You are on page 1of 66

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(1) Gravel Surface Course (Uncrushed)


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D) 95.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Uncrushed Aggregate Surface Course cu.m. 1.15 700.00 805.00


(w/ 15% Shrinkage Factor)

Sub - Total for F 805.00


G. Direct Unit Cost (E + F) 900.58
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 81.05
I. Contractor's Profit (CP) 8% of G 72.05
J. Value Added Tax (VAT) 5% of (G + H + I) 52.68
K. Total Unit Cost (G + H + I + J) 1,106.36

60
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 300(2) Crushed Aggregate Surface Course


Unit of Measurement : cu.m
Output per hour : 50.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 2 1.00 38.97 77.94

Sub - Total for A 147.36


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 4,631.50


C. Total (A + B) 4,778.86
D. Output per hour = 50.00 cu.m.
E. Direct Unit Cost (C ÷ D) 95.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Crushed Aggregate Surface Course cu.m. 1.15 750.00 862.50


(w/ 15% Shrinkage Factor)

Sub - Total for F 862.50


G. Direct Unit Cost (E + F) 958.08
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.23
I. Contractor's Profit (CP) 8% of G 76.65
J. Value Added Tax (VAT) 5% of (G + H + I) 56.05
K. Total Unit Cost (G + H + I + J) 1,177.00

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(1) Bituminous Prime Coat (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC 70 Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,491.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,184.21
I. Contractor's Profit (CP) 8% of G 3,719.30
J. Value Added Tax (VAT) 5% of (G + H + I) 2,719.74
K. Total Unit Cost (G + H + I + J) 57,114.48

62
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 301(2) Bituminous Prime Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70
I. Contractor's Profit (CP) 8% of G 3,826.40
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05
K. Total Unit Cost (G + H + I + J) 58,759.13

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(1) Bituminous Tack Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70
I. Contractor's Profit (CP) 8% of G 3,826.40
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05
K. Total Unit Cost (G + H + I + J) 58,759.13

82
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 302(2) Bituminous Tack Coat (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,376.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,533.86
I. Contractor's Profit (CP) 8% of G 4,030.10
J. Value Added Tax (VAT) 5% of (G + H + I) 2,947.01
K. Total Unit Cost (G + H + I + J) 61,887.20

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(1) Bituminous Seal Coat (Cover Aggregate)


Unit of Measurement : m.t.
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 20 1.00 38.97 779.40

Sub - Total for A 848.82


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00


b. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 2,264.50


C. Total (A + B) 3,113.32
D. Output per hour = 16.00 m.t.
E. Direct Unit Cost (C ÷ D) 194.58
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Cover Aggregate m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Note: 1.60 m.t./cu.m.


using unit wt. of 1,600 kg./m³

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 661.77
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 59.56
I. Contractor's Profit (CP) 8% of G 52.94
J. Value Added Tax (VAT) 5% of (G + H + I) 38.71
K. Total Unit Cost (G + H + I + J) 812.98

102
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(2) Bituminous Seal Coat (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% Wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,491.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,184.21
I. Contractor's Profit (CP) 8% of G 3,719.30
J. Value Added Tax (VAT) 5% of (G + H + I) 2,719.74
K. Total Unit Cost (G + H + I + J) 57,114.48

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(3) Bituminous Seal Coat (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70
I. Contractor's Profit (CP) 8% of G 3,826.40
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05
K. Total Unit Cost (G + H + I + J) 58,759.13

122
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 303(4) Bituminous Seal Coat (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00 53,313.75


(w/ 5% Wastage)

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,489.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,174.10
I. Contractor's Profit (CP) 8% of G 4,599.20
J. Value Added Tax (VAT) 5% of (G + H + I) 3,363.16
K. Total Unit Cost (G + H + I + J) 70,626.44

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(1) Bituminous Surface Treatment (Aggregate Grading)


Unit of Measurement : m.t.
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 20 1.00 38.97 779.40

Sub - Total for A 848.82


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00


c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 2,458.50


C. Total (A + B) 3,307.32
D. Output per hour = 16.00 m.t.
E. Direct Unit Cost (C ÷ D) 206.71
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregates m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 673.90
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.65
I. Contractor's Profit (CP) 8% of G 53.91
J. Value Added Tax (VAT) 5% of (G + H + I) 39.42
K. Total Unit Cost (G + H + I + J) 827.88

142
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(2) Bituminous Surface Treatment (Asphalt Cement Penetration Grade 120-150)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement Penetration Grade 120-150 m.t. 1.05 50,775.00 53,313.75


(w/ 5% Wastage)

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,489.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,174.10
I. Contractor's Profit (CP) 8% of G 4,599.20
J. Value Added Tax (VAT) 5% of (G + H + I) 3,363.16
K. Total Unit Cost (G + H + I + J) 70,626.44

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(3) Bituminous Surface Treatment (MC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00


(w/ 5% Wastage)

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 46,491.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,184.21
I. Contractor's Profit (CP) 8% of G 3,719.30
J. Value Added Tax (VAT) 5% of (G + H + I) 2,719.74
K. Total Unit Cost (G + H + I + J) 57,114.48

162
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(4) Bituminous Surface Treatment (RC Cut-back Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70
I. Contractor's Profit (CP) 8% of G 3,826.40
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05
K. Total Unit Cost (G + H + I + J) 58,759.13

