Professional Documents
Culture Documents
Project Management
1. Definition of Project
2. Project Management
4. Network Diagram
6. PERT
Definition of Project
Draw the network diagram, find the critical path and the duration along the
critical path
Example 2 - Developing a new power supply for a
console television set
A research and development department is developing a new power supply for a console
television set. It has broken down the job into the following form:
Activity Description Immediate Duration
predecessors
A Determine output voltages - 5
B Determine whether to use solid A 7
estate rectifiers
C Choose rectifiers B 2
D Choose filter B 3
E Choose transformer C 1
F Choose chassis D 2
G Choose rectifiers mounting C 1
H Layout chassis E.F. 3
I Build and test G.H. 10
Draw the critical path schedule, indicate the critical path. What is the time required for
Project Planning & Scheduling
After listing & defining of activities & establishing the relation between the
In Project Planning & Scheduling we are concerned with the following broad
objectives:
1. Estimating Project Completion time
2. Identifying Critical Path
3. Review of Project
4. Compressing Project Completion time
5. Probabilistic estimates for duration of Project
Network Analysis
The project with the list of activities, their duration & cost & their
parts:
1. Construction of Network (Network Diagram)
Tail Head
It signifies the deployment of finite resources over
a finite period of time. The tail of the arrow
signifies the commencement of the activity and
the head signifies the completion of the activity.
A
i j
tij
Tail Event Head Event
i<j
Tail event signifies commencement status of the activity.
Head Event signifies completion status of the activity
Arrow signifies deployment of finite resources over a finite period of time.
tij is the duration of the activity
Good practices of drawing a Network Diagram
vi. The numbering of events starts with the first event and progressively moves
from the left to the right of the network diagram.
vii. There is no uniqueness in the final picture of the network diagram.
Manager’s View of Critical Path Method
Inputs Outputs
(What information must be (What information results
supplied to CPM) from CPM that provides for
better project management)
1. A Complete list of
C 1. Estimated duration of
project activities P project
2. Precedence 2. Identification of critical
relationship among M activities
activities 3. Amount of Float for
3. Estimate of each each activity
activities duration
Critical Path Method
that joins the first event with the last event of the network diagram.
Critical Path Method
joins the first event with the last event of the network diagram.
To quicken the process, the activities lying on the critical path should
i j
tij
Tail Event Lj
Total Float of Activityi-j = Lj – Ei – tij
LFT EST
Total Float of Activity = (Head Event)
– (Tail Event)
– Duration of Activity
Time Estimates in Critical Path Method
Time estimates in CPM relate to estimating the time for the events
of the network diagram. Since the event signifies the status of the
project at a point of time, the time estimates in turn signify the
status of the project at different points of time.
There are two important time estimates;
(i) Earliest starting time (The earliest that an activity can start with
reference to the commencement status of the project)
(ii) Latest finishing time (The latest that an activity should finish
otherwise the project completion time will be delayed).
Guidelines for Earliest Start Time (EST)
Ei Ej
i j
tij
Tail Event Head Event
Ej = Ei + tij
EST of the head event = EST of the tail event + the duration of the activity
Slide 20
Guidelines for Earliest Start Time
(EST)
iv. Consider a merging event (in case more
than one activity is merging towards an
event).
Ea
Ed = Ea + tad
a
tad Ed = Eb + tbd
Eb Ed
tbd
b d Ed = Ec + tcd
tcd
Ec
Take the maximum value
c
Guidelines for Latest Finish Time (LFT)
i j
tij
Li Lj
Li = Lj – tij
LFT of the tail event = LFT of the head event – the duration of that activity
Slide 23
Guidelines for Latest Finish Time
(LFT)
For a bursting event (If there are more than one subsequent
activities busting from an event), calculate LFT for each of
the head events and take the minimum value
2
t12 L1 = L2 – t12
L2
t13 L1 = L3 – t13
1 3
L1 t14 L3 L1 = L4 – t14
4
Take the minimum value
L4
Time Estimates in Critical Path Method
Consider a Project situation where the indirect cost of the project is one
lakh per day. The Normal project completion time is 15 days. The
management wants to compress the project completion time by one day to
save indirect cost of 1 lakh. This compression would be feasible if the
additional direct cost required is less than 1 lakh
Crashing of Activities / Compressing Project Completion time
1. Normal Time: is the time required to complete the activity using the
2. Normal Cost: is the cost required to complete the activity in Normal Time
3. Crash Time: is the minimum time required to complete the activity using
4. Crash Cost: is the total cost which is inclusive of the normal cost & the
(known) from the past precedence of similar projects. The CPM Model was
developed by USA Navy in 1958 for Polaris Submarine Project for carrying
Nuclear war heads. There was no past precedence for this project. It was
the first of its type. Therefore, the duration of the activities were not known.
PERT: Program (Project) Evaluation & Review Technique:
Since the duration of activities in PERT are not known, they have to be estimated.
2. Normal time (t2) is the most likely time required to complete an activity assuming
normal delays (based on our past experience we estimate the likely delays &
add the equivalent time to the minimum time of the activity – most likely
scenario).
2
Estimated variance = Ve = (t3 – t1)
36
PERT: Program (Project) Evaluation & Review Technique:
diagrams, internal calculations and resulting project management reports. The minor
exceptions surround the activity time estimates. In CPM an activity’s duration is
based on single time estimate. In PERT, three time estimates are made. PERT uses
three time estimates because we are uncertain about the duration of the activities.
provided. The most likely time is our best estimate of the duration. When the duration
distribution of a path is assumed to be normal & its mean & variance have been
computed, we can make probabilistic statements about the path for e.g. there is only
a 10% probability that duration of project will be greater than 35 weeks. On the other
hand, in CPM since duration of activities is known, the project completion time is
deterministic.