Professional Documents
Culture Documents
GK Click Here
www.extragyani.com
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
CPM AND PERT
Unit-I
Introduction
project complete material man power (labour, engg)
project cost element
(i) Material cost (ii) Construction cost
Material cost structure design change construc-
tion cost material, man power resource relation
project management
a. major activity
b. project progress
c. activities proper relation
d. techniques non-repetitive projects
Piping
etc.
development
Types of activity :
UNIT-II
PERT
Time estimate of activity :PERT activity time estimate
(i) Optimistic Time (to): minimum time activity complete
Ideal condition calculate
(ii) Pessemistic time (tp) maximum time activity complete
worst conditon calculate
(iii) Most likely time (tl): time activity complete
actual conditon calculate
Note :
(i) Expected time (tE) PERT network activity time estimate
network show time signal time convert
expected time
tE =
6
2. Standard deviation :
E ve nt Suc ce eding t ij t ij TL
Ev e nt
A B 8 0 0
B C 12 12
D 14 8 8
E 4 16
C F 6 24 24
D F 8 22 22
E F 10 20 20
F G 12 30 30
G - - 42 42
Unit-III
CPM
Time estimates of activity:
1. Earliest start time (EST) : activity minimum time activity
start
Est= TEi
2. Earliest Finish time (EFT): activity minimum time activity
finish
or
3. Latest finish time (LFT) : activity latest allowable time
activity finish project schedule time effect
LFT=TLj
4. Latest Start Time (LST): activity latest allowable time
activity start project schedule time
LST= TLj-tij
or
LST
Activity times
EST = TEA= 3
EFT=TEA+tAB=3+5=8
LFT=TLB=10
LST=TLB-tAB=10-5=5
Unit-IV
Cost Analysis & construction Equipment
Cost Slope CS
C.S.
day
Crashing
(i) network critical path
(ii) critical path activity cost slope
Study Material & Online Exams Facility available on web App.
Website:-WWW.civilianinstitutealwar.in 10 Contact No.: 9610446964
Little Birds School, Sanjay Nagar, Front of Railway Station, Alwar
(iii) activity crashing cost slope minimum
(iv) Crashing critical path
Construction equipment :
(A) Transporting equipment :
(i) Tractors : load
(a) Wheel : in plain area
(b) Crawler : in muddy area
(ii) Dozer : soil excavation, transportation, ground surface
m
(iii) Scraper: same dozer blade
www.extragyani.com