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 304(5) Bituminous Surface Treatment (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,376.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,533.86
I. Contractor's Profit (CP) 8% of G 4,030.10
J. Value Added Tax (VAT) 5% of (G + H + I) 2,947.01
K. Total Unit Cost (G + H + I + J) 61,887.20

182
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(1) Bituminous Penetration Macadam Pavement (Aggregates)


Unit of Measurement : m.t.
Output per hour : 16.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 20 1.00 38.97 779.40

Sub - Total for A 848.82


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1,846.00 1,846.00


c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B 2,458.50


C. Total (A + B) 3,307.32
D. Output per hour = 16.00 m.t.
E. Direct Unit Cost (C ÷ D) 206.71
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Aggregates m.t. 1.15 406.25 467.19


(w/ 15% Shrinkage Factor)

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 673.90
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.65
I. Contractor's Profit (CP) 8% of G 53.91
J. Value Added Tax (VAT) 5% of (G + H + I) 39.42
K. Total Unit Cost (G + H + I + J) 827.88

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(2) Bituminous Penetration Macadam Pavement (Asphalt Cement)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (w/ 5% Wastage) m.t. 1.05 50,775.00 53,313.75

Sub - Total for F 53,313.75


G. Direct Unit Cost (E + F) 57,489.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 5,174.10
I. Contractor's Profit (CP) 8% of G 4,599.20
J. Value Added Tax (VAT) 5% of (G + H + I) 3,363.16
K. Total Unit Cost (G + H + I + J) 70,626.44

202
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(3) Bituminous Penetration Macadam Pavement (RC Cut-back Asphalt)
Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. RC 70 Cut-back Asphalt m.t. 1.05 41,575.00 43,653.75


(w/ 5% Wastage)

Sub - Total for F 43,653.75


G. Direct Unit Cost (E + F) 47,829.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,304.70
I. Contractor's Profit (CP) 8% of G 3,826.40
J. Value Added Tax (VAT) 5% of (G + H + I) 2,798.05
K. Total Unit Cost (G + H + I + J) 58,759.13

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 305(4) Bituminous Penetration Macadam Pavement (Emulsified Asphalt)


Unit of Measurement : m.t.
Output per hour : 0.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 186.33


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00


b. Power Broom (20 m. wide) 1 1.00 130.54 130.54

Sub - Total for B 1,066.54


C. Total (A + B) 1,252.87
D. Output per hour = 0.30 m.t.
E. Direct Unit Cost (C ÷ D) 4,176.23
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Emulsified Asphalt SS-1 m.t. 1.05 44,000.00 46,200.00


(w/ 5% wastage)

Sub - Total for F 46,200.00


G. Direct Unit Cost (E + F) 50,376.23
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 4,533.86
I. Contractor's Profit (CP) 8% of G 4,030.10
J. Value Added Tax (VAT) 5% of (G + H + I) 2,947.01
K. Total Unit Cost (G + H + I + J) 61,887.20

222
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(a) Bituminous Road Mix Surface Course


Unit of Measurement : m.t.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 236.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader w/ Scarifier (140 hp), G710A 1 1.00 2,824.90 2,824.90
b. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
d. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00
e. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50
Minor Tools (10% of Labor Cost) 23.65

Sub - Total for B 6,610.05


C. Total (A + B) 6,846.56
D. Output per hour = 12.00 m.t.
E. Direct Unit Cost (C ÷ D) 570.55
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Crushed Gravel m.t. 1.15 406.25 467.19


b. MC Cut-back Asphalt (7%) m.t. 0.07 40,300.00 2,821.00
c. Hydrated Lime (0.75%) bag 0.30 180.00 54.00

0.0575(2.335)(1.05) = 0.141
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F 3,342.19


G. Direct Unit Cost (E + F) 3,912.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 352.15
I. Contractor's Profit (CP) 8% of G 313.02
J. Value Added Tax (VAT) 5% of (G + H + I) 228.89
K. Total Unit Cost (G + H + I + J) 4,806.79

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(b) Bituminous Road Mix Surface Course


Unit of Measurement : m.t.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 236.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader w/ Scarifier (140 hp), G710A 1 1.00 2,824.90 2,824.90
b. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
d. Asphalt Distributor, 10 ft. wide (5 ton) 1 1.00 936.00 936.00
e. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50
Minor Tools (10% of Labor Cost) 23.65

Sub - Total for B 6,610.05


C. Total (A + B) 6,846.56
D. Output per hour = 12.00 m.t.
E. Direct Unit Cost (C ÷ D) 570.55
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Crushed Gravel m.t. 1.15 406.25 467.19


b. Emulsified Asphalt (10%) m.t. 0.10 44,000.00 4,400.00
c. Hydrated Lime (0.75%) bag 0.30 180.00 54.00

0.08(2.335)(1.05) = 0.196
0.0075(35.29) = 0.26, say 0.30

Sub - Total for F 4,921.19


G. Direct Unit Cost (E + F) 5,491.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 494.26
I. Contractor's Profit (CP) 8% of G 439.34
J. Value Added Tax (VAT) 5% of (G + H + I) 321.27
K. Total Unit Cost (G + H + I + J) 6,746.60

242
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(1) Aggregates for Bituminous Road Mix Surface Course
Unit of Measurement : m.t.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 236.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Motorized Road Grader w/ Scarifier (140 hp), G710A 1 1.00 2,824.90 2,824.90
b. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50
Minor Tools (10% of Labor Cost) 23.65

