Professional Documents
Culture Documents
EQUIPMENT
NO. OF UNITS
DESCRIPTION
OWNED / LEASED
Stake Truck 1
Backhoe (0.80 cu.m.) 2
Dump Truck (10 cu.m.) 2
Backhoe w/ Breaker (0.80 cu.m.) 1
Jackhammer 2
Air Compressor (103 Hp) 1
Payloader (1.50 cu.m.) 2
Truck Mounted Crane (35 T) 1
Cutting Outpit 1
Drilling Rig 1
Crawler Crane (45 T) 1
Crawler Crane (25 T) 1
Wheel Loader 1
Generator Set (301-350 KW) 1
Bentonite Bin 1
Bentonite Mixer 1
Water Pump 1
Water Truck (1000 gal.) 2
Bar Cutter 2
Bar Bender 2
Welding Machine 1
Tremie Pipe Set 1
SPT & Desanding Machine 1
Portable Breaker 2
Air Compressor, Portable 1
Lighting System/Tower Lights 1
Pile Integrity Testing (Sonic) and accessories 1
Dynamic Pile Testing 1
Truck Mounted Crane (45T) 2
Drop Hammer w/ accessories (20T) 1
Compressor w/ Jack Hammer 1
Concrete Vibrator 2
Service Crane (25T, 145Hp) 1
Cargo Truck (10 T, 270 Hp) 2
Transit Mixer (5 cu.m.) 4
Batching Plant (30 cu.m.) 1
Crane w/ Bucket 1
One Bagger Mixer 1
Wood/Steel Ladder 1
Backhoe (Wheel Type 0.28 cu.m.) 1
Generator 1
Compressor 1
Disc Sander 3
Concrete Saw, Blade 14" Ø (7.50 Hp) 1
Chain Saw 1
Bulldozer (155 Hp), D65A-8 1
Plate Compactor (5 Hp) 2
Motorized Road Grader, G710A 1
Vibratory Roller (10 m.t.), SP56 1
Concrete Screeder (5.5 Hp) 1
Applicator Machine 1
Kneading Machine 1
ANNEX "A"
MANPOWER
NO. OF TOTAL Same POSITION IN
POSITION PERSONNE EXPERIENCE SIMILAR WORKS
L (years) (years)
Project Engineer 1 5 3
Accredited Material Engineer I 1 - -
Construction Foreman 1 5 3
Safety Officer 1 - -
First Aider 1 - -
Traffic Aide 6 - -
Skilled Laborer 20 - -
Laborer 60 - -
103(1)a Structure Excavation (Common Soil) QTY. 1566.63 cu.m.
DRAINAGE
AREA FROM CROSS SECTIONS
LEFT SIDE
STATION AREA CUT LENGTH VOLUME
FROM TO A1 A2
K0114+179.00 K0114+180.00 7.440 7.414 1.00 7.43
K0114+180.00 K0114+200.00 7.414 6.994 20.00 144.08
K0114+200.00 K0114+220.00 6.994 6.435 20.00 134.29
K0114+220.00 K0114+240.00 6.435 5.757 20.00 121.92
K0114+240.00 K0114+260.00 5.757 5.227 20.00 109.84
K0114+260.00 K0114+280.00 5.227 4.628 20.00 98.55
K0114+280.00 K0114+300.00 4.628 5.000 20.00 96.28
K0114+300.00 K0114+318.00 5.000 4.297 18.00 83.67
K0114+318.00 K0114+338.00 0.00
K0114+338.00 K0114+358.00 0.00
K0114+358.00 K0114+378.00 0.00
K0114+378.00 K0114+398.00 0.00
K0114+398.00 K0114+418.00 0.00
K0114+418.00 K0114+438.00 0.00
K0114+438.00 K0114+458.00 0.00
K0114+458.00 K0114+468.00 0.00
SUBTOTAL = 796.06 m³
DRAINAGE
