Plate NO.

4
Cost and Duration
Project: Proposed Four - Storey Apartment with Pent House

ACTIVITY DURATION COST MANPOWER EQUIPMENTS


Operators, Dumptruck,
Mobilization 2 days 50,000 laborers=2,
carpenter
Clearing and grubbing 4 days 20,160.00 laborers=6
Construction of temporary carpenter= 3
1.5days 19,968.00
perimeter fence helper= 3
Construction of temporary 3 days 50,000 carpenter=2
bunkhouse/facilities helper= 2

survey team=
3men
Lay-out/ stake out 2 days 20,000 carpenters= 4
laborers= 4

Excavation of footing,tie
Backhoe
beam,wall footing and ground 15days 134,639.55 20 men Jackhammer
floor columns

Fabrication of rebars for


footing,tie beam,wall footing 5 days 660,441.77 Steelman= 20 bar bending machine
helper= 20
and ground floor columns

Installation of rebars for Steelman= 20


footing,tie beam,wall footing 5 days 660,441.77 helper= 20 10- Bar Cutter
and ground floor columns

masons = 2
Pouring of concrete for carpenters = 1
footing, wall footing and tie 1 day 217,342.43 laborers = 4 1 concrete mixer, 1
vibrator
beams vibratory operator
=1

Removal of formworks for tie .5 days 568.10 Carpenter=4


beam Helper=4

Installation of formworks and carpenter=10


scaffolds for Ground Floor 1.5 days 22,118.40 helper= 10
Columns

Pouring of concrete for 1 concrete mixer, 1


Ground Floor Columns .5 day 36,445.19 10 men vibrator

Backhoe
Backfill 2.5 day 33,575.97 32 men Jackhammer
Grader
Fabrication of rebars for 2nd steelman=20
floor beams and slab 2 days 235,260.17 helper= 20 10- Bar Cutter

Installation of rebars for 2nd 2 days 235,260.17 steelman=20 10- Bar Cutter
floor beams and slab helper= 20

Installation of formworks for carpenter= 10


2 days 183,696.00
2nd floor beams and slab helper= 10

Installation of rough-ins for 1 plumber 1helper


Second Floor electrical and 10 days 107,200.00 electrician=5
plumbing helper=5

masons = 2
carpenters = 1
Pouring of concrete for 1 concrete mixer, 1
Second floor beam and slab 1 days 281,209.65 laborers = 4 vibrator, 1 pump crete
vibratory operator
=1

Removal of formworks for Carpenter=4


1 days 7,654.00
Second Floor beam and slab Helper=4

Fabrication of rebars for Steelman= 20


1 days 103,062.20 bar bending machine
Second floor columns helper= 20
Installation of rebars for Steelman= 10
Second floor columns 1 days 103,062.20 helper= 10 5- Bar Cutter

Installation of formworks and


scaffolds for Second floor 1 days 36,249.60 carpenter=20
helper= 20
columns
masons = 2
carpenters = 1
Pouring of concrete of Second 1 concrete mixer, 1
0.5 day 44,254.88 laborers = 4
floor columns vibratory operator vibrator, 1 pump crete
=1
Removal of forms and carpenter=20
scaffolds for Second floor .5 day 1,510.40
columns helper= 20

Fabrication of rebars for Third steelman=20


2days 235,260.17 bar bending machine
floor beams and slab helper= 20
Installation of rebars for Third 2days 235,260.17 steelman=20 10- Bar Cutter
floor beams and slab helper= 20

Installation of formworks for 5days 183,696.00 carpenter=20


Third floor beams and slab helper= 20

Installation of rough-ins for 1 plumber 1helper


Third Floor electrical and 10days 107,200.00 electrician=5
plumbing helper=5

masons = 2
Pouring of concrete for Third carpenters = 1 1 concrete mixer, 1
floor beam and slab 1day 281,209.65 laborers = 4 vibrator, 1 pump crete
vibratory operator
=1
Removal of formworks for Carpenter=4
Third floor beam and slab 1day 7,654.00 Helper=4
Fabrication of rebars for Third steelman=20
1day 103,062.20 bar bending machine
floor columns helper= 20

Installation of rebars for Third steelman=20


1day 103,062.20 10- Bar Cutter
floor columns helper= 20

Installation of formworks and


carpenter=20
scaffols for Third floor 1day 36,249.60
helper= 20
columns

masons = 2
carpenters = 1
Pouring of concrete for Third .5day 44,254.88 laborers = 4 1 concrete mixer, 1
floor columns vibrator, 1 pump crete
vibratory operator
=1

Removal of formworks and


carpenter=20
scaffolds for Third floor .5day 1,510.40 helper= 20
columns

Fabrication of rebars for 2days 235,260.17 steelman=20 bar bending machine


Fourth floor beams and slab helper= 20

Installation of rebars for 2days 235,260.17 steelman=20 10- Bar Cutter


Fourth floor beams and slab helper= 20

Installation of formworks for carpenter=20


Fourth floor beams and slab 5days 183,696.00 helper= 20

Installation of rough-ins for 1 plumber 1helper


Fourth floor electrical and 10days 107,200.00 electrician=5
plumbing helper=5

masons = 2
carpenters = 1
Pouring of concrete for Fourth 1day 281,209.65 laborers = 4 1 concrete mixer, 1
floor beam and slab vibrator, 1 pump crete
vibratory operator
=1

