You are on page 1of 5

Tugas Workshop Ms Project

Buatlah schedule berdasarkan data – data berikut:

 Proyek bangunan kantor


 Start pekerjaan tanggal 7 Januari 2020
 Masukkan hari libur berdasarkan kalender 2020
 Jam kerja dimulai dari jam 08.00 s/d 17.00, pergunakan kalender 5 hari kerja per minggu
 Buat Baseline setelah resource sudah dimasukkan ke masing – masing pekerjaan
 Buat Lintasan Kritis, WBS dengan level 1 dan panjang kode 2, buat dengan inisial nama
masing - masing
 Buat Updating pekerjaan pada tanggal 02 Maret, dengan progress pekerjaan
Begin Construction = 100%
Site Preparation = 100%
Excavation = 50 %
Install Underground Water Line = 50 %
Install Underground Electrical Conduit = 45%
Form/Pour Concrete Footings = 17%
 Tampilkan progress line
 Buat Kolom controling %Bobot Pekerjaan, %Plan, %Actual, dan Kolom Indikator
Cetak Laporan :
1. Gantchart
2. Resource Sheet
3. Cashflow Report
Task Name Duration Predecessors Resource Names

Office Building 197 days

Fondation 67 days

Begin Construction 0 days

Site Preparation 20 days 3SS Excavator,Pipe[100 M1],Fence[10 M2]

Excavation 10 days 4 Excavator

Install Underground Water


10 days 5 Plumber
Line

Install Underground Electrical


10 days 5 Electrcian
Conduit

Form/Pour Concrete Footings 10 days 6,7 Iron Worker,Laborer

Form/Pour Concrete Walls 10 days 8 Iron Worker,Laborer

Form/Pour Concrete Slab 5 days 9 Iron Worker,Laborer

Backfill and Compact Fills 2 days 10 Bakhoe[1],Excavator,Laborer

Structure 69 days

Erect Structural Frame 20 days 11 Hydrolic Crane[1],Iron Worker,Johan Wales

Floor Decking 14 days 13 Hydrolic Crane[1],Iron Worker,Johan Wales

Install Interior Wall Frame 15 days 15SS Carpenter

Form/Pour Basement Slab


25 days 14 Iron Worker,Laborer
and Floors

Erect Stairwall and Elevator


10 days 15 Carpenter,Iron Worker,Laborer
Walls

M/E System 50 days

Plumbing & Electrical 45 days

Set Mechanical and


15 days 15SS Electrcian,Nicholas Doe,Plumber
Electrical Equipment

Rough-in
15 days 17,20 Electrcian,Plumber
Plumbing/Electrical/Mechanical
Install Wiring and Cable 15 days 21 Electrcian

Elevator 15 days

Install Elevator Rails and


10 days 16 Elevator Vendor
Equipment

Install Elevator Cabinet and


5 days 22,24 Elevator Vendor
Finishes

Exterior 38 days

Install Exterior Doors and


10 days 27SS Carpenter
Windows

Brick Exterior Walls 28 days 17 Carpenter,Mason

Insulation and Buit-up


10 days 27,28 Laborer,Rooler
Roofing

Interior 38 days

Floors 7 days

Install Carpenting 5 days 32 Floor Layer

Install Floor Finishes 7 days 32 Floor Layer

Walls 35 days

Drywall in Office 15 days 25,29 Carpenter

Paint Building Interior 20 days 32 Painting Vendor

Fixtures 3 days

Install Plumbing Fixtures 2 days 33 Plumber

Install Lighting Fixtures 3 days 33 Electrcian

Puch List 5 days

Punchlist/Touchup and
5 days 33,35,36,38,39
Cleanup

Carpenter,Electrcian,Laborer,Painting
Completed Construction 0 days 41
Vendor,Plumber
Resource Material Max.
Type Initials Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar
Name Label Units
Mandor Office 5-Day
Work MD 100% $25.00/hr $10.00/hr $0.00 Prorated
Project Calendar
Office 5-Day
Johan Wales Work EN04 100% $40.00/hr $10.00/hr $0.00 Prorated
Calendar
Office 5-Day
Nicholas Doe Work EN89 100% $40.00/hr $10.00/hr $0.00 Prorated
Calendar
Bakhoe Material EQ03 $100.00 $25.00 Prorated
Hydrolic
Material EQ88 $100.00 $20.00 Prorated
Crane
Fence Material M2 MAT38 $119.00 $0.00 Prorated
Pipe Material M1 MAT36 $30.00 $0.00 Prorated
Painting Office 5-Day
Work VND02 100% $30.00/hr $7.00/hr $0.00 Prorated
Vendor Calendar
Elevator Office 5-Day
Work VND87 100% $30.00/hr $7.00/hr $0.00 Prorated
Vendor Calendar
Office 5-Day
Carpenter Work WR01 200% $25.00/hr $5.00/hr $0.00 Prorated
Calendar
Office 5-Day
Electrcian Work WR02 100% $25.00/hr $5.00/hr $0.00 Prorated
Calendar
Office 5-Day
Excavator Work WR03 100% $25.00/hr $5.00/hr $0.00 Prorated
Calendar
Office 5-Day
Floor Layer Work WR04 200% $25.00/hr $5.00/hr $0.00 Prorated
Calendar
Office 5-Day
Iron Worker Work WR05 100% $25.00/hr $5.00/hr $0.00 Prorated
Calendar
Office 5-Day
Laborer Work WR06 100% $25.00/hr $5.00/hr $0.00 Prorated
Calendar
Office 5-Day
Mason Work WR07 100% $25.00/hr $5.00/hr $0.00 Prorated
Calendar
Office 5-Day
Plumber Work WR08 100% $25.00/hr $5.00/hr $0.00 Prorated
Calendar
Office 5-Day
Rooler Work WR09 100% $25.00/hr $5.00/hr $0.00 Prorated
Calendar

You might also like