You are on page 1of 1

PROJECT: PROPOSED ROMAGO OFFICE BUILDING

LOCATION: 33 CORDILLERA ST., BRGY. HIGHWAY HILLS, MANDALUYONG CITY


OWNER: MR. FRANCISCO C. GONZALEZ
SUBJECT: BILL OF MATERIALS - DEMOLITION OF EXISTING STRUCTURE

UNIT UNIT
MATERIAL LABOR
WORK ITEMS QTY UNIT MATERIAL LABOR PRICE REMARKS
COST COST
COST COST

A.) DEMOLITION OF EXISTING ROOF AND TRUSSES

1.) TOP MOST LAYER OF THE EXISTING ROOF 65.00 sqm - 160.00 - 10,400.00 10,400.00

2.) SECONDARY LAYER OF THE EXISTING ROOF 54.00 sqm - 160.00 - 8,640.00 8,640.00

3.) PRIMARY LAYER OF EXISTING ROOF & TRUSSES 192.00 sqm - 160.00 - 30,720.00 30,720.00

Subtotal 49,760.00

B.) DEMOLITION OF EXISTING WALLS AND PARTITIONS

1.) EXTERIOR WALLS 266.00 sqm - 185.00 - 49,210.00 49,210.00

2.) INTERIOR WALLS AND PARTITIONS 155.00 sqm - 185.00 - 28,675.00 28,675.00

3.) FRONT GATE 48.00 sqm - 185.00 - 8,880.00 8,880.00

Subtotal 86,765.00

C.) DEMOLITION OF MISCELLANEOUS WOODEN STRUCTURES

1.) WOODEN BEAMS/GIRDERS 1.00 lot - - - - 5,000.00

Subtotal 5,000.00

D.) DEMOLITION OF EXISTING SLAB ON GRADE

1.) EXISTING SLAB ON GRADE 300.00 sqm - 185.00 - 55,500.00 55,500.00

Subtotal 55,500.00

E.) TOOLS AND EQUIPMENTS

1.) DEMOLITION HAMMER / CHIPPING GUN WITH CONSUMABLES 2.00 set 7,500.00 - 15,000.00 - 15,000.00

2.) OXYGEN-ACETHYLENE AND CONSUMABLES 1.00 set 2,500.00 - 2,500.00 - 2,500.00

3.) WELDING MACHINE AND CONSUMABLES 1.00 set 2,500.00 - 2,500.00 - 2,500.00

4.) SCAFFOLDINGS AND ACCESSORIES 20.00 set 400.00 - 8,000.00 - 8,000.00

5.) CROW BAR 3.00 set 800.00 - 2,400.00 - 2,400.00

Subtotal 30,400.00

F.) HAUL-OUT / DISPOSAL OF DEBRIS

1.) HAUL-OUT / DISPOSAL OF DEBRIS 20.00 truck loads 2,700.00 - 54,000.00 - 54,000.00

Subtotal 54,000.00

GRAND TOTAL 281,425.00

PREPARED BY : CONFORMED BY :

ENGR. KARLO NINO M. BAJO


CIVIL ENGINEER OWNER / OWNER'S REPRESENTATIVE