Productivity Rate (Unit/day) for Crew

Crew Description Productivity Rate


No. ITEM Unit (Unit/day)
Remarks
LABOR EQUIPMENT
1 STORM WATER
1 EXCAVATION TRENCH FOR SW PIPES 2 Asst. Forman + 10 Labor 2 Excavator + 2 Plate Compactor M 50

2 LAY STORM WATER PIPES 2 Pipe Fitter + 10 Labors 2 Crane + 1 Lorry Crane + 1 Truck M 60

3 BACKFILLING FOR STORM WATER PIPES 2 Asst. Forman + 10 Labor 2 Loader + 2 Plate Compactor + 2 Water Tanker M 50

4 MANHOLES 2 Carpenter + 2 Steel Fixer + 3 Labors 1 Half Lorry + 2 Concrete Vibrator No. 0.5 1 / 2 days

5 GULLIES 2 Carpenter + 2 Steel Fixer + 3 Labors 1 Half Lorry + 2 Concrete Vibrator No. 2

6 DROP INLET 2 Carpenter + 2 Steel Fixer + 3 Labors 1 Half Lorry + 2 Concrete Vibrator No. 3

8 CURB OPENING 2 Carpenter + 2 Steel Fixer + 3 Labors 1 Half Lorry + 2 Concrete Vibrator No. 0.5 1 / 2 days

9 OUTLET 2 Carpenter + 2 Steel Fixer + 3 Labors 1 Half Lorry + 2 Concrete Vibrator No. 1

7 PLUG FOR FUTURE CONNECTION FOR ANY DIA. 1 Carpenter + 1 Steel Fixer + 1 Labors 1/4 Half Lorry + 1 Concrete Vibrator No. 7

10 BRIDGE DECK DRAINAGE 1 Pipe Fitter + 2 Labors 1 Lorry Crane No. 0.3 1 / 3 days

11 PIPE CONNECTION TO EXISTING BOX-CULVERT 1 Pipe Fitter + 2 Labors 1 Lorry Crane No. 1

2 WATER PIPE LINE


1 EXCAVATION TRENCH FOR PIPELINE 2 Asst. Forman + 10 Labor 2 Excavator + 2 Plate Compactor MR 50

2 SUPPLY AND INSTALL WATER PIPE LINE 2 Pipe Fitter + 6 Labors 1 Crane + 1 Lorry Crane MR 30

3 BACKFILLING TRENCH FOR PIPELINE 2 Asst. Forman + 10 Labor 2 Loader + 2 Plate Compactor + 2 Bob Cat + 2 Water Tanker MR 75

4 EXCAVATION & DEWATERING (IF NEEDED) FOR STORM WATER BOX CULVERT 1 Asst. Forman + 6 Labor 1 Excavator + 1 Loader + 1 Plate Compactor MR 20

5 CASTING PLAIN CONCRETE UNDER BOTTOM SLAB OF WATER BOX CULVERT 1 Asst. Forman + 2 Mason + 4 Labor 1 Concrete Vibrator + 1 Concrete Pump MR 50

6 FORMWORK FOR TOP SLAB / WALLS OF WATER BOX CULVERT 4 Carpenter + 3 Labors 1 Lorry Crane MR 20

7 REINFORCEMENT STEEL FOR BOTTOM SLAB / WALLS OF WATER BOX CULVERT 4 Steel Fixer + 3 Labors 1 Lorry Crane MR 15

8 CASTING CONCRETE & CURING FOR WALLS / SLAB OF WATER BOX CULVERT 1 Asst. Forman + 2 Mason + 4 Labor 1 Concrete Vibrator + 1 Concrete Pump MR 25

