Professional Documents
Culture Documents
Region : CAR
District : Kalinga
Name of Project :
:
Road Section I.D. :
Section :
Location : Tabuk City, Kalinga
Appropriation : P14,128,000.00
Source of Fund : GAA CY 2018 REGULAR INFRA.
Classification : By Contract
Limits : K0511+314 - K0512+020 & K0513+401 - K0513+1105
Starting Date : UPON APPROVAL
ITEM NO. ITEMS OF WORK TO BE DONE
#REF! ###
#REF! ###
#REF! ###
#REF! ###
#REF! ###
#REF! ###
#REF! ###
#REF! ###
#REF! ###
#REF! ###
#REF! ###
#REF! ###
T O TAL
ITEM DESCRIPTION
A.1.2 (4) PROVISION OF 4X2 PICKUP TYPE SERVICE FOR THE ENGINEER ON
BARE RENTAL BASIS
PART B OTHER GENERAL REQUIREMENT
B.5 PROJECT BILLBOARD/SIGNBOARD
B-7 OCCUPATIONAL SAFETY AND HEALTH PROGRAM
B.9 MOBILIZATION/DEMOBILIZATION
K0500+000-K0506+846
PART C EARTHWORKS
REMOVAL OF ACTUAL STRUCTURES/OBSTRUCTION, PCCP
101(3)b3
(Unreinforced), thk=0.23m
102(2) SURPLUS COMMON EXCAVATION
103(1)a STRUCTURE EXCAVATION
104(1)b1 EMBANKMENT FROM BORROW
105(1)a SUBGRADE PREPARATION
PART D SUBBASE AND SUBBASE COURSE
200(1) AGGREGATE SUB-BASE COURSE
PART E SURFACE COURSE
311(1)e1 PCC PAVEMENT (Unreinforced) - 280mm thk. @ 14days
PART F DRAINAGE CONSTRUCTION
404(1)a REINFORCING STEEL BAR Grade 40
405(1)a3 STRUCTURAL CONCRETE, 20.68 Mpa @ 28days
612(1) REFLECTORIZED THERMOPLASTIC PAVEMENT MARKINGS (White)
K0506+905-K0507+208
PART C EARTHWORKS
REMOVAL OF ACTUAL STRUCTURES/OBSTRUCTION, PCCP
101(3)b3
(Unreinforced), thk=0.23m
102(2) SURPLUS COMMON EXCAVATION
103(1)a STRUCTURE EXCAVATION
104(1)b1 EMBANKMENT FROM BORROW
105(1)a SUBGRADE PREPARATION
PART D SUBBASE AND SUBBASE COURSE
200(1) AGGREGATE SUB-BASE COURSE
PART E SURFACE COURSE
311(1)e1 PCC PAVEMENT (Unreinforced) - 280mm thk. @ 14days
PART F DRAINAGE CONSTRUCTION
404(1)a REINFORCING STEEL BAR Grade 40
405(1)a3 STRUCTURAL CONCRETE, 20.68 Mpa @ 28days
612(1) REFLECTORIZED THERMOPLASTIC PAVEMENT MARKINGS (White)
K0509+270-K0509+414
PART C EARTHWORKS
REMOVAL OF ACTUAL STRUCTURES/OBSTRUCTION, PCCP
101(3)b3
(Unreinforced), thk=0.23m
102(2) SURPLUS COMMON EXCAVATION
103(1)a STRUCTURE EXCAVATION
104(1)b1 EMBANKMENT FROM BORROW
105(1)a SUBGRADE PREPARATION
PART D SUBBASE AND SUBBASE COURSE
200(1) AGGREGATE SUB-BASE COURSE
PART E SURFACE COURSE
311(1)e1 PCC PAVEMENT (Unreinforced) - 280mm thk. @ 14days
PART F DRAINAGE CONSTRUCTION
404(1)a REINFORCING STEEL BAR Grade 40
405(1)a3 STRUCTURAL CONCRETE, 20.68 Mpa @ 28days
612(1) REFLECTORIZED THERMOPLASTIC PAVEMENT MARKINGS (White)
DIRECT COST
1. Labor
2. Equipment
3. Material
4. Project Supervision
Total Direct Cost
INDIRECT COST
1. Mark-up (OCM, Profit)
2. VAT
3. Quality Control
4. Eng'g & Administrative Overhead
5. Construction Contingency
6. Central Office Retention
7. Road Right-of-Way
8. Soil Exploration
9. Survey Plan and Preparation
Total Indirect Cost
RUBY A. UYAM
Asst. District Engineer
Republic of the Philippines
MENT OF PUBLIC WORKS AND HIGHWAYS
ALINGA DISTRICT ENGINEERING OFFICE
FICE OF THE DISTRICT ENGINEER
Bulanao, Tabuk City, Kalinga
PROGRAM OF WORK
Date : November 25, 2019
Roadbed Width : 6.70 m.
Pavement Width : 6.70 m.
Net Length : 1,418.00 m.
Thickness : 50.00 mm.
Type of Structure :
Type of Substructure :
No. of Spans :
No. of Piers :
Dimensions :
No.of Days to Complete : 45.00 CD
E Q U I PM E NT
%
DESCRIPTION NEEDED AVAILABLE
#REF!
Backhoe 1
#REF! Pay Loader 1
#REF! Dumptrucks 3
#REF! Concrete Vibrator 1
#REF! Transit Mixer 3
Stake Truck 1
#REF! 1-Bagger Conc. Mixer 1
#REF! Water Truck 1
#REF! Road Grader 1
#REF! Road Roller 1
Batching Plant 1
Compactor 1
Concrete Saw 1
Bar Cutter 1
Bar Bender 1
Hand Tools lot
#REF!
ESTIMATED COST OF PROPOSED WORKS
UNIT QUANTITY UNIT COST COST
mo 3.83 - 0.00
P 10,847,146.36 76.78
P 2,143,834.60 15.17
P 649,252.62 4.60
P
P 494,480.00 3.50
P
P
P
P
P
P 3,287,567.22 23.27
14,134,713.58 100.05
Say P 14,128,000.00 100.00
Reviewed and Submitted by:
RAFAEL L. FERNANDO
Chief, Planning and Design Section
Approved :
IRENEO S. GALLATO
District Engineer
2846 K0500+000-K0506+846
ADJUSTED 303 K0506+905-K0507+208
COST 144 K0509+270-K0509+414
13,633,520.00
#REF!
-6,713.58
#REF!
Name of Project: #REF!
#REF!
3. Materials :
#REF!
3. Materials :
Rope 1" dia m. 2000 3.5 PhP 7,000.00
#REF!
3. Materials :
Rope 1" dia m. 2000 3.5 PhP 7,000.00
#REF!
3. Materials :
Rope 1" dia m. 2000 3.5 PhP 7,000.00
#REF!
3. Materials :
Rope 1" dia m. 200 3.5 PhP 700.00
Sub - Total for 3 Php 700.00
Direct Cost PhP 199,333.24
Overhead,Contingencies & Miscellaneouse 12% PhP 23,919.99
Contractor's Profit 8% PhP 15,946.66
VAT 5% PhP 11,959.99
Item Cost PhP 251,159.88
Total Unit Cost PhP 25,115.99
Name of Project: #REF!
#REF!
#REF!
#REF!
#REF!
ITEM 101(1)D - REMOVAL OF CONCRETE DRAINAGE STRUCTURE
Unit of Measurement = cu.m. Quantity = 100.00
Output/hour = 2 cu.m./hr Duration= 50.00
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 50.00
Skilled Laborers 1 50.00
Laborers 2 50.00
#REF!
ITEM 101(4)B - REMOVAL OF ACTUAL STRUCTURES/OBSTRUCTION,RCPC (30" dia) - 760mm
Unit of Measurement = l.m. Quantity = 30.00
Output/hour = 5 l.m./hr Duration= 6.00
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 6.00
Laborers 2 6.00
#REF!
ITEM 101(4)c - REMOVAL OF ACTUAL STRUCTURES/OBSTRUCTION,RCPC (36" dia) - 910mm
Unit of Measurement = l.m. Quantity = 30.00
Output/hour = 4 l.m./hr Duration= 7.50
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 7.50
Laborers 2 7.50
#REF!
#REF!
ITEM 101(3)a.3 - REMOVAL OF EXISTING PCC PAVEMENT,0.23m thk (for Reblocking at Intermitte
Unit of Measurement = sq.m. Quantity = 100.00
Output/hour = 30 sq.m./hr Duration= 3.33
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 3.33
Laborers 2 3.33
#REF!
#REF!
