SCREEDS
1 Floor screeds-small areas ( 1 2 30 Sqm
2 Floor screeds-large areas 1 2 100 Sqm
3 Roof screeds to falls 1 2 35 Sqm
WALL TILING
1 Wall tiling-small areas 1 1 7 Sqm
2 Wall tiling-large areas 1 1 12 Sqm
3 Skirtings 1 1 30 Sqm
4 Grouting 1 50 Sqm
FLOOR TILING
1 Floor tiling-small areas 1 1 10 Sqm
2 Floor tiling-large areas 1 1 13 Sqm
3 Grouting 1 55 Sqm
4 Terrazzo tiles 1 1 16 Sqm
5 Marble tiles 1 1 6 Sqm
6 Grano 1 1 18 Sqm
7 Mossaic tiles 1 1 16 Sqm
Painting
Stucco 75 Sqm
First Coat Paint 75 Sqm
Final Coat Paint 50 Sqm
Production Target Outputs
CONCRETE WORK
Team Size Production
Re Activity Steel Fixer per team day
Carpent Mason Labourer
1 Concrete pile caps/bases-pump 1 2 4 16 Cum
2 Concrete founds/ground beams-
pump 1 2 4 20 Cum
3 Concrete raft slabs-pump 1 2 4 65 Cum
4 Concrete surface beds-pump 1 2 4 25 Cum
5 Concrete retaining walls-pump 1 2 4 18 Cum
6 Concrete walls-pump 1 2 4 15 Cum
7 Concrete columns-in foundations 1 2 4 12 Cum
8 Concrete columns 1 2 4 12 Cum
9 Concrete susp slabs/beams-pump 1 2 4 50 Cum
10 Concrete susp slabs/beams-crane 1 2 4 35 Cum
11 Concrete isolated beams 1 2 4 15 Cum
12 Concrete parapet/upstand walls 1 2 4 12 Cum
13 Concrete stairs/landings 1 2 4 10 Cum
14 Concrete blinding-pile caps/bases 2 4 18 Cum
15 Concrete blinding-under slabs 2 4 25 Cum
16 Power float surface beds/slabs 2 1 200 Sqm
REINFORCEMENT
Team Size Production
Re Activity Steel Fixer per team day
Carpent Mason Labourer
1 In pile caps/column bases 1 350 Kg
2 In foundations/ground beams 1 250 Kg
3 In raft slabs 1 350 Kg
4 In columns 1 250 Kg
5 In walls 1 250 Kg
6 In beams 1 350 Kg
7 In suspended slabs 1 350 Kg
8 In hollow rib slabs 1 200 Kg
9 Mesh reinforcement in surface
beds 1 400 Sqm
SERVICES/CEILING/DRY WALL PARTITIONS
Team Size Production
Re Activity Steel Fixer per team day
Carpent Mason Labourer
MEP INSTALLATIONS
1 MEP 1st fix installations-small 100-120m2
areas
2 MEP 1st fix installations-large 120-150m2
areas
3 MEP 2nd fix installations-small 60-80m2
areas
4 MEP 2nd fix installations-large 80-100m2
areas
SUSPENDED CEILINGS
1 Suspended ceiling grids 45-50m2
2 Suspended ceiling tiles-drop in 100-120m2
3 Suspended ceiling/gypsum 20
boarding. Sqm
4 Suspended ceiling/gypsum skim 14 Sqm
STRIKE
1 Pile caps/bases 1 0.5 65.0m2
2 Columns 1 0.5 50.0m2
3 Walls 1 0.5 70.0m2
4 Suspended slabs 1 0.5 50.0m2
5 Parapet/upstand walls 1 0.5 45.0m2
6 Beams 1 0.5 35.0m2
7 Stairs/landings 1 0.5 30.0m2
MASONARY WORK
Team Size Production
Re Activity Steel Fixer per team day
Carpent Mason Labourer
BLOCKWORK
1 Solid blockwork in foundations
1 1 8m2
2 Solid blocks in walls 1 1 8m2
3 100mm-200mm blocks in walls
1 1 6m2
4 290mm blocks in walls 1 1 10m2
5 390mm blocks in walls 1 1 8m2
6 Bitumen paint to blockwork 1 40.0m2
SITE WORKS/ROADS & PAVING
Team Size Production
Re Activity Steel Fixer per team day
Carpent Mason Labourer
1 Lay PC kerb base-straight runs 1 1 30 lm
2 Lay PC kerb-curved runs 1 1 25 lm
3 Concrete haunching 1 1 40 lm
4 Lay PC kerbs 1 1 15 lm
Base course 1000m2
Prime coat 3500m2
Aphalte paving 4000m2
REINFORCEMENT
Team Size Production
Re Activity Steel Fixer per team day
Carpent Mason Labourer
1 In pile caps/column bases 1 650
2 In foundations/ground beams 1 250
3 In raft slabs 1 750
4 In columns 1 250
5 In walls 1 250
6 In beams 1 350
7 In suspended slabs 1 600
8 In hollow rib slabs 1 200
9 Mesh reinforcement in surface 1 400
beds Sqm