9 WATERPROFFING WORKS FOR WATER BOX CULVERT 1 Asst. Forman + 2 Mason + 2 Labor 1/4 Lorry Crane MR 25

10 BACKFILLING FOR WATER BOX CULVERT 1 Asst. Forman + 6 Labor 1 Loader + 1 Plate Compactor + 1 Water Tanker MR 40

11 CONSTRUCTION OF MANHOLES 4 Carpenter + 4 Steel Fixer + 8 Labors 1 Half Lorry + 2 Concrete Vibrator No. 0.25

12 CAST THROUST BLOCKS 1 Carpenter + 1 Steel Fixer + 2 Labors 1 Half Lorry + 2 Concrete Vibrator M3 20

13 SUPPLY & INSTALL ELECTRO MAGNETIC FLOW METER WITH ACCESSORIES 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 4

14 SUPPLY AND FIX VALVE 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 4

15 SUPPLY AND INSTALL SLUICE VALVES 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 2

16 C.I./D.I. DOUBLE FLANGED DISTANCE PIECE 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 4

17 DOUBLE SOCKET COLLAR 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 2

18 DUCK FOOT BEND 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 4

19 END CAP 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 2

20 FLANGED SOCKET PIECE 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 2

21 ISOLATING VALVE FOR A.V. 150 mm DIA. 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 1

22 SOCKET BEND 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 2

23 STOCK TEE 1/2 Pipe Fitter + 1 Labors 1/2 Crane + 1/4 Lorry Crane No. 2

24 CONNECT TO EXISTING WORKING PIPELINES 1 Pipe Fitter + 2 Labors 1/2 Crane + 1/4 Lorry Crane No. 2

25 FLUSH AND DISINFECT FOR PIPE LINE 1/2 Pipe Fitter + 1 Labors 2 Water Tanker L.S 1

26 REMOVAL EXISTING PIPES WITH FITTINGS MR 80

27 REMOVAL EXISTING PRESSURE REDUCING VALVE 2 Pipe Fitter + 8 Labors 1 Excavator + 1 Loader + 1/2 Crane + 1/2 Trailer + 1 Plate Compactor No. 4

28 REMOVAL EXISTING VALVES WITH FITTINGS No. 4

3 SANITARY SEWER WORKS


1 EXCAVATION FOR SANITARY PIPE LINE 1 Asst. Forman + 3 Labor 1 Excavator + 1 Plate Compactor M 40

2 LAYING SANITARY PIPELINES 1 Pipe Fitter + 3 Labors 1 Crane + 1 Truck M 20


Productivity Rate (Unit/day) for Crew

Crew Description Productivity Rate


No. ITEM Unit (Unit/day)
Remarks
LABOR EQUIPMENT
3 BACKFILLING FOR SANITARY PIPELINES 1 Asst. Forman + 3 Labor 1 Plate Compactor + 1 Water Tanker M 25

5 INSTALL OF SANITARY MANHOLE 1 Carpenter + 2 Steel Fixer + 3 Labors 1/2 Half Lorry + 1 Concrete Vibrator No. 2

4 TELEPHONE WORKS
1 REMOVE EXISTING TELEPHONE MANHOLES No. 4

2 REMOVE EXISTING TELEPHONE DUCT 9 WAY MR 300


1 Excavator + 1 Loader + 1 Dump Truck + 1 Plate Compactor + 1/4 Jack
3 REMOVE EXISTING TELEPHONE DUCT 12 WAY 1/2 Asst. Forman + 2 Labor MR 250
Hammer
4 REMOVE EXISTING TELEPHONE DUCT 20 WAY MR 200

5 REMOVE EXISTING TELEPHONE DUCT 28 WAY MR 200

6 EXCAVATION & INSTALL OF NEW TELEPHONE MANHOLES 1 Carpenter + 2 Steel Fixer +1 Mason + 3 Labors 1/2 Crane + 1/2 Trailer + 1/2 Transit Mixer No. 0.5

7 EXCAVATION & INSTALL TELEPHONE DUCTS 4 WAY 1 Asst. Forman + 2 Pipe Fitter + 6 Labors 1 Excavator + 1 Plate Compactor MR 250

8 EXCAVATION & INSTALL TELEPHONE DUCTS 9 WAY 1 Asst. Forman + 2 Pipe Fitter + 6 Labors 1 Excavator + 1 Plate Compactor MR 200

9 EXCAVATION & INSTALL TELEPHONE DUCTS 12 WAY 1 Asst. Forman + 2 Pipe Fitter + 6 Labors 1 Excavator + 1 Plate Compactor MR 150

