Project Name: A Proposed 2 Storey Duplex Residential Building

DURATION

Precedessor MARCH APRIL MAY JUNE JULY AUGUST


No Task Description HOUR DAY

1 Start 0
2 Excavation Works 1 64 8
3 Foundation Works 2 200 25
4 Column Structure Works 3 200 25
5 Sloof Works 3 200 25
6 Wall and Frame Works 5 120 15
7 Roof Trust Works 4 56 7 ...........
8 Roof (Ceiling and Tiles) Works 7 120 15
Sanitary Works and Electrical 25
9 Installations 6,8 200

10 Plaster Works 6,8 160 20 ...


11 Floor Works 9 200 25
Installation Works (Lamps, 15
Glass, Doors, Windows,
12 Switches, Outlets, Locks, 6 120
Sanitation)

13 Painting Works 10,11 160 20


14 Fencing Works 12 80 10
15 Complementary Works 13,14 40 5
Finished
TOTAL DAYS 155 Days
Sumeguin, Aurelio Jr E.
Project Name: Toilet & Bath Renovati DURATION SEPTEMBER 20 TO 26 SEP 27 TO OCT 03

Precedessor
No Task Description HOUR DAY S 1 2 3 4 5 6 7 8 9 10 11 12 13

1 Start 0
2 Purchasing all needed in Reno 1 2 0.5 .........
3 Removal all fixtures 1 7 0.86
4 Removal of Tiles 1 8 1
5 Removal of wall 1 12 1.25
6 Removal of Plumbing 1 5 0.63
7 Removal of Ceiling and Electri 6 7 0.89
8 Excavation for wall Footing 7 7 0.89
9 CHB laying 8 9 1.1
10 Installation of Plumbing 8 7 0.89
11 Installation of Electrical wirin 8 7 0.89
12 Slab construction 11 7 0.89
13 Installatation Ceiling panel 12 7 0.89
14 Installation of exhaust fan 13 1 0.1
15 Wall Finishing 14 9 1.1
16 Installatation all fixtures 15 5 0.63
17 Installation of Tiles & Draina 16 8 1
19 Application of Grout 18 3 0.375
FINISH
TOTAL HOUR 111
TOTAL DAYS 8 days and 2 hours only because other tasks can be done in one day at the same time