Sub - Total for B 5,674.05


C. Total (A + B) 5,910.56
D. Output per hour = 12.00 m.t.
E. Direct Unit Cost (C ÷ D) 492.55
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Crushed Gravel m.t. 1.15 406.25 467.19

Sub - Total for F 467.19


G. Direct Unit Cost (E + F) 959.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 86.38
I. Contractor's Profit (CP) 8% of G 76.78
J. Value Added Tax (VAT) 5% of (G + H + I) 56.14
K. Total Unit Cost (G + H + I + J) 1,179.03

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 306(2) Bituminous Material for Bituminous Road Mix Surface Course
Unit of Measurement : m.t.
Output per hour : 1.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 1 1.00 50.18 50.18
c. Unskilled Labor 3 1.00 38.97 116.91

Sub - Total for A 236.51


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1.00 936.00 936.00

Sub - Total for B 936.00


C. Total (A + B) 1,172.51
D. Output per hour = 1.00 m.t.
E. Direct Unit Cost (C ÷ D) 1,172.51
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC Cut-back Asphalt m.t. 1.05 40,300.00 42,315.00

Sub - Total for F 42,315.00


G. Direct Unit Cost (E + F) 43,487.51
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 3,913.88
I. Contractor's Profit (CP) 8% of G 3,479.00
J. Value Added Tax (VAT) 5% of (G + H + I) 2,544.02
K. Total Unit Cost (G + H + I + J) 53,424.41

262
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 307 Bituminous Plant Mix Surface Course-General (50mm thk.)
Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


C. Total (A + B) 15,995.72
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 93.38
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Material (8%) m.t 0.00981 44,000.00 431.64


b. Aggregates, Sand (79%) cu.m. 0.041 650.00 26.65
c. Aggregates, 3/8 (19%) cu.m. 0.010 650.00 6.50
d. Mineral Filler (7%) bag 0.130 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 776.32


G. Direct Unit Cost (E + F) 869.69
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 78.27
I. Contractor's Profit (CP) 8% of G 69.58
J. Value Added Tax (VAT) 5% of (G + H + I) 50.88
K. Total Unit Cost (G + H + I + J) 1,068.42

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(a) Cold Asphalt Plant Mix (50mm thk.)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


C. Total (A + B) 15,995.72
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 93.38
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Emulsified Asphalt (10%) m.t 0.01226 44,000.00 539.44


b. Aggregates, Sand (79%) cu.m. 0.041 650.00 26.65
c. Aggregates, 3/8 (19%) cu.m. 0.01 650.00 6.50
d. Mineral Filler (7%) bag 0.13 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 884.12


G. Direct Unit Cost (E + F) 977.49
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 87.97
I. Contractor's Profit (CP) 8% of G 78.20
J. Value Added Tax (VAT) 5% of (G + H + I) 57.18
K. Total Unit Cost (G + H + I + J) 1,200.85

282
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 308(b) Cold Asphalt Plant Mix (50mm thk.)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


C. Total (A + B) 15,995.72
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 93.38
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC - 70 Cut-back Asphalt (7%) m.t 0.00858 40,300.00 345.77


b. Aggregates, Sand (79%) cu.m. 0.0488 650.00 31.72
c. Aggregates, 3/8 (19%) cu.m. 0.01 650.00 6.50
d. Mineral Filler (7%) bag 0.13 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 695.52


G. Direct Unit Cost (E + F) 788.90
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 71.00
I. Contractor's Profit (CP) 8% of G 63.11
J. Value Added Tax (VAT) 5% of (G + H + I) 46.15
K. Total Unit Cost (G + H + I + J) 969.16

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 309 Bituminous Plant Mix (Stockpile Maintenance Mixture)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Dump Truck (12 cu. yd) 2 1.00 1,420.00 2,840.00


b. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
c. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 11,367.82


C. Total (A + B) 11,949.72
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 69.76
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. MC - 70 Cut-back Asphalt (10%) m.t 0.01226 40,300.00 494.08


b. Aggregates, Sand (79%) cu.m. 0.041 650.00 26.65
c. Aggregates, 3/8 (19%) cu.m. 0.01 650.00 6.50
d. Mineral Filler (7%) bag 0.13 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 838.75


G. Direct Unit Cost (E + F) 908.51
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 81.77
I. Contractor's Profit (CP) 8% of G 72.68
J. Value Added Tax (VAT) 5% of (G + H + I) 53.15
K. Total Unit Cost (G + H + I + J) 1,116.11

302
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.1) Bituminous Concrete Surface Course (30mm thk.)


Unit of Measurement : sq.m.
Output per hour : 285.51

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 6,554.19


C. Total (A + B) 7,136.09
D. Output per hour = 285.51 sq.m.
E. Direct Unit Cost (C ÷ D) 24.99
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.074 4,500.00 333.00


thickness = 30mm (w/ 5% wastage)

Sub - Total for F 333.00


G. Direct Unit Cost (E + F) 357.99
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 32.22
I. Contractor's Profit (CP) 8% of G 28.64
J. Value Added Tax (VAT) 5% of (G + H + I) 20.94
K. Total Unit Cost (G + H + I + J) 439.80

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.2) Bituminous Concrete Surface Course (40mm thk.)


