Daily Report

Project work Type Team


Max Villa Civil Works BOBBC

Current Tasks
Tasks % Complete
Master Bathroom tiles 80.00%
Checking and fixing all wirings in GF & FF 10.00%
Applying putty works and touch ups - twin's bedroom 100.00%
General cleaning

Assigned Team for today


Name Role Task Description
Vinod Panamkulangara Tile mason Tile works inside master bathroom
Mahendra Kushwah mason helper Tile works inside master bathroom
Siluvai Maria Lawrance Electricion Checking and fixing all wirings in twin's bedroom
Rinku Lal Electricion hel[er Checking and fixing all wirings in twin's bedroom
Israr Jan painter Applying putty works and touch ups - twin's bedroom
Fasil Helper General Cleaning and help tile team

Visitors
Name Role Purpose of Visit
Andy client representative Checking site
Max client Checking site

Site issues
1.we face a problem of delaying the decking people due to IKSAA, until now they did nothing about the lights in th
2.AC team not come until now becouse of late payment.
eport
Project Incharge Date
Mohammed kamal 29/08/2023

Tasks
Expected date to finish Notes
30/08/2023
02/09/2023 with redwood
Finished for the stars roof
continue GF&FF

m for today
Task Description Time
works inside master bathroom 8:00 -1:00
works inside master bathroom 8:00 - 5:00
d fixing all wirings in twin's bedroom 8:00 - 1:00
d fixing all wirings in twin's bedroom 8:00 - 5:00
works and touch ups - twin's bedroom 8:00 - 5:00
ral Cleaning and help tile team 8:00 - 1:00

rs
Purpose of Visit Time In/Out
Checking site 9:00 - 3:50
Checking site 3:00 -3:50

ues
AA, until now they did nothing about the lights in the roof.
becouse of late payment.