Current Tasks
Tasks % Complete
Master Bathroom tiles 80.00%
Checking and fixing all wirings in GF & FF 10.00%
Applying putty works and touch ups - twin's bedroom 100.00%
General cleaning
Visitors
Name Role Purpose of Visit
Andy client representative Checking site
Max client Checking site
Site issues
1.we face a problem of delaying the decking people due to IKSAA, until now they did nothing about the lights in th
2.AC team not come until now becouse of late payment.
eport
Project Incharge Date
Mohammed kamal 29/08/2023
Tasks
Expected date to finish Notes
30/08/2023
02/09/2023 with redwood
Finished for the stars roof
continue GF&FF
m for today
Task Description Time
works inside master bathroom 8:00 -1:00
works inside master bathroom 8:00 - 5:00
d fixing all wirings in twin's bedroom 8:00 - 1:00
d fixing all wirings in twin's bedroom 8:00 - 5:00
works and touch ups - twin's bedroom 8:00 - 5:00
ral Cleaning and help tile team 8:00 - 1:00
rs
Purpose of Visit Time In/Out
Checking site 9:00 - 3:50
Checking site 3:00 -3:50
ues
AA, until now they did nothing about the lights in the roof.
becouse of late payment.