Professional Documents
Culture Documents
TABLE OF CONTENTS
1. INTRODUCTION........................................................................................4
2. PURPOSE OF DOCUMENT..................................................................7
3.1 Definitions................................................................................................8
3.2 Abbreviations............................................................................................8
5.1 General.....................................................................................................9
5.5 Select Installation Method for Nam Con Son 2 - Phase 2 Pipeline................14
8. SEABED INTERVENTION.................................................................16
9. SURVEYING.....................................................................................17
1. INTRODUCTION
GPP2
Landfall Station
DC: 20.0 MMSCMD
DP: 160 barg
DT: -10/70º C
TU-NCS2 Pipeline
Length: 5.8 km
Diameter: 26'’
Pipeline DP: 160 barg
DT: -10/70º C
future
Bach Ho Platform
DP: 139 barg
MOP: 125 barg
DT: 70º C
Bach Ho
Platform
Dai Hung
Hai Thach Platform Platform DP: Design Pressure
DP: 160 barg MOP: Max. Operating Pressure
MOP: 151 barg DC: Design Capacity
DT: -10/70º C SSIV DT: Design Temperature
GDC: Gas Distribution Center
SƯ TỬ VÀNG
DINH CỐ
RẠNG ĐÔNG
CCP BẠCH H Ổ
11,8 km đoạn ống kết nối NCS2
với Bạch Hổ tại BK4A
Vị trí kết nối cũ
(Barred tee)
GĐ1 của Dự án NCS2
(khoảng 151 km)
THIÊN ƯNG
Vị trí kết nối mới
(PLEM tie-in)
ĐẠI NGUYỆT
Khoảng 20 km tuyến ống 16”
từ Đại Hùng về Thiên Ưng Đ/ô NCS2
ĐẠI HÙNG
theo FS đã
được phê
CÁ CHÓ-GẤU CHÚA duyệt
RỒNG ĐÔI
LAN TÂY
THIÊN NGA
DỪA
to landfall point at Long Hai and approximately 60km 26” pipeline from
Hai Thach Platform to NCS2 gas pipeline – phase 1;
- The onshore pipeline including about 9km 26” pipeline from landfall point
at Long Hai to GPP2 and about 30km 30” pipeline for transferring sale gas
from GPP2 to Phu My GDC and Phuoc Hoa LBV station, extension of Phu
My Gas Distribution Center;
- The Gas Processing Plant 2 (GPP2) is located in Dinh Co, and two liquid
product pipelines (LPG and Condensate) is approximately 25km from outlet
of GPP2 to transport to Thi Vai Terminal and 03 LBV Stations.
DINH CỐ SƯ TỬ VÀNG
RẠNG ĐÔNG
SƯ TỬ TRẮNG - CPP
CCP-B H
B K-4A
KP 227.5
GĐ1 của Dự án NCS2
(khoảng 151 km 26”)
KP 64+170
(WYE tie-in)
ĐẠI NGUYỆT
CÁ CHÓ-GẤU CHÚA
RỒNG ĐÔI
LAN TÂY
THIÊN NG A
2 DỪA
Figure 1.3: Layout of NCS2 Gas Pipeline Project – Phase 2 (Offshore part)
2. PURPOSE OF DOCUMENT
This document contains a review of the installation and construction methods
for the 26” offshore pipeline sections of NCS2 – Phase 2 project. It comprises
a compilation of Installation and Construction Methodology to be used for the
Basis of Design of the pipeline system.
This document and other project related documentation and activities shall
ensure that practicable the Nam Con Son 2 – Phase 2 Gas Pipeline Project are
designed, constructed and implemented in a safe manner and minimizes
adverse environmental effects associated with the project.
3.1 Definitions
3.2 Abbreviations
5.1 General
Terminate pipelay 3.5km from Hai Thach platform close to the pre-laid
pipeline from Hai Thach.
The Hai Thach pipeline end is raised using the barge davit system to the
lay barge and welded to the end of pipeline laid from shore. Lower the
connected pipeline to the seabed with davit system. Alternatively, tie-in
spool is inserted subsea to connect both ends of the pipeline.
Along pipeline route, tie-in will be placed, connecting NCS2 pipeline to others
platform such as Hai Thach platform, Sao Vang platform, Su Tu Trang
platform.
Pipeline burial can be carried out by one of the following methods:
Ploughing;
Mechanical Cutters;
Jetting;
Fluidisation.