AREA FROM CROSS SECTIONS
LEFT SIDE
STATION AREA FILL LENGTH VOLUME
FROM TO A1 A2
K0114+179.00 K0114+180.00 6.529 6.506 1.00 6.52
K0114+181.30 K0114+200.00 6.506 6.079 18.70 117.67
K0114+201.30 K0114+220.00 6.079 5.551 18.70 108.74
K0114+221.30 K0114+240.00 5.551 5.106 18.70 99.64
K0114+241.30 K0114+260.00 5.106 4.633 18.70 91.06
K0114+261.30 K0114+280.00 4.633 4.374 18.70 84.22
K0114+281.30 K0114+300.00 4.374 3.877 18.70 77.15
K0114+301.30 K0114+318.00 3.877 3.480 16.70 61.43
K0114+319.30 K0114+338.00 0.00
K0114+339.30 K0114+358.00 0.00
K0114+359.30 K0114+378.00 0.00
K0114+379.30 K0114+398.00 0.00
K0114+399.30 K0114+418.00 0.00
K0114+419.30 K0114+438.00 0.00
K0114+439.30 K0114+458.00 0.00
K0114+459.30 K0114+468.00 0.00
SUBTOTAL = 646.42 m³
TOTAL = 1305.64 m³
SAY 1632.05 m³
K0114+179.00
139.00 7.00 L/S
K0114+318.00
K0114+179.00
139.00 7.00 R/S
K0114+318.00
K0114+179.00
139.00 7.00 L/S
K0114+318.00
K0114+179.00
139.00 7.00 R/S
K0114+318.00
SIDEWALK
total length of sidewalk x 1.30 x 0.10 ;length = 259.80
33.77 cu.m.
TOTAL VOLUME = 223.23 cu.m.
SAY 223.20 cu.m.
500(1)c Pipe Culverts, 910 mm dia. (36" Ø) QTY. 264.00 l.m.
DRAINAGE
LEFT SIDE RIGHT SIDE
STATION LENGTH STATION LENGTH
FROM TO FROM TO
K0114+179.00 K0114+180.00 1.00 K0114+179.00 K0114+180.00 1.00
K0114+181.00 K0114+200.00 19.00 K0114+181.00 K0114+200.00 19.00
K0114+201.00 K0114+220.00 19.00 K0114+201.00 K0114+220.00 19.00
K0114+221.00 K0114+240.00 19.00 K0114+221.00 K0114+240.00 19.00
K0114+241.00 K0114+260.00 19.00 K0114+241.00 K0114+260.00 19.00
K0114+261.00 K0114+280.00 19.00 K0114+261.00 K0114+280.00 19.00
K0114+281.00 K0114+300.00 19.00 K0114+281.00 K0114+300.00 19.00
K0114+301.00 K0114+318.00 17.00 K0114+301.00 K0114+318.00 17.00
K0114+319.00 K0114+338.00 K0114+319.00 K0114+338.00
K0114+339.00 K0114+358.00 K0114+339.00 K0114+358.00
K0114+359.00 K0114+378.00 K0114+359.00 K0114+378.00
K0114+379.00 K0114+398.00 K0114+379.00 K0114+398.00
K0114+399.00 K0114+418.00 K0114+399.00 K0114+418.00
K0114+419.00 K0114+438.00 K0114+419.00 K0114+438.00
K0114+439.00 K0114+458.00 K0114+439.00 K0114+458.00
K0114+459.00 K0114+468.00 K0114+459.00 K0114+468.00
SUBTOTAL = 132.00 SUBTOTAL = 132.00
TOTAL = 264.00
VOLUME
No. of manholes x (1.30x1.30x0.1)
2.70 cu.m.
REBARS
8-10mmØ longitudinal bars 7-10mmØ transverse bars 4-16mmØ handle bars
8 x 1.30 x no. of manholes 7 x (0.65x2) x no. of manholes 4 x 0.60 x no. of manholes
166.40 m. 145.60 m. 38.40 m.
