Professional Documents
Culture Documents
I. EARTHWORKS
QUANTITY: 27.14 cu.m
DURATION: 10 CD
Description of Materials Quantity Unit Unit Cost Total Cost
Excavation 27.14 cu.m - -
BACKFILL 30.27 cu.m 100 3,027.00
Gravel Bedding 2.65 cu.m 150 397.50
MANPOWER NEEDED RATE/DAY DURATION TOTAL COST
Construction Foreman 1 - - -
Skilled WORKERS 2 - - -
Laborer 6 - - -
MATERIAL COST 3,424.50
LABOR COST 1,027.35
SUB TOTAL: 4,451.85
III.MASONRY WORKS
QUANTITY: 305.39 sq.m
DURATION: 20 CD
Description of Materials Quantity Unit Unit Cost Total Cost
4" THK CHB 400.00 pcs 10 4,000.00
Portland cement 40kg 15 bags 260 3,900.00
Sand 6 cu.m 650 3,900.00
MANPOWER NEEDED RATE/DAY DURATION TOTAL COST
Construction Foreman 1 - - -
Skilled WORKERS 3 - - -
Laborer 4 - - -
MATERIAL COST 11,800.00
LABOR COST 2,360.00
SUB TOTAL: 14,160.00
VI STEEL WORKS
QUANTITY: 1.00 LOT
DURATION: 2 CD
Description of Materials Quantity Unit Unit Cost Total Cost
LUMP SUM other materials 1.00 L.S 5,000.00 5,000.00
MANPOWER NEEDED RATE/DAY DURATION TOTAL COST
Construction Foreman 1 - - -
Skilled Laborer/plumber 1 - - -
Laborer 1 - - -
MATERIAL COST 5,000.00
LABOR COST 1,000.00
SUB TOTAL: 6,000.00