Professional Documents
Culture Documents
No. of
Item Designation No. of Days Daily Rate Amount
Person
A. Labor
a. Foreman 1 5 807.18 4,035.90
b. Skilled Laborer 4 5 584.30 11,686.00
c. Unskilled Laborer 4 5 450.06 9,001.20
F. Materials
Structural Concrete:
a. Portland Cement 7.00 bags 273.61 1,915.27
b. Washed Sand 1.00 cu.m 972.01 972.01
c. Crushed Gravel 3/4" 1.00 cu.m 922.01 922.01
d. 10mmØ x 6m Reinforcing Steel bars Deformed (Grade40) - 13 pcs 48.09 kgs 51.00 2,452.59
e. 12mmØ x 6m Reinforcing Steel bars Deformed (Grade40) - 30 pcs 157.11 kgs 51.00 8,012.61
f. #16 G.I Tie wire 6.00 kgs 66.00 396.00
g. Marine Plywood 4' x 8' x 1/2" thk (4 uses) 2.00 sheets 795.00 1,590.00
h. Assorted Coco Lumber (4 uses) 54.00 bd.ft 22.00 1,188.00
i. Assorted Common Wire Nails 3.00 kgs 65.00 195.00
Masonry:
a. CHB 4" thk 203.00 pcs 15.00 3,045.00
b. Portland Cement 26.00 bags 273.61 7,113.86
c. Washed Sand 2.00 cu.m 972.01 1,944.02
d. 10mmØ x 6m Reinforcing Steel bars Deformed (Grade40) - 14 pcs 51.79 kgs 51.00 2,641.29
e. #16 G.I Tie wire 1.00 kgs 66.00 66.00
Roofing:
a. LC Purlins 2" x 3" x 6m x 2mm thk 64.44 kgs 75.00 4,833.00
b. LC Purlins 2" x 4" x 6m x 2mm thk 55.38 kgs 75.00 4,153.50
c. G.I Corrugated Sheet roofing Ga.26 6.07 sq.m 415.00 2,519.05
d. 2" Umbrella roofing nails 2.00 kls. 65.00 130.00
e. Assorted nails 6.00 kgs 72.00 432.00
f. Vulcaseal 1.00 can 85.00 85.00
Roofing:
a. Concrete Neutralizer 1.00 liter 170.00 170.00
b. Permacoat Flat Latex (Primer) 2.00 gal 780.00 1,560.00
c. Permacoat Flat Latex Top Coat 2.00 gal 667.00 1,334.00
d. Paint Roller 2.00 pcs 75.00 150.00
Door:
a. Flush Door (0.8m x 2.1m) 1.68 sq.m 720.00 1,209.60
b. Hinges, (50mm x 101mm) 2.00 pairs 95.00 190.00
PART I. EART
803(1)a Structure Excavation cu.m
804(1)a Embankment From Structure Excavation cu.m
7.125 0.330
0.027
1.000 1.00 Welding Machine
1.00 Cutting Outfit
1.243 0.365
1.131
0.357
1.000
6.000
0.238
14.000
4.000
5.560
1.365 1.050
0.325
0.026
0.125
0.143
1.95 1.050
0.325
0.026
0.125
0.125
2.100 0.020
0.040
0.050
0.080
1.890 0.050
0.040
0.040
0.040
0.010
2.000 0.040
0.100
0.040
0.010
2.076 1.050
20.000
10.000 1.050
19.000
5.000 1.050
19.000
10.000 1.050
19.000
85.000 0.75 Welding Machine 1.000
0.25 Cutting Outfit 0.011
0.022
0.020
85.000 0.75 Welding Machine 1.000
0.25 Cutting Outfit 0.010
0.020
0.020
90.450 1.00 Welding Machine 1.050
7.000
1.000
12.995 1.050
13.000 1.050
12.995 1.050
1.000 0.070
70.000
1.000
1.000 30.000
9.000
9.000
14.000
12.000
3.000
4.000
7.000
5.000
MATERIALS
Materials to be Use
32.63
Phenolic Board (5 uses) 725 181.25
Good Lumber (4 uses) 9872 2468
C.W.N 435 108.75
Hinges
Lockset
Cement
Sand
2nd DISTRICT
1st 2nd
Material Prices incl. Hauling Base Price
Cement 275.44 280.00 270.00
Washed Sand 995.49 888.00 900.00
Gravel 945.49 900.00 850.00
sahara 55.44 43.00 50.00
4" thk CHB 17.60 15.00
#16 G.I Tie Wire 82.00 74.00
CATEGORY IV: All other areas not covered under the above categories
Sources of Data: National Wages and Productivity Commission, Department of Labor and Employment,
Philippine Contractors Association, Private Contractors, Civil Engineering Consultants and other related
NEW
REF. NO. JOB ITEM LABOR BASIC WAGE
COST CATEGORY I CATEGORY II CATEGORY III
MONTHL MONTHL
INDEX DAILY DAILY DAILY
Y Y
WAGE
CATEGORY III CATEGORY IV
MONTHL MONTHL
DAILY
Y Y
COMPUTATIONS OF ESTIMATED CYCLE TIME FOR HAULING FROM VARIOUS SOURCES AS BASIS FOR EQUIPMENT RENTAL
NUMBER OF HOURS
AS OF YEAR 2018
0.151
10mmØ 10mmØ DRB x 6m 3.699 0.188
12mmØ 12mmØ DRB x 6m 5.237 0.226
16mmØ 16mmØ DRB x 6m 9.470 0.302
20mmØ 20mmØ DRB x 6m 14.797 0.377
25mmØ 25mmØ DRB x 6m 23.120 0.471
32mmØ 32mmØ DRB x 6m 37.880 0.603
PROVINCE OF MISAMIS ORIENTAL CONTRACT REFERENCE NUMBER:
Water System