Unit of Measurement : sq.m.
Output per hour : 214.13

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
Minor Tools (10% of Labor Cost ) 58.19

Sub - Total for B 6,554.19


C. Total (A + B) 7,136.09
D. Output per hour = 214.13 sq.m.
E. Direct Unit Cost (C ÷ D) 33.33
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.098 4,500.00 441.00


thickness = 40mm (w/ 5% wastage)

Sub - Total for F 441.00


G. Direct Unit Cost (E + F) 474.33
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 42.69
I. Contractor's Profit (CP) 8% of G 37.95
J. Value Added Tax (VAT) 5% of (G + H + I) 27.75
K. Total Unit Cost (G + H + I + J) 582.71

322
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(a.3) Bituminous Concrete Surface Course (50mm thk.)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76

Sub - Total for A 581.90


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
c. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 6,554.19


C. Total (A + B) 7,136.09
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 41.66
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Bituminous Concrete Surface Course m.t. 0.123 4,500.00 553.50


thickness = 50mm (w/ 5% wastage)

Sub - Total for F 553.50


G. Direct Unit Cost (E + F) 595.16
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 53.56
I. Contractor's Profit (CP) 8% of G 47.61
J. Value Added Tax (VAT) 5% of (G + H + I) 34.82
K. Total Unit Cost (G + H + I + J) 731.15

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.1) Bituminous Concrete Surface Course (30mm thk.)


Unit of Measurement : sq.m.
Output per hour : 285.51

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 512.48
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 51.25

Sub - Total for B 15,406.88


C. Total (A + B) 15,919.36
D. Output per hour = 285.51 sq.m.
E. Direct Unit Cost (C ÷ D) 55.76
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00588 40,300.00 236.96


b. Aggregates, Sand (79%) cu.m. 0.025 650.00 16.25
c. Aggregates, 3/8 (19%) cu.m. 0.006 650.00 3.90
d. Mineral Filler (7%) bag 0.078 240.56 18.76
e. Diesel L 0.699 240.56 168.15

Sub - Total for F 444.03


G. Direct Unit Cost (E + F) 499.79
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 44.98
I. Contractor's Profit (CP) 8% of G 39.98
J. Value Added Tax (VAT) 5% of (G + H + I) 29.24
K. Total Unit Cost (G + H + I + J) 613.99

342
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.2) Bituminous Concrete Surface Course (40mm thk.)


Unit of Measurement : sq.m.
Output per hour : 214.13

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


C. Total (A + B) 15,995.72
D. Output per hour = 214.13 sq.m.
E. Direct Unit Cost (C ÷ D) 74.70
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00785 40,300.00 316.36


b. Aggregates, Sand (79%) cu.m. 0.033 650.00 21.45
c. Aggregates, 3/8 (19%) cu.m. 0.008 650.00 5.20
d. Mineral Filler (7%) bag 0.104 240.56 25.02
e. Diesel L 0.932 240.56 224.20

Sub - Total for F 592.23


G. Direct Unit Cost (E + F) 666.93
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.02
I. Contractor's Profit (CP) 8% of G 53.35
J. Value Added Tax (VAT) 5% of (G + H + I) 39.02
K. Total Unit Cost (G + H + I + J) 819.32

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 310(b.3) Bituminous Concrete Surface Course (50mm thk.)


Unit of Measurement : sq.m.
Output per hour : 171.30

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman Laying & 1 1.00 69.42 69.42
b. Skilled Labor Compaction 4 1.00 50.18 200.72
c. Unskilled Labor 8 1.00 38.97 311.76
a. Batching Plant Engineer Batching/ 1 1.00 0.00
b. Mechanical Engineer Mixing 1 1.00 0.00
c. Electrical Engineer operation 1 1.00 0.00
d. Unskilled Laboratory Technician 1 1.00 0.00
e. Unskilled Labor 4 1.00 0.00
Sub - Total for A 581.90
Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Asphalt Paver (80 Hp), NF220BIIVDM 1 1.00 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1.00 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1.00 1,652.00 1,652.00
d. Dump Truck (12 cu.yd.) 2 1.00 1,420.00 2,840.00
e. Asphalt Batch Plant ( 60-80 TPH) 1 1.00 4,286.63 4,286.63
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
Minor Tools (10% of Labor Cost) 58.19

Sub - Total for B 15,413.82


C. Total (A + B) 15,995.72
D. Output per hour = 171.30 sq.m.
E. Direct Unit Cost (C ÷ D) 93.38
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Asphalt Cement (8%) m.t 0.00981 40,300.00 395.34


b. Aggregates, Sand (79%) cu.m. 0.041 650.00 26.65
c. Aggregates, 3/8 (19%) cu.m. 0.01 650.00 6.50
d. Mineral Filler (7%) bag 0.13 240.56 31.27
e. Diesel L 1.165 240.56 280.25

Sub - Total for F 740.02


G. Direct Unit Cost (E + F) 833.40
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 75.01
I. Contractor's Profit (CP) 8% of G 66.67
J. Value Added Tax (VAT) 5% of (G + H + I) 48.75
K. Total Unit Cost (G + H + I + J) 1,023.83

362
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.
Unit of Measurement : sq.m.
Output per hour : 107.33

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


C. Total (A + B) 12,771.27
D. Output per hour = 107.33 sq.m.
E. Direct Unit Cost (C ÷ D) 118.99
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.0825 850.00 70.13
f. Gravel cu.m. 0.15 650.00 97.50
g. Cement bag 1.43 220.00 314.60
h. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
j. Grease/Tar L 0.0015 300.00 0.45

