Professional Documents
Culture Documents
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
#REF!
#REF!
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
No. of Man
Designation No. of Person
days
Daily Rates Amount (Php)
A.1 Labor
a. Safety Practitioner/Officer (Part Time) 1.00 8.0 500.00 4,000.00
b. Health Personnel 1.00 30.0 280.00 8,400.00
Sub-Total for A.1 As Submitted 12,400.00
A.2 Labor
Sub-Total for A.2 As Evaluated
Name and Capacity No. of Units No. of Hours Hourly Rates Amount (Php)
B.1 Equipment
Sub-Total for B.1 As Submitted -
B.2 Equipment
Sub-Total for B.2 As Evaluated
C.1 Total(A.1+B.1) As Submitted 12,400.00
C.2 Total(A.2+B.2) As Evaluated
D.1 Output per hour- As Submitted 1.00
D.2 Output per hour- As Evaluated
E.1 Direct Unit Cost(C.1÷D.1) As Submitted 12,400.00
E.2 Direct Unit Cost(C.2÷D.2) As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
a. Safety Helmet man-day 3.00 0.25 0.75
b. Safety Shoes man-day 3.00 2.77 8.31
c. Safety Vest man-day 3.00 2.22 6.66
d. Working Gloves man-day 3.00 7.67 23.01
e. Rubber Boots man-day 3.00 1.39 4.17
f. Rain Coats (30% of duration) man-day 27.00 0.34 9.18
j. First Aid Kit ( 1 set for the whole duration) LS 1.00 333.33 333.33
Sub-Total for F.1 As Submited 385.41
F.2 Materials
Sub-Total for F.1 As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Sumitted 12,785.41
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contigency & Miscellaneous (OCM) - As Sumitted 0% of G.1 -
H.2 Overhead, Contigency & Miscellaneous (OCM) - As Evaluated 0% of G.2
I.1 Contractor's Profit(CP) - As Sumitted 10% of G.1 1,278.54
I.2 Contractor's Profit(CP) - As Evaluated 10% of G.2
J.1 Value Added Tax (VAT) - As Sumitted 5% of (G.1+H.1+I.1) 703.20
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+H.2+I.2)
K.1 Total Unit Cost - As Sumitted (G.1+H.1+I.1+J.1) 14,767.15
K.2 Total Unit Cost - As Evaluated (G.2+H.2+I.2+J.2)
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Total man-
Designation No. of Person
days
Unit Rate Amount (Php)
A.1 Labor
Sub-Total for A.1 As Submitted -
A.2 Labor
Sub-Total for A.2 As Evaluated
Name and Capacity No. of Units No. of Hours Hourly Rates Amount (Php)
B.1 Equipment
a. Water Truck/Pump (16000 L) 1.0 1.3 2,450.00 3,185.00
b. Cargo Truck (10 T, 270 HP) 1.0 1.3 1,212.00 1,575.60
c. Backhoe (0.80 m³) 1.0 1.3 1,537.00 2,020.67
d. One Bagger Conc. Mixer 1.0 1.3 172.00 223.60
Sub-Total for B.1 As Submitted 7,004.87
B.2 Equipment
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
#REF!
#REF!
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
ROMEO B. FRANCA 0
Engineer II 0
#REF!
#REF!
