Weightage Factor for individual tasks are calculated based on billing value, as it represents a more realistic pictu
We can arrange for a free consulting session for your project team.
Created on WorkPack
% www.workpack.in
Unit Weightage Weightage Actual Work Unit Actual Effort Actual Costs
(Effort Basis) (Value Basis) Done Spent (Days)
Nos 2.21 0.18 1.00 Nos 17.00 $ 510.00
Nos 0.29 0.04 4.00 Nos 2.00 $ 90.00
Cubic M 5.15 3.03 30.00 Cubic M 28.00 $ 6,120.00
Kg 6.19 5.34 500.00 Kg 20.00 $ 6,428.57
Lit 8.84 8.90 1,000.00 Lit 9.00 $ 3,375.00
Kg 2.21 6.59 500.00 Kg 3.00 $ 3,330.00
Sq. Ft 14.73 18.16 300.00 Sq. Ft 7.00 $ 3,213.00
M 1.47 3.03 50.00 M 2.00 $ 1,530.00
Cubic M 22.09 30.62 Cubic M $ -
Sq. Ft 29.46 22.43 Sq. Ft $ -
M 1.18 0.43 M $ -
Lit 1.47 0.21 Lit $ -
Nos 0.74 0.25 Nos $ -
Nos 1.77 0.28 Nos $ -
Kg 2.21 0.53 Kg $ -
100.00 100.00 88.00 $ 24,596.57