Sub - Total for F 533.74


G. Direct Unit Cost (E + F) 652.73
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 58.75
I. Contractor's Profit (CP) 8% of G 52.22
J. Value Added Tax (VAT) 5% of (G + H + I) 38.18
K. Total Unit Cost (G + H + I + J) 801.88

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.1.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.
Unit of Measurement : sq.m.
Output per hour : 107.33

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


C. Total (A + B) 1,556.77
D. Output per hour = 107.33 sq.m.
E. Direct Unit Cost (C ÷ D) 14.50
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.15 850.00 127.50
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
h. Grease/Tar L 0.0015 300.00 0.45

Sub - Total for F 179.02


G. Direct Unit Cost (E + F) 193.52
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 17.42
I. Contractor's Profit (CP) 8% of G 15.48
J. Value Added Tax (VAT) 5% of (G + H + I) 11.32
K. Total Unit Cost (G + H + I + J) 237.74

382
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2 PCC Pavement (Plain) - Conventional Method, 200mm thk.
Unit of Measurement : sq.m.
Output per hour : 80.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


C. Total (A + B) 12,771.27
D. Output per hour = 80.50 sq.m.
E. Direct Unit Cost (C ÷ D) 158.65
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.39 36.00 14.04


b. Curing Compound L 0.29 75.00 21.75
c. Asphalt Sealant L 0.12 50.00 6.00
d. Steel Forms (Rental) m 0.46 56.00 25.76
e. Sand cu.m. 0.11 500.00 55.00
f. Gravel cu.m. 0.20 600.00 120.00
g. Cement bag 1.90 240.00 456.00
h. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1 1/2" dia. m 0.0086 97.00 0.83
j. Grease/Tar L 0.0056 210.00 1.18

Sub - Total for F 701.76


G. Direct Unit Cost (E + F) 860.41
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 77.44
I. Contractor's Profit (CP) 8% of G 68.83
J. Value Added Tax (VAT) 5% of (G + H + I) 50.33
K. Total Unit Cost (G + H + I + J) 1,057.01

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.2.1 PCC Pavement (Plain) - Conventional Method, 200mm thk.
Unit of Measurement : sq.m.
Output per hour : 80.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


C. Total (A + B) 1,556.77
D. Output per hour = 80.5 sq.m.
E. Direct Unit Cost (C ÷ D) 19.34
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.39 40.00 15.60


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.2 850.00 170.00
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0086 34.33 0.30
h. Grease/Tar L 0.0056 300.00 1.68

Sub - Total for F 225.18


G. Direct Unit Cost (E + F) 244.51
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 22.01
I. Contractor's Profit (CP) 8% of G 19.56
J. Value Added Tax (VAT) 5% of (G + H + I) 14.30
K. Total Unit Cost (G + H + I + J) 300.39

402
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 70.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


C. Total (A + B) 12,771.27
D. Output per hour = 70.00 sq.m.
E. Direct Unit Cost (C ÷ D) 182.45
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.1265 850.00 107.53
f. Gravel cu.m. 0.23 650.00 149.50
g. Cement bag 2.19 220.00 481.80
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0071 97.00 0.69
j. Grease/Tar L 0.0087 300.00 2.61

Sub - Total for F 796.92


G. Direct Unit Cost (E + F) 979.37
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 88.14
I. Contractor's Profit (CP) 8% of G 78.35
J. Value Added Tax (VAT) 5% of (G + H + I) 57.29
K. Total Unit Cost (G + H + I + J) 1,203.16

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.3.1 PCC Pavement (Plain) - Conventional Method, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 70.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


C. Total (A + B) 1,556.77
D. Output per hour = 70. sq.m.
E. Direct Unit Cost (C ÷ D) 22.24
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.23 850.00 195.50
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0071 34.33 0.24
h. Grease/Tar L 0.0087 300.00 2.61

Sub - Total for F 253.15


G. Direct Unit Cost (E + F) 275.39
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 24.79
I. Contractor's Profit (CP) 8% of G 22.03
J. Value Added Tax (VAT) 5% of (G + H + I) 16.11
K. Total Unit Cost (G + H + I + J) 338.32

422
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.4 PCC Pavement (Plain) - Conventional Method, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 64.40

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


C. Total (A + B) 12,771.27
D. Output per hour = 64.40 sq.m.
E. Direct Unit Cost (C ÷ D) 198.31
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.1375 850.00 116.88
f. Gravel cu.m. 0.25 650.00 162.50
g. Cement bag 2.38 220.00 523.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
j. Grease/Tar L 0.0095 300.00 2.85

Sub - Total for F 863.50


G. Direct Unit Cost (E + F) 1,061.81
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 95.56
I. Contractor's Profit (CP) 8% of G 84.95
J. Value Added Tax (VAT) 5% of (G + H + I) 62.12
K. Total Unit Cost (G + H + I + J) 1,304.44

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.4.1 PCC Pavement (Plain) - Conventional Method, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 64.40

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


C. Total (A + B) 1,556.77
D. Output per hour = 64.4 sq.m.
E. Direct Unit Cost (C ÷ D) 24.17
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.25 850.00 212.50
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
h. Grease/Tar L 0.0095 300.00 2.85