PhP 2,445.10
No. of Hours Hourly Rate Amount
Php 17,012.36
PhP 19,457.46
Quantity Unit Cost Amount
Php -
PhP 19,457.46
9% PhP 1,751.17
8% PhP 1,556.60
5% PhP 1,138.26
PhP 23,903.48
PhP 239.03
cu.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 40,276.00
No. of Hours Hourly Rate Amount
Php 316,882.50
PhP 357,158.50
Quantity Unit Cost Amount
Php 2,500.00
PhP 359,658.50
9% PhP 32,369.27
8% PhP 28,772.68
5% PhP 21,040.02
PhP 441,840.47
PhP 4,418.40
kgs
hrs.
No. of Hours Hourly Rate Amount
PhP 40.28
No. of Hours Hourly Rate Amount
Php 348.33
PhP 388.61
Quantity Unit Cost Amount
Php 98.00
PhP 486.61
9% PhP 43.79
8% PhP 38.93
5% PhP 28.47
PhP 597.80
PhP 5.98
UCTURES
cu.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 2,782.60
No. of Hours Hourly Rate Amount
Php 31,875.50
PhP 34,658.10
Quantity Unit Cost Amount
Php -
PhP 34,658.10
9% PhP 3,119.23
8% PhP 2,772.65
5% PhP 2,027.50
PhP 42,577.48
PhP 425.77
cu.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 12,225.00
No. of Hours Hourly Rate Amount
Php 97,331.25
PhP 109,556.25
Quantity Unit Cost Amount
Php 2,500.00
PhP 112,056.25
9% PhP 10,085.06
8% PhP 8,964.50
5% PhP 6,555.29
PhP 137,661.10
PhP 1,376.61
CPC (24" dia) - 610mm
l.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 911.25
No. of Hours Hourly Rate Amount
Php 10,320.88
PhP 11,232.13
Quantity Unit Cost Amount
Php -
PhP 11,232.13
9% PhP 1,010.89
8% PhP 898.57
5% PhP 657.08
PhP 13,798.67
PhP 459.96
CPC (30" dia) - 760mm
l.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 1,093.50
No. of Hours Hourly Rate Amount
Php 12,385.05
PhP 13,478.55
Quantity Unit Cost Amount
Php -
PhP 13,478.55
9% PhP 1,213.07
8% PhP 1,078.28
5% PhP 788.50
PhP 16,558.40
PhP 551.95
PC (36" dia) - 910mm
l.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 1,366.88
No. of Hours Hourly Rate Amount
Php 15,481.31
PhP 16,848.19
Quantity Unit Cost Amount
Php -
PhP 16,848.19
9% PhP 1,516.34
8% PhP 1,347.86
5% PhP 985.62
PhP 20,698.00
PhP 689.93
PhP 455.63
No. of Hours Hourly Rate Amount
Php 11,148.31
PhP 11,603.94
Quantity Unit Cost Amount
Php -
PhP 11,603.94
9% PhP 1,044.35
8% PhP 928.32
5% PhP 678.83
PhP 14,255.44
PhP 142.55
PhP 606.89
No. of Hours Hourly Rate Amount
Php 14,843.19
PhP 15,450.08
Quantity Unit Cost Amount
Php 120.00
PhP 15,570.08
9% PhP 1,401.31
8% PhP 1,245.61
5% PhP 910.85
PhP 19,127.85
PhP 191.28
PhP 606.89
No. of Hours Hourly Rate Amount
Php 8,250.24
PhP 8,857.13
Quantity Unit Cost Amount
Php -
PhP 8,857.13
12% PhP 1,062.86
8% PhP 708.57
5% PhP 531.43
PhP 11,159.99
PhP 111.60
Php 5,906.66
PhP 6,149.06
Quantity Unit Cost Amount
Php -
PhP 6,149.06
9% PhP 553.41
8% PhP 491.92
5% PhP 359.72
PhP 7,554.11
PhP 75.54
PhP 2,445.10
PhP 1,751.17
PhP 1,556.60
PhP 1,138.26
PhP 40,276.00
PhP 32,369.27
PhP 28,772.68
PhP 21,040.02
PhP 40.28
PhP 43.79
PhP 38.93
PhP 28.47
PhP 2,782.60
PhP 3,119.23
PhP 2,772.65
PhP 2,027.50
PhP 12,225.00
PhP 10,085.06
PhP 8,964.50
PhP 6,555.29
PhP 911.25
PhP 1,010.89
PhP 898.57
PhP 657.08
PhP 1,093.50
PhP 1,213.07
PhP 1,078.28
PhP 788.50
PhP 1,366.88
PhP 1,516.34
PhP 1,347.86
PhP 985.62
PhP 455.63
PhP 1,044.35
PhP 928.32
PhP 678.83
PhP 606.89
PhP 1,401.31
PhP 1,245.61
PhP 910.85
PhP 606.89
PhP 1,062.86
PhP 708.57
PhP 531.43
PhP 242.39
PhP 553.41
PhP 491.92
PhP 359.72
Php 17,012.36
Php -
Php 316,882.50
Php 2,500.00
Php 348.33
Php 98.00
Php 31,875.50
Php -
Php 97,331.25
Php 2,500.00
Php 10,320.88
Php -
Php 12,385.05
Php -
Php 15,481.31
Php -
Php 11,148.31
Php -
Php 14,843.19
Php 120.00
Php 8,250.24
Php -
Php 5,906.66
Php -
Name of Project: #REF!
#REF!
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
#REF!
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
#REF!
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
#REF!
ITEM 102(3)A - SURPLUS EXCAVATION ( SOFT ROCK)
Unit of Measurement = cu.m. Quantity = 1,000.00
Output/hour = 42 cu.m./hr Duration = 24.00
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 24
Laborers 2 24
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3km,
the time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Direct Cost
Overhead, Contingencies & Maintenance (OCM)
Contractor's Profit (CP)
VAT
Item Cost
Total Unit Cost
#REF!
ITEM 102(3)B- SURPLUS EXCAVATION (HARD ROCK)
Unit of Measurement = cu.m. Quantity = 1,000.00
Output/hour = 4.2 cu.m./hr Duration = 238.00
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 95
Skilled Laborers (Drilling) 2 95
Laborers 4 95
Construction Foreman 1 48
Skilled Laborers (Blasting) 1 48
Laborers 2 48
Construction Foreman 1 95
Laborers (Disposal) 2 95
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3km,
the time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Dynamite kg 400.00
Detonation Cord m. 2,000.00
Detonator pc. 150.00
Ammonium Sulfate kg 200.00
Blasting Cap pc. 400.00
Safety Fuse m. 100.00
Direct Cost
Overhead, Contingencies & Maintenance (OCM)
Contractor's Profit (CP)
VAT
Item Cost
Total Unit Cost
cu.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 11,513.00
No. of Hours Hourly Rate Amount
Php 237,315.00
PhP 248,828.00
Quantity Unit Cost Amount
PhP 248,828.00
9% PhP 22,394.52 PhP 22,394.52
8% PhP 19,906.24 PhP 19,906.24
5% PhP 14,556.44
PhP 305,685.20
PhP 305.69
cu.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 3,038.27
No. of Hours Hourly Rate Amount
No. of Hours Hourly Rate Amount
Php 139,782.12
PhP 142,820.39
Quantity Unit Cost Amount
PhP 142,820.39
9% PhP 12,853.84 PhP 12,853.84
8% PhP 11,425.63 PhP 11,425.63
5% PhP 8,354.99
PhP 175,454.85
PhP 175.45
cu.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 2,278.25
No. of Hours Hourly Rate Amount
Php 142,861.25
PhP 145,139.50
Quantity Unit Cost Amount
PhP 145,139.50
9% PhP 13,062.56 PhP 13,062.56
8% PhP 11,611.16 PhP 11,611.16
5% PhP 8,490.66
PhP 178,303.88
PhP 178.30
cu.m.
hrs.
No. of Hours Hourly Rate Amount
PhP 3,645.20
No. of Hours Hourly Rate Amount
Php 165,972.00
PhP 169,617.20
Quantity Unit Cost Amount
PhP 169,617.20
9% PhP 15,265.55 PhP 15,265.55
8% PhP 13,569.38 PhP 13,569.38
5% PhP 9,922.61
PhP 208,374.73
PhP 208.37
cu.m.
hr
Php 199,166.40
PhP 203,540.64
Quantity Unit Cost Amount
PhP -
PhP 203,540.64
9% PhP 18,318.66 PhP 18,318.66
8% PhP 16,283.25 PhP 16,283.25
5% PhP 11,907.13
PhP 250,049.68
Php 250.05
cu.m.
hr
Php 356,839.11
PhP 424,171.69
Quantity Unit Cost Amount
PhP 348,000.00
PhP 772,171.69
9% PhP 69,495.45 PhP 69,495.45
8% PhP 61,773.74 PhP 61,773.74
5% PhP 45,172.04
PhP 948,612.92
Php 948.61
PhP 11,513.00
Php 237,315.00
PhP 14,556.44
PhP 3,038.27
Php 139,782.12
PhP 8,354.99
PhP 2,278.25
Php 142,861.25
PhP 8,490.66
PhP 3,645.20
Php 165,972.00
PhP 9,922.61
PhP 4,374.24
Php 199,166.40
PhP 11,907.13
PhP 67,332.58
Php 356,839.11
PhP 45,172.04
PhP -
PhP 348,000.00
Name of Project: #REF!