Removal of formworks for Carpenter=4


Fourth floor beam and slab 1day 7,654.00 Helper=4
Fabrication of rebars for steelman=20
1day 103,062.20
Fourth floor columns helper= 20
Installation of rebars for steelman=20
1day 103,062.20
Fourth floor columns helper= 20
Installation of formworks and carpenter=20
scaffolds for Fourth floor 1day 36,249.60
helper= 20
columns
masons = 2
carpenters = 1
Pouring of concrete for Fourth .5day 44,254.88 laborers = 4 1 concrete mixer, 1
floor columns vibratory operator vibrator, 1 pump crete
=1

Removal of formworks and


carpenter=20
scaffolds for Fourth floor .5day 1,510.40
columns helper= 20

Fabrication of rebars for Rood steelman=20


deck and Penthouse beams 2days 267,820.82 bar bending machine
helper= 20
and slab

Installation of rebars for Roof


deck and Penthouse beams 2days 267,820.82 steelman=20 10- Bar Cutter
helper= 20
and slab

Installation of formworks for


carpenter=20
Roof deck and Penthouse 5.5days 207,421.92
beams and slab helper= 20

Installation of rough-ins for 1plumber 1helper


Roof deck and Penthouse 2days 75,200.00 electrician=5
electrical and plumbing helper=5

masons = 2
Pouring of concrete for Roof carpenters = 1 1 concrete mixer, 1
deck and Penthouse beam 1day 313,478.29 laborers = 4
vibrator, 1 pump crete
and slab vibratory operator
=1

Removal of formworks for


carpenter=20
Roof deck and Penthouse 1.5days 8,642.58 helper= 20
beam and slab
Fabrication of rebars for steelman=20
.5day 25,267.94 bar bending machine
Penthouse columns helper= 20
Installation of rebars for steelman=20
.5day 25,267.94 10- Bar Cutter
Penthouse columns helper= 20
Installation of formworks and
carpenter=20
scaffolds for Penthouse .5day 10,886.40
helper= 20
columns

masons = 2
carpenters = 1
Pouring of concrete for 1 concrete mixer, 1
Penthouse columns .5day 13,178.84 laborers = 4
vibratory operator vibrator, 1 pump crete
=1

Removal of formworks and


carpenter=20
scaffolds for Penthouse .5day 453.60 helper= 20
columns

Fabrication of rebars for 2nd


floor , 3rd floor, 4th floor, and steelman=20
3.5days 466,953.47 bar bending machine
Roof deck and Penthouse helper= 20
staircase
Installation of rebars for 2nd
floor , 3rd floor, 4th floor, and 3.5days 466,953.47 steelman=20 10- Bar Cutter
Roof deck and Penthouse helper= 20
staircase
Fabrication of formworks for
2nd floor , 3rd floor, 4th floor, 1.5days 25,503.36 carpenter=20
and Roof deck and Penthouse helper= 20
staircase

masons = 2
Pouring of concrete for 2nd
carpenters = 1
floor , 3rd floor, 4th floor, and 1 concrete mixer, 1
Roof deck and Penthouse 1.5days 471,021.60 laborers = 4 vibrator, 1 pump crete
staircase vibratory operator
=1

Removal of formworksfor 2nd


floor , 3rd floor, 4th floor, and .5day 1,062.64 carpenter=10
Roof deck and Penthouse helper= 10
staircase

Installation of CHB for walls masons=20


and firewalls 7.5days 677,291.71 helper=20

Installation of rebars for slab steelman=20


1.5days 100,872.02
of grade (SOG) helper= 20

Installation of rough-ins for 1plumber 1helper


Ground floor electrical and 4days 83,200.00 electrician=5
plumbing helper=5

masons = 2
carpenters = 1
Concreting of SOG .5day 151,854.98 laborers = 4 1 concrete mixer, 1
vibratory operator vibrator, 1 pump crete
=1

Fabrication of Penthouse welders=10


.5day 1,638.38 5 welding machine
Trusses helper= 10

Installation of Penthouse .5day 1,638.38 welders=10 5 welding machine


Trusses helper= 10

Installation of purlins, rafter, welders=10


.5day 2,976.12 5 welding machine
and fascia boards helper= 10

insulators=5
Insulation works 2days 120,000.00 helper=5

Roofing and Gutter Installation 2days 41,781.38 carpenter=2


helper= 2

Ceiling Works 1day 16,001.18 carpenter=2


helper= 2
Installation of electrical wires 9days 336,000.00 electrician=5
and fixtures helper=5
Installation of stairs and
balcony railings 1day 5,000.00 steelman=2

Installation of doors and carpenter=10


windows jamb 3days 133,461.50 helper= 10
Installation of doors , windows carpenter=10
3days 370,100.00
and looksets helper= 10
water proofer=10
Waterproofing works 7days 12,061.54
helper=10
masons=40
Plastering of walls 7.5days 568,335.30 helper=40
Installation of fire escape 1day 25,600.00 laborer=5 helper=5
ladder

Installation of water tank .5day 8,519.00 laborer=4 helper=4

Installation of plumbing 3days 60,000.00 plumber=1


fixtures helper=1
mason=20
Tile Works 1.5days 43,200.00 helper=20
Painting Works 5days 46,046.00 crew=10
Construction of septic tank, 5days 30,400.00 mason=3 helper=3 1 backhoe
cistern and catch basins

Installation of downspout 4.5days 13,464.00 labror=2

Construction of gate 2days 70,000.00 masons=10


helper=10
tester=1
Testing and Commissioning 1day 331,358.72
commisioner=1
Drainage, Permanent power,
labror=10
telephone and other services 2days 352,000.00
connection helper=10

Demobilization 2days 50,000.00 labor=2 Dumptruck,


carpenter=2
General Cleaning 1day 3,000.00 labor=6

TOTAL COST PHP 12,243,692.89


TOTAL FLOOR AREA 896.00 sq.m
COST PER AREA PHP 13,664.84 /sq.m.