Sub - Total for F 272.54


G. Direct Unit Cost (E + F) 296.71
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 26.70
I. Contractor's Profit (CP) 8% of G 23.74
J. Value Added Tax (VAT) 5% of (G + H + I) 17.36
K. Total Unit Cost (G + H + I + J) 364.51

442
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 57.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


C. Total (A + B) 12,771.27
D. Output per hour = 57.50 sq.m.
E. Direct Unit Cost (C ÷ D) 222.11
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.154 850.00 130.90
f. Gravel cu.m. 0.28 650.00 182.00
g. Cement bag 2.66 220.00 585.20
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
j. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F 961.00


G. Direct Unit Cost (E + F) 1,183.11
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 106.48
I. Contractor's Profit (CP) 8% of G 94.65
J. Value Added Tax (VAT) 5% of (G + H + I) 69.21
K. Total Unit Cost (G + H + I + J) 1,453.45

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.5.1 PCC Pavement (Plain) - Conventional Method, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 57.50

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


C. Total (A + B) 1,556.77
D. Output per hour = 57.5 sq.m.
E. Direct Unit Cost (C ÷ D) 27.07
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.28 850.00 238.00
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
h. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F 300.41


G. Direct Unit Cost (E + F) 327.48
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 29.47
I. Contractor's Profit (CP) 8% of G 26.20
J. Value Added Tax (VAT) 5% of (G + H + I) 19.16
K. Total Unit Cost (G + H + I + J) 402.31

462
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6 PCC Pavement (Plain) - Conventional Method, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 53.67

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00


b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 12,033.49


C. Total (A + B) 12,771.27
D. Output per hour = 53.67 sq.m.
E. Direct Unit Cost (C ÷ D) 237.96
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.165 850.00 140.25
f. Gravel cu.m. 0.30 650.00 195.00
g. Cement bag 2.85 220.00 627.00
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 2" dia. m 0.0094 97.00 0.91
j. Grease/Tar L 0.0094 300.00 2.82

Sub - Total for F 1,028.22


G. Direct Unit Cost (E + F) 1,266.18
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 113.96
I. Contractor's Profit (CP) 8% of G 101.29
J. Value Added Tax (VAT) 5% of (G + H + I) 74.07
K. Total Unit Cost (G + H + I + J) 1,555.50

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)a.6.1 PCC Pavement (Plain) - Conventional Method, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 53.67

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
c. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 818.99


C. Total (A + B) 1,556.77
D. Output per hour = 53.67 sq.m.
E. Direct Unit Cost (C ÷ D) 29.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.3 850.00 255.00
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0094 34.33 0.32
h. Grease/Tar L 0.0094 300.00 2.82

Sub - Total for F 320.38


G. Direct Unit Cost (E + F) 349.39
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 31.45
I. Contractor's Profit (CP) 8% of G 27.95
J. Value Added Tax (VAT) 5% of (G + H + I) 20.44
K. Total Unit Cost (G + H + I + J) 429.22

482
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1 PCC Pavement (Plain) - Using Concrete Paver, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 90.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50


b. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
f. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 18,043.23


C. Total (A + B) 18,703.07
D. Output per hour = 90.00 sq.m.
E. Direct Unit Cost (C ÷ D) 207.81
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Sand cu.m. 0.1265 850.00 107.53
e. Gravel cu.m. 0.23 650.00 149.50
f. Cement bag 2.19 220.00 481.80
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0071 97.00 0.69
i. Grease/Tar L 0.0087 300.00 2.61

Sub - Total for F 773.92


G. Direct Unit Cost (E + F) 981.74
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 88.36
I. Contractor's Profit (CP) 8% of G 78.54
J. Value Added Tax (VAT) 5% of (G + H + I) 57.43
K. Total Unit Cost (G + H + I + J) 1,206.06

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.1.1 PCC Pavement (Plain) - Using Concrete Paver, 230mm thk.
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
d. Concrete Vibrator 1 0.10 91.25 9.13
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 7,341.10


C. Total (A + B) 8,000.94
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D) 80.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.43 40.00 17.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Ready Mix Concrete, 3500 psi cu.m. 0.23 850.00 195.50
e. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
f. Pipe Sleeve, 1" dia. m 0.0071 34.33 0.24
g. Grease/Tar L 0.0087 300.00 2.61

Sub - Total for F 230.15


G. Direct Unit Cost (E + F) 310.16
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 27.91
I. Contractor's Profit (CP) 8% of G 24.81
J. Value Added Tax (VAT) 5% of (G + H + I) 18.14
K. Total Unit Cost (G + H + I + J) 381.04

502
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.2 PCC Pavement (Plain) - Using Concrete Paver, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 82.80

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50


b. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
f. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 18,043.23


C. Total (A + B) 18,703.07
D. Output per hour = 82.80 sq.m.
E. Direct Unit Cost (C ÷ D) 225.88
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Sand cu.m. 0.1375 850.00 116.88
e. Gravel cu.m. 0.25 650.00 162.50
f. Cement bag 2.38 220.00 523.60
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
i. Grease/Tar L 0.0095 300.00 2.85

Sub - Total for F 840.50


G. Direct Unit Cost (E + F) 1,066.38
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 95.97
I. Contractor's Profit (CP) 8% of G 85.31
J. Value Added Tax (VAT) 5% of (G + H + I) 62.38
K. Total Unit Cost (G + H + I + J) 1,310.05

