Item No.

: 311
Name of Work Item : PCC Pavement - 300 mm thick
Unit of Measurement : sq.m.

oph opd days


Quantity 49,069.00 53.67 8 429.36 114.28

No. of
Designation Days Daily Rate Amount
Person
1. Labor

a. Construction Foreman 1 90.00 600.00 54,000.00


b. Skilled Laborers 4 90.00 500.00 180,000.00
c. Laborer 12 90.00 400.00 432,000.00

Sub - Total for 1 666,000.00

Name and Capacity No. of Units No. of days Daily Rate Amount
2. Equipment

a. Transit Mixer ( 5 cu.m.) 4 90.00 10,500.00 3,780,000.00


b. Concrete Vibrator 2 90.00 1,200.00 216,000.00
c. Batching Plant (30 cu.m.) 1 90.00 9,000.00 810,000.00
d. Payloader (1.50 cu.m.), LX80-2C 1 90.00 14,000.00 1,260,000.00
e. Concrete Screeder (5.5 Hp) 1 90.00 4,500.00 405,000.00
f. Water Truck 1 90.00 12,000.00 1,080,000.00
g. Concrete Saw, Blade ø 14" (7.5 hp) 1 90.00 1,400.00 126,000.00
h. Bar Cutter, Single Phase 1 9.00 2,000.00 18,000.00
Minor Tools (5% of Labor) 33,300.00

Sub - Total for 2 7,728,300.00


Name and Specification Unit Quantity Unit Cost Amount
3. Materials

a. Reinforcing Steel Bar kg. 26,987.95 43.00 1,160,481.85


b. Curing Compound lit. 14,230.01 75.00 1,067,250.75
c. Asphalt Sealant lit. 8,832.42 59.00 521,112.78
d. Steel Forms (Rental) l.m. 22,571.74 100.00 2,257,174.00
e. Sand cu.m. 8,096.39 500.00 4,048,195.00
f. Gravel cu.m. 14,720.70 600.00 8,832,420.00
g. Cement bag 176,648.40 244.00 43,102,209.60
h. Concrete Saw (diamond blade 14") pc. 7.00 5,000.00 35,000.00
i. Pipe Sleeve, 2" dia. l.m. 434.00 110.00 47,740.00
j. Grease/Tar lit. 434.00 240.00 104,160.00

Sub - Total for 3 61,175,743.98


Direct Unit Cost 1,417.80
OCM/CP 0.08 113.42
Vat 0.12 183.75
Total Unit Cost 1,714.97