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
ROMEO B. FRANCA 0
Engineer II 0
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Labor
Installation
a. Construction Foreman 1.0 1.0 85.28 85.28
b. Skilled Laborer 2.0 1.0 61.75 123.50
A.1 c. Unskilled Laborer 4.0 1.0 47.59 190.36
Stripping
a. Construction Foreman 1.0 0.41 85.28 34.96
b. Unskilled Laborer 6.0 0.41 47.59 117.07
Sub-Total for A.1 As Submitted 551.18
Labor
A.2
Sub-Total for A.2 As Evaluated
Name and Capacity No. of Units No. of Hours Hourly Rates Amount (Php)
Equipment
B.1 Minor Tools (10% of Labor Cost) 55.12
Sub-Total for B.1 As Submitted 55.12
Equipment
B.2
Sub-Total for B.2 As Evaluated
C.1 Total(A.1+B.1) As Submitted 606.30
C.2 Total(A.2+B.2) As Evaluated
D.1 Output per hour- As Submitted 3.24
D.2 Output per hour- As Evaluated
E.1 Direct Unit Cost(C.1÷D.1) As Submitted 187.13
E.2 Direct Unit Cost(C.2÷D.2) As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Ordinary Plywood - 3 uses (4''x8'x1/2') pcs 0.347 740.00 85.59
F.1 b. Good Lumber - 3 uses bd ft 7.190 70.00 167.77
c. Assorted common wire nails kg 0.210 75.00 15.75
d. consumables (5% of material cost) 13.46
Sub-Total for F.1 As Submited 282.57
Materials
F.2
Sub-Total for F.1 As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Sumitted 469.70
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contigency & Miscellaneous (OCM) - As Sumitted 15% of G.1 70.45
H.2 Overhead, Contigency & Miscellaneous (OCM) - As Evaluated 15% of G.2
I.1 Contractor's Profit(CP) - As Sumitted 10% of G.1 46.97
I.2 Contractor's Profit(CP) - As Evaluated 10% of G.2
J.1 Value Added Tax (VAT) - As Sumitted 5% of (G.1+H.1+I.1) 29.36
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+H.2+I.2)
K.1 Total Unit Cost - As Sumitted (G.1+H.1+I.1+J.1) 616.48
K.2 Total Unit Cost - As Evaluated (G.2+H.2+I.2+J.2)
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Labor
a. Construction Foreman 1.0 0.33 85.28 28.14
A.1 b. Skilled Laborer 1.0 0.33 61.75 20.38
c. Unskilled Laborer 2.0 0.33 47.59 31.41
Sub-Total for A.1 As Submitted 79.93
Labor
A.2
Sub-Total for A.2 As Evaluated
Name and Capacity No. of Units No. of Hours Hourly Rates Amount (Php)
Equipment
B.1 Minor Tools (10% of Labor Cost) 7.99
Sub-Total for B.1 As Submitted 7.99
Equipment
B.2
Sub-Total for B.2 As Evaluated
C.1 Total(A.1+B.1) As Submitted 87.92
C.2 Total(A.2+B.2) As Evaluated
D.1 Output per hour- As Submitted 1.00
D.2 Output per hour- As Evaluated
E.1 Direct Unit Cost(C.1÷D.1) As Submitted 87.92
E.2 Direct Unit Cost(C.2÷D.2) As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
F.1 a. 25 mm Ø x 6m Galvanized Iron Pipe m. 1.00 197.17 197.17
b. Consumables (5% of Material cost) 9.86
Sub-Total for F.1 As Submited 207.03
Materials
F.2
Sub-Total for F.1 As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Sumitted 294.95
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contigency & Miscellaneous (OCM) - As Sumitted 15% of G.1 44.24
H.2 Overhead, Contigency & Miscellaneous (OCM) - As Evaluated 15% of G.2
I.1 Contractor's Profit(CP) - As Sumitted 10% of G.1 29.49
I.2 Contractor's Profit(CP) - As Evaluated 10% of G.2
J.1 Value Added Tax (VAT) - As Sumitted 5% of (G.1+H.1+I.1) 18.43
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+H.2+I.2)
K.1 Total Unit Cost - As Sumitted (G.1+H.1+I.1+J.1) 387.11
K.2 Total Unit Cost - As Evaluated (G.2+H.2+I.2+J.2)
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Labor
a. Construction Foreman 1.0 0.33 85.28 28.14
A.1 b. Skilled Laborer 1.0 0.33 61.75 20.38
c. Unskilled Laborer 2.0 0.33 47.59 31.41
Sub-Total for A.1 As Submitted 79.93
Labor
A.2
Sub-Total for A.2 As Evaluated
Name and Capacity No. of Units No. of Hours Hourly Rates Amount (Php)
Equipment
B.1 Minor Tools (10% of Labor Cost) 7.99
Sub-Total for B.1 As Submitted 7.99
Equipment
B.2
Sub-Total for B.2 As Evaluated
C.1 Total(A.1+B.1) As Submitted 87.92
C.2 Total(A.2+B.2) As Evaluated
D.1 Output per hour- As Submitted 1.00
D.2 Output per hour- As Evaluated
E.1 Direct Unit Cost(C.1÷D.1) As Submitted 87.92
E.2 Direct Unit Cost(C.2÷D.2) As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
