Professional Documents
Culture Documents
4
Cost and Duration
Project: Proposed Four - Storey Apartment with Pent House
survey team=
3men
Lay-out/ stake out 2 days 20,000 carpenters= 4
laborers= 4
Excavation of footing,tie
Backhoe
beam,wall footing and ground 15days 134,639.55 20 men Jackhammer
floor columns
masons = 2
Pouring of concrete for carpenters = 1
footing, wall footing and tie 1 day 217,342.43 laborers = 4 1 concrete mixer, 1
vibrator
beams vibratory operator
=1
Backhoe
Backfill 2.5 day 33,575.97 32 men Jackhammer
Grader
Fabrication of rebars for 2nd steelman=20
floor beams and slab 2 days 235,260.17 helper= 20 10- Bar Cutter
Installation of rebars for 2nd 2 days 235,260.17 steelman=20 10- Bar Cutter
floor beams and slab helper= 20
masons = 2
carpenters = 1
Pouring of concrete for 1 concrete mixer, 1
Second floor beam and slab 1 days 281,209.65 laborers = 4 vibrator, 1 pump crete
vibratory operator
=1
masons = 2
Pouring of concrete for Third carpenters = 1 1 concrete mixer, 1
floor beam and slab 1day 281,209.65 laborers = 4 vibrator, 1 pump crete
vibratory operator
=1
Removal of formworks for Carpenter=4
Third floor beam and slab 1day 7,654.00 Helper=4
Fabrication of rebars for Third steelman=20
1day 103,062.20 bar bending machine
floor columns helper= 20
masons = 2
carpenters = 1
Pouring of concrete for Third .5day 44,254.88 laborers = 4 1 concrete mixer, 1
floor columns vibrator, 1 pump crete
vibratory operator
=1
masons = 2
carpenters = 1
Pouring of concrete for Fourth 1day 281,209.65 laborers = 4 1 concrete mixer, 1
floor beam and slab vibrator, 1 pump crete
vibratory operator
=1
masons = 2
Pouring of concrete for Roof carpenters = 1 1 concrete mixer, 1
deck and Penthouse beam 1day 313,478.29 laborers = 4
vibrator, 1 pump crete
and slab vibratory operator
=1
masons = 2
carpenters = 1
Pouring of concrete for 1 concrete mixer, 1
Penthouse columns .5day 13,178.84 laborers = 4
vibratory operator vibrator, 1 pump crete
=1
masons = 2
Pouring of concrete for 2nd
carpenters = 1
floor , 3rd floor, 4th floor, and 1 concrete mixer, 1
Roof deck and Penthouse 1.5days 471,021.60 laborers = 4 vibrator, 1 pump crete
staircase vibratory operator
=1
masons = 2
carpenters = 1
Concreting of SOG .5day 151,854.98 laborers = 4 1 concrete mixer, 1
vibratory operator vibrator, 1 pump crete
=1
insulators=5
Insulation works 2days 120,000.00 helper=5