You are on page 1of 2

Team: Jjamppong CE-4202

Members: De Mesa, Shara Mae Z.


Higuit, Jewel Emerald V.
Marasigan, Jean A.
Tejada, Allan Cedric P.
Tolentino, Julius Mae P.
Uao, Lyka Mae O.

LABOR PRODUCTION RATES

EXCAVATION Laborers Production rates


Manual Excavation 1 Helper
Backfill + levelling 1 Helper
Shaping of sloped earth for blinding for 1 Mason + 2 3
1.35 m /man/day
bases including compaction Helper

PRODUCTIVITY Laborers Hourly Product


Product ion per
ion 10
Rates hours
Formworks - Average
Formworks Columns 2 Carpenters, 1 9
Helper
Formworks - Shear Wall/Walls
Formworks - Beam & Stairs 2 Carpenters, 1 4
helper
Formworks - Tie Beams 2 Carpenters, 1 1 10
helper
Formworks - Slab decking 2 Carpenters, 1 1.6 16
helper
Concrete Pouring- Slab on Fill (Direct 3 masons, 6 1.8 150
Pouring) helpers
Concrete Pouring- Columns 8 helpers 1.40 10
Concrete Pouring- Suspended Slab 3 masons + 6 1.8 150
(Pumpcrete) helpers
Concrete Pouring- Stairs (Crane & Bucket) 8 helpers 1 7
Concrete Pouring- Mat Foundation (PCD) 1 mason + 4 12 120
helpers
Fix rebar to footings and tie beams 1 steel fixer 78
Fix rebar to walls, columns, beams, solid 1 steel fixer 38
slab
fix rebar to mesh reinforcement 1 steel fixer 15
Fix rebar to hidden beams 1 steel fixer 20
CHB Laying- Ground Floor
CHB Laying- 2nd Floor 4th Floor
Plastering 4 masons, 8 75 m
2
660 m
2

helpers

TILING WORKS Laborers Hourly Product


Product ion per
ion 10
Rates hours
1 mason, 1
Mosiac / Terrazo tiles to roofs helper 1.6 16 m2
1 mason, 1
Mosiac / Terrazo tiles to floors helper 1.4 14 m2
1 mason, 1
Mosiac skirting to halls helper 2.5 25 m
1 mason, 1
Mosiac skirting flush / recessed helper 1.4 14 m
Grouting / sealing to roof / floor tiles 1 helper 2.5 25 m

Door Installation 2 carpenters 4 Nos.

You might also like