Professional Documents
Culture Documents
seabed-to-surface
Contents
Introduction
J-Lay Versus S-Lay
Project Description
Flowline Design
Installation
Analysis & Fatigue
Pipelay Monitoring
Conclusions
seabed-to-surface
private and confidential
October 5, 2020
slide 2
Introduction
J-Lay Versus S-Lay ?
seabed-to-surface
private and confidential
October 5, 2020
slide 3
J-Lay versus S-Lay
seabed-to-surface
private and confidential
October 5, 2020
slide 4
Why J-Lay Versus S-Lay ?
seabed-to-surface
private and confidential
October 5, 2020
slide 5
J-Lay versus S-Lay
S-Lay J-Lay
1-Offloading 2-Bevelling
3 - Transfer 4-Welding
(GMAW)
5-NDE (AUT)
6 - FJC (HSS+injected resin)
seabed-to-surface
private and confidential
October 5, 2020
slide 6
Project Description
seabed-to-surface
private and confidential
October 5, 2020
slide 7
Project Description
BONGA PROJECT - SOUTHERN NIGER DELTA OFFSHORE NIGERIA
Client SNEPCO (Shell Nigeria Exploration & Production Co Ltd)
90km Gas Export Line - S-Lay
3 x W.I. Lines 4km,5km,15km (Polymer lined) J-lay
10 x Pipe-in-Pipe Production Flowlines (6x10” +4x12”) 35km Total
Length J-Lay
5000 Individual PIP components
> 1000m Water Depth
Flowlines connected via SCR to BONGA FPSO (300,000 Te Hull,
17,000 Te Topsides)
J-Lay performed by SEAWAY POLARIS - J-Lay Tower
Installation of 20 Flowline Termination (FTA) & In-line Tee
Assemblies (ITA)
Clad pipeline sections for SCR TDP zones
seabed-to-surface
private and confidential
October 5, 2020
slide 8
Field Layout
seabed-to-surface
private and confidential
October 5, 2020
slide 9
FPSO
seabed-to-surface
private and confidential
October 5, 2020
slide 10
Flowline Design
seabed-to-surface
private and confidential
October 5, 2020
slide 11
Flowline Design
Doris Engineering - Flowline Design Sub-contractor
Pipe-in-pipe Chosen to Satisfy Thermal Requirement (U Value )
Itp Pipe-in-pipe Concept Chosen
Fabrication Eupec
Inner Pipe - Burst Pressure
Outer Pipe - Collapse Pressure
Design Data
U Value = 1.0 [W/m2 K] or less
Design Pressure = 31.7 Mpa
Ops Temp Range = 4 deg C to 80 deg C
Design Temp Range = -15 deg to 93 deg C
Design Code API RP 1111
Inner Pipe Corrosion Allowance = 6 mm
External Coating Outer Pipe = FBE
seabed-to-surface
private and confidential
October 5, 2020
slide 12
Pipe In Pipe Field Joint
seabed-to-surface
private and confidential
October 5, 2020
slide 13
Pipe In Pipe Solution
CAPABILITIES LIMITATIONS
seabed-to-surface
private and confidential
October 5, 2020
slide 14
Installation
seabed-to-surface
private and confidential
October 5, 2020
slide 15
Installation
seabed-to-surface
private and confidential
October 5, 2020
slide 16
Seaway Polaris
1- Offloading
2- Bevelling
3- Transfer
4- Welding (GMAW)
5- NDE (AUT)
6- FJC (HSS + injected resin)
seabed-to-surface
private and confidential
October 5, 2020
slide 17
General Arrangement 1
Tower
HIAB crane
ERECTOR
WS1
STINGER
PES
WS2
seabed-to-surface
private and confidential
October 5, 2020
slide 18
General Arrangement 2
seabed-to-surface
private and confidential
October 5, 2020
slide 19
Pipelay Specifics
Offshore welding :
GMAW 2G
AUT process
Field Joint Coating :
Anticorrosion coating : HSS
Thermal protection : Insulated sleeve + injected resin
Laying tension
10” Production flowline
235 mt (empty) / 280 mt (wet)
12” Production flowline
250 mt (empty) / 310 mt (wet)
seabed-to-surface
private and confidential
October 5, 2020
slide 20
Working Station 1
jacks
Centralizer
+ welding table
bushing
seabed-to-surface
private and confidential
October 5, 2020
slide 21
Stinger
WS1
Gimballing
jacks
Centralizer stinger
(guillotine)
Rollers
level1
level2
seabed-to-surface
private and confidential
October 5, 2020
slide 22
Working Station 2
Jack + jaws
to clamp
onto pipe
gangway
seabed-to-surface
private and confidential
October 5, 2020
slide 23
Pipe Passing Through Rollers
seabed-to-surface
private and confidential
October 5, 2020
slide 24
Pipe In Pipe
Design applicable : ITP
sleeve to cover field joint (750kg
approx.)