#REF!
ITEM 103(1)a - STRUCTURE EXCAVATION (Common Soil)
Unit of Measurement = cu.m. Quantity = 100.00 cu.m.
Output/hour = 20 cu.m./hr Duration= 5.00 hrs.
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 5.00
Laborers 3 5.00
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
#REF!
ITEM 103(1)b - STRUCTURE EXCAVATION (Soft Rock)
Unit of Measurement = cu.m. Quantity = 100.00 cu.m.
Output/hour = 14 cu.m./hr Duration= 7.14 hrs.
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 7.14
Laborers 3 7.14
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
#REF!
ITEM 103(1)c - STRUCTURE EXCAVATION (Solid Rock)
Unit of Measurement = cu.m. Quantity = 30.00 cu.m.
Output/hour = 4 cu.m./hr Duration= 7.50 hrs.
No. of
Designation No. of Hours
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 7.50
Laborers 3 7.50
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
#REF!
ITEM 103(4)a - FOUNDATION FILL
Unit of Measurement = cu.m. Quantity = 30.00 cu.m.
Output/hour = 1.25 cu.m./hr Duration= 24.00 hrs.
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 24.00
Laborers 4 24.00
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
#REF!
ITEM 103(6)a - PIPE CULVERT AND DRAIN EXCAVATION
Unit of Measurement = cu.m. Quantity = 30.00 cu.m.
Output/hour = 20 cu.m./hr Duration= 1.50 hrs.
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 1.50
Laborers 3 1.50
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Hourly Rate Amount
PhP 1,151.30
Hourly Rate Amount
Php 22,000.13
PhP 23,151.43
Unit Cost Amount
PhP 23,151.43
9% PhP 2,083.63 PhP 2,083.63
8% PhP 1,852.11 PhP 1,852.11
5% PhP 1,354.36 PhP 1,354.36
PhP 28,441.53
PhP 284.42
Hourly Rate Amount
PhP 1,644.06
Hourly Rate Amount
Php 33,061.96
PhP 34,706.01
Unit Cost Amount
PhP 34,706.01
9% PhP 3,123.54 PhP 3,123.54
8% PhP 2,776.48 PhP 2,776.48
5% PhP 2,030.30 PhP 2,030.30
PhP 42,636.34
PhP 426.36
PhP 1,726.95
Hourly Rate Amount
Php 35,593.32
PhP 37,320.27
Unit Cost Amount
PhP 37,320.27
9% PhP 3,358.82 PhP 3,358.82
8% PhP 2,985.62 PhP 2,985.62
5% PhP 2,183.24 PhP 2,183.24
PhP 45,847.95
PhP 1,528.27
PhP 6,678.24
Hourly Rate Amount
Php 4,217.42
PhP 10,895.66
Unit Cost Amount
PhP 10,895.66
9% PhP 980.61 PhP 980.61
8% PhP 871.65 PhP 871.65
5% PhP 637.40 PhP 637.40
PhP 13,385.32
PhP 446.18
PhP 345.39
Hourly Rate Amount
Php 6,600.04
PhP 6,945.43
Unit Cost Amount
PhP 6,945.43
9% PhP 625.09 PhP 625.09
8% PhP 555.63 PhP 555.63
5% PhP 406.31 PhP 406.31
PhP 8,532.46
PhP 284.42
PhP 1,151.30
Php 22,000.13
PhP 1,644.06
Php 33,061.96
PhP 1,726.95
Php 35,593.32
PhP 6,678.24
Php 4,217.42
PhP 345.39
Php 6,600.04
Name of Project:
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Name of Project:
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Hourly Rate Amount
Php 9,263.00
PhP 9,565.55
Unit Cost Amount
PhP 50,000.00
PhP 59,565.55
15% PhP 8,934.83 PhP 8,934.83
8% PhP 4,765.24 PhP 4,765.24
5% PhP 3,663.28 PhP 3,663.28
PhP 76,928.91
PhP 769.29
Hourly Rate Amount
Php 9,263.00
PhP 9,930.07
Unit Cost Amount
PhP 9,930.07
10% PhP 993.01 PhP 993.01
8% PhP 794.41 PhP 794.41
5% PhP 585.87 PhP 585.87
PhP 12,303.36
PhP 123.03
Php 9,263.00
PhP 50,000.00
Php 9,263.00
Name of Project:
3. Materials :
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Hourly Rate Amount
Php 15,422.90
PhP 16,029.82
PhP -
PhP 16,029.82
12% PhP 1,923.58 PhP 1,923.58
8% PhP 1,282.39 PhP 1,282.39
5% PhP 961.79 PhP 961.79
PhP 20,197.57
PhP 20.20
0
Php 15,422.90
Name of Project:
3. Materials :
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Name of Project:
Name of Project:
3. Materials :
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Hourly Rate Amount
PhP 364.52
Php 9,263.00
PhP 9,627.52
PhP 66,700.00
PhP 76,327.52
12% PhP 9,159.30 PhP 9,159.30
8% PhP 6,106.20 PhP 6,106.20
12% PhP 10,991.16 PhP 10,991.16
PhP 102,584.19
PhP 1,025.84
Hourly Rate Amount
PhP 378.19
Php 12,520.63
PhP 12,898.82
PhP 66,700.00
PhP 79,598.82
12% PhP 9,551.86 PhP 9,551.86
8% PhP 6,367.91 PhP 6,367.91
12% PhP 11,462.23 PhP 11,462.23
PhP 106,980.81
PhP 1,069.81
PhP 364.52
Php 9,263.00
PhP 66,700.00
PhP 378.19
Php 12,520.63
PhP 66,700.00
D E TAI LE D E ST I MAT E S
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 66
Skilled Laborers 6 66
Laborers 12 66
1,640.00 sq.m.
66.00 hrs.
PhP 68,360.16
No. of Hours Hourly Rate Amount
Php 507,941.02
PhP 576,301.18
ITEM 310(1)A.3 -BITUMINOUS CONCRETE WEARING SURFACE COURSE , HOT LAID( 50mm THK
Unit of Measurement = sq.m. Quantity = 1,640.00
Output/hour = 171.30 sq.m./hr Duration= 10.00 hrs.
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor :
Construction Foreman 1 10 PhP 86.26
Skilled Laborers 6 10 PhP 62.25
Laborers 8 10 PhP 48.00
PhP 8,437.60
Hourly Rate Amount
Php 65,803.76
PhP 74,241.36
Php 65,803.76
Php 137,156.00
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 9
Skilled Laborers 4 9
Laborers 12 9
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 12
Skilled Laborers 4 12
Laborers 12 12
Name of Project:
No. of
Designation No. of Hours
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 14
Skilled Laborers 4 14
Laborers 12 14
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 17
Skilled Laborers 4 17
Laborers 12 17
PhP 8,201.34
No. of Hours Hourly Rate Amount
Php 108,501.85
PhP 116,703.19
330.00 Php -
290.00 75.00 Php 21,750.00
120.00 45.00 Php 5,400.00
460.00 44.00 Php 20,240.00
83.00 Php -
150.00 Php -
1,430.00 Php -
0.15 8,000.00 Php 1,200.00
7.80 97.00 Php 756.60
1.50 230.00 Php 345.00
Php 49,691.60
PhP 166,394.79
12% PhP 19,967.37 PhP 19,967.37
8% PhP 13,311.58 PhP 13,311.58
5% PhP 9,983.69
PhP 209,657.43
Php 209.66
d, 200mm thk
1,000.00 sq.m.
12.00 hrs.
PhP 10,935.12
No. of Hours Hourly Rate Amount
Php 144,669.13
PhP 155,604.25
390.00 Php -
290.00 75.00 Php 21,750.00
120.00 45.00 Php 5,400.00
460.00 44.00 Php 20,240.00
110.00 Php -
200.00 Php -
1,900.00 Php -
0.15 8,000.00 Php 1,200.00
8.60 97.00 Php 834.20
5.60 230.00 Php 1,288.00
Php 50,712.20
PhP 206,316.45
12% PhP 24,757.97 PhP 24,757.97
8% PhP 16,505.32 PhP 16,505.32
5% PhP 12,378.99
PhP 259,958.72
Php 259.96
d, 230mm thk
1,000.00 sq.m.