Natubo, Jasaan, Misamis Oriental
BILL OF QUANTITIES
GENERAL REQUIREMENTS
WATER SUPPLY
Submitted by:
Name: Date:
Designation:
Const. Firm:
Project Name: Water System
Location: Natubo, Jasaan, Misamis Oriental
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
1
2
3
4
5
6
7
8
9
GENERAL REQUIREMENTS
B.5 Project Billboard/Signboard 1 day(s)
B.7(1) Occupational Safety and Health Program 24 day(s)
B.9 Mobilization/Demobilization 2 day(s)
CONSTRUCTION OF COLLECTION BOX
900(1)c1 Structural Concrete, Class "A" (28 days) 2 day(s)
902(1)a1 Reinforcing Steel (Deformed) Grade 40 1 day(s)
903(2) Formworks and Falseworks 2 day(s)
1603(1) Installation of Valve 2 day(s)
Err:509 Err:509 ### day(s)
CONSTRUCTION OF 1-UNIT GROUND TANK (3.00M X 3.00M X 3.00M)
803(1)a Structure Excavation 2 day(s)
804(1)a Embankment (from structure excavation) 2 day(s)
900(1)c1 Structural Concrete, Class "A" (28 days) 1 5 day(s)
902(1)a1 Reinforcing Steel (Deformed) Grade 40 1 4 day(s)
903(2) Formworks and Falseworks 1 5 day(s)
1032(1)a Painting Works (Masonry/Concrete) 5 day(s)
1603(1) Installation of Valve 2 day(s)
WATER SUPPLY
Err:509 Err:509 ### day(s)
Err:509 Err:509 ### day(s)
1602 Installation of Pipeline 1 2 day(s)
4 27 day(s)
4
Working Days - 27 day(s)
Rainy Days (20% of WD) - 4 day(s)
TOTAL PROJECT DURATION = 31 Calendar Days
PREPARED BY:
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
MONTH 5
138
139
140
141
142
143
144
145
146
147
BAR CHART
www.misamisoriental.gov.ph
148
149
Republic of the Philippines
150
151
PROVINCE OF MISAMIS ORIENTAL
152
153
154
155
156
PROVINCIAL ENGINEERING OFFICE
157
158
159
160
161
162
163
164
165
166
167
MONTH 6
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
MONTH 7
198
199
200
ONTH 7
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
MONTH 8
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
MONTH 9
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
MONTH 10
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
MONTH 11
318
319
320
321
322
MONTH 11
323
324
325
326
327
328
329
330
Republic of the Philippines
PROVINCE OF MISAMIS ORIENTAL
PROVINCIAL ENGINEERING OFFICE
www.misamisoriental.gov.ph
Unit Cost : Based on DPWH Construction Materials Price Data, 2nd Quarter C.Y.
2022, Region X
Recommending Approval:
PRISCO G. VALMORIA
Acting Provincial Engineer
Approved by:
PETER M. UNABIA
Provincial Governor
Water System
Natubo, Jasaan, Misamis Oriental
A. Labor
a. Construction Foreman 1 1 807.18 807.18
b. Unskilled Laborer 1 1 584.30 584.30
c. Skilled Laborer 1 1 450.06 450.06
E. Materials
a. 4' x 8' x 1/2" thk Marine Plywood 3.00 sheet 855.00 2,565.00
b. Coco Lumber 2" x 3" 99.00 bd.ft 19.00 1,881.00
c. Assorted Common Wire Nails 2.00 kgs 65.00 130.00
d. Project Sign (Tarpaulin) 96.00 sq.ft 25.00 2,400.00
A. Labor
-
E. Materials
a. Safety Helmet 961 man-days 0.25 240.25
b. Safety Shoes 961 man-days 2.77 2,661.97
c. Safety Gloves 961 man-days 7.67 7,370.87
Computation of man-days:
number of personnel 31 persons
duration 31 cal. Days
average working hours 8 hrs/day
man-days 961 man-days
A. Labor
-
E. Materials
BAR Ø LENGTH QUANTITY PCS FOR 6m. Weight No. Struc TOTAL WT.
TOP SLAB:
Top Bars:
(T) 12mmØ 2.20 14.00 6.00 5.24 1.00 31.42
(L) 12mmØ 2.20 14.00 6.00 5.24 1.00 31.42
BOTTOM SLAB:
Top Bars:
(T) 12mmØ 2.20 14.00 6.00 5.24 1.00 31.42
(L) 12mmØ 2.20 14.00 6.00 5.24 1.00 31.42
WALL
(V) 16mmØ 1.70 14.00 5.00 9.47 4.00 189.40
(H) 12mmØ 2.20 10.00 4.00 5.24 4.00 83.79
sub-total: 398.88
Footing
26.04
QTY LENGTH WIDTH HEIGHT AREA UNIT 10
124
Top Slab 2.00 2.00 0.10 0.80 sq.m 13
Side Walls 4.00 2.00 1.50 24.00 sq.m
sub-total: 24.80 sq.m
9.0416666666667
2.50 Phenolic Board
118.00 Good Lumber
6.00 C.W.N
1600(2) Pipeline Trench Excavation
Nominal dia.
