Crash Table

Crash
Task
Task Name Task Cost Reduction in
Duration
Weeks
Critical task 1 3 $10,000.00 0.25
Critical task 2 3 $15,000.00 1.5
Critical task 3 2 $5,000.00 1
Critical task 4 1.5 $5,000.00 0.25
Critical task 5 4 $8,000.00 0.5
Critical task 6 2 $15,000.00 1
Critical task 7 3 $15,000.00 0.5
Critical task 8 3 $15,000.00 0.5
ash Table
Crash
Cost per Project Total Crash
Cost for
Week Duration Cost
Task
$250.00 $1,000.00 39.75 $250.00
$2,400.00 $1,600.00 38.25 $2,650.00
$1,000.00 $1,000.00 37.25 $3,650.00
$200.00 $800.00 37 $3,850.00
$300.00 $600.00 36.5 $4,150.00
$3,000.00 $3,000.00 35.5 $7,150.00
$2,000.00 $4,000.00 35 $9,150.00
$4,000.00 $8,000.00 34.5 $13,150.00