You are on page 1of 1

LamGiang – Entech World JV Company STARCITY APARTMENTS PROJECT

Nha Be, Ho Chi Minh City


__________________________________________________________________________________________________________________

10.0 Project Design Schedule

Design stage 1 STEP 2 STEP 3 STEP TOTAL

Approval services (1/500


Master Plan, fire-fighting,
2 weeks 2 weeks 4 weeks
environmental assessment,
construction permit)

Design development 4 weeks 8 weeks 12 weeks

Construction Documents 16 weeks 16 weeks

TOTAL 6 weeks 10 weeks 16 weeks 32 weeks

_______________________________________________________________________________________________________________
Technical Proposal Report Page 35 ELTOP Architecture Vietnam Co., Ltd.
12th July 2010