10 EXCAVATION & INSTALL TELEPHONE DUCTS 20 WAY 1 Asst. Forman + 2 Pipe Fitter + 6 Labors 1 Excavator + 1 Plate Compactor MR 100

11 BACKFILLING WORKS FOR TELEPHONE DUCTS 4 WAY 1 Asst. Forman + 8 Labor 1 Loader + 2 Plate Compactor + 2 Bob Cat + 2 Water Tanker MR 250

12 BACKFILLING WORKS FOR TELEPHONE DUCTS 9 WAY 1 Asst. Forman + 8 Labor 1 Loader + 2 Plate Compactor + 2 Bob Cat + 2 Water Tanker MR 200

13 BACKFILLING WORKS FOR TELEPHONE DUCTS 12 WAY 1 Asst. Forman + 8 Labor 1 Loader + 2 Plate Compactor + 2 Bob Cat + 2 Water Tanker MR 150

14 BACKFILLING WORKS FOR TELEPHONE DUCTS 20 WAY 1 Asst. Forman + 8 Labor 1 Loader + 2 Plate Compactor + 2 Bob Cat + 2 Water Tanker MR 100

15 CONCRETE ENCASEMENT FOR TELEPHONE CROSSING DUCTS 9 WAY 1 Mason + 2 Labors 1/2 Transit Mixer MR 25

16 CONCRETE ENCASEMENT FOR TELEPHONE CROSSING DUCTS 20 WAY 1 Mason + 2 Labors 1/2 Transit Mixer MR 15

5 ROAD WORKS
DEMOLITION & REMOVEL OF EXISTING ASPHALTIC PAVEMENT, NON ASPHALTIC PAVEMENT &
1 1 Asst. Forman + 2 Labor 1 Loader + 1 Excavator + 2 Dump Truck ---
STRUCTURES
2 CLEARING AND GRUBBING 1 Asst. Forman + 2 Labor 1 Grader + 1 Loader + 1 Dump Truck L.S.

3 EXCAVATION AND REMOVAL UNSUITABLE SOIL 1 Asst. Forman + 2 Labor 1 Excavator + 1 Loader + 2 Dump Truck M3 350

4 EMBANKMENT MATERIALS 1 Asst. Forman + 4 Labor 2 Grader + 1 water Tanker + 1 Roller + 1 Loader + 2 Dump Truck 3 350
M
2
5 SUBGRADE WORKS 1 Asst. Forman + 4 Labor 2 Grader + 1 water Tanker + 1 Roller + 1 Loader + 2 Dump Truck M 350

2
6 AGGREGATE SUBBASE COURSES 1 Asst. Forman + 4 Labor 2 Grader + 1 water Tanker + 1 Roller + 1 Loader + 2 Dump Truck M 500

2
7 ASPHALT BASE COURSE 1 Asst. Forman + 6 Labor 1 Asphalt paver + 1 Steel Roller + 1 Tire Roller + 2 Dump Truck M 350

8 PAVEMENT MILLING ( 100mm thk.) 1 Asst. Forman + 2 Labor 1 Milling Machine + 2 Dump Truck M2 1000

9 PRIME COAT/ TACK COAT 1 Asst. Forman Tack/Prime Sprayer M2 500

10 RUMBLE STRIPS (AT ANY LENGTH) BY FIXED BOARDS 1 Asst. Forman + 2 Labor -- No. 10

11 KERBSTONE WORKS 1 Asst. Forman + 3 Labor 1/4 Lorry Crane + 1 Bobcat + 1/2 Transit Mixer MR 150

12 INTERLOCKING PAVING BLOCKS 1 Asst. Forman + 3 Labor 1/4 Lorry Crane + 1 Bobcat M2 80

13 CONCRETE BARRIER 1 Asst. Forman + 3 Labor 1/2 Lorry Crane MR 60

6 IRRIGATION WORKS
1 EXC., LAYING & BACKFILLING IRRIGATION SLEEVE FOR CROSSING MAIN LINE 1 Asst. Forman + 2 Pipe Fitter + 3 Labors 1 Excavator + 1 Loader + 1 Plate Compactor + 1 Water Tanker MR 30