14.00 hrs.
PhP 12,757.64
No. of Hours Hourly Rate Amount
Php 168,780.65
PhP 181,538.29
430.00 Php -
290.00 75.00 Php 21,750.00
120.00 45.00 Php 5,400.00
460.00 44.00 Php 20,240.00
127.00 Php -
230.00 Php -
2,190.00 Php -
0.15 8,000.00 Php 1,200.00
7.10 97.00 Php 688.70
8.70 230.00 Php 2,001.00
Php 51,279.70
PhP 232,817.99
12% PhP 27,938.16 PhP 27,938.16
8% PhP 18,625.44 PhP 18,625.44
5% PhP 13,969.08
PhP 293,350.67
Php 293.35
d, 280mm thk
1,000.00 sq.m.
17.00 hrs.
PhP 15,491.42
No. of Hours Hourly Rate Amount
Php 204,947.93
PhP 220,439.35
Quantity Unit Cost Amount
Err:509
Err:509
12% Err:509 Err:509
8% Err:509 Err:509
5% Err:509
Err:509
Err:509
PhP 8,201.34
Php 108,501.85
PhP 9,983.69
PhP 10,935.12
Php 144,669.13
PhP 12,378.99
PhP 12,757.64
Php 168,780.65
PhP 13,969.08
PhP 15,491.42
Php 204,947.93
Err:509
Php 49,691.60
Php 50,712.20
Php 51,279.70
Err:509
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 6
Skilled Laborers 2 6
Laborers 8 6
3. Materials :
Tie Wire (2% of RSB) kgs. 21.00
Reinforcing Steel Bars ,Grade 40(w/ 5% wastage) kgs. 1,050.00
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 36
Skilled Laborers 4 36
Laborers 8 36
Installation/Removal of Formworks
Skilled Laborers 4 36
Laborers 8 36
3. Materials :
Lumber, Good- 4 uses bdft 875.00
Marine Plywood(1/2"x4'x8')-4 uses pc 20.00
Assorted CWN(1kg/100 bdft of Lumber) kg 35.00
Cement bags 475.00
Sand cu.m. 25.00
Gravel cu.m. 50.00
Name of Project:
3. Materials :
Portland Cement bags 800.00
Coarse Aggregate cu.m. 100.00
Fine Aggregate cu.m. 50.00
Sub - Total for 3
Direct Cost
Overhead Contingencies & Maintenance
Contractor's Profit
VAT
Item Cost
Total Unit Cost
1,000.00 kgs
hrs.
PhP 3,568.56
Php 2,804.55
PhP 6,373.11
Php -
Php -
Php -
PhP 6,373.11
12% PhP 764.77 PhP 764.77
8% PhP 509.85 PhP 509.85
5% PhP 382.39 PhP 382.39
PhP 8,030.12
Php 8.03
50.00 cu.m
hrs.
PhP 52,138.80
Php 20,903.94
PhP 73,042.74
Php 45,000.00
PhP 118,042.74
12% PhP 14,165.13 PhP 14,165.13
8% PhP 9,443.42 PhP 9,443.42
5% PhP 7,082.56 PhP 7,082.56
PhP 148,733.85
Php 2,974.68
hrs.
Php 36,085.75
PhP 87,153.21
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509
Err:509
12% Err:509 Err:509
8% Err:509 Err:509
5% Err:509 Err:509
Err:509
Err:509
PhP 3,568.56
Php 2,804.55
Php -
PhP 52,138.80
Php 20,903.94
Php 45,000.00
115
Php 36,085.75
Err:509
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 4
Skilled Laborers 2 4
Laborers 4 4
3. Materials :
Portland cement bags 8.00
Sand cu.m. 0.44
R.C. Pipes (610mm dia) pc 10.00
Sand Bedding/Selected Sandy Soil cu.m. 0.88
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 3
Skilled Laborers 2 3
Laborers 4 3
3. Materials :
Portland cement bags 9.00
Sand cu.m. 0.52
R.C. Pipes (760mm dia) pc 10.00
Sand Bedding/Selected Sandy Soil cu.m. 1.08
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 3
Skilled Laborers 2 3
Laborers 4 3
3. Materials :
Portland cement bags 11.00
Sand cu.m. 0.61
R.C. Pipes (910mm dia) pc 10.00
Sand Bedding/Selected Sandy Soil cu.m. 1.28
Sub - Total for 3
Direct Cost
Overhead, Contingencies & Maintenance (OCM)
Contractor's Profit (CP)
VAT
Item Cost
Total Unit Cost
10.00 l.m.
hrs.
PhP 1,772.14
Php 8,477.21
PhP 10,249.35
Php -
Php -
Php -
Php -
Php -
PhP 10,249.35
12% PhP 1,229.92
8% PhP 819.95
5% PhP 614.96 PhP 614.96
PhP 12,914.19
Php 1,291.42
10.00 l.m.
hrs.
PhP 1,006.90
Php 2,175.69
PhP 3,182.59
Php -
Php -
Php -
Php -
Php -
PhP 3,182.59
12% PhP 381.91
8% PhP 254.61
5% PhP 190.96 PhP 190.96
PhP 4,010.06
Php 401.01
10.00 l.m.
hrs.
PhP 1,377.44
Php 3,026.14
PhP 4,403.58
Php -
Php -
Php -
Php -
Php -
PhP 4,403.58
12% PhP 528.43
8% PhP 352.29
5% PhP 264.22 PhP 264.22
PhP 5,548.52
Php 554.85
PhP 1,772.14
Php 8,477.21
Php -
PhP 1,006.90
Php 2,175.69
Php -
PhP 1,377.44
Php 3,026.14
Php -
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 8
Skilled 2 8
Laborers 8 8
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
3. Materials :
10 mm. ØReinforcing Steel Bars kgs. 171.00
Sand cu.m. 1.11
Gravel cu.m. 2.23
Cement bags 25.00
# 16 Tie Wire ( 2% of RSB ) kgs. 0.07
1/4" x 4' x 8' Ordinary Plywood - 4 uses pcs. 3.00
2"x3"x10" Lumber - 4 uses bd. Ft. 25.00
Assorted CWN ( 1 kg/100bd.ft. of lumber) kgs. 0.25
Php 785.68
PhP 5,543.76
171.00 Php -
1.11 Php -
2.23 Php -
25.00 Php -
0.07 65.00 Php 4.45
3.00 605.00 Php 1,815.00
25.00 40.00 Php 1,000.00
0.25 65.00 Php 16.25
PhP 2,835.70
PhP 8,379.47
9% PhP 754.15 PhP 754.15
8% PhP 670.36 PhP 670.36
5% PhP 490.20
PhP 10,294.17
Php 10,294.17
PhP 4,758.08
Php 785.68
PhP 490.20
PhP 2,835.70
Name of Project:
3. Materials :
Cement bags 900.00
Sand cu.m. 75.00
Gravel Fill cu.m 4.50
Weep Holes (4" diam.) (.30ln.m./cu.m.) ln.m 90.00
Filter Cloth sq.m 5.00
Boulders cu.m 315.00
Miscelaneous (1% of Materials)
Sub - Total for 3
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Name of Project:
ITEM 506(1) - STONE MASONRY
Unit of Measurement = cu.m. Quantity =
Output/hour = 1 cu.m./man-day Duration =
1.5625 cu.m./hr.
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 192
Skilled 2 192
Laborers 8 192
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
1-Bagger Mixer 1 192
Water Truck (16,000 L) 1 10
Backhoe (Wheel type 0.28 cu.m.) 1 19
Minor tools (10% of Labor Cost)
Sub - Total for 2
Total (1+2)
Output per hour = 1.00 3.00 /hr
Unit Cost = PhP 660.95 /cu.m.
3. Materials :
Cement bags 1,650.00
Sand cu.m. 90.00
Gravel Fill cu.m 6.00
Weep Holes (4" diam.) (.30ln.m./cu.m.) ln.m 90.00
Filter Cloth sq.m 5.00
Boulders cu.m 315.00
Miscelaneous (1% of Materials)
Sub - Total for 3
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Name of Project:
ITEM 507(1) - RUBBLE CONCRETE
Unit of Measurement = cu.m. Quantity =
Output/hour = 1 cu.m./man-day Duration =
1.4 cu.m./hr.
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 214
Skilled 2 214
Laborers 8 214
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
1-Bagger Mixer 1 214
Water Truck (16,000 L) 1 11
Backhoe (Wheel type 0.28 cu.m.) 1 21
Minor tools (10% of Labor Cost)
Sub - Total for 2
Total (1+2)
Output per hour = 1.00 3.00 /hr
Unit Cost = PhP 736.69 /cu.m.