DESCRIPTION LENGTH WIDTH DEPTH (0.6+Ø) QUANTITY VOLUME UNIT
(mm)
1 1/2"Ø x 60m P.E Pipe 0.00 0.30 0.65 1.00 0.00 cu.m. 0.05
2"Ø x 60m P.E Pipe 0.00 0.30 0.66 1.00 0.00 cu.m. 0.063
3"Ø x 6m P.E Pipe 0.00 0.30 0.69 1.00 0.00 cu.m. 0.09
0.00 cu.m.
DESCRIPTION LENGTH RADIUS OF PIPE AREA QUANTITY VOLUME UNIT BF VOL. (m³)
1 1/2"Ø x 60m P.E Pipe 0.00 0.03 0.0020 1.00 0.00 cu.m. 0.00
2"Ø x 60m P.E Pipe 0.00 0.03 0.0031 1.00 0.00 cu.m. 0.00
3"Ø x 6m P.E Pipe 0.00 0.05 0.0064 1.00 0.00 cu.m. 0.00
0.00 cu.m.
TOTAL VOLUME OF PIPES: 0.00 cu.m.
VOLUME OF EXCAVATION: 0.00 cu.m.
VOLUME OF BACKFILL: 0.00 cu.m.
CUTTING
DESCRIPTION PIPE DIA. Ø LENGTH NO. OF ROLLS T'L LENGTH UNIT
LENGTH (mtrs)
1 1/2"Ø P.E Pipe 1 1/2"Ø
2"Ø P.E Pipe 2"Ø 60.00 0.00 0.00 mtrs
3"Ø P.E Pipe 3"Ø
2"Ø G.I Pipe 2"Ø
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 0 807.18 -
b. Skilled Labor 2 0 584.30 -
c. Unskilled Laborer 8 0 450.06 -
E. Materials
*Wall cu.m
*Top Slab cu.m
*Bottom cu.m
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 2 807.18 1,614.36
b. Skilled Labor 4 2 584.30 4,674.40
c. Unskilled Laborer 4 2 450.06 3,600.48
E. Materials
*Wall 273.19 kgs
*Wing wall 0.00 kgs
*Top Slab 62.84 kgs
*Apron 0.00 kgs
a. 12mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 37 pcs 193.77 kgs 51.67 10,012.04
b. 16mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 22 pcs 208.34 kgs 51.67 10,764.93
c. #16 G.I Tie Wire 11.00 kgs 82.00 902.00
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 3 807.18 2,421.54
b. Skilled Labor 4 3 584.30 7,011.60
c. Unskilled Laborer 4 3 450.06 5,400.72
E. Materials
a. Marine Plywod 4' x 8' x 1/2" thk 10.00 sheets 855.00 8,550.00
b. Assorted Coco Lumber 124.00 bd.ft 19.00 2,356.00
c. Assorted Common Wire Nails 13.00 kgs 78.00 1,014.00
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 1 807.18 807.18
b. Skilled Labor 2 1 584.30 1,168.60
c. Unskilled Laborer 2 1 450.06 900.12
E. Materials
a. 2"Ø Gate Valve, brass 2.00 pcs 4,922.50 9,845.00
b. 2"Ø x 12" G.I nipple 4.00 pcs 500.00 2,000.00
c. 2"Ø G.I Elbow 1.00 pcs 300.00 300.00
d. PVC strainer 1.00 pcs 350.00 350.00
e. 2"Ø G.I Pipe Sch. 40 1.00 length 1,740.00 1,740.00
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 10 100.90 1,008.98
b. Skilled Labor 2 10 73.04 1,460.75
c. Unskilled Laborer 4 10 56.26 2,250.30
E. Materials
*Wall 1.80 cu.m
*Slab 0.80 cu.m
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 3 100.90 302.69
b. Skilled Labor 3 3 73.04 657.34
c. Unskilled Laborer 12 3 56.26 2,025.27
E. Materials
*Wall 273.19 kgs
*Slab 125.69 kgs
a. 12mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 40 pcs 209.48 kgs 51.67 10,823.83
b. 16mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 20 pcs 189.40 kgs 51.67 9,786.30
c. #16 G.I Tie Wire 10.00 kgs 82.00 820.00
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 6 100.90 605.39
b. Skilled Labor 2 6 73.04 876.45
c. Unskilled Laborer 3 6 56.26 1,012.64
E. Materials
a. Marine Plywod 4' x 8' x 1/2" thk 3.00 sheets 850.00 2,550.00
b. Assorted Coco Lumber 31.00 bd.ft 30.00 930.00
c. Assorted Common Wire Nails 6.00 kgs 80.00 480.00
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 2 100.90 201.80
b. Skilled Labor 1 2 73.04 146.08
c. Unskilled Laborer 1 2 56.26 112.52
E. Materials
a. 2"Ø x 6m G.I Pipe Sch.40 2.00 length 1,508.00 3,016.00
b. 2"Ø x 12" G.I nipple sch.40 2.00 pcs 150.00 300.00
c. 2"Ø x 90° G.I elbow sch.40 5.00 pcs 60.00 300.00