The ploughing operation is the most suitable method of pipeline burial for the
project as the following conditions apply:
Sands and soft silts;
Cohesive soils up to 5 kPa undrained shear strength.
The economics of the project allow for a large pull vessel (with a
correspondingly large crane and winch) to lift and pull the plough.
The most common method of pipeline installation in shallow water is the S-lay
method.
The main features are as:
Being able to lay a variety of different pipeline diameters;
Allows concrete coated pipe to be installed thus not requiring heavy wall
pipe to ensure on-bottom stability;
Availability of vessel;
Disadvantage of S-lay installation include:
S-lay configuration is characterized by high bending and tension loads at
top of the pipe span and these loads are amplified as water depth
With Reel lay method, pipeline can be installed either in S-lay or J-lay
depending on the design of the reel vessel and the depth of water.
The main features of Reel lay installation are as:
Faster than conventional method;
Lower labor costs.
Disadvantage of Reel lay installation are as:
Connecting the ends of the pipeline segments;
Amount of time to re-reel the pipeline to remove a buckle;
Establishing a spool base close to the location where the pipeline is to be
laid;
Limited to small diameter pipelines;
Concrete coated pipelines cannot be reeled;
Only specifically designed pipe-in-pipe pipelines can be reeled;
The pipeline is plastically deformed and then straightened. Some thinning
of the wall and loss of ductility of the material in localized areas can occur
(Bauschinger effect).
5.5 Select Installation Method for Nam Con Son 2 - Phase 2 Pipeline
S-lay method is the most common method used for pipeline installation in the
industry. For Nam Con Son 2 - Phase 2 pipeline installation, it is suggested S-
lay method to be used for the reasons listed below:
The water depth and the diameter of pipeline are within the range of S-lay
method. Two previous similar pipelines adjacent to NCS2 - Phase 2 have
been installed with the same method.
There is bigger number of S-lay barge in the area. Compared to J-lay
barge, daily cost of S-lay barge could be relatively cheaper.
Suitability of J-lay method on shallower water is limited because sufficient
distance is required to deflect the pipe into horizontal in seabed. If J-lay
method is chosen for NCS2-Phase 2, it means second barge is required for
pipeline installation in shallower water. The total cost to mobilized two
barges will be bigger that only one S-lay barge.
The diameter size and the concrete coating requirements for NCS2 - Phase
2 pipeline make the option for reel pipeline method improbable.
Further installation analysis is required to be undertaken in the next
engineering phase to check suitability of different possible S-lay barges to be
used and pipeline stresses (yield, local buckling, fatigue damage and damage
to weight coating and field joint) arise during installation if installed with those
barges.
Fatigue damage;
Excessive damage to weight coating and field joint.
The installation techniques discussed previously, comprising of pipelay by
laybarge or DP vessels and need to be examined with respect to:
The basic analysis required to determine feasibility;
The data requirements for analysis;
The basic load cases;
The acceptance criteria.
8. SEABED INTERVENTION
To place a structure on the seabed securely, the seabed should be as flat and
regular as possible. If the seabed is irregular or undulating, the structure, for
this instance is a pipeline, will suffer the risk of spanning and overstressing.
PIN2.2-PVE-BD-1-01-02-PH-001 Rev. A1 Page 15/18
NAM CON SON 2 GAS PIPELINE PROJECT
UPDATING FEASIBILITY STUDY – PHASE 2
OFFSHORE PIPELINE INSTALLATION PHILOSOPHY
9. SURVEYING
During the installation phase, seabed surveys need to be carried out to check
if it complies with the design and if scope for pre-sweep and post trenching
can be further optimized to achieve a more cost effective solution.
During the pipeline operation, a survey should be carried out generally within
one year after the installation. The objective of the survey is to:
Monitor pipeline status;
Monitor pipeline seabed interaction and natural self-lowering;
Identify free spans;
Evaluate seabed dynamics.
The survey should include the pipeline burial, free span locations, lengths and
gap heights and seabed profiles around the pipeline.
ROV inspections are recommended for critical free spans, if any.
The survey data should be reviewed in order to determine the future survey
strategy.
If the free span correction method is chosen and if the any part of the pipeline
is exposed on the seabed, it is necessary to carry out the survey with high
resolution multi-beam echsoundings, by three surveys: one post-lay, another
one after 1 year and the third one after 3 years.
Unless these measurements show different results in seabed changes, from
then on a repeat survey every 5 year would be sufficient to identify any critical
free spans developing. If some significant span developments identified in the
survey, more frequent survey would be required.