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.2.1 PCC Pavement (Plain) - Using Concrete Paver, 250mm thk.
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
d. Concrete Vibrator 1 0.10 91.25 9.13
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 7,341.10


C. Total (A + B) 8,000.94
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D) 80.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.45 40.00 18.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.15 44.00 6.60
d. Ready Mix Concrete, 3500 psi cu.m. 0.25 850.00 212.50
e. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
f. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
g. Grease/Tar L 0.0095 300.00 2.85

Sub - Total for F 249.54


G. Direct Unit Cost (E + F) 329.55
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 29.66
I. Contractor's Profit (CP) 8% of G 26.36
J. Value Added Tax (VAT) 5% of (G + H + I) 19.28
K. Total Unit Cost (G + H + I + J) 404.85

522
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.3 PCC Pavement (Plain) - Using Concrete Paver, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 73.93

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50


b. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
f. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 18,043.23


C. Total (A + B) 18,703.07
D. Output per hour = 73.93 sq.m.
E. Direct Unit Cost (C ÷ D) 252.98
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Sand cu.m. 0.154 850.00 130.90
e. Gravel cu.m. 0.28 650.00 182.00
f. Cement bag 2.66 220.00 585.20
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0078 97.00 0.76
i. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F 938.00


G. Direct Unit Cost (E + F) 1,190.98
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 107.19
I. Contractor's Profit (CP) 8% of G 95.28
J. Value Added Tax (VAT) 5% of (G + H + I) 69.67
K. Total Unit Cost (G + H + I + J) 1,463.12

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.3.1 PCC Pavement (Plain) - Using Concrete Paver, 280mm thk.
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
d. Concrete Vibrator 1 0.10 91.25 9.13
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 7,341.10


C. Total (A + B) 8,000.94
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D) 80.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.50 40.00 20.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.17 44.00 7.48
d. Ready Mix Concrete, 3500 psi cu.m. 0.28 850.00 238.00
e. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
f. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
g. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F 277.41


G. Direct Unit Cost (E + F) 357.42
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 32.17
I. Contractor's Profit (CP) 8% of G 28.59
J. Value Added Tax (VAT) 5% of (G + H + I) 20.91
K. Total Unit Cost (G + H + I + J) 439.09

542
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4 PCC Pavement (Plain) - Using Concrete Paver, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 69.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Batching Plant (30 cu.m.) 1 1.00 1,759.50 1,759.50


b. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00
c. Transit Mixer (5 cu.m.) 4 1.00 1,318.00 5,272.00
d. Payloader (1.50 cu.m.), LX80-2C 1 1.00 1,733.00 1,733.00
e. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
f. Concrete Saw (7.5 Hp), 14" Blade Ø 1 1.00 32.63 32.63
g. Concrete Vibrator 1 0.10 91.25 9.13
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 18,043.23


C. Total (A + B) 18,703.07
D. Output per hour = 69.00 sq.m.
E. Direct Unit Cost (C ÷ D) 271.06
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Sand cu.m. 0.165 850.00 140.25
e. Gravel cu.m. 0.30 650.00 195.00
f. Cement bag 2.85 220.00 627.00
g. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
h. Pipe Sleeve, 2" dia. m 0.0094 97.00 0.91
i. Grease/Tar L 0.0094 300.00 2.82

Sub - Total for F 1,005.22


G. Direct Unit Cost (E + F) 1,276.28
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 114.87
I. Contractor's Profit (CP) 8% of G 102.10
J. Value Added Tax (VAT) 5% of (G + H + I) 74.66
K. Total Unit Cost (G + H + I + J) 1,567.91

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)b.4.1 PCC Pavement (Plain) - Using Concrete Paver, 300mm thk.
Unit of Measurement : sq.m.
Output per hour : 100.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 10 1.00 38.97 389.70

Sub - Total for A 659.84


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Paver, COM, III, FOUR-TRACK 1 1.00 6,765.00 6,765.00


b. Concrete Screeder (5.5 Hp) 1 1.00 545.00 545.00
d. Concrete Vibrator 1 0.10 91.25 9.13
d. Bar Cutter, Single Phase 1 0.10 219.75 21.98

Sub - Total for B 7,341.10


C. Total (A + B) 8,000.94
D. Output per hour = 100.00 sq.m.
E. Direct Unit Cost (C ÷ D) 80.01
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.55 40.00 22.00


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Ready Mix Concrete, 3500 psi cu.m. 0.3 850.00 255.00
e. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
f. Pipe Sleeve, 1" dia. m 0.94 34.33 32.27
g. Grease/Tar L 0.94 300.00 282.00

Sub - Total for F 608.51


G. Direct Unit Cost (E + F) 688.52
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 61.97
I. Contractor's Profit (CP) 8% of G 55.08
J. Value Added Tax (VAT) 5% of (G + H + I) 40.28
K. Total Unit Cost (G + H + I + J) 845.85

562
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)c PCC Pavement (Plain) - Conventional Method, 150mm thk.
Unit of Measurement : sq.m.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 8 1.00 50.18 401.44
c. Unskilled Labor 16 1.00 38.97 623.52

Sub - Total for A 1,094.38


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. One Bagger Mixer 1 1.00 172.00 172.00


b. Water Truck/Pump (16000L) 1 0.05 2,450.00 122.50
c. Concrete Vibrator 2 1.00 91.25 182.50
d. Bar Cutter, Single Phase 1 0.05 219.75 10.99
e. Concrete Saw (7.5 Hp), 14" Blade Ø 1 0.10 32.63 3.26
Minor Tools (5% of Labor Cost ) 54.72