2 EXC., LAYING & BACKFILLING IRRIGATION SLEEVE FOR CROSSING CONTROL CABLE 1 Asst. Forman + 2 Pipe Fitter + 3 Labors 1 Excavator + 1 Loader + 1 Plate Compactor + 1 Water Tanker MR 30

3 LAYING OF UPVC IRRIGATION PIPES 1 Asst. Forman + 2 Pipe Fitter + 3 Labors 1 Truck MR 50

4 LAYING OF IRRIGATION CONTROL CABLE 1 Asst. Forman + 2 Pipe Fitter + 3 Labors 1 Truck MR 160

5 EXC., INSTALL & BACKFILLING FOR VALVE CHAMBER 1 Asst. Forman + 1 Pipe Fitter + 2 Labors 1 Excavator+ 1 Plate Compactor + 1 Water Tanker No. 0.5

7 SUPPLY AND INSTALL ISOLATING VALVE 1 Asst. Forman + 1 Pipe Fitter + 2 Labors 1 Truck No. 4

7 ELECTRICAL WORKS
1 REMOVAL OF EXISTING STREET LIGHTING POLES, CONTROL CABINET & FEEDER PILLAR 1 Asst. Forman + 1 Electrician + 3 Labors 1 Basket Crane No. 5

2 EXCAVATION AND LAYING STREET LIGHTING UPVC CABLE DUCT 1 Asst. Forman + 3 Labors -- MR 200

3 SUPPLY AND INSTALL ELECTRIC CABLES IN UPVC DUCTS 1 Asst. Forman + 3 Labors Cable Winch MR 200
Productivity Rate (Unit/day) for Crew

Crew Description Productivity Rate


No. ITEM Unit (Unit/day)
Remarks
LABOR EQUIPMENT
4 EXCAVATION & CAST FOUNDATIONS FOR LIGHTING MASTS & POLES 1 Asst. Forman + 3 Labors 1 JCB Excavator No. 5

5 SUPPLY & INSTALLATION OF LIGHTING MASTS & POLES 1 Asst. Forman + 1 Electrician + 3 Labors 1 Basket Crane No. 5

6 SUPPLY & INSTALLATION OF EARTH BONDING &GROUNDING SYSTEM 1 Electrician + 3 Labors -- No. 10

8 EXC.TRENCH FOR STREET LIGHTING CROSSING 1 Asst. Forman + 3 Labors 1 JCB Excavator + 1 Loader + 1 Plate Compactor + 1 Water Tanker MR 50

9 SUPPLY & INSTALL STREET LIGHTING CROSSING DUCTS 1 Asst. Forman + 3 Labors -- MR 50

10 BACKFILLING WORKS FOR STREET LIGHTING CROSSING DUCTS 1 Asst. Forman + 3 Labors 1 Loader + 1 Plate Compactor + 1 Water Tanker MR 50

11 SUPPLY & INSTALL STEEL CONDUIT EMBEDDED IN PIER / LANTERNS / SWITCHS /SIGN LIGHTING 1 Electrician + 3 Labors 1 Basket Crane No. 10

7 PILLING WORKS
1 CAST-IN-PLACE CONCRETE PILES 6 Riggers + 2 Labors 1 Piling Rig + 1 Polymer Plant + 1 Crane No. 3

2 BREAK PILES HEADS 1 Asst. Forman + 6 Labors -- No. 2

3 PILES TEST 1 Technician + 2 Labors 1 Crane No. 6

8 BRIDGES WORK
ABUTMENT
SHUTTER WORKS FOR THE BEAM OF ABUTMENT 3 Carpenter + 3 Labors 1 Crane + 1 Trailer No. 1/8 Day

REINFORCEMENT STEEL FOR THE BEAM OF ABUTMENT 4 Steel Fixer + 4 Labors 1 Crane + 1 Trailer No. 1/8 Day

CAST CONCRETE FOR THE BEAM OF ABUTMENT 4 Mason + 4 Labors 2 Transit Mixer + 3 Concrete Vibrator No. 1

CURING & REMOVE SHUTTER FOR THE BEAM OF ABUTMENT 3 Carpenter + 3 Labors 1 Crane No. 1/12 Day