d. 2"Ø G.I Cap 1.00 pcs 62.00 62.00
e. 2"Ø Gate valve, brass 2.00 pcs 3,900.00 183.90
f. Valve box with steel cover (fabricated) 1.00 each 2,000.00 2,000.00
g. 2"Ø Transition female adapter 2.00 pcs 660.00 1,320.00
h. Tefflon tape 10.00 pcs 30.00 300.00
Adopt-a-Barangay Program
Water System at Bantaawan, Gingoog City
Unit Cost : Based on DPWH Construction Materials Price Data, 2nd Quarter C.Y. 2022, Region
X
GENERAL REQUIREMENTS
B.5 Project Billboard/Signboard each 2.00 11,814.72
B.7(1) Occupational Safety and Health Program mos. 0.80 11,865.42
B.9 Mobilization/Demobilization L.S 1.00 3,389.92
GENERAL REQUIREMENTS EST. COST 27,070.06
CONSTRUCTION OF COLLECTION BOX
900(1)c1 Structural Concrete, Class "A" (28 days) cu.m 2.60 3,948.55
902(1)a1 Reinforcing Steel (Deformed) Grade 40 kgs 398.88 17,536.85
903(2) Formworks and Falseworks sq.m 26.04 18,924.25
1603(1) Installation of Valve L.S 1.00 21,756.23
Err:509 Err:509 Err:509 Err:509 13,897.54
Err:509 Err:509 Err:509 Err:509 11,116.40
CONSTRUCTION OF 3-UNITS TUB (6' X 8') EST. COST 87,179.81
CONSTRUCTION OF 1-UNIT GROUND TANK (3.00M X 3.00M X 3.00M)
803(1)a Structure Excavation cu.m 7.50 389.34
804(1)a Embankment (from structure excavation) cu.m 3.31 2,568.09
804(4) Gravel Fill cu.m 3.02 5,237.02
900(1)c1 Structural Concrete, Class "A" (28 days) cu.m 10.46 92,327.94
902(1)a1 Reinforcing Steel (Deformed) Grade 40 kgs 1,872.67 155,590.53
903(2) Formworks and Falseworks sq.m 76.23 42,297.19
1032(1)a Painting Works (Masonry/Concrete) sq.m 89.46 32,753.32
1603(1) Installation of Valve L.S 1.00 13,503.42
CONSTRUCTION OF 1-UNIT GROUND TANK (3.00M X 3.00M X 3.00M) EST. COST 344,666.85
WATER SUPPLY
1600(2) Pipeline Trench Excavation Err:509 Err:509 #REF!
1601(1) Fill and Backfill Err:509 Err:509 #REF!
1602 Installation of Pipeline L.S 1.00 303,984.06
WATER SUPPLY EST. COST #REF!
TOTAL ESTIMATED COST #REF!
Republic of the Philippines
PROVINCE OF MISAMIS ORIENTAL
PROVINCIAL ENGINEERING OFFICE
www.misamisoriental.gov.ph
Adopt-a-Barangay Program
Water System at Natubo, Jasaan
Unit Cost : Based on DPWH Construction Materials Price Data, 2nd Quarter C.Y. 2022, Region
X
GENERAL REQUIREMENTS
B.5 Project Billboard/Signboard each 2.00 11,814.72
B.7(1) Occupational Safety and Health Program mos. 0.80 11,865.42
B.9 Mobilization/Demobilization L.S 1.00 3,389.92
CONSTRUCTION OF COLLECTION BOX
900(1)c1 Structural Concrete, Class "A" (28 days) cu.m 2.60 26,244.39
902(1)a1 Reinforcing Steel (Deformed) Grade 40 kgs 398.88 33,544.78
903(2) Formworks and Falseworks sq.m 26.04 8,798.89
1603(1) Installation of Valve L.S 1.00 10,484.67
CONSTRUCTION OF 1-UNIT GROUND TANK (3.00M X 3.00M X 3.00M)
803(1)a Structure Excavation cu.m 7.50 389.34
804(1)a Embankment (from structure excavation) cu.m 3.31 2,568.09
804(4) Gravel Fill cu.m 3.02 5,237.02
900(1)c1 Structural Concrete, Class "A" (28 days) cu.m 10.46 92,327.94
902(1)a1 Reinforcing Steel (Deformed) Grade 40 kgs 1,872.67 155,590.53
903(2) Formworks and Falseworks sq.m 76.23 42,297.19
1032(1)a Painting Works (Masonry/Concrete) sq.m 89.46 32,753.32
1603(1) Installation of Valve L.S 1.00 13,503.42
WATER SUPPLY
1602 Installation of Pipeline L.S 1.00 303,984.06
1201(1) Water Pumping System L.S 1.00 183,570.87
1724(16) Pump House and Accessories L.S 1.00 121,210.11
TOTAL ESTIMATED COST 1,059,574.68
BACK UP COMPUTATION
Slab
BAR Ø LENGTH QUANTITY PCS FOR 6m. Weight No. Struc TOTAL WT.