Sub - Total for B 545.97


C. Total (A + B) 1,640.35
D. Output per hour = 12.00 sq.m.
E. Direct Unit Cost (C ÷ D) 136.70
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.0825 850.00 70.13
f. Gravel cu.m. 0.15 650.00 97.50
g. Cement bag 1.43 220.00 314.60
h. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
i. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
j. Grease/Tar L 0.0015 300.00 0.45

Sub - Total for F 533.74


G. Direct Unit Cost (E + F) 670.44
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 60.34
I. Contractor's Profit (CP) 8% of G 53.64
J. Value Added Tax (VAT) 5% of (G + H + I) 39.22
K. Total Unit Cost (G + H + I + J) 823.63

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(1)c.1 PCC Pavement (Plain) - Conventional Method, 150mm thk.
Unit of Measurement : sq.m.
Output per hour : 12.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 8 1.00 50.18 401.44
c. Unskilled Labor 16 1.00 38.97 623.52

Sub - Total for A 1,094.38


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Concrete Saw (7.5 Hp), 14" Blade Ø 1 0.05 32.63 1.63
c. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 54.72

Sub - Total for B 260.83


C. Total (A + B) 1,355.21
D. Output per hour = 12. sq.m.
E. Direct Unit Cost (C ÷ D) 112.93
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 0.33 40.00 13.20


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.15 850.00 127.50
f. Concrete Saw (diamond blade 14" dia) pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1" dia. m 0.0078 34.33 0.27
h. Grease/Tar L 0.0015 300.00 0.45

Sub - Total for F 179.02


G. Direct Unit Cost (E + F) 291.95
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 26.28
I. Contractor's Profit (CP) 8% of G 23.36
J. Value Added Tax (VAT) 5% of (G + H + I) 17.08
K. Total Unit Cost (G + H + I + J) 358.66

582
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2) PCC Pavement (Reinforced), 300mm thk.


Unit of Measurement : sq.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Batching Plant (30 cu.m.) 1 0.10 1,759.50 175.95


b. Concrete Screeder (5.5 Hp) 1 0.10 545.00 54.50
c. Transit Mixer (5 cu.m.) 2 0.10 1,318.00 263.60
d. Payloader (1.50 cu.m.), LX80-2C 1 0.10 1,733.00 173.30
e. Water Truck/Pump (16000L) 1 0.10 2,450.00 245.00
f. Concrete Vibrator 1 0.10 91.25 9.13
g. Bar Cutter, Single Phase 1 0.25 219.75 54.94
h. Bar Bender 1 0.25 351.50 87.88
Minor Tools (5% of Labor) 36.89

Sub - Total for B 1,101.18


C. Total (A + B) 1,838.96
D. Output per hour = 6.00 sq.m.
E. Direct Unit Cost (C ÷ D) 306.49
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 54.21 40.00 2,168.40


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Sand cu.m. 0.1650 850.00 140.25
f. Gravel cu.m. 0.30 650.00 195.00
g. Cement bag 2.85 220.00 627.00
h. # 16 GI Tie Wire (2% of RSB) kg. 1.084 47.00 50.95

Sub - Total for F 3,220.64


G. Direct Unit Cost (E + F) 3,527.13
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 317.44
I. Contractor's Profit (CP) 8% of G 282.17
J. Value Added Tax (VAT) 5% of (G + H + I) 206.34
K. Total Unit Cost (G + H + I + J) 4,333.08

665
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 311(2)1 PCC Pavement (Reinforced), 300mm thk.


Unit of Measurement : sq.m.
Output per hour : 6.00

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.00 69.42 69.42


b. Skilled Labor 4 1.00 50.18 200.72
c. Unskilled Labor 12 1.00 38.97 467.64

Sub - Total for A 737.78


Name and Capacity No of Units No. of Hours Hourly Rate Amount

B. Equipment

a. Concrete Vibrator 1 0.10 91.25 9.13


b. Concrete Saw (7.5 Hp), 14" Blade Ø 1 0.10 32.63 3.26
c. Bar Cutter, Single Phase 1 0.25 219.75 54.94
d. Bar Bender 1 0.25 351.50 87.88
Minor Tools (5% of Labor Cost) 36.89

Sub - Total for B 192.09


C. Total (A + B) 929.87
D. Output per hour = 6. sq.m.
E. Direct Unit Cost (C ÷ D) 154.98
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Reinforcing Steel Bar kg. 54.21 40.00 2,168.40


b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.18 44.00 7.92
d. Steel Forms (Rental) m 0.46 50.00 23.00
e. Ready Mix Concrete, 3500 psi cu.m. 0.30 850.00 255.00
f. # 16 GI Tie Wire (2% of RSB) kg. 1.084 47.00 50.95

Sub - Total for F 2,513.39


G. Direct Unit Cost (E + F) 2,668.37
H. Overhead, Contingencies & Miscellaneous (OCM) 9% of G 240.15
I. Contractor's Profit (CP) 8% of G 213.47
J. Value Added Tax (VAT) 5% of (G + H + I) 156.10
K. Total Unit Cost (G + H + I + J) 3,278.09

602
665
622
665
642
665
662
665
682
665

You might also like