
OR
Excavation for foundation pits in
1 Cum 150 1 1 1
normal ground
Excavation for foundations in
2 strips/trenches in normal Cum 130 1 1 1
ground
Hand excavation in normal
3 Cum 3 1
ground upto 1.5m lift
Foundation bed levelling &
4 Cum 90 2 1
compaction
Backfilling in 150mm layers in
5 Cum 180 2 1 0.75 1
buildings below slab on grade
Backfilling around building in
6 Cum 200 2 1 0.75 1
150mm layers
CONCRETE RAPID
DISMANTLING & DISPOSAL (MANUAL) LABOUR
BREAKER BREAKER
1 Plain Concrete/Block Walls Cum 5 2 1

2 Hard Rock/Reinforced Concrete Cum 2 2 2

3 Concrete Paving Sqm 100 2 1


4 Asphalt & Subase Sqm 16 1 1
5 Pile Head Cutting - 300mm Dia No 5 1 1
6 Pile Head Cutting - 600mm Dia No 5 2 1
WOOD CUTTING
SHUTTER MAKING CARPENTER HELPER
MACHINE
1 Columns (Square/Rectangular) Sqm 14 1 1 1

2 Wall Shutter Sqm 22 1 1 1

3 Beam Bottom Sqm 14 1 1 1

4 Beam Sides Sqm 20 1 1 1

5 Staicase/Steps Sqm 8 1 1 1
8HRS
PRODUCTIVITY
SR. NO. ITEM LABOUR
UNIT QTY

CON
CONCRETE WORKS CARPENTER FITTER HELPER
MASON

1 PCC Below Footings

a Formwork Sqm 40 1 1
b Concrete Cum 20 2 3
2 PCC Below Slab on Grade

a Formwork Sqm 25 1 1
b Concrete Cum 40 2 3
3 Column Footings/Pile Caps

a Formwork Sqm 30 2 2
b Reinforcement (Fabrication & Fix) Kg 170 1
c Concrete Cum 55 2 2
4 Strip Footings

a Formwork Sqm 25 2 2
b Reinforcement (Fabrication & Fix) Kg 170 1
c Concrete Cum 55 2 2
5 Pedestals (Neck Column)

a Formwork Sqm 25 2 1
b Reinforcement (Fabrication & Fix) Kg 160 1
c Concrete Cum 20 1 2
6 Tie Beams

a Formwork Sqm 30 2 1
b Reinforcement (Fabrication & Fix) Kg 180 1
c Concrete Cum 20 2 2
7 Slab on Grade

a Formwork & Joints Sqm 200 2 1


b Mesh Reinforcement Sqm 300 2
c Bar Reinforcement (Fabrication & Fix) Kg 250 1
d Concrete - Trowel Finished Cum 40 2 3
8 Retaining Walls

a Formwork Sqm 30 3 1
b Reinforcement (Fabrication & Fix) Kg 160 1
c Concrete Cum 18 1 2
9 Columns Upto 0.5 Sqm in area (Using Fabricated Forms)

a Formwork Sqm 14 2 1
b Reinforcement (Fabrication & Fix) Kg 160 1
c Concrete Cum 9 1 2
10 Beams

a Formwork Sqm 20 2 2
b Reinforcement (Fabrication & Fix) Kg 160 1
c Concrete Cum 15 1 2
11 Slabs (Solid)

a Formwork Sqm 15 1 1
b Reinforcement (Fabrication & Fix) Kg 200 1
c Concrete Cum 75 3 3
12 Parapets

a Formwork Sqm 20 2 2
b Reinforcement (Fabrication & Fix) Kg 175 1
c Concrete Cum 12 1 1
13 Cantilevers

a Formwork Sqm 12 1 1
b Reinforcement (Fabrication & Fix) Kg 180 1
c Concrete Cum 50 3 3
14 Stairs

a Formwork Sqm 15 1 1
b Reinforcement (Fabrication & Fix) Kg 170 1
c Concrete Cum 20 1 1
8HRS
SR. NO. ITEM LABOUR
UNIT QTY
BLOCK WORK BLOCK MASON HELPER

Sub-Structure - Solid Blocks


1 200mm Blockwork Sqm 12 1 1
Super Structure (Upto 3m Height) - Solid Blocks
1 100mm Blockwork With Pointing Sqm 15 1 2

2 150mm Blockwork With Pointing Sqm 13 1 2

3 200mm Blockwork With Pointing Sqm 10 1 2

4 250mm Blockwork With Pointing Sqm 8 1 2


Super Structure (Upto 3m Height) - Hollow Blocks
2 200mm Blockwork With Pointing Sqm 16 1 2
200mm Blockwork With In Non-
3 Sqm 12 1 2
Straight Walls With Pointing
4 150mm Blockwork With Pointing Sqm 16 1 2
150mm Blockwork With In Non-
5 Sqm 12 1 2
Straight Walls With Pointing
100mm Blockwork In Straight Walls
6 Sqm 18 1 2
With Pointing
100mm Blockwork With In Non-
7 Sqm 14 1 2
Straight Walls With Pointing
Miscellaneous
1 Cover Block Sqm 9 1 1
2 Block Shifting GF To 3RD Floor No 240 1