3. Materials :
Cement bags 1,260.00
Sand cu.m. 78.75
Gravel Fill cu.m 6.00
Weep Holes (4" diam.) (.30ln.m./cu.m.) ln.m 90.00
Filter Cloth sq.m 5.00
Boulders cu.m 189.00
Gravel cu.m 157.50
Miscelaneous (2% of Materials)
Sub - Total for 3
Direct Cost
Overhead,Contingencies & Miscellaneouse
Contractor's Profit
VAT
Item Cost
Total Unit Cost
300.00 cu.m.
300.00 cu.m. =
240 hrs
1.25cu.m./hr
900.00 Php -
75.00 Php -
4.50 Php -
90.00 206.67 Php 18,600.30
5.00 160.00 Php 800.00
315.00 Php -
Php 194.00
PhP 19,594.30
PhP 240,153.82
12% PhP 28,818.46
8% PhP 19,212.31
5% PhP 14,409.23
PhP 302,593.82
Php 1,008.65
300.00 cu.m.
300.00 cu.m. =
192 hrs
1.5625cu.m./hr
1,650.00 Php -
90.00 Php -
6.00 Php -
90.00 206.67 Php 18,600.30
5.00 160.00 Php 800.00
315.00 Php -
Php 194.00
PhP 19,594.30
PhP 217,879.62
12% PhP 26,145.55
8% PhP 17,430.37
5% PhP 13,072.78
PhP 274,528.31
Php 915.09
300.00 cu.m.
300.00 cu.m. =
214 hrs
1.5625cu.m./hr
1,260.00 Php -
78.75 Php -
6.00 Php -
90.00 206.67 Php 18,600.30
5.00 160.00 Php 800.00
189.00 Php -
157.50 Php -
Php 388.01
PhP 19,788.31
PhP 240,793.81
12% PhP 28,895.26
8% PhP 19,263.50
5% PhP 14,447.63
PhP 303,400.20
Php 1,011.33
PhP 142,742.40
PhP 28,818.46
PhP 19,212.31
PhP 14,409.23
PhP 114,193.92
PhP 26,145.55
PhP 17,430.37
PhP 13,072.78
PhP 127,278.64
PhP 28,895.26
PhP 19,263.50
PhP 14,447.63
Php 77,817.12
PhP 19,594.30
Php 84,091.39
PhP 19,594.30
Php 93,726.86
PhP 19,788.31
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 120
Skilled 2 120
Laborers 8 120
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
3. Materials :
Gabion Wire Mesh (1x1x2) w/ Complete accessories pc 150.00
Boulders cu.m 315.00
Name of Project:
3. Materials :
Matresses (6x2x.3) w/ Complete accessories pc 84.00
Boulders cu.m 315.00
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 96
Skilled 2 96
Laborers 8 96
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
Cargo Truck (10T) 1 24
3. Materials :
Filter Cloth sq.m. 315.00
Miscellaneous (5% of Materials)
Php -
PhP 71,371.20
PhP 435,000.00
PhP 506,371.20
12% PhP 60,764.54 PhP 60,764.54
8% PhP 40,509.70 PhP 40,509.70
5% PhP 30,382.27
PhP 638,027.71
Php 2,126.76
300.00 cu.m.
300.00 cu.m. =
96 hrs
96 hrs
3.125 cu.m./hr
Php -
PhP 57,096.96
PhP 420,000.00
PhP 477,096.96
12% PhP 57,251.64 PhP 57,251.64
8% PhP 38,167.76 PhP 38,167.76
5% PhP 28,625.82
PhP 601,142.17
Php 2,003.81
300.00 sq.m.
300.00 cu.m. =
96 hrs
3.125 cu.m./hr
Php 26,448.00
PhP 83,544.96
PhP 52,920.00
PhP 136,464.96
12% PhP 16,375.80 PhP 16,375.80
8% PhP 10,917.20 PhP 10,917.20
5% PhP 8,187.90
PhP 171,945.85
Php 573.15
PhP 71,371.20
Php -
PhP 30,382.27
PhP 57,096.96
Php -
PhP 28,625.82
PhP 57,096.96
Php 26,448.00
PhP 8,187.90
PhP 435,000.00
PhP 420,000.00
PhP 52,920.00
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 11
Skilled 4 11
Laborers 8 11
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
Concrete Vibrator 1 11
1-Bagger Mixer 1 11
Water Truck 1 1
Minor tools (10% of Labor Cost)
Sub - Total for 2
Total (1+2)
Output per hour = 17.50 3.00 /hr
Unit Cost = PhP 59.71 /cu.m.
3. Materials :
Cement bags 144.00
Sand cu.m. 8.00
Gravel cu.m 16.00
Form Lumber-4 uses bdft 328.00
Assorted CWN(1 kg/100bdft of Lumber) kgs 3.00
ITEM 600(4)- CURB AND GUTTER, TYPE A (CAST IN PLACE)- NATIONAL ROAD
Unit of Measurement = ln..m. Quantity =
Output/hour = 10.3 ln.m./hr. Duration =
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 19
Skilled 4 19
Laborers 8 19
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
Concrete Vibrator 1 19
1-Bagger Mixer 1 19
Water Truck 1 1
Minor tools (10% of Labor Cost)
Sub - Total for 2
Total (1+2)
Output per hour = 10.30 3.00 /hr
Unit Cost = PhP 103.14 /cu.m.
3. Materials :
Cement bags 258.00
Sand cu.m. 14.00
Gravel cu.m 28.00
Ordinary Plywood, 1/2" x 4' x 8 - 4-Uses pc. 12.00
Form Lumber-4 uses bdft 573.50
Assorted CWN(1 kg/100bdft of Lumber) kgs 6.00
Miscellaneous (2% of Materials)
ITEM 600(4)- CURB AND GUTTER, TYPE A (CAST IN PLACE)- NATIONAL ROAD
Unit of Measurement = ln..m. Quantity =
Output/hour = 10.3 ln.m./hr. Duration =
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 19
Skilled 4 19
Laborers 8 19
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
Concrete Vibrator 1 19
1-Bagger Mixer 1 19
Water Truck 1 1
Minor tools (10% of Labor Cost)
Sub - Total for 2
Total (1+2)
Output per hour = 10.30 3.00 /hr
Unit Cost = PhP 103.14 /cu.m.
3. Materials :
Cement bags 258.00
Sand cu.m. 14.00
Gravel cu.m 28.00
Ordinary Plywood, 1/2" x 4' x 8 - 4-Uses pc. 12.00
Form Lumber-4 uses bdft 573.50
Assorted CWN(1 kg/100bdft of Lumber) kgs 6.00
Miscellaneous (2% of Materials)
ITEM 600(4)- CURB AND GUTTER, TYPE A (CAST IN PLACE)- NATIONAL ROAD
Unit of Measurement = ln..m. Quantity =
Output/hour = 10.3 ln.m./hr. Duration =
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 19
Skilled 4 19
Laborers 8 19
Sub - Total for 1
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
Concrete Vibrator 1 19
1-Bagger Mixer 1 19
Water Truck 1 1
Minor tools (10% of Labor Cost)
Sub - Total for 2
Total (1+2)
Output per hour = 10.30 3.00 /hr
Unit Cost = PhP 103.14 /cu.m.
3. Materials :
Cement bags 258.00
Sand cu.m. 14.00
Gravel cu.m 28.00
Ordinary Plywood, 1/2" x 4' x 8 - 4-Uses pc. 12.00
Form Lumber-4 uses bdft 573.50
Assorted CWN(1 kg/100bdft of Lumber) kgs 6.00
Miscellaneous (2% of Materials)
144.00 Php -
8.00 Php -
16.00 Php -
328.00 40.00 Php 13,120.00
3.00 65.00 Php 195.00
PhP 13,315.00
PhP 25,257.55
12% PhP 3,030.91
8% PhP 2,020.60
5% PhP 1,515.45
PhP 31,824.51
Php 159.12
200.00 ln..m.
200.00 ln..m.
19 hrs
10.30 ln.m./hr
258.00 Php -
14.00 Php -
28.00 Php -
12.00 605.00 Php 7,260.00
573.50 40.00 Php 22,940.00
6.00 65.00 Php 390.00
Php 611.80
PhP 31,201.80
PhP 51,829.83
12% PhP 6,219.58
8% PhP 4,146.39
5% PhP 3,109.79
PhP 65,305.59
Php 326.53
200.00 ln..m.
200.00 ln..m.
19 hrs
10.30 ln.m./hr
258.00 Php -
14.00 Php -
28.00 Php -
12.00 605.00 Php 7,260.00
573.50 40.00 Php 22,940.00
6.00 65.00 Php 390.00
Php 611.80
PhP 31,201.80
PhP 51,829.83
12% PhP 6,219.58
8% PhP 4,146.39
5% PhP 3,109.79
PhP 65,305.59
Php 326.53
200.00 ln..m.
