August, 2022
Addis Ababa
Contents
1 Project Information .................................................................................................................... 3
2 Project location .......................................................................................................................... 3
3 Resource Utilization .................................................................................................................. 4
4 Activities performed on the site.................................................................................................. 4
5 Executed Tasks by Counterpart Engineer: .................................................................................. 5
6 Subcontractors related issues. ..................................................................................................... 5
7 Project Status ............................................................................................................................. 4
7.1 Physical performance ......................................................................................................... 4
7.2 Financial Performance........................................................................................................ 4
8 Project Management knowledge Areas ....................................................................................... 4
8.1 Construction Project Integration Management .................................................................... 4
8.2 Project Time Management.................................................................................................. 4
8.3 Project Stakeholders Management ...................................................................................... 4
8.4 Project Procurement Management ...................................................................................... 4
8.5 Project Communication Management ................................................................................. 5
8.6 Project human resource management .................................................................................. 5
8.7 Project Heavy Equipment management .............................................................................. 5
8.8 Project Finance management .............................................................................................. 5
8.9 Project Safety management ................................................................................................ 5
8.10 Project cost management .................................................................................................... 5
8.11 Construction Project quality management ........................................................................... 6
8.11.1 Inspection and Test Plan ............................................................................................. 7
Page | 1
Figure 1: Project location from Google Earth ....................................................................... 3
Figure 2: Project cost variance starting from Jan, 2022 to July, 2022 ..................................... 6
Figure 3 :Reinforcement work on second basement floor .................................................... 12
Figure 4 :Concrete casting for second basement slab ........................................................... 13
Figure 5 :Formwork fixing for vertical structure n second basement floor ........................... 13
Figure 6:Scaffolding erection for 1st basement floor ............. Error! Bookmark not defined.
Page | 2
1 Project Information
Project Name FDARA 4B+G+21 Head Quarter Office Building
2 Project location
The location of 4B+G+21 Project is at Central part of Addis Ababa Lideta sub-city in front of
National Alcohol and Liquor Factory.
Supportive staff 24 7
Equipment report
Equipment type Total number
Page | 4
5 Executed Tasks by Counterpart Engineer:
Following up of Inspections and Test plan.
Internal work inspection during each activity
Follow up of Non-conformance works
Subcontractors performance evaluation
Center of some circular columns [C-6, C-15 on shear wall, SW-12 and C-15 on SW-
7] on first basement floor has shifted due to improper reinforcement work.
Page | 5
7 Project Status
7.1 Physical performance
Physical performance of the project is 17.81 %
7.2 Financial Performance
To date financial performance of the project is 17.18%
To reduce losing sight of the integration and alignment of the intended purpose.
In our project, the procurement process is good to some extent in this month.
Page | 4
8.5 Project Communication Management
Communication management applicable to ensure information needs of stakeholders are
met, project performance is tracked on and reported on and project results are formally
documented.
Page | 5
Cost Variance comparison
35,000,000.00
30,000,000.00
25,000,000.00
20,000,000.00
15,000,000.00
10,000,000.00
5,000,000.00
-
Jan,2022 Feb, 2022 Mar, 2022 Apr,2022 May,2022 June,2022 July, 2022 Aug, 2022
Series1 31,701,376. 30,082,699.1 32,591,899. 31,406,768. 31,324,981. 27,884,602. 23,554,367. 17,924,300.
Figure 2: Project cost variance starting from Jan, 2022 to August, 2022
Page | 6
8.11.1 Inspection and Test Plan
Concrete compressive strength is conducted for vertical and horizontal structure in this
month.
Page | 7
Page | 10
Appendix
Page | 12
Figure 4 :Concrete casting for first basement slab
Figure 5: Reinforcement and Formwork fixing for vertical structure first basement floor
Page | 13
Figure 6 :Concrete casting for vertical structure on first basement floor
Page | 14