injection of resin solid PU
External pipe is swaged
Izoflex is injected into intertubular
space
sliding sleeve (itself in PiP - izoflex)
FJC operation carried out in WS2
seabed-to-surface
private and confidential
October 5, 2020
slide 25
Pipe in Pipe
seabed-to-surface
private and confidential
October 5, 2020
slide 26
AUT
ring
Calibration block
Scanning
machine
seabed-to-surface
private and confidential
October 5, 2020
slide 27
Flowline Initiation
seabed-to-surface
private and confidential
October 5, 2020
slide 28
Flowline Initiation ctd.
seabed-to-surface
private and confidential
October 5, 2020
slide 29
Initiation Steps
Insertion of PFTA in tower
Connection of Initiation chain to PFTA
Connection of Temporary Buoyancy Modules on PFTA
Lowering of PFTA
Connection of the chain to the suction anchor
Deployment of pipe to form catenary
Tower angle changes
Pre-tension of Chain moving Vessel
Set Tower Angle for normal pipelay
Landing of the PFTA on Seabed
Normal Flowline Lay
Buoyancy Removal
seabed-to-surface
private and confidential
October 5, 2020
slide 30
PFTA Details
PFTA characteristics :
PFTA weight : 20.3t or 21.2t
DJ weight : 5.4 to 7 t
Initiation chain : 58mm or 87mm
25m initiation chain connected during lift : 1.8t or 4t
Total lift weight : 27.4 to 32.7t
Total initiation chain length : 77 to 108m
Temporary buoyancy : 22.5t approx.
Extreme tension in chain during field life : 88 to 286t
seabed-to-surface
private and confidential
October 5, 2020
slide 31
FTA - Flowline Termination Assembly
25.8m
10m
6.4m
3.5m
seabed-to-surface
private and confidential
October 5, 2020
slide 32
Initiation - Production Sled
Initiation chain
Stay system
+ clamp
seabed-to-surface
private and confidential
October 5, 2020
slide 33
Insertion of PFTA in Tower
seabed-to-surface
private and confidential
October 5, 2020
slide 34
Initiation - Production Sled
Stay system
scaffolding
connector
seabed-to-surface
private and confidential
October 5, 2020
slide 35
Lowering of PFTA with Buoyancy
seabed-to-surface
private and confidential
October 5, 2020
slide 36
Temporary Buoyancy
seabed-to-surface
private and confidential
October 5, 2020
slide 38
Flowline Lay & Laydown
Normal Pipelay performed with 6 deg and 7 deg Tower angle for
10” and 12” lines respectively.
Tower can be rotated (gimballed) about its own axis to aid
positioning
8 temporary laydowns at interface with SCR’s - Lines later
recovered for addition of RBGL structures
2 permanent laydowns for 2 in-field lines with FTA’s
Laydown load exceeded capacity of A/R winch
(180 Te) Pipeline laid down with drill string fed through J-Lay
system
Laydown FTA’s installed also with Temporary Buoyancy modules
seabed-to-surface
private and confidential
October 5, 2020
slide 39
RBGL
Riser Base Gas Lift 6 reasons to never to it again:
27 tons in air
10m x 5.5m x 3.5m
Stability issue
center of gravity 1m
above the pipe
structure not symmetrical
5T of permanent buoy
24T of temporary buoy
ABB design
without consideration of
installation constraints
seabed-to-surface
private and confidential
October 5, 2020
slide 40
VIV Strake
strake
Inconel banding
Straightener
Extension pipe
Flexjoint
Last pipe 8m
seabed-to-surface
private and confidential
October 5, 2020
slide 42
Pull-in Head Rigging Connection
nose
Pull-in
head
Flexjoint
seabed-to-surface
private and confidential
October 5, 2020
slide 43
SCR Hand Over
seabed-to-surface
private and confidential
October 5, 2020
slide 44
Analysis and Fatigue
seabed-to-surface
private and confidential
October 5, 2020
slide 45
Analysis & Fatigue
Static Analysis – Determination of limiting vessel translational
movements.
Dynamic Analysis – Considering All Environmental Loads & Vessel
motions to determine allowable lay seastates with the limits being
set based on pipe strains and roller reactions. General dynamic
analyses were performed for different seastates with the seastates
being defined by a Jonswap spectrum for periods Tp of 9-12sec.
Fatigue Analysis - Considering critical flowline locations in the
tower and at pipe/structure interface – the objective being to
determine allowable standby durations for an assumed seastate
based on limiting fatigue damage to 0.01.
seabed-to-surface
private and confidential
October 5, 2020
slide 46
Criteria
The Installation criteria for the J-lay installation using the
POLARIS were as follows :
The total strain in the outer pipe shall not exceed 0.15% all
along the pipeline.
The total horizontal reaction on tower rollers shall not exceed
16 tonnes.
Installation Fatigue damage should be limited to 0.01. i.e.
Installation fatigue damage limited to 10% of the total 0.10
damage allowed during Installation and operation phases.