200.00 ln..m.
19 hrs
10.30 ln.m./hr
258.00 Php -
14.00 Php -
28.00 Php -
12.00 605.00 Php 7,260.00
573.50 40.00 Php 22,940.00
6.00 65.00 Php 390.00
Php 611.80
PhP 31,201.80
PhP 51,829.83
12% PhP 6,219.58
8% PhP 4,146.39
5% PhP 3,109.79
PhP 65,305.59
Php 326.53
PhP 7,911.86
Php 4,030.69
PhP 1,515.45
PhP 13,665.94
Php 6,962.09
PhP 3,109.79
PhP 13,665.94
Php 6,962.09
PhP 3,109.79
PhP 13,665.94
Php 6,962.09
PhP 3,109.79
PhP 13,315.00
PhP 31,201.80
PhP 31,201.80
PhP 31,201.80
Name of Project:
3. Materials :
Curing Compound L 58.00
Asphalt Sealant L 24.00
Forms m 92.00
Sand cu.m. 2.75
Gravel cu.m. 5.00
Cement bags 190.00
Name of Project:
3. Materials :
Curing Compound L 58.00
Asphalt Sealant L 24.00
Forms m 92.00
Sand cu.m. 2.75
Gravel cu.m. 5.00
Cement bags 190.00
Php 12,019.69
Php 12,019.69
PhP 12,930.95
PhP 9,478.00
PhP 22,408.95
12% PhP 2,689.07
8% PhP 1,792.72
5% PhP 1,344.54
PhP 28,235.28
Php 141.18
sq.m.
sq.m.
10 hrs
10.30 sq.m./hr
Hourly Rate Amount
Php 18,849.43
Php 18,849.43
PhP 27,962.03
PhP 9,478.00
PhP 37,440.03
12% PhP 4,492.80
8% PhP 2,995.20
5% PhP 2,246.40
PhP 47,174.44
Php 235.87
PhP 911.26
Php 12,019.69
PhP 1,344.54
PhP 9,112.60
Php 18,849.43
PhP 2,246.40
PhP 9,478.00
PhP 9,478.00
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 6
Skilled 2 6
Laborers 6 6
3. Materials :
Thermoplastic Paint (White) bag 48.75
Glass Beads bag 4.95
Primer lit. 18.00
LPG (50 kg.) cyl. 0.60
LPG (12 kg.) cyl. 0.30
Calsumine kg. 18.75
Miscellaneous (5% of Materials)
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 0.80
Skilled 2 0.80
Laborers 6 0.80
3. Materials :
Thermoplastic Paint (Yellow) bag 6.50
Glass Beads bag 0.66
Primer lit. 2.40
LPG (50 kg.) cyl. 0.08
LPG (12 kg.) cyl. 0.04
Calsumine kg. 2.50
Miscellaneous (5% of Materials)
Sub - Total for 3
Direct Cost
Overhead Contingencies & Maintenance
Contractor's Profit
VAT
Item Cost
Total Unit Cost
sq.m.
hrs.
PhP 2,992.56
Php 6,684.76
PhP 9,677.32
PhP 153,218.68
PhP 162,895.99
12% PhP 19,547.52
8% PhP 13,031.68 PhP 19,547.52
5% PhP 9,773.76 PhP 13,031.68
PhP 205,248.95
Php 1,368.33
sq.m.
hrs.
PhP 399.01
Php 891.30
PhP 1,290.31
Php 6,684.76
PhP 153,218.68
PhP 9,773.76
PhP 399.01
Php 891.30
PhP 21,124.26
PhP 1,344.87
Name of Project:
3. Materials :
Portland Cement (0.48) bags 7.00
Coarse Aggregate (0.050) cu.m. 0.70
Fine Aggregate (0.025) cu.m. 0.35
Form Lumber, Good -4-Uses 4 uses bd.ft. 28.00
75mm Φ G.I. Pipe (3.25) m. 46.00
G.I. Flat Bar, 1 1/2"x1/8" kgs. 70.00
G.I. Bolts w/ nut & washer, 5mmØ pc 42.00
G.I. Bolts w/ nut & washer, 2mmØ pc 168.00
Sign Face, 3mm thick Aluminum Sheet pcs. 28.00
Assorted CWN (1kg/100bdft of Lumber) kgs. 0.02
Miscellaneous(0.3 of materials)
PhP 3,423.14
Php 3,082.81
PhP 6,505.95
Php -
Php -
Php -
35.00 Php 980.00
530.00 Php 24,380.00
Php -
10.00 Php 420.00
11.00 Php 1,848.00
3,750.00 Php 105,000.00
65.00 Php 1.30
Php 397.89
PhP 133,027.19
PhP 139,533.14
12% PhP 16,743.98
8% PhP 11,162.65
5% PhP 8,371.99
PhP 175,811.75 PhP 8,371.99
Php 12,557.98
PhP 3,423.14
Php 3,082.81
PhP 133,027.19
ITEM B-17 TEMPORARY DIVERSION OF WATE
Unit of Measurement = lumpsum Quantity = 1.00
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor :
Construction Foreman 1 230.00 PhP 86.26
Skilled Laborers 2 230.00 PhP 62.25
Laborers 4 230.00 PhP 48.00
PhP -
PhP 462,365.78
PhP 46,236.58 ###
PhP 36,989.26 ###
PhP 27,279.58 ###
PhP 572,871.20
Php 572,871.20
Name of Project:
PhP 124,214.40
Hourly Rate Amount
Php -
PhP 124,214.40
900.00 9,000.00
900.00 9,000.00
900.00 9,000.00
900.00 9,000.00
900.00 9,000.00
900.00 9,000.00
-
5,000.00 25,000.00
-
-
800.00 48,000.00
900.00 9,000.00
-
300.00 1,500.00
PhP 137,500.00
PhP 261,714.40
0% PhP -
8% PhP 20,937.15 PhP -
5% PhP 14,132.58 PhP 20,937.15
PhP 296,784.13 PhP 14,132.58
Php 296,784.13
PhP 124,214.40
Php -
PhP 137,500.00
Name of Project:
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor :
Traffic Enforcer 1 24.00 PhP 86.26
Traffic Aid 2 24.00 PhP 48.00
Direct Cost
Overhead, Contingencies & Maintenance (OCM) 12%
Contractor's Profit (CP) 8%
VAT 5%
Item Cost
Total Unit Cost
Hourly Rate Amount
PhP 4,374.24
Hourly Rate Amount
Php -
PhP 4,374.24
Unit Cost Amount
232.96 2,329.60
2,616.00 5,232.00
325.00 325.00
650.00 650.00
550.00 550.00
100.00 100.00
60.00 60.00
PhP 9,246.60
PhP 13,620.84
PhP 1,634.50 PhP 1,634.50
PhP 1,089.67 PhP 1,089.67
PhP 817.25 PhP 817.25
PhP 17,162.26
PhP 17,162.26
PhP 4,374.24
Php -
PhP 9,246.60
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 29
Skilled Laborers 1 29
Laborers 2 29
3. Materials :
Direct Cost
Overhead, Contingencies & Maintenance (OCM)
Contractor's Profit (CP)
VAT
Item Cost
Total Unit Cost
Hourly Rate Amount
PhP 7,090.79
Hourly Rate Amount
Php 134,761.55
PhP 141,852.34
Unit Cost Amount
PhP 141,852.34
9% PhP 12,766.71 PhP 12,766.71
8% PhP 11,348.19 PhP 11,348.19
12% PhP 19,916.07
PhP 185,883.31
Php 185.88
PhP 7,090.79
Php 134,761.55
PhP 19,916.07
PhP -
D E TAI LE D U N I T P R I C E ANALY S I S
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Driver 1 1680
3. Materials :
No. of
Designation No. of Hours
Person
1. Labor :
3. Materials :
No. of
Designation No. of Days
Person
1. Labor :
Part time Practitioner 1 6
First Aider 1 10
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
3. Materials :
Safety Gloves man-day 7.77
Safety Shoes man-day 2.77
Shafety Helmet man-day 0.25
Name of Project:
No. of
Designation No. of Days
Person
1. Labor :
Construction Foreman 1 1
Skilled 1 1
Laborers 1 1
3. Materials :
1/4'x4'x8' Marine Plywood pcs 2
Good Lumber bd.ft. 74
Tarpaulin (4"x8") sq.ft. 64
CWN (as) kgs 1.00
Sub - Total for 3
Direct Cost
Overhead, Contingencies & Maintenance (OCM)
Contractor's Profit (CP)
VAT
Item Cost
Total Unit Cost
R I C E ANALY S I S
PhP 104,580.00
Units Unit Cost Amount
Php 1,212,801.98
Quantity Unit Cost Amount
PhP -