ANGLE BARS
2 x 2 x (1.30x2 + 0.65x2) x no. of manholes
249.60 m.
1"Ø PVC PIPES
8 x 0.10 x no. of manholes
12.80 m.
FORMWORKS
2 x (1.30x0.65 + 1.30x0.10x2+ 0.65x0.10x2) x no. of manholes
39.52 sq.m. 4 uses
Summary
Cement = 25.00 bags
Sand = 2.00 cu.m.
Gravel = 3.00 cu.m.
10mmØ deformed bars = 203.00 kgs. w/ 5% wastage
16mmØ round bars = 64.00 kgs. w/ 5% wastage
Tie Wire = 5.00 kgs.
2" x 2" x 1/4" angle bars = 1,243.00 kgs. w/ 5% wastage
Welding Rod = 0.70 kgs.
1"Ø PVC Pipes = 5.00 pcs.
4' x 8' x 1/2" Marine Plywood = 4.00 pcs. 4 uses
Good Lumber = 119.00 bd.ft. 4 uses
CW Nails = 2.00 kgs.
AVERAGE HEIGHT = SUM OF HEIGHT BOTHSIDES / TOTAL NUMBER OF SERVICE HOLES BOTHSIDES
AVERAGE HEIGHT = 3.06
TOTAL AREA OF CHB = NO. OF SERVICE HOLES x{ AVE. HT. x [(1.30x2)+(1.15x2)]-(0.23x1.30)-(2πx1.10²/4)}
TOTAL AREA OF CHB = 230.3
Mortar
cement = AREA x 1.018 235.00 bags
sand = AREA x 0.0844 19.44 cu.m.
Plastering
cement = AREA x 0.24 56.00 bags
sand = AREA x 0.020 4.61 cu.m.
FLOORING
VOLUME = 1.45 x 1.30 x 0.10 x NO. OF SERVICE HOLES
VOLUME = 3.39
cement = 30.54
sand = 1.70
gravel = 3.39
REINFORCEMENTS
LENGTH NO. OF BARS TOTAL
J-BAR 5.126 3.00 276.80 m 10 mm Ø along 1.45
U-BAR 5.206 3.00 281.12 m 10 mm Ø along 1.30
horizontal bars @ flooring
LENGTH NO. OF BARS TOTAL
1.45 2.00 52.20 m 10 mm Ø
1.30 2.00 46.80 m 10 mm Ø
horizontal bars @ CHB
LENGTH = AREA x 2.15 = 495.15 m 10 mm Ø
Steel Ladder
LENGTH NO. OF BARS TOTAL
2.44 3.00 131.76
Summary
600(3) Concrete Curb and Gutter, Type A (Cast in Place) - National Road QTY. 278.00 L.M.
