Statement of Work and Plan [Replace kid bathtub]

Last Revised: [09/17/2020]

[Replace Kids’ Bathtub] Statement of Work


Project Manager: Julio A. Martinez
Sponsor: Blanca Martinez

Revision History
Revision date Revised by Approved by Description of change
09/29/2020 Julio Martinez Blanca Martinez Corrected errors

Purpose and Context

The purpose of this project is to replace the bathtub/ shower from the kids’ bathroom.
My wife and I recently moved back to our home in California. The house was being
rented to another family while I was preforming military duty in Pennsylvania and Texas.
My family had been out of the house for over seven years. A month after we come back
to our house, the kids’ bathtub broke. The project will intake the removal of the existing
tub, re-piping the shower, installing a new bathtub with shower walls, and installing new
fixtures.

Phases or Timeline
Phase 1: Remove the existing water fixtures, bathtub, and shower walls. (Expected
completion time: two days.)

Phase 2: Make repairs if needed and re-pipe shower line to be raised to a height of six
and a half feet. (Expected completion time: three days.)

Phase3: Install new bathtub, shower walls, water fixtures, and frameless glass.
(Expected completion time: two days.)

MODIFIED FROM
Fast Foundation for Project Management – Statement of Work
Reference The Fast Forward MBA in Project Management
Filename: JMartinez_Small Project SOW and Plan -1 (1)
1 of 4
Statement of Work and Plan [Replace kid bathtub]
Last Revised: [09/17/2020]

Work to Be Performed
All project tasks

Task Description Who is Responsible Due Date

1. Receive quotes from contractors PM: Julio Martinez Sep 30,2020

2. Hire contractor and sign contract PM: Julio Martinez Oct 2, 2020

3. Design new bathtub and shower walls PM: Julio Martinez Oct 2, 2020

4. Select new water fixtures PM: Julio Martinez Oct 2, 2020

5. Begin demolition Contractor Oct 4, 2020

6. Re-pipe /repair Contractor Oct 7, 2020

7. Install new equipment Contractor Oct 7, 2020

8. Install frameless glass door Contractor Oct 9, 2020

9. Final work through PM/ Contractor Oct 10, 2020

Out of scope activities that are critical to the success of the project

1. Consult with an interior decorator

2. Consider contemporary designs

3. Set forth phase dates and deadlines

4. Order glass door

Deliverables & Quality Criteria

Deliverable Name Due Date Quality Criteria

Find a contractor Oct 2, 2020 Licensed and bonded

Removal of old items Oct 4, 2020 Removal of all items and trash

Re-pipe Oct 7, 2020 Re-pipe shower line to 6’6’’ in height from the floor of
bathtub

New install Oct 9, 2020 Installing of bathtub, shower walls, fixates, and final
touches

MODIFIED FROM
Fast Foundation for Project Management – Statement of Work
Reference The Fast Forward MBA in Project Management
Filename: JMartinez_Small Project SOW and Plan -1 (1)
2 of 4
Statement of Work and Plan [Replace kid bathtub]
Last Revised: [09/17/2020]

Deliverable Name Due Date Quality Criteria

Final walk through Oct 10, Demonstrate new installation is waterproof


2020

Risk Analysis

Risk Impact Mitigation Plan(s)

Uninsured contractor Poor quality of labor Check license and insurance

Newfound water Unexpected financial Add 15% to the budget


damage expenses

Existing black mold Addition cost for removal Higher mold inspector and
found of mold removal company

Measures of Success
The project will be judged complete and successful by
1. Waterproof test (passed)
2. Aesthetically pleasant
3. Staying within budget price

Stakeholder Analysis
Name & Role Major Responsibility or Contribution
Julio Martinez Oversees major decisions
Proprietary
Blanca Martinez Deals with the finances
Sponsor
Julio Martinez Oversees the projects and performs inspections
Management
Pancho’s Plumbing and Contracts and performs the labor
Remodeling
Team

MODIFIED FROM
Fast Foundation for Project Management – Statement of Work
Reference The Fast Forward MBA in Project Management
Filename: JMartinez_Small Project SOW and Plan -1 (1)
3 of 4
Statement of Work and Plan [Replace kid bathtub]
Last Revised: [09/17/2020]

Assumptions

Assumption: Professional license


Impact if assumption is incorrect: Poor quality labor
Assumption: Budget
Impact if assumption is incorrect: More expenses
Assumption: Job will be done on time
Impact if assumption is incorrect: Delay completion date
Assumption: Project will pass inspection
Impact if assumption is incorrect: More money

MODIFIED FROM
Fast Foundation for Project Management – Statement of Work
Reference The Fast Forward MBA in Project Management