F.1 a. 40 mm Ø x 6m Galvanized Iron Pipe m. 1.00 320.83 320.83
b. Consumables (5% of Material cost) 16.04
Sub-Total for F.1 As Submited 336.87
Materials
F.2
Sub-Total for F.1 As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Sumitted 424.79
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contigency & Miscellaneous (OCM) - As Sumitted 15% of G.1 63.72
H.2 Overhead, Contigency & Miscellaneous (OCM) - As Evaluated 15% of G.2
I.1 Contractor's Profit(CP) - As Sumitted 10% of G.1 42.48
I.2 Contractor's Profit(CP) - As Evaluated 10% of G.2
J.1 Value Added Tax (VAT) - As Sumitted 5% of (G.1+H.1+I.1) 26.55
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+H.2+I.2)
K.1 Total Unit Cost - As Sumitted (G.1+H.1+I.1+J.1) 557.54
K.2 Total Unit Cost - As Evaluated (G.2+H.2+I.2+J.2)
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
A.1 Labor
a. Construction Foreman 1.00 25.00 85.28 2,132.00
b.Skilled Laborer 1.00 25.00 61.75 1,543.75
c. Unskilled Laborer 2.00 25.00 47.59 2,379.50
Sub-Total for A.1 As Submitted 6,055.25
A.2 Labor
Sub-Total for A.2 As Evaluated
Name and Capacity No. of Units No. of Hours Hourly Rates Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 605.53
Sub-Total for B.1 As Submitted 605.53
B.2 Equipment
Sub-Total for B.2 As Evaluated
C.1 Total(A.1+B.1) As Submitted 6,660.78
C.2 Total(A.2+B.2) As Evaluated
D.1 Output per hour- As Submitted 1.00
D.2 Output per hour- As Evaluated
E.1 Direct Unit Cost(C.1÷D.1) As Submitted 6,660.78
E.2 Direct Unit Cost(C.2÷D.2) As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
For 1 Hp Pump
a. 14 mm² THHN Copper Wire, Stranded m 40.00 94.00 3,760.00
b. 8 mm² THHN Copper Wire, Stranded m 50.00 59.25 2,962.50
Sub-Total for F.1 As Submited 6,722.50
F.2 Materials
Prepared By:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
A.1 Labor
a. Construction Foreman 1.00 25.00 85.28 2,132.00
b.Skilled Laborer 1.00 25.00 61.75 1,543.75
c. Unskilled Laborer 2.00 25.00 47.59 2,379.50
Sub-Total for A.1 As Submitted 6,055.25
A.2 Labor
Sub-Total for A.2 As Evaluated
Name and Capacity No. of Units No. of Hours Hourly Rates Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 605.53
Sub-Total for B.1 As Submitted 605.53
B.2 Equipment
Sub-Total for B.2 As Evaluated
C.1 Total(A.1+B.1) As Submitted 6,660.78
C.2 Total(A.2+B.2) As Evaluated
D.1 Output per hour- As Submitted 1.00
D.2 Output per hour- As Evaluated
E.1 Direct Unit Cost(C.1÷D.1) As Submitted 6,660.78
E.2 Direct Unit Cost(C.2÷D.2) As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Pannel Board and Cabinets (Enclosed 60Amps ,2 PST) pc 1.00 1991.00 1,991.00
30 AT,100AF,2P Circuit breaker pc 2.00 1058.00 2,116.00
50 AT,100AF,2P Circuit breaker pc 1.00 1177.25 1,177.25
30 AT Circuit breaker built in with Nema 3R Enclosure set 1.00 2010.00 2,010.00
Sub-Total for F.1 As Submited 7,294.25
F.2 Materials
Sub-Total for F.1 As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Sumitted 13,955.03
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated
H.1 Overhead, Contigency & Miscellaneous (OCM) - As Sumitted 15% of G.1 2,093.25
H.2 Overhead, Contigency & Miscellaneous (OCM) - As Evaluated 15% of G.2
I.1 Contractor's Profit(CP) - As Sumitted 10% of G.1 1,395.50
I.2 Contractor's Profit(CP) - As Evaluated 10% of G.2
J.1 Value Added Tax (VAT) - As Sumitted 5% of (G.1+H.1+I.1) 872.19
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+H.2+I.2)
K.1 Total Unit Cost - As Sumitted (G.1+H.1+I.1+J.1) 18,315.97
K.2 Total Unit Cost - As Evaluated (G.2+H.2+I.2+J.2)
Prepared By:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
A.1 Labor
a. Construction Foreman 1.00 64.00 85.28 5,457.92
b. Skilled Laborer 3.00 64.00 61.75 11,856.00
c. Unskilled Laborer 3.00 64.00 47.59 9,137.28
Sub-Total for A.1 As Submitted 26,451.20
A.2 Labor
Sub-Total for A.2 As Evaluated
Name and Capacity No. of Units No. of Hours Hourly Rates Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 2,645.12
Sub-Total for B.1 As Submitted 2,645.12
B.2 Equipment
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
#REF!