AT CURB AND GUTTER
LEFT SIDE
STATION LENGTH
FROM TO
K0114+179.00 K0114+318.00 139.00
SUBTOTAL = 139.00
RIGHT SIDE
STATION LENGTH
FROM TO
K0114+179.00 K0114+318.00 139.00
SUBTOTAL = 139.00
TOTAL = 278.00
DERIVATION OF DURATION per D.O. #71 Series 2013
Construction/ Rehabilitation of Barangay/ Farm to Market Road at Brgy. Alangilan
Batangas City
1,200,000.00 168 - x
=
28,800,000.00 x - 130.50
x = 166.50 days
AMOUNT - 5,000,000.00
CALENDAR DAYS 0.00 1369.50
DURATION REDUCTION FACTOR 0.00 0.125
SAY 0.00 171.19
5,000,000.00 168 - x
=
- x - 130.50
x = 0.00 days
Batangas City
Total = 0.00 m²
Total = 79.60 m³
Total = 398.00 m²
Total = 39.80 m³
Total = 39.80 m³
311 PCC Pavement (Plain) - Conventional Method, 200mm thk 398.00 sq.m.
Total = 398.00 m²
EQUIPMENT
DESCRIPTION OF WORKS TO BE DONE % OF TOTAL
DESCRIPTION REQUIRED
PART A FACILITIES FOR ENGINEER 3.24%
PART B OTHER GENERAL REQUIREMENTS 7.15%
PART C EARTHWORK 12.91%
PART D SUBBASE AND BASE COURSE 8.51%
PART E SURFACE COURSES 68.19% (SEE ATTACHED ESTIMATE)
Total 100%
ESTIMATED COST OF PROJECT
DESCRIPTION QUANTITY UNIT TOTAL
### PART A FACILITIES FOR ENGINEER Php 25,000.00
### PART B OTHER GENERAL REQUIREMENTS Php 55,243.15
PART C EARTHWORK (SEE ATTACHED ESTIMATE) Php 99,666.36
PART D SUBBASE AND BASE COURSE Php 65,753.19
PART E SURFACE COURSES Php 526,589.82
Total Php 772,252.52
BREAKDOWN OF EXPENDITURES:
1. Labor Php 76,240.01 A. Sub-total Php 772,252.52
2. Materials Php 494,702.90 B. Taxes (VAT, etc.) Php 227,747.48
3. Rental of Equipment Php 201,309.61 C. ROW Acquisition/Contingencie Php -
4. Provisional Sum D. Total Estimated Cost Php 1,000,000.00
5. Direct Cost Php 772,252.52
6. OCM, Profit Php 180,261.36
7. Engineering Overhead
8. VAT Php 47,486.12
9. ROW Acquisition/Contingencies
10. TOTAL Php 1,000,000.00
Approved:
HERMILANDO I. MANDANAS
Governor
blic of the Philippines
cial Engineer's Office
vince of Batangas
ng Ilaya, Batangas City
###
NDO I. MANDANAS
Governor
APPROVED BUDGET FOR CONTRACT
Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
MARK-UPS
DIRECT UNIT ESTIMATED DIRECT TOTAL MARK-UP VAT INDIRECT COST ITEM COST UNIT COST
ITEM NO. DESCRIPTION QUANTITY UNIT (PERCENT)
COST COST
OCM PROFIT % VALUE 5%(6+10) (10)+(11) (12)+(6) (12)/(3)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
PART A FACILITIES FOR ENGINEER
A.1.1 Provision of Field Office for Engineer 1.00 lot 25,000.00 25,000.00 0 10 10 2,500.00 1,375.00 3,875.00 28,875.00 28,875.00
SUB-TOTAL A 25,000.00 28,875.00
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 2.00 ea 6,153.37 12,306.74 0 10 10 1,230.67 676.87 1,907.54 14,214.28 7,107.14
B.7 Safety and Health 1.00 mo. 5,051.92 5,051.92 0 10 10 505.19 277.86 783.05 5,834.97 5,834.97
B.8 Traffic Management/Roadwork Safety Devices 1.00 mo. 30,231.60 30,231.60 0 10 10 3,023.16 1,662.74 4,685.90 34,917.50 34,917.50
B.9 Mobilization / Demobilization 1.00 Lump sum 7,652.89 7,652.89 0 0 0 - 382.64 382.64 8,035.53 8,035.53
SUB-TOTAL B 55,243.15 63,002.28
PART C EARTHWORK
101(3)a.1 Removal of Existing Concrete Pavement (0.15m thk.) 398.00 sq.m. 185.95 74,008.10 15 10 25 18,502.02 4,625.51 23,127.53 97,135.63 244.06
102 Roadway Excavation 79.60 cu.m. 241.74 19,242.50 15 10 25 4,810.62 1,202.66 6,013.28 25,255.78 317.28
105(1) Subgrade Preparation (Common Material) 398.00 sq.m 16.12 6,415.76 15 10 25 1,603.94 400.99 2,004.93 8,420.69 21.16
SUB-TOTAL C 99,666.36 130,812.10