GROUND WATER TANK
TOP SLAB:
Top Bars:
SL-1 (T) 12mmØ 1.05 30.00 6.00 5.24 1.00 31.42
SL-1 (L) 12mmØ 3.20 30.00 18.00 5.24 1.00 94.27
Bottom Bars:
SL-1 (T) 12mmØ 3.12 20.00 12.00 5.24 1.00 62.84
SL-1 (L) 12mmØ 3.10 20.00 12.00 5.24 1.00 62.84
BOTTOM SLAB:
SL-1 (T) 16mmØ 3.20 20.00 12.00 9.47 1.00 113.64
SL-1 (L) 16mmØ 3.20 20.00 12.00 9.47 1.00 113.64
WALL-FOOTING:
SL-1 (T) 12mmØ 0.87 92.00 15.00 5.24 1.00 78.56
SL-1 (L) 16mmØ 3.65 20.00 14.00 9.47 1.00 132.58
APRON:
SL-1 (T) 16mmØ 1.23 106.00 24.00 9.47 1.00 227.28
SL-1 (L) 16mmØ 5.20 32.00 31.00 9.47 1.00 293.57
WALL
SL-1 (V) 16mmØ 3.38 80.00 50.00 9.47 1.00 473.50
SL-1 (H) 12mmØ 3.10 60.00 34.00 5.24 1.00 178.06
LADDER
Steps 12mmØ 0.82 8.00 2.00 5.24 1.00 10.47
sub-total: 1,872.67
Footing
76.23
PERIMETER THK / HT. NO. OF SIDE QTY. TOTAL AREA UNIT 27
GROUND WATER TANK 361
Wall 12.00 2.80 1.00 1.00 33.60 sq.m 37
Wall 10.80 2.80 1.00 1.00 30.24 sq.m
Slab
BAR Ø LENGTH QUANTITY PCS FOR 6m. Weight No. Struc TOTAL WT.
GROUND WATER TANK
SLAB:
SL-1 (T) 12mmØ 2.37 10.00 5.00 5.24 3.00 78.56
SL-1 (L) 12mmØ 2.98 15.00 9.00 5.24 3.00 141.40
sub-total: 219.95
0.00 sq.m
0.00 sq.m
0.00 sq.m
sub-total: 20.50 sq.m
0.00 sq.m
0.00 sq.m
0.00 sq.m
sub-total: 40.99 sq.m
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project Name : Water System
Location : Natubo, Jasaan, Misamis Oriental
Item No./Description : 804(4) Gravel Fill
Unit of Measurement : cu.m
Output : 1.20 cu.m/hr
Quantity : 2.29
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 2 100.90 201.80
b. Unskilled Laborer 3 2 56.26 337.55
E. Materials
a. Gravel G1 (w/ 15% Shrinkage factor) 2.29 cu.m 945.49 2,169.14
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 8 100.90 807.18
b. Skilled Labor 2 8 73.04 1,168.60
c. Unskilled Laborer 4 8 56.26 1,800.24
E. Materials
*Slab 1.90 cu.m
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 2 100.90 201.80
b. Skilled Labor 3 2 73.04 438.23
c. Unskilled Laborer 12 2 56.26 1,350.18
E. Materials
*Slab 219.95 kgs
a. 12mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 14.00 pcs 219.95 kgs 51.67 11,365.02
b. #16 G.I Tie Wire 6.00 kgs 82.00 492.00
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 6 100.90 605.39
b. Skilled Labor 2 6 73.04 876.45
c. Unskilled Laborer 3 6 56.26 1,012.64
E. Materials
a. 100 mm thk CHB (Non-Load Bearing) 280.00 pcs 19.93 5,580.40
b. Cement 12.00 bag 275.44 3,305.28
c. Sand 1.00 cu.m 995.49 995.49
d. Reinforcing Steel 69.73 kgs 55.39 3,862.20
e. #16 G.I Tie Wire 1.08 kgs 82.61 88.89
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 7 100.90 706.28
b. Skilled Labor 2 7 73.04 1,022.53
c. Unskilled Laborer 4 7 56.26 1,575.21
E. Materials
a. Portland Cement 15.00 bags 275.44 4,131.60
b. Fine Sand 2.00 cu.m 995.49 1,990.98
c. Sahara waterproofing cement 15.00 bags 55.44 831.60
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 3 100.90 302.69
b. Skilled Labor 1 3 73.04 219.11
c. Unskilled Laborer 1 3 56.26 168.77
E. Materials
a. 2"Ø x 6m G.I Pipe Sch.40 3.00 length 1,508.00 4,524.00
b. 2"Ø x 12" G.I nipple sch.40 6.00 pcs 150.00 900.00
c. 2"Ø x 90° G.I elbow sch.40 6.00 pcs 60.00 360.00
d. 2"Ø G.I Cap 3.00 pcs 62.00 186.00
e. 2"Ø G.I coupling 6.00 pcs 60.00 360.00
f. Faucet 6.00 pcs 230.00 1,380.00
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 1 100.90 100.90
b. Unskilled Laborer 3 1 56.26 168.77
E. Materials
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 1 100.90 100.90
b. Unskilled Laborer 3 1 56.26 168.77
