The document provides costing details for various road construction and maintenance items. It includes costs for labor, equipment, materials and calculates the total cost per unit of each item. Labor costs include hourly rates for construction foremen, skilled laborers and laborers. Equipment costs include hourly rates for asphalt pavers, rollers, trucks and other machinery. Material costs are calculated based on quantities required and unit costs. The total cost per unit for each item is broken down into direct costs, overhead costs, contractor profit and taxes.
The document provides costing details for various road construction and maintenance items. It includes costs for labor, equipment, materials and calculates the total cost per unit of each item. Labor costs include hourly rates for construction foremen, skilled laborers and laborers. Equipment costs include hourly rates for asphalt pavers, rollers, trucks and other machinery. Material costs are calculated based on quantities required and unit costs. The total cost per unit for each item is broken down into direct costs, overhead costs, contractor profit and taxes.
The document provides costing details for various road construction and maintenance items. It includes costs for labor, equipment, materials and calculates the total cost per unit of each item. Labor costs include hourly rates for construction foremen, skilled laborers and laborers. Equipment costs include hourly rates for asphalt pavers, rollers, trucks and other machinery. Material costs are calculated based on quantities required and unit costs. The total cost per unit for each item is broken down into direct costs, overhead costs, contractor profit and taxes.
Designation No. of Person No. of Hours Hourly Rate Amount
Labor
a. Construction Foreman 1 1 105.00 105.00
b. Skilled Laborer 3 1 75.00 225.00 A. c. Laborer 8 1 60.00 480.00
Sub - Total for A 810.00
Name and Capacity No. of Units No. of Hours Hourly Rate Amount Equipment
a. Asphalt Paver (80hp), NF220BIIVDM 1 1 1,850.00 1,850.00
b. Pneumatic Tire Roller (10 m.t.) 1 1 547.00 547.00 c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,650.00 1,650.00 B. d. Water Truck/Pump (16,000 L) 1 1 2,300.00 2,300.00 Minor Tools -
Sub - Total for B 6,347.00
C. Total (A+B) 7,157.00 D. Output Per Hour 171.30 E. Direct Unit Cost (C/D) 41.78 Name and Specification Unit Quantity Unit Cost Amount Materials
a. Bituminous Concrete Surface Course m.t. 0.123 8,950.00 1,100.85
thickness = 50mm (w/ 5% wastage)
F.
Sub - Total for F 1,100.85
G. Direct Unit Cost (E+F) 1,142.63 H. Overhead, Contingencies, & Miscellaneous (OCM) (15% of G) 171.39 I. Contractor's Profit (CP) (10% of G) 114.26 J. Value Added Tax ( VAT) (5% of G+H+I) 71.41 K. Total Cost (G+H+I+J) 1,499.69
Prepared by: Prepared by:
HENRY B. ADECER JR. KARLO MARKO L. NARIO
Contractor's Project Engineer DPWH's Junior Project Engineer Item No./Description : 302(2) Emulsified Asphalt Unit of Measurement : sq.m Output per hour : 601.32
Designation No. of Person No. of Hours Hourly Rate Amount
Labor
a. Construction Foreman 1 1 105.00 105.00
b. Laborer 3 1 60.00 180.00 A.
Sub - Total for A 285.00
Name and Capacity No. of Units No. of Hours Hourly Rate Amount Equipment
C. Total (A+B) 1,397.00 D. Output Per Hour 601.32 E. Direct Unit Cost (C/D) 2.32 Name and Specification Unit Quantity Unit Cost Amount Materials
a. Emulsified Asphalt SS-1 m.t. 0.00053 70,000.00 37.10
(w/ 5% Wastage)
F.
Sub - Total for F 37.10
G. Direct Unit Cost (E+F) 39.42 H. Overhead, Contingencies, & Miscellaneous (OCM) (15% of G) 5.91 I. Contractor's Profit (CP) (10% of G) 3.94 J. Value Added Tax ( VAT) (5% of G+H+I) 2.46 K. Total Cost (G+H+I+J) 51.73
Prepared by: Prepared by:
HENRY B. ADECER JR. KARLO MARKO L. NARIO
Contractor's Project Engineer DPWH's Junior Project Engineer Item No./Description : 612(1) Reflectorized Thermoplastic Pavement Markings White Unit of Measurement : sq.m Output per hour : 25.00
Designation No. of Person No. of Hours Hourly Rate Amount
Labor
a. Construction Foreman 1 1 105.00 105.00
b. Skilled Laborer 1 1 75.00 75.00 A. c. Laborer 3 1 60.00 180.00
Sub - Total for A 360.00
Name and Capacity No. of Units No. of Hours Hourly Rate Amount Equipment
a. Cargo Truck/Delivery Truck (5T) 1 1 708.00 708.00
b. Applicator Machine 1 1 90.00 90.00 c. Kneading Machine 1 1 185.00 185.00 B. Minor Tools 15.00
Sub - Total for B 998.00
C. Total (A+B) 1,358.00 D. Output Per Hour 25.00 E. Direct Unit Cost (C/D) 54.32 Name and Specification Unit Quantity Unit Cost Amount Materials
a. Thermoplastic Paint (White) bag 0.325 1,550.00 503.75
b. Glass Beads bag 0.033 890.00 29.37 c. Primer liter 0.121 180.00 21.78 d. LPG (50 kgs.) cyl. 0.004 3,900.00 15.60 e. LPG (12 kgs.) cyl. 0.002 920.00 1.84 f. Calsumine kg. 0.125 3.00 0.38 F.
Sub - Total for F 572.72
G. Direct Unit Cost (E+F) 627.04 H. Overhead, Contingencies, & Miscellaneous (OCM) (15% of G) 94.06 I. Contractor's Profit (CP) (10% of G) 62.70 J. Value Added Tax ( VAT) (5% of G+H+I) 39.19 K. Total Cost (G+H+I+J) 822.99