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course (for Intermittent Reblocking) 39.80 cu.m. 811.67 32,304.47 15 10 25 8,076.12 2,019.03 10,095.15 42,399.62 1,065.32
201(1) Aggregate Base Course (for Reblocking) 39.80 cu.m. 840.42 33,448.72 15 10 25 8,362.18 2,090.54 10,452.72 43,901.44 1,103.05
SUB-TOTAL D 65,753.19 86,301.06
PART E SURFACE COURSES
311 PCC Pavement (Plain) - Conventional Method, 200mm thk 398.00 sq.m. 1,323.09 526,589.82 15 10 25 131,647.46 32,772.28 164,419.74 691,009.56 1,736.20
SUB-TOTAL E 526,589.82 691,009.56
Sub-Total for A
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Sub-Total for B -
C. Total (A+B)
D. Output
E. Direct Unit Cost (C/D)
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
Provision for Temporary Facilities lot 1.00 25,000.00 25,000.00
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: B.5 Project Billboard / Signboard
Unit of Measurement: ea
Output per hour: 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 4.00 96.79 387.16
b. Unskilled Labor 2 4.00 53.92 431.36
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Welding Machine 1 2.00 371.00 742.00
Minor Tools 81.85
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: B.7 Safety and Health
Unit of Measurement: mo.
Output per hour: 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. First Aider 1 26.00 53.92 1,401.92
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Sub-Total for B -
C. Total (A+B) 1,401.92
D. Output 1.00
E. Direct Unit Cost (C/D) 1,401.92
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
a. Medicine Kit including Medicine (small) kit 1.00 500.00 500.00
b. Gloves pair 3.00 300.00 900.00
c. Boots pair 3.00 350.00 1,050.00
d. Hard Hat pcs. 3.00 350.00 1,050.00
e. Miscellaneous 150.00
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: B.8 Traffic Management/Roadwork Safety Devices
Unit of Measurement: mo.
Output per hour: 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Sub-Total for B -
C. Total (A+B) 25,881.60
D. Output 1.00
E. Direct Unit Cost (C/D) 25,881.60
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
a. Fabricated informative signs 1.22m x pair 1.00 3,000.00 3,000.00
1.22m plywood with angular frame
b. Reflectorized single arrow signs pair 1.00 1,350.00 1,350.00
(0.30m x 0.45m)
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: B.9 Mobilization / Demobilization
Unit of Measurement: Lump sum
Output per hour: 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Unskilled Labor 2 8.50 53.92 916.64
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Elf Truck 1.00 8.50 783.00 6,655.50
b. Minor Tools 80.75
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 100(1) Clearing and Grubbing (with Stripping)
Unit of Measurement: ha
Output per hour: 0.05
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 81.07 81.07
b. Unskilled Labor 2 1.00 45.27 90.54
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Bulldozer 2 1.00 3,379.00 6,758.00
b. Payloader (1.50 cu.m), LX80-2C 1 1.00 1,733.00 1,733.00
c. Dump Truck (12 cu.yd.) 1 1.00 1,420.00 1,420.00
Sub-Total for F
G. Direct Unit Cost (E+F) 201,652.20
H. Overhead, Contingencies & Miscellaneous (OCM), per DO 197, 2016 12% of G 24,198.26
I. Contractor's Profit (CP) 10% of G 20,165.22
J. Value Added Tax (VAT), per DO 197, 2016 5% of (G+H+I) 12,300.79
K. Total Unit Cost (G+H+I+J) 258,316.47
Prepared by:
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 100(3)a Individual Removal of Trees (small a, 150mm up to 300mm dia.)
