CPM AND PERT
Unit-I
Introduction
project complete material man power (labour, engg)
project cost element
(i) Material cost (ii) Construction cost
Material cost structure design change construc-
tion cost material, man power resource relation
project management

Project Management Techniques:


(i) Bar chart or Gantt chart: chart time x-axis activity y-axis

a. major activity
b. project progress
c. activities proper relation
d. techniques non-repetitive projects

Example: Research & development Project


(ii) Mile Stone Diagrams:-Mile stone point minor activity complete
project progress
(iii) Linked Bar Diagram : activities link link activity
relation
(iv) Work Break Down Structure: technique project works divide

Piping

Transportation Excavation Laying of pipe line Filling

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 1 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
Bar Chart Mile Stone

Linked bar diagram

S.No. Pert CPM


1. Program evaluation & Critical path method
review technique
2. event activity
3. activity time activity singal time
estimate estimate
4. activity -distribution activity normal
follow distribution follow
5. technique probabilistic technique deterministic
approach approach
6. use non-repetitive use repetitive pr oject
project
7. project cost time time

etc.
development

Note: Stages of project management


Planning - Scheduling - Controlling

Pre project During project


(v) Network Technique: Network, activity event diagram
technique

Types of activity :

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 2 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
1. Parallel Activity : activities event
2. Serial Activity : activities serial activity
3. Successor Activity : activity activity successor activity

4. Predecessor Activity : activity activity predecessor activty

5. Dummy Activity : activity time resource


dashed arrow network grammatical logical relation-
ship

project activity 2 4 activity

Types of Event: Event, activity zero time


(i) Head Event : event activity
(ii) Tail Event : event activity start
(iii) Dual Role Event: event activity
(iv) Successor Event: event event successor event
(v) Predecessor Event: event event predecessor event

Q. Show all event & activity of following network.

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 3 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar

Event Activity Head Tail Successor Preddecessor Successor Preddessor


Event Event Event Event Activity Activ ity
A 1 X B*,C,D,E,F,G X 2*,3 *,4 *,5,6,7,8 X
­
B 2 ­ C*,D*,E *,F,G A* 5*,8 1*
­
C 3 ­ F*,G AB* 6*,8 1*
­
D 4 ­ F*,G AB* 7* 8 1*
­
E 5 ­ F*,G AB* 8* 1 2*
­
F 6 ­ G* A,B,C* ,D* ,E *, 8* 1 3*
X
G 7 X A,B,C,D,E,F* 8* 1 4*
8 X 1,2,3,4,5* ,6* ,
7 *,8 *

Serial Activity :- 1-2-5-8


1-3-6-8
1-4-7-8
Parrallel Activity: 2-3-4
* Immediate
- Dual Role
Rules to draw a network:-
(i) fulkerson's rule
(ii) activtiy event
(iii) event activity
Type of Network:

S.No. Activity on Arrow (A.O.A.) Activity on node (A.O.N)


1. activity arrow activity node

2. event node event

3. dummy use dummy

4. network change network change

5. PERT CPM CPM

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 4 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
Errors in network:
(i) Looping Error : network event error
looping error

(ii) Dangling Error : network head finished event


error dangling error

(iii) Wagon wheel Errors: network relation actual


error wagon wheel error

UNIT-II

PERT
Time estimate of activity :PERT activity time estimate
(i) Optimistic Time (to): minimum time activity complete
Ideal condition calculate
(ii) Pessemistic time (tp) maximum time activity complete
worst conditon calculate
(iii) Most likely time (tl): time activity complete
actual conditon calculate
Note :
(i) Expected time (tE) PERT network activity time estimate
network show time signal time convert
expected time

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 5 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar

tE =
6

2. Standard deviation :

Time estimate of event : PERT event time estimate


(1) Earliest Expected time (TE) minimum time event

2. Latest allowable occurance time (Tl): latest allowable time


event project schedule time effect

Slack : time period activity delay project schelude


time effect
[S=TL=TE]
Note:
(i) S=0 :- Critical activity : Project
Schedule time complete
(ii) S> 0:- Subcritical activity : -Project schedule time complete
(iii) S<0: Super critical activity :- Project schedule time complete

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 6 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
Note : Critical path : Zero slack activities path critical path
path time maximum
Q. Calculate time estimate of activity & event of a network given below and also
calculate critical path of network.