#REF!
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
ROMEO B. FRANCA 0
Engineer II 0
#REF!
#REF!
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Installation/Removal of Formworks
a. Skilled Laborer 4.00 1.00 61.34 245.36
b. Unskilled Laborer 8.00 1.00 47.3 378.40
Sub-Total for A.1 As Submitted 1,332.24
A.2 Labor
ROMEO B. FRANCA 0
Engineer II 0
#REF!
#REF!
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
Construction of Water System Level 2, Salvacion, San Ramon, Alongong, Libon, Albay
I. Salvacion, Libon, Albay
Detailed Unit Price Analysis (DUPA) FORM POW-2015-01D-00
Prepared by:
ROMEO B. FRANCA
Engineer II
Planning and Design Section
DERIVATION OF HAULING COST FOR GRAVEL MATERIALS
Project : ###
Location : Guinobatan, Albay
A. Hauling from Source to Project Site:
ROMEO B. FRANCA
Engineer II
Republic of the Philippines
Department of Public Works and Highways
OFFICE OF THE DISTRICT ENGINEER
Albay 3rd District Engineering Office
Paulog, Ligao City, Albay
Name of Project: Concreting of Pinaric-Agpay Road with Spillway, Guinobatan, Albay - Phase II
Formula:
Where:
C.D. = 130.90 say 131 CD
Dh = Reference Duration (Higher)
Dl = Reference Duration (Lower) Plus:
7 For PCCP Concrete Curing, Sealing of transverse & longitudinal joints and Shouldering, and other
Ah = Reference Amount (Higher) subsidiary item, generated value were taken from D.O.# 44 series of 2012 & D.O. 141 sereis of 2014 by
Al = Reference Amount (Lower) interpolation computation application.
Ap = Appropriation, amount to be programmed Total Cal. 138 CD
Days
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
PREPARED BY:
RICHARD A. MOIT
Engineer II
CONPUTATION OF THE ESTIMATED PROJECT DURATION (BAR CHART)
#REF!
ITEM NO. DESCRIPTION UNIT QTY. UNIT COST AMOUNT % WT. 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
ITEM NO. DESCRIPTION UNIT QTY. UNIT COST AMOUNT % WT. 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF!
PREPARED BY:
RICHARD A. MOIT
Engineer II
CONPUTATION OF THE ESTIMATED PROJECT DURATION (BAR CHART)
#REF!
ITEM NO. DESCRIPTION UNIT QTY. UNIT COST AMOUNT % WT. 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF!
DESCRIPTION
RICHARD A. MOIT
Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 1052(29) Micro Piles in Drilled Holes, 0.2m Ø (Ordinary Soil Condition)
Unit of Measurement : m
Output per hour : 3.00
A. Labor
Installation
a. Construction Foreman 1 1.00 100.36 100.36
b. Skilled Laborer 5 1.00 73.01 365.05
c. Unskilled Laborer 6 1.00 56.27 337.62
Fabrication of Cage Bar
a. Construction Foreman 4 0.25 100.36 100.36
b. Unskilled Laborer 8 0.25 56.27 112.54
Sub - Total for A 1,015.93
Hourly Rental
Name and Capacity Quantity No. of Day/s Amount (PhP)
Rate
B. Equipment
F. Materials
A. Labor
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Prepared by:
CLARO L. MAGNAYE
Architect II
Planning & Design Section
DETAILED UNIT PRICE ANALYSIS (DUPA)
A. Labor
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B. Equipment
F. Materials
Prepared by:
CLARO L. MAGNAYE
Architect II
Planning & Design Section