BACKWALL
SHUTTER WORKS FOR BACKWALL - 1st SIDE 3 Carpenter + 3 Labors 1 Crane + 1 Trailer No. 1/2 Day

FIXING REINFORCEMENT FOR BACKWALL 3 Steel Fixer + 3 Labors 1 Crane + 1 Trailer No. 1/4 Day

SHUTTER WORKS FOR BACKWALL - 2nd SIDE 3 Carpenter + 3 Labors 1 Crane + 1 Trailer No. 1/2 Day

CASTING CONCRETE FOR BACKWALL 2 Mason + 2 Labors 2 Transit Mixer + 2 Concrete Vibrator No. 1

CURING & REMOVE SHUTTER FOR BACKWALL 3 Carpenter + 3 Labors 1 Crane No. 1/2 Day

CURTAIN WALL
SHUTTER WORKS FOR THE CURTAIN WALL - 1st SIDE 3 Carpenter + 3 Labors 1 Crane + 1 Trailer No. 1/4 Day

REINFORCEMENT STEEL FOR THE CURTAIN WALL 3 Steel Fixer + 3 Labors 1 Crane + 1 Trailer No. 1/5 Day

SHUTTER WORKS FOR THE CURTAIN WALL - 2nd SIDE 3 Carpenter + 3 Labors 1 Crane + 1 Trailer No. 1/4 Day

CASTING CONCRETE FOR THE CURTAIN WALL 4 Mason + 4 Labors 2 Transit Mixer + 3 Concrete Vibrator No. 1

CURING & REMOVE SHUTTER WORKS FOR THE CURTAIN WALL 3 Carpenter + 3 Labors 1 Crane No. 1/3 Day

APPLY WATER PROOFING FOR ABUTMENT & CURTAIN WALL 1 Assit. Foreman + 4 Labors -- No. 1/4 Day

APPROACH SLAB
FORMWORK FOR APPROACH SLAB 3 Carpenter + 3 Labors 1 Crane + 1 Trailer No. 1/2 Day

REINFORCEMENT STEEL FOR APPROACH SLAB 3 Steel Fixer + 3 Labors 1 Crane + 1 Trailer No. 1/4 Day

CASTING CONCRETE FOR APPROACH SLAB 4 Mason + 4 Labors 2 Transit Mixer + 3 Concrete Vibrator No. 1

CURING & REMOVE THE FORMWORK FOR APPROACH SLAB 2 Carpenter + 2 Labors 1 Crane No. 1/4 Day

BOX GIRDER
FIXED SCAFOLDING & BOTTOM SHUTTER & OUTSIDE SHUTTER 6 Carpenter + 6 Labors 1 Crane + 1 Trailer No. 1/6 Day

FIXED POT BEARING ( PIER (PG-1000)) 1 Carpenter + 2 Labors 1/2 Crane No. 1/3 Day

REINFORCEMENT STEEL & DUCT POST TENSION 8 Steel Fixer + 6 Labors 1 Crane + 1 Trailer No. 1/7 Day

FIXED INSIDE SHUTTER 6 Carpenter + 6 Labors 1 Crane + 1 Trailer No. 1/3 Day

CASTING BOTTOM SLAB & WEB 6 Mason + 6 Labors 4 Transit Mixer + 6 Concrete Vibrator No. 1

REMOVE INSIDE SHUTTER FOR WEB 3 Carpenter + 3 Labors 1 Crane No. 1

FIXED SHUTTER FOR TOP SLAB 6 Carpenter + 6 Labors 1 Crane + 1 Trailer No. 1/2 Day

REINFORCEMENT FOR TOP SLAB 8 Steel Fixer + 6 Labors 1 Crane + 1 Trailer No. 1/2 Day
Productivity Rate (Unit/day) for Crew

Crew Description Productivity Rate


No. ITEM Unit (Unit/day)
Remarks
LABOR EQUIPMENT
CASTING THE TOP SLAB 6 Mason + 6 Labors 4 Transit Mixer + 6 Concrete Vibrator No. 1