Earliest expected time :-

Event Preceding event tij TEi TE


A - - 0 0
B A B B B
C B 12 20 20
D B 14 22 22
E B 4 12 12
C 6 26
F D 8 30 30
E 10 22
G F 12 42 42

Latest allowable occurance time:

E ve nt Suc ce eding t ij t ij TL
Ev e nt
A B 8 0 0
B C 12 12
D 14 8 8
E 4 16
C F 6 24 24
D F 8 22 22
E F 10 20 20
F G 12 30 30
G - - 42 42

Critical path : A-B-D-F-G


Max. Days= 42 days

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 7 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar

Unit-III
CPM
Time estimates of activity:
1. Earliest start time (EST) : activity minimum time activity
start
Est= TEi
2. Earliest Finish time (EFT): activity minimum time activity
finish

or
3. Latest finish time (LFT) : activity latest allowable time
activity finish project schedule time effect
LFT=TLj
4. Latest Start Time (LST): activity latest allowable time
activity start project schedule time
LST= TLj-tij
or

LST

Activity times

Q. Calculate activity times of following activity.

EST = TEA= 3
EFT=TEA+tAB=3+5=8
LFT=TLB=10
LST=TLB-tAB=10-5=5

Time estimate of event

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 8 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
1. Earliest start time (EST)
2. Latest Allowable occurance time (TL)
Float: slack activity delay project schedule time

1. Total Float (FT): float time period activity schedule time


delay activity float
FT=LFT-EFT
LST-EST
2. Free Float (FF): total float activity float
FF= FT-Sj
3. Independent Float (FI): free float part activity
float
FI =FT-Sj-Si or FI=FF-S i
4. Interferring Float (FIT): succeding event slack
FIT=Sj
Note:
(i) F=0, Critical activity:- Project schedule time complete
(ii) F>0, Subcritical Activity: Project schedule time complete
(iii) F<0, Super critical activity: Project schedule time complete

Unit-IV
Cost Analysis & construction Equipment

Total Cost : Project total cost cost


(i) Direct cost: cost planning time calculate time
decrease
Example: Material cost, labour cost, equipment cost

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 9 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
(ii) Indirect Cost : cost project planning time calculate
time increase Supervision charge penalty, outage
loss, overhead charges, loss on profit.
Note; Project total cost time decrease minimum
increase

Indirect Cost Total Cost


Normal time & Normal cost : standard time project generally complete
Normal time cost normal cost
Crash time & crash cost : minimum time project complete
time cost crash cost normal cost
Crashing: Project duration crashing crashing
cost slope

Cost Slope CS

C.S.
day
Crashing
(i) network critical path
(ii) critical path activity cost slope
Study Material & Online Exams Facility available on web App.
Website:-WWW.civilianinstitutealwar.in 10 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
(iii) activity crashing cost slope minimum
(iv) Crashing critical path

Q. Calculate crash time and crash cost of following activities:


Activity Time (days) Cost
7 500
A-B 6 600
5 700
B-C 10 800
9 1000
8 1200

(A) (B) (C)


Critical Path : A-B-C

Cost slope of A-B=

Cost slope of B-C=

Normal time : 10+7= 17 days


Noram cost =- 800+500=1300
Crashing of A-B
Time 6+10= 16 days
Cost 600+800=1400 Rs.
Crashing of A-B
Time 5+10=15days
Cost 700+1800=1500 days
Crashing of B-C by 2- days
Time = 5+8=13 days
Cost = 700+800+2x200=1900 Rs
So crash time = 13 days
Crash cost = 1900 Rs.
Updating : Project rescheduling updating
Resource Allocation : project activity resource
calculate resource allocation

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 11 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
Resource Allocation

Resource Smoothening Resouce levelling


resource
project critical activity, project critical activity, Critical path
Critical path project duration project duration change
Change

Construction equipment :
(A) Transporting equipment :
(i) Tractors : load
(a) Wheel : in plain area
(b) Crawler : in muddy area
(ii) Dozer : soil excavation, transportation, ground surface
m
(iii) Scraper: same dozer blade

(B) Excavating Equipment:


(i) Power shovel /Dipper shovel : loose soil excavation
movement upward direction limited area
(ii) Back Hoe: movement downward direction Hard rocks
excavation trench, digging
(iii) Clam Shell : loose soil vertical excavation transportation

(iv) Drag Line : bucket under water excavation

(C) Compacting Equipment :


(i) Vibratory Roller : roller impact action loose grained soil
compaction
Example - Sand
(ii) Sheep footed roller: kneeding action fine
grained soil compaction
Example : Clay

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 12 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
(iii) Pneumatic Tyre Roller : kneeding impact action
limited area
Ex. = Highway, dam, compaction
(D) Lifting Equipment:
(i) Derrick Crane: building material floor floor

Study Material & Online Exams Facility available on web App.


Website:-WWW.civilianinstitutealwar.in 13 Contact No.: 9610446964
/extragyani /extragyani /extragyani

Exam Study Material

Indian Geography Click Here

Indian History Click Here

Child Development Click Here

Rajasthan GK Click Here

www.extragyani.com

You might also like