PLASTER PLASTER MASON HELPER

1 Plastering Accessories Fixing Sqm 60 1 1


Internal Plaster 12mm Thick On
2 Sqm 16 1 1
Walls
Internal Plaster 12mm Thick On
3 Sqm 12 1 1
Ceilings
External Plaster 19mm Thick (Upto
4 Sqm 20 1 1
3m High)
External Plaster 19mm Thick (Over
5 Sqm 18 1 1
3m High)
6 External Plaster - Rush Coat Sqm 100 1 1

7 Compresses Plaster Sqm 60 1 1

8 Sub-Frame Fixing No 5 1 1
TILING WORK TILER HELPER

1 Ceramic Floor Tiles Sqm 20 1 1


2 Ceramic Wall Tiles Sqm 18 1 1
3 Ceramic Tiles Skirting LM 40 1 1
4 Ceramic Floor/Wall Tiles Grouting Sqm 32 1 1
5 Ceramic Cloustra Work Sqm 6 1 1
6 Granite/Marble Threshold No 10 1 1
7 Granite/Marble Floor Tiles Sqm 10 1 1
8 Terrazzo Tiles Sqm 20 1 1
9 Terrazzo Skirting LM 40 1 1
10 Terrazzo Treads & Risers LM 30 1 1
11 Floor Screed 50mm Thick Sqm 27 1 1
12 Interlocking Pavers Sqm 48 1 1
13 Kerbstone m 56 1 1

FALSE CEILING CELLER HELPER

1 Suspension System Sqm 35 1 1


2 Ceiling Tiles Sqm 60 1 1
3 Gypsum Ceiling/Cornish Sqm 2.5 1 1
4 Dry Wall Partition Sqm 20 1 1

PAINT WORK PAINTER HELPER

1 Prime Coat Sqm 200 1 1


2 Surface Preparation For Paint Sqm 80 1
Paint 1st Coat - Brush Application
3 Sqm 100 1 1
(Emulsion Paint)
Paint 2nd Coat - Brush Application
4 Sqm 100 1 1
(Emulsion Paint)
Paint 1st Coat - Roller Application
5 Sqm 125 1 1
(Emulsion Paint)
Paint 2nd Coat - Roller Application
6 Sqm 125 1 1
(Emulsion Paint)
Paint 1st Coat - Brush Application
7 Sqm 60 1 1
(Enamel Paint)
Paint 2nd Coat - Brush Application
8 Sqm 60 1 1
(Enamel Paint)
Paint 1st Coat - Roller Application
9 Sqm 95 1 1
(Enamel Paint)
Paint 2nd Coat - Roller Application
10 Sqm 70 1 1
(Enamel Paint)
11 Epoxy Paint on Floors Per Coat Sqm 50 1 1
Bitumen Paint For Waterproofing
12 Sqm 50 1
Single Coat
Ebooks

100 Autocad Floor Plan 200 Autocad Commands 500 Various Sizes of House Plans
SSSSS SSSSS SSSSS
₹99.00 ₹49.00 ₹299.00

AutoCAD Exercises Learn 2d and 3d Autocad House Floor Plan Building Estimation Notes
Pratice Drawings SSSSS SSSSS
SSSSS ₹99.00 ₹299.00
₹49.00

https://www.civildigitalstore.com/product-category/ebooks/ 1/4
Ebooks - Civil DigitalStore

Civil Engineering 50 Practical Knowledge Civil Engineering Indian Standards Code Civil Engineering Interview Questions
SSSSS Books SSSSS
₹49.00
SSSSS ₹149.00
₹199.00

Civil Engineering Objective Type Questions Civil Site Knowledge Book Construction Quantity Surveying
SSSSS SSSSS SSSSS
₹99.00 ₹200.00 ₹299.00

Construction Work Checklist Construction Work Contracts Estimation and Costing


SSSSS SSSSS SSSSS
₹149.00 ₹149.00 ₹299.00

https://www.civildigitalstore.com/product-category/ebooks/ 2/4
Ebooks - Civil DigitalStore

Practical Hand Book for Building Road Construction Notes Shorts Notes Guide for Civil Engineer
Construction SSSSS SSSSS
SSSSS ₹149.00 ₹49.00
₹299.00

Site Engineer Pocket Data Standard Data for Civil Site Engineer Thumb Rule for Site Engineer
SSSSS SSSSS SSSSS
₹99.00 ₹99.00 ₹149.00

Thumb Rules For Civil Engineer Vastu Shastra Tips for Building
SSSSS Construction
₹200.00
SSSSS
₹99.00

https://www.civildigitalstore.com/product-category/ebooks/ 3/4

You might also like