Professional Documents
Culture Documents
PLASTIC BOTTLES
SUBMITTED TO:
SUBMITTED BY:
OCTOBER 3, 2022
I. Introduction
Plastic bottles are all around us. They contain everything from water to weakening entities to
household cleaners. While convenient, these bottles do have disadvantages when used on a
large scale. While most of these disadvantages are environmental, the long-term effects could
have broad economic consequences. A small place to call home is one of everyone's most
cherished aspirations and fundamental needs, right up there with food and water. Housing is
significant problem in the current period of growth. The shortage of housing is a result of
several issues, including the growing cost and decreasing availability of building supplies.
However, by enabling people to construct houses out of recycled plastic bottles, our Eco Art
Project aims to provide low-income earners with access to inexpensive and long-lasting
housing. Our initiative, Eco Art, also tries to provide affordable building materials and
2.1 Objectives
2.2 Outcomes
sponsoring and approval phase (September 17, 2022) to the present, our Eco Art
2. To build residential homes for our Eco Art Project, 191,590 used plastic bottles—or
83.30% of the total—were collected and acquired from nearby landfills in the Davao
3. Plastic bottle construction results in a total loss of 320,315 when compared to building
single-story residential dwelling (4.1 m x 4.9 m). Our Eco Art Project successfully
built 7 units in total, cutting the cost of constructing residential homes by almost
$2,242,205.
Our Eco Art Project has built a total of 7 units in Matanao, Davao Del Sur (as its target
environmentally friendly home in the following barangays: 2 units in Brgy.San Jose, 1 unit
in Brgy. Sinawilan, 1 unit in Brgy. Sinaragan, 1 unit in Brgy. Saboy and 2 units in Brgy.
Poblacion. And 2 units are still in ongoing construction: 1 unit in Brgy. San Jose and 1 unit in
The project implementation listed in the table below intends to illustrate the activities and
development of our Eco Art Project to visualize the project's goal and put the plans into
action. However, there are still two residential units that need to be built to finish the project.
To guarantee that the proposed changes at the subject site are moving forward in compliance
with the contract and agreement, our Eco Art Project team regularly (monthly) conducts
construction progress site reviews. Our staff checks the accuracy of the client's information
and assesses the project's status, construction progress, and collateral situation. To ascertain if
the necessary changes have been made and comply with the scope of work supplied by the
customer, our team assessor also makes site visits as instructed or on a pre-arranged timetable
and creates a written report. This acts as one of our assessment systems, and the outcome
Before starting the project, our Eco Art Project contractor produced a building specification
to outline and specify the materials to be utilized. However, faulty custom orders required for
the 2 remaining residential units cause delays in the building process since the crew cannot
install the material as-is, whether the material is cut wrongly or has an unanticipated problem.
And whether seen from the perspective of the owner, the contractor, or the project team,
timetable delays serve several crucial objectives in the construction industry to avoid the
requirement for a new order, our staff must return the inaccurate custom order to the supplier.
Almost all building projects will certainly involve incorrect custom orders. Even while many
alteration orders are quite legitimate, disputed and unclear charges can be very annoying. We
replenish to address this inconvenience and make sure we receive all that we require.
However, this extends the deadline for our accomplishment. To establish accountability, we
also evaluate the project requirements and a copy of the custom order that the contractor
Our Eco Art Project team decided to change the project's target completion date from
September 2022 to December 2022 due to the inconvenience that results in delays during the
construction process of residential home units. The majority of our Eco Art project team
requests a change order to modify the work required by contract documents or adjust the
amount of time the contractor has to complete the work, or both, even though delays must
already be taken into account when determining our prior target completion date. The owner
and contractor must both concur on all conditions for there to be a legitimate modification
order.
IX. Conclusion
Turn-over
Architectural
Design
Monitoring
Constructing
Site Clearing
Buying Materials
Hiring Workers
Permits
Finalizing Funds
0 1 2 3 4 5 6 7 8
The Chart in Figure 1 clarifies our status as of the given date (October 2022).
Though we have just begun this project, the status of our project finished around 85% of the
work, regardless of that, there are still tasks that need to be completed and our project
Only the delays on the custom orders present a problem. The necessary custom orders
required for the final 2 residential remaining units have finally arrived, and our project team