Professional Documents
Culture Documents
2108Project.mpp
Page 1
2108Project.mpp
as of Sun 12/1/19
Dates
Start: Mon 3/2/20 Finish: Fri 1/29/21
Baseline Start: NA Baseline Finish: NA
Actual Start: NA Actual Finish: NA
Start Variance: 0 days Finish Variance: 0 days
Duration
Scheduled: 240 days Remaining: 240 days
Baseline: 0 days? Actual: 0 days
Variance: 240 days Percent Complete: 0%
Work
Scheduled: 27,872 hrs Remaining: 27,872 hrs
Baseline: 0 hrs Actual: 0 hrs
Variance: 27,872 hrs Percent Complete: 0%
Costs
Scheduled: $4,834,183.36 Remaining: $4,834,183.36
Baseline: $0.00 Actual: $0.00
Variance: $4,834,183.36
Page 1
ID ID Task Name Duration Start Finish Predecessors
Resource Names Mar 1, '20
S M T W T
31 31 Pour and Cure 4th Floor Slab & Columns 12 days Wed 11/25/20 Thu 12/10/20 29,30 L[600%],Co[200%]
32 32 Strip 4th Floor Formwork 4 days Fri 12/11/20 Wed 12/16/20 31 Ca[300%],L[300%]
33 33 1st Floor External and Internal Walls 6 days Fri 7/10/20 Fri 7/17/20 11 L[400%],B[600%]
34 34 2nd Floor External and Internal Walls 6 days Wed 9/2/20 Wed 9/9/20 18,33 L[400%],B[600%]
35 35 3rd Floor External and Internal Walls 6 days Mon 10/26/20 Mon 11/2/20 25,34 L[400%],B[600%]
36 36 4th Floor External and Internal Walls 6 days Thu 12/17/20 Thu 12/24/20 32,35 L[400%],B[600%]
37 37 Roof Works 18 days Thu 12/17/20 Mon 1/11/21 32 L[400%],B[600%],Co[400%]
38 38 1st Doors & Windows 6 days Mon 7/20/20 Mon 7/27/20 33 L[400%],Ca[600%]
39 39 2nd Doors & Windows 6 days Thu 9/10/20 Thu 9/17/20 34,38 L[400%],Ca[600%]
40 40 3rd Doors & Windows 6 days Tue 11/3/20 Tue 11/10/20 35,39 L[400%],Ca[600%]
41 41 4th Doors & Windows 6 days Fri 12/25/20 Fri 1/1/21 36,40 L[400%],Ca[600%]
42 42 1st Floor Indoor Decoration 12 days Tue 7/28/20 Wed 8/12/20 38 L[600%],E[300%],P[300%]
43 43 2nd Floor Indoor Decoration 12 days Fri 9/18/20 Mon 10/5/20 39,42 L[600%],E[300%],P[300%]
44 44 3rd Floor Indoor Decoration 12 days Wed 11/11/20 Thu 11/26/20 40,43 L[600%],E[300%],P[300%]
45 45 4th Floor Indoor Decoration 12 days Mon 1/4/21 Tue 1/19/21 41,44 L[600%],E[300%],P[300%]
46 46 Clean up & vacate site 6 days Wed 1/20/21 Wed 1/27/21 37,45 L[400%]
47 47 Final check 2 days Thu 1/28/21 Fri 1/29/21 46 L[300%]
Page 2
Mar 8, '20 Mar 15, '20 Mar 22, '20 Mar 29, '20 Apr 5, '20 Apr 12, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
L[400%]
L[600%],O[600%]
Page 3
Mar 8, '20 Mar 15, '20 Mar 22, '20 Mar 29, '20 Apr 5, '20 Apr 12, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Page 4
Apr 19, '20 Apr 26, '20 May 3, '20 May 10, '20 May 17, '20 May 24, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
L[600%],O[500%]
L[400%],Ca[400%],S[400%],Co[400%
S[
Page 5
Apr 19, '20 Apr 26, '20 May 3, '20 May 10, '20 May 17, '20 May 24, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Page 6
May 31, '20 Jun 7, '20 Jun 14, '20 Jun 21, '20 Jun 28, '20 Jul 5, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
],E[600%],P[600%]
500%]
Ca[600%],L[400%]
Ca[400%],L[400%]
S[400%]
E[600%],P[600%]
L[600%],Co[200%]
Page 7
May 31, '20 Jun 7, '20 Jun 14, '20 Jun 21, '20 Jun 28, '20 Jul 5, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Page 8
Jul 12, '20 Jul 19, '20 Jul 26, '20 Aug 2, '20 Aug 9, '20 Aug 16, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Ca[300%],L[300%]
S[500%]
Ca[600%],L[400%]
Ca[400%],L[400%]
S[400%]
E[600%],P[600%]
Page 9
Jul 12, '20 Jul 19, '20 Jul 26, '20 Aug 2, '20 Aug 9, '20 Aug 16, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
L[400%],B[600%]
L[400%],Ca[600%]
L[600%],E[300%],P[300%]
Page 10
Aug 23, '20 Aug 30, '20 Sep 6, '20 Sep 13, '20 Sep 20, '20 Sep 27, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
L[600%],Co[200%]
Ca[300%],L[300%]
S[500%]
Ca[600%],L[400%]
Ca[400%],L[400%]
E[
Page 11
Aug 23, '20 Aug 30, '20 Sep 6, '20 Sep 13, '20 Sep 20, '20 Sep 27, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