The tension at the tower bushing point location shall not
exceed 500 tons. This was always the case for the Bonga
flowlines.
seabed-to-surface
private and confidential
October 5, 2020
slide 47
FTA in Splashzone - Orcaflex
OrcaFlex : init-splas h-11-(1).dat (modified 08:24 on 20/05/03) (azimuth=225; elev ation=15) Res et
8m Z
Y X
y
x
z
y
x
z y
z z
yx x xy
seabed-to-surface
private and confidential
October 5, 2020
slide 48
Modelling
seabed-to-surface
private and confidential
October 5, 2020
slide 49
Fatigue
In-place Fatigue Analysis based on 1000 complete thermal shut-
downs
Damage Incurred during Installation to be limited to 0.01 i.e. 10
% of total fatigue budget (Operation + Installation) of 0.1.
Swaged weld detail fatigue sensitive
Fatigue damage assessment for the pipeline during installation is
carried out using a deterministic fatigue analysis approach.
Damage Accumulation based on MINERS RULE
Wave Occurrences based on RAYLEIGH DISTRIBUTION
BUSHING LOCATION : API X’ Curve SCF = 1.64 based on TWI
Fatigue tests
ROLLER LOCATION S : R1 F1 Curve SCF 1.3 Top 1.0 Btm
seabed-to-surface
private and confidential
October 5, 2020
slide 50
Fatigue Locations in Stinger
Bushing
Guillotine
Rollers R1
Rollers R2
seabed-to-surface
private and confidential
October 5, 2020
slide 51
View on Bottom Stinger Rollers
seabed-to-surface
private and confidential
October 5, 2020
slide 52
Typical Fatigue Results
seabed-to-surface
private and confidential
October 5, 2020
slide 53
Pipelay Monitoring
seabed-to-surface
private and confidential
October 5, 2020
slide 54
Pipelay Monitoring
Monitoring Principle
Limiting Vessel Motions
Limiting Seastates
Limiting Standby Durations
seabed-to-surface
private and confidential
October 5, 2020
slide 55
Monitoring Principle
seabed-to-surface
private and confidential
October 5, 2020
slide 56
Roller Status
Notes: Roller fully open means the roller is fully retracted out of the way . Roller closed means
the roller is closed on the pipeline but practically a 10-15mm is left due to the pipeline out of
roundness.
It is also recommended that the second roller is closed as the FTA is being fitted up in the tower
and roller hydraulic system should be operated at full pressure.
seabed-to-surface
private and confidential
October 5, 2020
slide 57
Limiting Vessel Motions
seabed-to-surface
private and confidential
October 5, 2020
slide 58
Limiting Seastates
Location
FTA Location Limiting Limiting Limiting of Comments
Roll Pitch Maximum
Hs (m) (Deg) (Deg) Strain
In Air 2.0 2.5 2.5 FTA Strain ok at higher approx
Hs but fatigue damage
Combined 2.0 Deg should be limited due to
roll and pitch movement in tower.
Splashzone 2.0 ditto ditto FTA
Submerged 2.5 ditto ditto FTA Lowering surface to chain
connection
Chain 2.0 ditto ditto FTA Approx Seastate should be
connection to limited to Hs=2m to limit
movements prior to ROV
Suction Pile connection
Sagbend 2.0 2.0 2.3 Sagbend Including tower angle
changes
Combined 2.0deg
roll and pitch
Chain 2.0 1.5 1.5 Tower Caution must be
Pretensioning (1.0) (0.4) (1.0) excercised
Values shown in brackets
are values applicable if
pre-tension is performed
at 8deg tower angle
instead of 10deg
Final FTA 2.0 2.0 2.3 Sagbend
positioning on
seabed
seabed-to-surface
private and confidential
October 5, 2020
slide 59
Limiting Standby Duration
Barge orientated +/- 20 deg from swell direction
2 phase standby considered 1) Leave Normal Pipe payout
configuration i.e. 100mm gap at lower rollers and fatigue
damage is concentrated at upper rollers 2) close lower rollers
and fatigue point now shifts to this location and essentially the
clock is re-set.
During typical initiation certain critical long duration operations .
Values in hours not days due to stringent project requirements.
seabed-to-surface
private and confidential
October 5, 2020
slide 60
Typical Standby Durations Initiation
Minimum allowable stand-by for
PIP Step 0.01 damage in the tower
20° Swell
seabed-to-surface
private and confidential
October 5, 2020
slide 61
Polaris
Standby Decision
seabed-to-surface
private and confidential
October 5, 2020
slide 62
Operational Observations
seabed-to-surface
private and confidential
October 5, 2020
slide 63
Conclusion
seabed-to-surface
private and confidential
October 5, 2020
slide 64
Conclusion
seabed-to-surface
private and confidential
October 5, 2020
slide 65
Conclusion
seabed-to-surface
private and confidential
October 5, 2020
slide 66