E. Materials
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 3 100.90 302.69
b. Unskilled Laborer 3 3 56.26 506.32
E. Materials
a. Gravel G1 (w/ 15% Shrinkage factor) 3.02 cu.m 945.49 2,854.20
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 20 100.90 2,017.95
b. Skilled Labor 4 20 73.04 5,843.00
c. Unskilled Laborer 8 20 56.26 9,001.20
E. Materials
*Wall 4.62 cu.m
*Top Slab 1.35 cu.m
*Bottom Slab 1.15 cu.m
*Wall Footing 1.54 cu.m
*Apron 1.80 cu.m
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 14 100.90 1,412.57
b. Skilled Labor 3 14 73.04 3,067.58
c. Unskilled Laborer 12 14 56.26 9,451.26
E. Materials
*Wall 651.56 kgs
*Top Slab 251.38 kgs
*Bottom Slab 227.28 kgs
*Wall Footing 211.14 kgs
*Apron 520.85 kgs
*Ladder Rung 10.47 kgs
a. 12mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 99 pcs 518.46 kgs 51.67 26,788.98
b. 16mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 143 pcs 1,354.21 kgs 51.67 69,972.03
c. #16 G.I Tie Wire 47.00 kgs 82.00 3,854.00
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 17 100.90 1,715.26
b. Skilled Labor 2 17 73.04 2,483.28
c. Unskilled Laborer 3 17 56.26 2,869.13
E. Materials
a. Marine Plywod 4' x 8' x 1/2" thk 20.00 sheets 855.00 17,100.00
b. Assorted Coco Lumber 272.00 bd.ft 19.00 5,168.00
c. Assorted Common Wire Nails 28.00 kgs 78.00 2,184.00
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 22 100.90 2,219.75
b. Skilled Labor 2 22 73.04 3,213.65
c. Unskilled Laborer 2 22 56.26 2,475.33
E. Materials
a. Skimcoat 15.00 liters 118.75 1,781.25
b. Primer 5.00 gal 700.00 3,500.00
c. Spot Putty 5.00 gal 690.00 3,450.00
d. Top Coat 9.00 gal 750.00 6,750.00
e. Consumables (5% of Materials Cost) 774.06
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 2 100.90 201.80
b. Skilled Labor 1 2 73.04 146.08
c. Unskilled Laborer 1 2 56.26 112.52
E. Materials
a. 2"Ø x 6m G.I Pipe Sch.40 2.00 length 1,508.00 3,016.00
b. 2"Ø x 12" G.I nipple sch.40 2.00 pcs 150.00 300.00
c. 2"Ø x 90° G.I elbow sch.40 5.00 pcs 60.00 300.00
d. 2"Ø G.I Cap 1.00 pcs 62.00 62.00
e. 2"Ø Gate valve, brass 2.00 pcs 3,900.00 183.90
f. Valve box with steel cover (fabricated) 2.00 each 2,000.00 4,000.00
g. 2"Ø Transition female adapter 2.00 pcs 660.00 1,320.00
h. Tefflon tape 20.00 pcs 30.00 600.00
BACK UP COMPUTATION
Footing
Column
AREA UNIT
GROUND WATER TANK
Column sq.m
Wall sq.m
sub-total 0.00 sq.m
Reinforcing Steel (Deformed), Grade 40
Wall
BAR Ø LENGTH QUANTITY # of STRUC Weight PCS FOR 6m. TOTAL WT.
Vertical 16mmØ 3.43 200.00 1.00 9.47 125.00 1183.75
Horizontal 12mmØ 5.10 208.00 1.00 5.24 193.00 1010.74
sub-total: 2194.49
Wall-Footing
BAR Ø LENGTH QUANTITY # of STRUC Weight PCS FOR 6m. TOTAL WT.
(T) 10mmØ 1.25 98.00 1.00 3.70 23.00 85.08
(L) 12mmØ 5.50 20.00 1.00 5.24 20.00 104.74
sub-total: 189.82
Apron
BAR Ø LENGTH QUANTITY # of STRUC Weight PCS FOR 6m. TOTAL WT.
(T) 10mmØ 1.55 140.00 1.00 3.70 40.00 147.96
(L) 12mmØ 7.20 24.00 1.00 5.24 32.00 167.58
sub-total: 315.54
Ladder Rung
BAR Ø LENGTH QUANTITY # of STRUC Weight PCS FOR 6m. TOTAL WT.
F-1 (T) 10mmØ 3.70 0.00 0.00
F-1 (L) 12mmØ 0.88 9.00 1.00 5.24 2.00 10.47
sub-total: 10.47
Beam
BAR Ø LENGTH QUANTITY # of STRUC Weight PCS FOR 6m. TOTAL WT.
Main bars 16mmØ 9.47 0.00 0.00
Main bars 16mmØ 5.20 4.00 2.00 9.47 8.00 75.76
Stirrups 10mmØ 0.60 44.00 2.00 3.70 10.00 36.99
Temperature 10mmØ 1.90 2.00 2.00 3.70 2.00 7.40
sub-total: 120.15
Slab
BAR Ø LENGTH QUANTITY PCS FOR 6m. Weight No. Struc TOTAL WT.
