The document provides a detailed unit price analysis for installing a hydraulic filter using a geotextile tube. It includes calculations for labor costs, equipment costs, material costs, overhead costs, profit, and taxes to determine a total unit cost of PHP 15,908.63 to install 10 linear meters of the geotextile tube filter. Labor, equipment, and material costs make up the direct unit cost, while overhead, profit, and taxes are added to determine the full unit price.
The document provides a detailed unit price analysis for installing a hydraulic filter using a geotextile tube. It includes calculations for labor costs, equipment costs, material costs, overhead costs, profit, and taxes to determine a total unit cost of PHP 15,908.63 to install 10 linear meters of the geotextile tube filter. Labor, equipment, and material costs make up the direct unit cost, while overhead, profit, and taxes are added to determine the full unit price.
The document provides a detailed unit price analysis for installing a hydraulic filter using a geotextile tube. It includes calculations for labor costs, equipment costs, material costs, overhead costs, profit, and taxes to determine a total unit cost of PHP 15,908.63 to install 10 linear meters of the geotextile tube filter. Labor, equipment, and material costs make up the direct unit cost, while overhead, profit, and taxes are added to determine the full unit price.
ITEM/DESCRIPTION : 715.7.6 A HYDRAULIC FILTER (GEOTEXTILE TUBE)
UNIT OF MEASUREMENT : Lm. QUANTITY: OUTPUT PER HOUR : 10.00 lm/hr
Designation No. of Person No.of Hours Hourly Rate (PhP) Amount
A. Labor
a. Construction Foreman 1 1.00 108.99 108.99
b. Skilled Laborer 2 1.00 78.85 157.70 c. Unskilled Laborer 8 1.00 60.82 486.56
Sub-total for A: 753.25
Name and Capacity No. of Units No.of Hours Hourly Rate (PhP) Total Cost (PhP)
B. Equipment
a. Boom Truck (2 - 5mt) 1.00 1.00 1,017.90 1,017.90
b. Backhoe (0.80 m^3) 1.00 1.00 1,537.00 1,537.00 c. Sand pump @ 54 cum/hr output sand capacity 1.00 1.00 15,000.00 15,000.00 d. 6" dia pipe outlet 1.00 1.00 6,099.00 6,099.00 e. Crane on Barge (60-ton capacity) 1.00 1.00 3,843.00 3,843.00 Minor Tools (5% of Labor) 37.66 Sub-total for B: 27,534.56 C. Total (A + B) 28,287.81 D. Output per Hour 10.00 Lm. E. Direct Unit Cost (C/D) 2,828.78
Name and Specification Unit Quantity Unit Cost Amount
F. Materials
a. Geotextile Tube sqm 10.12 370.80 3,752.50
Tensile Strength: 75KN/m x 75 KN/m Circumference = 9.2 m; Length =61.40 m Filled Height = 1.7m; Filled W = 7.0 m b. Dredge sand filling cum 5.40 1,200.00 6,480.00 Volume = 5.4 cum per length of geotextile tube
Sub-total for F: 10,232.50
G. Direct Unit Cost (E + F) 13,061.28 H. Overhead, Contingencies & Miscellaneous (OCM) 8% of G 1,044.90 I. Contractor's Profit (CP) 8% of G 1,044.90 J. Value Added Tax (VAT) 5% of (G + H + I) 757.55 K. Total Unit Cost (G + H + I + J) 15,908.63