ID Task Name Duration PredecessorsCrash Time Normal Cost Crash cost Total allowable Crash cost per Qtr

tal allowable Crash cost per Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021
crash time week Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
0 Project1 295 days 0 days ₹ 0.00 ₹ 0.00 0 days ₹ 0.00
1 1 Finalize plans 4 wks 3 wks ₹ 25,000.00 ₹ 30,000.00 1 wk ₹ 5,000.00
and develop
estimate with
2 2 Design / 8 wks 1 6 wks ₹ 25,000.00 ₹ 30,000.00 2 wks ₹ 2,500.00
approval of plan
3 3 site work 1 wk 2 1 wk ₹ 50,000.00 ₹ 0.00 0 wks ₹ 0.00
4 4 Select and order 4 wks 2 4 wks ₹ 100,000.00 ₹ 0.00 0 days ₹ 0.00
electrical and
other accessories
5 5 Foundation / 12 wks 3,4 8 wks ₹ 500,000.00 ₹ 600,000.00 4 wks ₹ 25,000.00
superstructure
6 6 Framing 5 wks 5 5 wks ₹ 250,000.00 ₹ 0.00 0 days ₹ 0.00
7 7 Perform inspection1 wk 5,6 1 wk ₹ 10,000.00 ₹ 0.00 0 days ₹ 0.00
8 8 Building structure15 wks 7 13 wks ₹ 600,000.00 ₹ 650,000.00 2 wks ₹ 25,000.00
9 9 Plastering 5 wks 8 4 wks ₹ 250,000.00 ₹ 300,000.00 1 wk ₹ 50,000.00
10 10 interior finish 1 wk 9 1 wk ₹ 10,000.00 ₹ 0.00 0 days ₹ 0.00
11 11 exterior finish 0.5 wks 9 0.5 wks ₹ 10,000.00 ₹ 0.00 0 days ₹ 0.00
12 12 Laying of roof 2 wks 8 2 wks ₹ 200,000.00 ₹ 0.00 0 days ₹ 0.00
13 13 Inspection 0.5 wks 10,11,12 0.5 wks ₹ 10,000.00 ₹ 0.00 0 days ₹ 0.00
14 1.5 wks
14 wiring for the building 12,13 1 wk ₹ 25,000.00 ₹ 35,000.00 0.5 wks ₹ 20,000.00
15 15 Fixing fittings 1 wk 13 1 wk ₹ 25,000.00 ₹ 0.00 0 days ₹ 0.00
16 16 Doors and 0.5 wks 13 0.5 wks ₹ 10,000.00 ₹ 0.00 0 days ₹ 0.00
windows fitting
17 17 Interior painting1 wk 15 1 wk ₹ 40,000.00 ₹ 0.00 0 days ₹ 0.00
18 18 exterior painting1 wk 15 1 wk ₹ 30,000.00 ₹ 0.00 0 days ₹ 0.00
19 19 Final polishing 0.5 wks 17,18 0.5 wks ₹ 15,000.00 ₹ 0.00 0 days ₹ 0.00
20 20 Cleaning and 1 wk 19 1 wk ₹ 5,000.00 ₹ 0.00 0 days ₹ 0.00
handing over

MPC Assignment No 5
Project Management

Patil Omkar Shivaji 2019H1420604P

Task Project Summary Manual Task Start-only Deadline Progress

Project: Project1 Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Fri 15-05-20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split Slack

Summary Inactive Summary Manual Summary External Milestone Late

Page 1
Total
Predecess Crash Crash cost
Activities Task Name Duration Normal Cost Crash cost allowable Total Cost
ors Time per week
crash time
Finalize plans and develop
A 4 wks 3 wks ₹ 25,000.00 ₹ 30,000.00 1 ₹ 5,000.00 ₹ 5,000.00
estimate with owner, architect
B Design / approval of plan 8 wks 1 6 wks ₹ 25,000.00 ₹ 30,000.00 2 ₹ 2,500.00 5000
C site work 1 wk 2 1 wk ₹ 50,000.00 ₹ 0.00 0 ₹ 0.00 0
Select and order electrical
D 4 wks 2 4 wks ₹ 1,00,000.00 ₹ 0.00 0 ₹ 0.00
and other accessories 0
E Foundation / superstructure 12 wks 3,4 8 wks ₹ 5,00,000.00 ₹ 6,00,000.00 4 ₹ 25,000.00 100000
F Framing 5 wks 5 5 wks ₹ 2,50,000.00 ₹ 0.00 0 ₹ 0.00 0
G Perform inspection 1 wk 5,6 1 wk ₹ 10,000.00 ₹ 0.00 0 ₹ 0.00 0
H Building structure 15 wks 7 13 wks ₹ 6,00,000.00 ₹ 6,50,000.00 2 ₹ 25,000.00 50000
I Plastering 5 wks 8 4 wks ₹ 2,50,000.00 ₹ 3,00,000.00 1 ₹ 50,000.00 50000
J interior finish 1 wk 9 1 wk ₹ 10,000.00 ₹ 0.00 0 ₹ 0.00 0
K exterior finish 0.5 wks 9 0.5 wks ₹ 10,000.00 ₹ 0.00 0 ₹ 0.00 0
L Laying of roof 2 wks 8 2 wks ₹ 2,00,000.00 ₹ 0.00 0 ₹ 0.00 0
M Inspection 0.5 wks 10,11,12 0.5 wks ₹ 10,000.00 ₹ 0.00 0 ₹ 0.00 0
N wiring for the building 1.5 wks 12,13 1 wk ₹ 25,000.00 ₹ 35,000.00 0.5 ₹ 20,000.00 10000
O Fixing fittings 1 wk 13 1 wk ₹ 25,000.00 ₹ 0.00 0 ₹ 0.00 0
P Doors and windows fitting 0.5 wks 13 0.5 wks ₹ 10,000.00 ₹ 0.00 0 ₹ 0.00 0
Q Interior painting 1 wk 15 1 wk ₹ 40,000.00 ₹ 0.00 0 ₹ 0.00 0
R exterior painting 1 wk 15 1 wk ₹ 30,000.00 ₹ 0.00 0 ₹ 0.00 0
S Final polishing 0.5 wks 17,18 0.5 wks ₹ 15,000.00 ₹ 0.00 0 ₹ 0.00 0
T Cleaning and handing over 1 wk 19 1 wk ₹ 5,000.00 ₹ 0.00 0 ₹ 0.00 0
₹ 18,30,000.00 ₹ 2,20,000.00
Red boxes are showing critical path
(automatically generated gantt chart using Patil Omkar Shivaji 2019H1420604P

Even after crashing crashable activities critical path is remaining same hence crashing all crashable
activities.
TOTAL COST GETS INCREASED TO = 1830000 + 220000 = 2050000
Hence total project cost after crashing is Rs. 2050000
FS FS FS FS
0 1 2 3 5 6
FS FS FS
FS FS FS
FS 7 8 9 10
4

FS
FS FS

11
FS
FS FS FS FS
12 13 15 17 19 20
FS
FS FS 18
FS FS FS
16

14

Patil Omkar Shivaji 2019H1420604P