Unit of Measurement: ea
Output per hour: 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 0.33 81.07 26.75
b. Skilled Labor 1 0.33 58.59 19.33
c. Unskilled Labor 2 0.33 45.27 29.88
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Back Hoe (0.80 m3) 1 0.25 1,537.00 384.25
b. Dump Truck (12cu.yd.) 1 0.17 1,420.00 241.40
c. Chainsaw 1 0.17 75.36 12.81
Minor Tools (5% of Labor Cost) 3.80
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 101(1) Removal of Structures and Obstruction
Unit of Measurement: Lump Sum
Output per hour: 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 56.00 81.07 4,539.92
b. Unskilled Labor 6 56.00 45.27 15,210.72
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 1,521.07
Sub-Total for F -
G. Direct Unit Cost (E+F) 21,271.71
H. Overhead, Contingencies & Miscellaneous (OCM), per DO 197, 2016 15% of G 3,190.76
I. Contractor's Profit (CP) 10% of G 2,127.17
J. Value Added Tax (VAT), per DO 197, 2016 5% of (G+H+I) 1,329.48
K. Total Unit Cost (G+H+I+J) 27,919.12
Prepared by:
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 100(1) Clearing and Grubbing (with Stripping)
Unit of Measurement: LS
Output per hour: 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 2.00 81.07 162.14
b. Unskilled Labor 3 2.00 45.27 271.62
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Backhoe (0.80 cu.m) 1 2.00 1,537.00 3,074.00
Minor Tools (10% of Labor Cost) 43.38
Sub-Total for F -
G. Direct Unit Cost (E+F) 3,551.14
H. Overhead,Contingencies & Miscellaneous(OCM) per DO 197, s. 2016 15% of G 532.67
I. Contractor's Profit (CP) 10% of G 355.11
J. Value Added Tax (VAT), per DO 197, 2016 5% of (G+H+I) 221.95
K. Total Unit Cost (G+H+I+J) 4,660.87
Prepared by:
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 101(3)a.1 Removal of Existing Concrete Pavement (0.15m thk.)
Unit of Measurement: sq.m.
Output per hour: 26.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 96.79 96.79
b. Unskilled Labor 3 1.00 53.92 161.76
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Dump Truck (12 yd3) 2 1.00 1,420.00 2,840.00
b. Backhoe (0.80 cu.m) 1 1.00 1,537.00 1,537.00
c. Payloader (1.50 cu.m) at disposal site 1 0.10 1,733.00 173.30
Minor Tools (10% of Labor Cost) 25.86
Sub-Total for F -
G. Direct Unit Cost (E+F) 185.95
H. Overhead,Contingencies & Miscellaneous(OCM) per DO 197, s. 2016 15 of G 27.89
I. Contractor's Profit (CP) 10% of G 18.60
J. Value Added Tax (VAT), per DO 197, 2016 5% of (G+H+I) 11.62
K. Total Unit Cost (G+H+I+J) 244.06
Prepared by:
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 102 Roadway Excavation
Unit of Measurement: cu.m.
Output per hour: 20.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 96.79 96.79
b. Unskilled Labor 3 1.00 53.92 161.76
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
b. Backhoe (0.80 cu.m) 1 1.00 1,537.00 1,537.00
c. Payloader 1 0.10 1,733.00 173.30
Minor Tools (10% of Labor Cost) 25.86
Sub-Total for F
G. Direct Unit Cost (E+F) 241.74
H. Overhead, Contingencies & Miscellaneous (OCM), per DO 197, 2016 15% of G 36.26
I. Contractor's Profit (CP) 10% of G 24.17
J. Value Added Tax (VAT), per DO 197, 2016 5% of (G+H+I) 15.11
K. Total Unit Cost (G+H+I+J) 317.28
Prepared by:
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 105(1) Subgrade Preparation (Common Material)
Unit of Measurement: sq.m
Output per hour: 300.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 96.79 96.79
b. Unskilled Labor 2 1.00 53.92 107.84
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Motorized Road Grader (140hp), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10m.t), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
Sub-Total for F
G. Direct Unit Cost (E+F) 16.12
H. Overhead, Contingencies & Miscellaneous (OCM), per DO 197, 2016 15% of G 2.42
I. Contractor's Profit (CP) 10% of G 1.61
J. Value Added Tax (VAT), per DO 197, 2016 5% of (G+H+I) 1.01
K. Total Unit Cost (G+H+I+J) 21.16
Prepared by:
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 200(1) Aggregate Subbase Course (for Intermittent Reblocking)
Unit of Measurement: cu.m.