TOP SLAB:
Temp. Bars:
SL-1 (T) 10mmØ 5.20 24.00 23.00 3.70 1.00 85.08
SL-1 (L) 10mmØ 3.70 1.00 0.00
Main Bars:
SL-1 (T) 12mmØ 5.24 1.00 0.00
SL-1 (L) 12mmØ 5.10 68.00 68.00 5.24 1.00 356.12
Extra Bars:
SL-1 (T) 12mmØ 1.30 68.00 17.00 5.24 1.00 89.03
SL-1 (L) 12mmØ 5.24 1.00 0.00
BOTTOM SLAB:
Top Bars 16mmØ 5.20 40.00 38.00 9.47 1.00 359.86
Bottom Bars 16mmØ 5.20 30.00 29.00 9.47 1.00 274.63
sub-total: 1,164.71
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project Name : Water System
Location : Natubo, Jasaan, Misamis Oriental
Item No./Description : 803(1)a Structure Excavation
Unit of Measurement : cu.m
Output : 3.49 cu.m/ man-day
Quantity : 29.40
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 2 100.90 201.80
b. Unskilled Laborer 8 2 56.26 900.12
E. Materials
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 1 807.18 807.18
c. Unskilled Laborer 8 1 450.06 3,600.48
E. Materials
*Backfilling of Excavated Materials 21.41 cu.m
*Gravel Bedding 5.64 cu.m
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 7 807.18 5,650.26
b. Skilled Labor 2 7 584.30 8,180.20
c. Unskilled Laborer 8 7 450.06 25,203.36
E. Materials
*Wall 10.75 cu.m
*Top Slab 3.75 cu.m
*Bottom Slab 3.70 cu.m
*Wall Footing 2.88 cu.m
*Apron 3.47 cu.m
*Beam 0.49 cu.m
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 13 807.18 10,493.34
b. Skilled Labor 4 13 584.30 30,383.60
c. Unskilled Laborer 4 13 450.06 23,403.12
E. Materials
*Wall 2,194.49 kgs
*Top Slab 530.22 kgs
*Bottom Slab 634.49 kgs
*Wall Footing 189.82 kgs
*Apron 315.54 kgs
*Beam 120.15 kgs
*Ladder Rung 10.47 kgs
a. 10mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 98 pcs 362.50 kgs 51.67 18,730.48
b. 12mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 332 pcs 1,738.68 kgs 51.67 89,837.80
c. 16mmØ x 6m Reinforcing Steel Bars (Grade40) ~ 200 pcs 1,894.00 kgs 51.67 97,862.98
d. #16 G.I Tie Wire 100.00 kgs 82.00 8,200.00
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 3 807.18 2,421.54
b. Skilled Labor 4 3 584.30 7,011.60
c. Unskilled Laborer 4 3 450.06 5,400.72
E. Materials
a. Marine Plywood 4' x 8' x 1/2" thk 55.00 sheets 855.00 47,025.00
b. Assorted Coco Lumber 745.00 bd.ft 19.00 14,155.00
c. Assorted Common Wire Nails 33.00 kgs 78.00 2,574.00
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 3 807.18 2,421.54
b. Skilled Labor 2 3 584.30 3,505.80
c. Unskilled Laborer 1 3 450.06 1,350.18
E. Materials
a. Skimcoat 29.00 liters 118.75 3,443.75
b. Primer 17.00 gal 700.00 11,900.00
c. Spot Putty 17.00 gal 690.00 11,730.00
d. Top Coat 34.00 gal 750.00 25,500.00
e. Consumables (5% of Materials Cost) 2,628.69
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 1 807.18 807.18
b. Skilled Labor 1 1 584.30 584.30
c. Unskilled Laborer 2 1 450.06 900.12
E. Materials
a. 6"Ø Butterfly wafer type valve 4.00 pcs 11,600.00 46,400.00
a. 6"Ø x 6" HDPE Tee connector 2.00 pcs 5,000.00 10,000.00
a. 6"Ø x 90 degrees HDPE Elbow 6.00 pcs 5,000.00 30,000.00
a. 6"Ø P.E Flange 10.00 pcs 4,200.00 42,000.00
6,420.00
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 3 807.18 2,421.54
b. Skilled Labor 1 3 584.30 1,752.90
E. Materials
a. Electrical rPVC Pipe 25 mm dia. x 3m 24.00 length 115.00 2,760.00
b. Electrical rPVC adapter 25 mm dia. 24.00 pcs 15.00 360.00
c. Electrical rPVC coupling 25 mm dia. 24.00 pcs 12.00 288.00
d. Electrical rPVC elbows 25 mm dia. 10.00 pcs 22.00 220.00
e. Electrical rPVC clamp 25 mm dia. 74.00 pcs 5.00 370.00
f. Rigid Flexible galvanized Conduit 25 mm dia. Clamp 12.00 pcs 21.00 252.00
g. Rigid Flexible galvanized Conduit 25 mm connector 3.00 pcs 16.00 48.00
h. Rigid Flexible galvanized Conduit 25 mm dia. 3.00 mtrs. 240.00 720.00
i. Entrance cap 25 mm dia. 1.00 pcs 250.00 250.00
j. PVC Utility Box 8.00 pcs 40.00 320.00
k. PVC Junction Box 8.00 pcs 37.00 296.00
l. Large metal Pull Box 1.00 pcs 381.00 381.00
m. #7 PVC Tox with Screw 1.00 boxes 285.00 285.00
n. #16 G.I. Tie Wire 1.00 kls. 87.00 87.00
o. PVC Solvent 1.00 can 148.00 148.00
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 3 807.18 2,421.54
b. Skilled Labor 2 3 584.30 3,505.80
c. Unskilled Labor 18 3 450.06 24,303.24
E. Materials