PhP 1,317,381.98
0% PhP - PhP -
8% PhP 105,390.56 ###
5% PhP 71,138.63
PhP 1,493,911.17
Php 213,415.88
PhP -
Units Unit Cost Amount
Php 405,000.00
Quantity Unit Cost Amount
PhP -
PhP 405,000.00
0% PhP - PhP -
8% PhP 32,400.00 PhP 32,400.00
12% PhP 52,488.00
PhP 489,888.00
Php 489,888.00
1.00
PhP 9,120.48
PhP 9,120.48
PhP 14,070.16
PhP 23,190.64
0% PhP - PhP -
8% PhP 1,855.25 PhP 1,855.25
12% PhP 3,005.51
PhP 28,051.40
Php 28,051.40
day
PhP 1,572.08
No. of Hours Hourly Rate Amount
PhP -
PhP 1,572.08
PhP 104,580.00
Php1,212,801.98
PhP 71,138.63
PhP -
Php 405,000.00
PhP 52,488.00
PhP 9,120.48
PhP 14,070.16
PhP 3,005.51
PhP 1,572.08
PhP 6,410.00
PhP 1,120.68
D E TAI LE D U N I T P R I C E ANALY S I S
Name of Project:
No. of
Designation No. of Hours
Person
1. Labor :
Driver 1 1200
3. Materials :
No. of
Designation No. of Hours
Person
1. Labor :
Autocadd plotter pc 1
Loptop pc 1
GPS with Camera pc 1
3. Materials :
Sub - Total for 3
Direct Cost
Overhead, Contingencies & Maintenance (OCM)
Contractor's Profit (CP)
VAT
Item Cost
Total Unit Cost
Name of Project:
No. of
Designation No. of Days
Person
1. Labor :
Part time Practitioner 1 6
First Aider 1 10
No. of
Name and Capacity No. of Hours
Units
2. Equipment :
Name of Project:
No. of
Designation No. of Days
Person
1. Labor :
Construction Foreman 1 1
Skilled 1 1
Laborers 1 1
3. Materials :
1/4'x4'x8' Marine Plywood pcs 2
Good Lumber bd.ft. 74
Tarpaulin (4"x8") sq.ft. 64
CWN (as) kgs 1.00
PhP 74,700.00
Units Unit Cost Amount
Php 841,374.22
Quantity Unit Cost Amount
PhP -
PhP 916,074.22
0% PhP - PhP -
0% PhP - PhP -
5% PhP 45,803.71
PhP 961,877.93
Php 192,375.59
PhP -
Units Unit Cost Amount
Php 405,000.00
Quantity Unit Cost Amount
PhP -
PhP 405,000.00
0% PhP - PhP -
8% PhP 32,400.00 PhP 32,400.00
5% PhP 21,870.00
PhP 459,270.00
Php 459,270.00
1.00
PhP 7,376.00
PhP 7,376.00
PhP 14,070.16
PhP 21,446.16
0% PhP - PhP -
8% PhP 1,715.69 PhP 1,715.69
5% PhP 1,158.09
PhP 24,319.94
Php 24,319.94
day
PhP 1,317.60
No. of Hours Hourly Rate Amount
PhP -
PhP 1,317.60
PhP 6,410.00
PhP 7,727.60
9% PhP 695.48 PhP 695.48
8% PhP 618.21 PhP 618.21
5% PhP 452.06
PhP 9,493.35
PhP 9,493.35
labor equipment materials
PhP 74,700.00
Php 841,374.22
PhP 45,803.71
PhP -
Php 405,000.00
PhP 21,870.00
PhP 7,376.00
PhP 14,070.16
PhP 1,158.09
PhP 1,317.60
PhP 6,410.00
PhP 452.06
COMPUTATION OF EQUIPMENT RENTAL RATES
(DPWH FORMULA)
PER DO 03 SERIES 2010
HI LUX, 4X2 2.5 J DIESEL M/T, (BRAND NEW)
GIVEN:
Acquisition Cost (AC) =
Economic Life = 7
Capital Recovery Factor (CRF) =
Average Utilization Hours/Year (U) =
= Rfm + FC + LC + VAT
VAT 5% =
Rfo = PHP 956.11 /hr
(BRAND NEW)
PHP 838,000.00
years,based on COA Circular 2003-007
0.240360363
2,000.00 hours/yr
(2 + 0.23478)
0.240360363
0.240360363 ( 2 + 0.023478 )
2,000.00 0.240360363
2.0976783348
/hr
PHP 522.90
PHP 104.58
40.15
PHP 242.95
PHP 910.58
PHP 45.53
PHP 956.11
COMPUTATION OF EQUIPMENT RENTAL RATES
(DPWH FORMULA)
PER DO 03 SERIES 2010
HI LUX, 4X2 2.5 E DIESEL M/T, (BRAND NEW)
GIVEN:
Acquisition Cost (AC) =
Economic Life = 7
Capital Recovery Factor (CRF) =
Average Utilization Hours/Year (U) =
= Rfm + FC + LC + VAT
RAND NEW)
PHP 931,000.00
years,based on COA Circular 2003-007
0.240360363
2,000.00 hours/yr
(2 + 0.23478)
0.240360363
0.240360363 ( 2 + 0.023478 )
2,000.00 0.240360363
2.0976783348
/hr
PHP 522.90
PHP 104.58
40.15
PHP 269.91
PHP 937.54
PHP 46.88
PHP 984.42
UNIT COST DERIVATION OF COARSE & FINE AGGREGATES
A.) Coarse Aggregates
Volume = 801.75 cu.m.
Output of Bulldozer/day
No. of days = 2,004.36 /400
Equipment Cost
1Bulldozer = 1 Bulldozer x P18,392 /day
Hauling
Cycle Time
Ave. Hauling Dist. =
Loading Time =
Unloading Time =
Slack Time =
UNPAVED 18.5 km
18.50 kms x 60 min/hr
Loaded Trip =
25 kms/hr
18.50 kms x 60 min/hr
Unloaded Trip =
35 kms/hr
Utilizing 6 Dumptrucks
# of Days Required = 801.75 = 2.715938
60.00 4.92
Equipment Cost
dumptrucks = 6.00 DT P10,816 /day x
Fine Aggregates
Treat fine aggregates as by product of coarse aggregates (90% of coarse )
Unit Cost of Hauling of coarse and fine aggregates
Production Cost of fine aggregates
Aggregate Tax
Unit Cost of fine Aggregates
FINE AGGREGATES
x 5.00 = P91,960.00
21.5 kms.
3.00 min.
2.00 min.
6.00 min.
= 6.00 mins
= 4.50 min.
= 44.40 mins
= 31.71 min.
= 97.61 min.
=
4.92 trips
= 242.83 /cu.m.
= 309.85 /cu.m.
= 15.00 /cu.m.
= 567.68 /cu.m.
= 242.83 /cu.m.
= 278.87 /cu.m.
= 15.00 /cu.m.
= 536.70 /cu.m.
UNIT COST DERIVATION OF BOULDERS (Class "A")
1 Labor Cost
Breaking,Picking and Stockpiling
Labor Capacity = 1 cu.m./man-day due to multiple handling
No. of Laborers = 50
Total Output/day = 50 cu.m.
No. of days = 183.00 cu.m./ 50 = 3.66 say
2 Equipment Cost:
Loading Time = 6.00
Unloading Time = 2.00
Slack Time = 6.00
UNPAVED ROAD (mountainous) 8.00 km
8.00 kms x 60 min/hr
Loaded Trip = = 32.00
15 kms/hr
8 kms x 60 min/hr
Unloaded Trip = = 19.20
25 kms/hr
0
PAVED( Mountainous) 0 km
UNPAVED( Mountainous) km
0.00 kms x 60 min/hr
Loaded Trip = = 0.00
15 kms/hr
0.00 kms x 60 min/hr
Unloaded Trip = = 0.00
25 kms/hr
Total Cycle Time = 65.20
8 hrs x 60 min/hr =
No. of Trips/day = 7.362
65.2 mins
Utilizing 9 Dumptrucks
183.00 cu.m.
No. of days Required = = 0.27
7.400trips/day x 90 cu.m.
P94,266.16
Unit Cost = =
183.00
4.00 days
= P64,240.00
min.
min.
min.
mins
min.
mins
min.
mins
min.
min.
= P26,282.88
= P3,743.28
P30,026.16
P515.12 /cu.m.
/cu.m.
/cu.m.
ITEM A.1.1(11) - Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for t
Quantity= 0.00 lumpsum
Name and Specification unit Quantity
3. Materials :
Furniture, Fixtures & Appliances ls
DESKTOP COMPUTER set 1
SOFTWARE: Licensed OEM windows 10 Professional 64-bit with downgrade options for
Operating System (with original CD media installer or original recovery CD media with OS In
Activated with microsoft prior to delivery.