CURING & REMOVE THE SHUTTER FOR THE TOP SLAB 3 Carpenter + 3 Labors 1 Crane No. 1/9 day

POST TENSION + GROUTING 1 Assit. Foreman + 6 Labors No. 1/2 Day

REMOVING SCAFOLDING 6 Carpenter + 6 Labors 1 Crane + 1 Trailer No. 1/2 Day

PIER
EXCAVATION, GROUND LEVELING AND COMPACTION FOR PIER 1 Assit. Foreman + 2 Labors 1 Excavator No. 1/3 Day

PLAIN CONCRETE FOR PILES CAP 2 Carpenter + 2 Labors 1 Transit Mixer + 2 Concrete Vibrator No. 1/2 Day

SHUTTER WORKS FOR PILES CAP 3 Carpenter + 3 Labors 1/2 Crane + 1/2 Trailer No. 1/3 Day

REINFORCEMENT STEEL FOR PILES CAP 3 Steel Fixer + 3 Labors 1/2 Crane + 1/2 Trailer No. 1/5 Day

CASTING CONCRETE FOR PILES CAP 3 Mason + 3 Labors 1 Transit Mixer + 2 Concrete Vibrator No. 1

CURING & REMOVE SHUTTER FOR PILES CAP 3 Carpenter + 3 Labors 1/2 Crane + 1/2 Trailer No. 1/2 Day

REINFORCEMENT STEEL FOR PIER COLUMN 4 Steel Fixer + 4 Labors 1 Crane + 1/2 Trailer No. 1/4 Day

SHUTTER WORKS FOR PIER COLUMN 3 Carpenter + 3 Labors 1 Crane + 1/2 Trailer No. 1/4 Day

CASTING CONCRETE FOR PIER COLUMN 2 Mason + 2 Labors 1 Transit Mixer + 2 Concrete Vibrator No. 1

CURING & REMOVE SHUTTER FOR PIER COLUMN 2 Carpenter + 2 Labors 1 Crane + 1/2 Trailer No. 1/2 Day

REINFORCEMENT STEEL FOR THE HEAD OF PIER 4 Steel Fixer + 4 Labors 1 Crane + 1/2 Trailer No. 1/4 Day

SHUTTER WORKS FOR THE HEAD OF PIER 3 Carpenter + 3 Labors 1 Crane + 1/2 Trailer No. 1/3 Day

CASTING CONCRETE FOR THE HEAD OF PIER 2 Mason + 2 Labors 1 Transit Mixer + 2 Concrete Vibrator No. 1

CURING & REMOVE SHUTTER FOR THE HEAD OF PIER 2 Carpenter + 2 Labors 1 Crane + 1/2 Trailer No. 1/3 Day

APPLY WATER PROOFING FOR FOOTING 1 Assit. Foreman + 4 Labors -- No. 1/3 Day

BACK FILLING 1 Assit. Foreman + 4 Labors 1 Loader + 2 Plate Compactor + 1 Water Tanker No. 1/4 Day

SPREAD FOOTING
SHOORING, DEWATERING, EXCAVATION &LEVELING FOR THE PIER 1 Assit. Foreman + 2 Labors 1 Excavator No. 1/12 Day

PLAIN CONCRETE UNDER FOUNDATIONS & CURING OF PIER 2 Carpenter + 2 Labors 1 Transit Mixer + 2 Concrete Vibrator No. 1/3 Day

FORMWORK FOR FOUNDATION 3 Carpenter + 3 Labors 1/2 Crane + 1/2 Trailer No. 1/2 Day

REINFORCEMENT STEEL FOR FOUNDATION OF PIER 3 Steel Fixer + 3 Labors 1/2 Crane + 1/2 Trailer No. 1/4 Day

CASTING CONCRETE & CURING 3 Mason + 3 Labors 1 Transit Mixer + 2 Concrete Vibrator No. 1/2 Day

APPLY WATER PROOFING FOR FOOTING 1 Assit. Foreman + 4 Labors -- No. 1/3 Day

BACKFILLING & REMOVING SHOORING & DEWATERING 1 Assit. Foreman + 4 Labors 1 Loader + 2 Plate Compactor + 1 Water Tanker No. 1/12 Day