a. Electric Wires 14 mm2 THHN Stranded Copper Wire 60.00 mtrs 170.00 10,200.00
b. Electric Wires 5.5 mm2 THHN STRND copper 40.00 mtrs 45.00 1,800.00
c. Electric Wires 3.5 mm2 THHN Stranded Copper Wire 450.00 mtrs 32.00 14,400.00
d. Big Electrical Tape 3.00 roll 42.90 128.70
e. ONE-Gang Switch 7.00 pcs 65.00 455.00
f. RubberTape 4.00 roll 90.00 360.00
g. Service drop Wire 14 mm2 220.00 mtrs 140.00 30,800.00
h. Big Electrical Tape 8.00 roll 42.90 343.20
i. 2 GANG UNIVERSAL TYPE Outlet 3.00 pcs 285.00 855.00
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 1 807.18 807.18
b. Skilled Labor 1 1 584.30 584.30
c. Unskilled Labor 6 1 450.06 2,700.36
E. Materials
a. MCB Panel Board, 2 Pole, 4 Branches, Center 1.00 set 10,465.40 10,465.40
MAIN: 40AT, 60AF, 16 kaic, 2P, 230V, 60Hz, Bolt On Type
Branches:
1x16AT, 3P, 230V, 60Hz,mcb,
1x20AT, 3P, 230V, 60Hz,mcb,
2x32AT, 3P, 230V, 60Hz,mcb,
NEMA 1 enclosure Gauge 16
w/ complete Terminal Lugs, Busbar,
& Grounding Busbar rate : 100% copper + 30%
No. of
Item Description No. of Person Daily Rate Amount
days
A. Labor
a. Construction Foreman 1 2 807.18 1,614.36
b. Skilled Labor 1 2 584.30 1,168.60
E. Materials
a. 9 Watts Recessed pinlight 8.00 pcs 490.00 3,920.00
DAYLIGHT
No. of
Item Description No. of Person Hourly Rate Amount
Hour/s
A. Labor
a. Construction Foreman 1 16 100.90 1,614.36
b. Skilled Labor 10 16 73.04 11,686.00
c. Unskilled Laborer 22 16 56.26 19,802.64
B. Equipment
a. Minor Tools (10% of Labor Cost) 3,310.30
E. Materials
*Transmission
a. 2"Ø x 6m PE Pipes SDR 11, ISO 14.00 rolls 13,201.00 184,814.00
b. 2"Ø PE Straight Coupler Compression type, ISO 13.00 pcs 756.80 9,838.40
c. 2"Ø P.E End cap 1.00 pcs 541.20 541.20
No. Of No. Of
DESIGNATION Daily Rate AMOUNT
Person Days
A. LABOR
No. Of No. Of
NAME & CAPACITY Daily Rate AMOUNT
Unit Days
B. EQUIPMENT
Air Compressor 251-351 cfn 1.00 5.00 4,920.00 24,600.00
Generator Set 5.1 - 100 KW 1.00 5.00 3,440.72 17,203.60
Minor Tools (10% of Equipment) 4,180.36
No. of
Item Designation No. of Days Daily Rate Amount
Person
A. Labor
a. Foreman 1 2 807.18 1,614.36
b. Well Driller 1 2 584.30 1,168.60
c. Unskilled Laborer 2 2 450.06 1,800.24
F. Materials
Installation of 5HP Centrifugal Pump and Motor w/ complete accessories:
1.00 unit 84,000.00 84,000.00
a. One (1) unit Brandnew Centrifugal Pump and motor, with the following characterics:
Capacity = 33 GPM
Total Dynamic Head = 380 ft
Horsepower required = 5 HP
Number of stages = 14
No. of
Item Designation No. of Days Daily Rate Amount
Person
A. Labor
a. Foreman 1 5 807.18 4,035.90
b. Skilled Laborer 4 5 584.30 11,686.00
c. Unskilled Laborer 4 5 450.06 9,001.20
F. Materials
Structural Concrete:
a. Portland Cement 7.00 bags 275.44 1,928.08
b. Washed Sand 1.00 cu.m 995.49 995.49
c. Crushed Gravel 3/4" 1.00 cu.m 945.49 945.49
d. 10mmØ x 6m Reinforcing Steel bars Deformed (Grade40) - 13 pcs 48.09 kgs 51.67 2,484.81
e. 12mmØ x 6m Reinforcing Steel bars Deformed (Grade40) - 30 pcs 157.11 kgs 51.67 8,117.87
f. #16 G.I Tie wire 6.00 kgs 82.00 492.00
g. Marine Plywood 4' x 8' x 1/2" thk (4 uses) 2.00 sheets 850.00 1,700.00
h. Assorted Coco Lumber (4 uses) 54.00 bd.ft 30.00 1,620.00
i. Assorted Common Wire Nails 3.00 kgs 80.00 240.00
Masonry:
a. CHB 4" thk 203.00 pcs 15.00 3,045.00
b. Portland Cement 26.00 bags 275.44 7,161.44
c. Washed Sand 2.00 cu.m 995.49 1,990.98
d. 10mmØ x 6m Reinforcing Steel bars Deformed (Grade40) - 14 pcs 51.79 kgs 51.67 2,675.99
e. #16 G.I Tie wire 1.00 kgs 82.00 82.00
Roofing:
a. LC Purlins 2" x 3" x 6m x 2mm thk 64.44 kgs 75.00 4,833.00
b. LC Purlins 2" x 4" x 6m x 2mm thk 55.38 kgs 75.00 4,153.50
c. G.I Corrugated Sheet roofing Ga.26 6.07 sq.m 415.00 2,519.05
d. 2" Umbrella roofing nails 2.00 kls. 65.00 130.00
e. Assorted nails 6.00 kgs 80.00 480.00
f. Vulcaseal 1.00 can 85.00 85.00
Roofing:
a. Concrete Neutralizer 1.00 liter 170.00 170.00
b. Permacoat Flat Latex (Primer) 2.00 gal 780.00 1,560.00
c. Permacoat Flat Latex Top Coat 2.00 gal 667.00 1,334.00
d. Paint Roller 2.00 pcs 75.00 150.00
Door:
a. Flush Door (0.8m x 2.1m) 1.68 sq.m 720.00 1,209.60
b. Hinges, (50mm x 101mm) 2.00 pairs 95.00 190.00