Output per hour: 40.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 96.79 96.79
b. Unskilled Labor 2 1.00 53.92 107.84
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Motorized Road Grader (140hp), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10m.t), SD100DC 1 1.00 1,846.00 1,846.00
c. Plate Compactor (5hp) 1 0.25 123.00 30.75
d. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
JERICO O. EVANGELISTA
Engineer I
cu.m.
39.80 1
203.61
4,638.94
27,462.00
1,065.32
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 201(1) Aggregate Base Course (for Reblocking)
Unit of Measurement: cu.m.
Output per hour: 40.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 96.79 96.79
b. Unskilled Labor 2 1.00 53.92 107.84
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Motorized Road Grader (140hp), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10m.t), SD100DC 1 1.00 1,846.00 1,846.00
c. Plate Compactor (5hp) 1 0.25 123.00 30.75
d. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
JERICO O. EVANGELISTA
Engineer I
cu.m. hours
39.80 1
203.61
4,638.94
28,606.25
1,103.05
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 311 PCC Pavement (Plain) - Conventional Method, 200mm thk
Unit of Measurement: sq.m.
Output per hour: 10.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 96.79 96.79
b. Skilled Labor 4 1.00 69.93 279.72
c. Unskilled Labor 12 1.00 53.92 647.04
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Concrete Vibrator 2 1.00 91.25 182.50
b. Concrete Screeder (5.5hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
e. One Bagger Mixer 2 1.00 172.00 344.00
f. Water Truck (1000gal) 1 1.00 1,065.00 1,065.00
Minor Tools ( 5% of Labor Cost) 51.18
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 100(1) Clearing and Grubbing (with Stripping)
Unit of Measurement: LS
Output per hour: 1.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 9.50 96.79 919.51
b. Unskilled Labor 3 9.50 53.92 1,536.72
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 245.62
Sub-Total for F -
G. Direct Unit Cost (E+F) 2,701.85
H. Overhead,Contingencies & Miscellaneous(OCM) per DO 197, s. 2016 15% of G 224.57
I. Contractor's Profit (CP) 10% of G 270.18
J. Value Added Tax (VAT), per DO 197, 2016 5% of (G+H+I) 159.83
K. Total Unit Cost (G+H+I+J) 3,356.43
Prepared by:
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/Farm to Market Road at Brgy. Dao, Tuy, Batangas
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Motorized Road Grader (140hp), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10m.t), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
JERICO O. EVANGELISTA
Engineer I
cu.m
49.80
203.81
4,612.97
34,362.00
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/Farm to Market Road at Brgy. Dao, Tuy, Batangas
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Motorized Road Grader (140hp), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10m.t), SD100DC 1 1.00 1,846.00 1,846.00
d. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
JERICO O. EVANGELISTA
Engineer I
cu.m.
49.80
203.81
4,612.97
35,793.75
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 200 Aggregate Subbase Course
Unit of Measurement: cu.m.
Output per hour: 50.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 81.07 81.07
b. Unskilled Labor 2 1.00 45.27 90.54
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Motorized Road Grader, (140hp) G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10m.t), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
JERICO O. EVANGELISTA
Engineer I
DETAILED UNIT PRICE ANALYSIS
Project Name: Construction of Barangay/ Farm to Market Road at
Brgy. Salong, Calaca, Batangas
Item No./ Description: 201(1) Aggregate Base Course
Unit of Measurement: cu.m.
Output per hour: 50.00
Designation No. of Person No. of Hours Hourly Rate Amount
A Labor
a. Construction Foreman 1 1.00 81.07 81.07
b. Unskilled Labor 2 1.00 45.27 90.54
N ame and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
a. Motorized Road Grader (140hp), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10m.t), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
JERICO O. EVANGELISTA
Engineer I