Recovery Media Recory disk for OS and all drivers and utilities with original CD media. Burn
provided that it is properly labelled and virus free
Office Software Licensed Microsoft Office (latest version) with Word, Excel, PowerPoint and
CD media installer). Must be Licensed under volume licensing that is perpetu
delivered and installed, and made operational. Must be activated with Microso
UPS:
Power Capacity 1000VA/ 600W; Input Voltage - 230 / Output Voltage -230V
Battery Type Maintenance-free sealed lead-acid baterry with suspended electrolyte (leakpr
Backup Power Minimum of 12 minutes at half load
Alarm Indicators On line, on Baterry , replace baterry, and overload
Outlets 6 Baterry Backups
I/O Ports USB, RJ45, RS 232 (Optional)
Features Automatic Voltage Regulator (AVR) , Data line Protection, Automatic, Autom
Management Interface Built-in or with media installer monitoring tool and diagnostic software acce
Included Power cables, usb cable, and media installer
Warranty 2 years on-site on parts and service, 1 year on baterry
TECHNICAL SPECIFICATION
MISCELLANEOUS:
Brand And Model Must be an international Brand Name with existence of atleast ten (10) years
Model must be in current catalog and not end -of life. Manufacturer's Certifica
All components must be the same brand as the computer (except for the UPS
Components and new. The supplier is not allowed to change or add any componentsto the e
Documentation Complete documentation and user manual - electonic or softcopy.
Included Power cables, VGA cables, patch cord (factory crimped with RJ-45 connecto
Direct Cost
Overhead, Contingencies & Maintenance (OCM)
Contractor's Profit (CP)
VAT
Item Cost
Total Unit Cost
nces for the Field Office for the Engineer
M REQUIRED
U)
CPU)
nd as CPU) with mouse Pad
nal Bay and 5.25" external Bay
Voltage -230V
suspended electrolyte (leakproof); 8 hours recharge t
oad
1 Equipment Cost:
6,346.00 bags
# of days req'd. =
480 min./day DT x 250.00
X 1
354.34 min./trip trip
mins
mins.
mins
mins.
mins
mins.
min.
min.
min.
min.
= 18.74
bags
trip say 18.74
202,691.84
52,662.40
= P40.24
= P40.24
= P288.24
UNIT COST DERIVATION OF RSB ACIGA SECTION
Quantity: = 3,000.00 kgs.
Source = (Manila, PAG-ASA STEEL WORKS INC.)
Loading Time =
Unloading Time =
Manuevering Time =
Total Time =
8 hrs x 60 min/hr =
No. of Trips/day =
1,904.95 mins
3,000.00 kgs. =
No. of days Required =
0.25 trips x 10,000 kgs.
1 Equipment Cost:
1 Cargo Truck = 1 CT x P10,816 /day x 2.00
2 Labor Cost
6 Laborers = 6 Lab. x P312.24 /day x 2.00
Loading Time =
Unloading Time =
Manuevering Time =
Total Time =
8 hrs x 60 min/hr =
No. of Trips/day =
318.15 mins
3,000.00 kgs. =
No. of days Required =
1.51 trips x 10,000 kgs.
1 Equipment Cost:
1 Cargo Truck = 1 CT x P0 /day x 0.33
2 Labor Cost
6 Laborers = 6 Lab. x P312.24 /day x 0.33
= 28.00 min.
laborers
817.60 mins
721.41 min.
16.00 mins
9.60 min.
95.58 mins
63.72 mins.
0.00 mins
0.00 mins.
74.40 mins
mins.
44.64
28.00 min.
28.00 min.
6.00 min.
1,904.95 min.
0.25 trip
days = P21,632.00
days = P3,746.88
= P8.46 ,/kg.
= P41.46 ,/kg.
CIGA SECTION
= 28.00 min.
laborers
16.00 mins
9.60 min.
63.72 mins
47.79 mins.
0.00 mins
0.00 mins.
0.00 mins.
74.40 mins
mins.
44.64
28.00 min.
28.00 min.
6.00 min.
318.15 min.
1.51 trip
days = P0.00
days = P618.24
= P0.21 ,/kg.
= P37.21 ,/kg.
UNIT COST DERIVATION OF RCPC (Class IV)
Cycle Time
Ave. Hauling Dist. = 54.46 km.
Loading Time =
Unloading Time =
Slack Time =
Total Time =
8 hrs x 60 min/hr =
No. of Trips/day =
328.34 mins
No. of days Required
10.00 ln.m. =
910 mm. Diam. =
1.46 trips/day x 14 pcs.
1 Equipment Cost:
1 Cargotruck = P6,808 /day x 0.49 days =
1 Chain Block = P500 /day x 0.49 days =
2 Labor Cost (For Loading & Unloading)
6 Laborers = 6 Lab. x P312.24 /day x 0.49
Cost/ln.m.@ source
910 mm. Diam. = P2,800.00 /pc. CCIS 2nd Qrter 2017
8.00 mins
6.00 mins.
95.58 mins
63.72 mins.
74.40 mins
mins.
44.64
15.00 min.
15.00 min.
6.00 min.
328.34 min.
1.46 trips
P 3,335.92
P 245.00
3,580.92
day = P917.99
P 449.89
P3,249.89 /pc.
UNIT COST DERIVATION OF AGGREGATE SUB-BASE COURSE
Output of Bulldozer/day
No. of days = 1,000.00 /400 =
Equipment Cost
1Bulldozer = 1 Bulldozer x P18,392 /day x
PAVED( Mountainous) 3 km
UNPAVED( Mountainous) km
0.00 kms x 60 min/hr
Loaded Trip = =
Loaded Trip = =
15 kms/hr
0.00 kms x 60 min/hr
Unloaded Trip = =
25 kms/hr
Total Time =
c. Hauling Cost
Utilizing 10 Dumptrucks
700.00 cu.m.
No. of days Required = =
3.300 trips/day x 100 cu.m.
= 1,000.00 cu.m.
= 8.00 hrs.
= 400 cu.m./day
2.50 say 2.5 days
2.50 = P45,980.00
2.10 days
days = P29,114.40
= P20,000.00
P49,114.40
P95,094.40
P135.85 /cu.m.
6.00 min.
2.00 min.
6.00 min.
74.00 mins
44.40 min.
9.00 mins
6.00 min.
0.00 mins
0.00 mins
0.00 min.
147.40 min.
days = P229,299.20
327.57 /cu.m.
P327.57 /cu.m.
P135.85 /cu.m.
P15.00 /cu.m.
P478.42 /cu.m.
UNIT COST DERIVATION OF SELECTED EMBANKMENT
Output of Bulldozer/day
No. of days = 1,250.00 /400
Equipment Cost
1Bulldozer = 1 Bulldozer x P18,392 /day
UNPAVED( Mountainous) 60
60.00 kms x 60 min/hr
Loaded Trip =
15 kms/hr
60.00 kms x 60 min/hr
Unloaded Trip =
25 kms/hr
PAVED( Mountainous) 60
UNPAVED( Mountainous)
0.00 kms x 60 min/hr
Loaded Trip =
Loaded Trip =
15 kms/hr
0.00 kms x 60 min/hr
Unloaded Trip =
25 kms/hr
Total Time
c. Hauling Cost
Utilizing 10 Dumptrucks
1,000.00 cu.m.
No. of days Required =
0.700 trips/day x 100 cu.m.
x 3.10 = P57,015.20
= 6.00 min.
= 2.00 min.
= 6.00 min.
km
= 240.00 mins
= 144.00 min.
km
= 180.00 mins
= 120.00 min.
km
= 0.00 mins
= 0.00 mins
= 0.00 min.
= 698.00 min.
= 1,545.61 /cu.m.
= P1,545.61 /cu.m.
= P113.06 /cu.m.
= P15.00 /cu.m.
= P1,673.67 /cu.m.
ITEM 101(1)19 - Removal of Existing Mobey Bridge (L=24m)
Unit of Measurement = l.s. Quantity = 2,112.00
Output/hour = 0.5 panel/hr Duration = 64 hrs
No. of
Designation No. of Hours
Person
1. Labor :
Construction Foreman 1 64
Skilled Laborers 4 64
Laborers 8 64
Note: Scope of work includes removal of bridge abutments and superstructure, and hauling of
dismantled bailey panels and accessories to the District Office.
Direct Cost
Overhead Contingencies & Maintenance
Contractor's Profit
VAT
Item Cost
Total Unit Cost
Hourly Rate Amount
Php -
PhP 251,096.96
9% PhP 22,598.73 ###
8% PhP 20,087.76 ###
5% PhP 14,689.17 ###
PhP 308,472.61
146.06
104