L[400%],B[600%]
L[400%],Ca[600%]
Page 12
Oct 4, '20 Oct 11, '20 Oct 18, '20 Oct 25, '20 Nov 1, '20 Nov 8, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
S[400%]
600%],P[600%]
L[600%],Co[200%]
Ca[300%],L[300%]
S[500%]
Ca[600%],L[400%]
Page 13
Oct 4, '20 Oct 11, '20 Oct 18, '20 Oct 25, '20 Nov 1, '20 Nov 8, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
L[400%],B[600%]
L[4
L[600%],E[300%],P[300%]
Page 14
Nov 15, '20 Nov 22, '20 Nov 29, '20 Dec 6, '20 Dec 13, '20 Dec 20, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Ca[400%],L[400%]
S[400%]
E[600%],P[600%]
Page 15
Nov 15, '20 Nov 22, '20 Nov 29, '20 Dec 6, '20 Dec 13, '20 Dec 20, '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
L[600%],Co[200%]
Ca[300%],L[300%]
400%],Ca[600%]
L[600%],E[300%],P[300%]
Page 16
Dec 27, '20 Jan 3, '21 Jan 10, '21 Jan 17, '21 Jan 24, '21 Jan 31, '21
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Page 17
Dec 27, '20 Jan 3, '21 Jan 10, '21 Jan 17, '21 Jan 24, '21 Jan 31, '21
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
L[400%],B[600%]
L[400%],B[600%],Co[400%]
L[400%],Ca[600%]
L[600%],E[300%],P[300%]
L[400%]
L[300%]
Page 18
2108Project.mpp
Mar '20 Apr '20 May '20 Jun '20
1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
1,200%
1,000%
800%
600%
400%
200%
Peak Units:
B Overallocated: Allocated:
Page 1
2108Project.mpp
Jul '20 Aug '20 Sep '20 Oct '20
21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4
1,200%
1,000%
800%
600%
400%
200%
Page 2
2108Project.mpp
Nov '20 Dec '20 Jan '21
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
1,200%
1,000%
800%
600%
400%
200%
Page 3
2108Project.mpp
Mar '20 Apr '20 May '20 Jun '20
1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
1,200%
1,000%
800%
600%
400%
200%
Peak Units: 400% 400% 400% 400% 400% 600% 600% 400%
Ca Overallocated: Allocated:
Page 1
2108Project.mpp
Jul '20 Aug '20 Sep '20 Oct '20
21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4
1,200%
1,000%
800%
600%
400%
200%
Peak Units: 300% 1,200% 1,000% 300% 300% 1,200% 1,200% 400%
Ca Overallocated: Allocated:
Page 2
2108Project.mpp
Nov '20 Dec '20 Jan '21
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
1,200%
1,000%
800%
600%
400%
200%
Peak Units: 300% 1,200% 1,000% 400% 300% 300% 600% 600%
Ca Overallocated: Allocated:
Page 3
2108Project.mpp
Mar '20 Apr '20 May '20 Jun '20
1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
600%
500%
400%
300%
200%
100%
Page 1
2108Project.mpp
Jul '20 Aug '20 Sep '20 Oct '20
21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4
600%
500%
400%
300%
200%
100%
Page 2
2108Project.mpp
Nov '20 Dec '20 Jan '21
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
600%
500%
400%
300%
200%
100%
Peak Units: 200% 200% 200% 200% 200% 400% 400% 400% 400% 400%
Co Overallocated: Allocated:
Page 3
2108Project.mpp
Mar '20 Apr '20 May '20 Jun '20
1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
900%
800%
700%
600%
500%
400%
300%
200%
100%
Page 1
2108Project.mpp
Jul '20 Aug '20 Sep '20 Oct '20
21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4
900%
800%
700%
600%
500%
400%
300%
200%
100%
Page 2
2108Project.mpp
Nov '20 Dec '20 Jan '21
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
900%
800%
700%
600%
500%
400%
300%
200%
100%
Page 3
2108Project.mpp
Mar '20 Apr '20 May '20 Jun '20
1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
1,200%
1,000%
800%
600%
400%
200%
Peak Units: 400% 600% 600% 600% 600% 600% 600% 600% 400% 400% 400% 400% 400% 400% 400% 600%
L Overallocated: Allocated:
Page 1
2108Project.mpp
Jul '20 Aug '20 Sep '20 Oct '20
21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4
1,200%
1,000%
800%
600%
400%
200%
Peak Units: 600% 600% 400% 400% 800% 1,000% 600% 1,200% 600% 600% 400% 800% 1,000% 1,000% 1,200% 1,200%
L Overallocated: Allocated:
Page 2
2108Project.mpp
Nov '20 Dec '20 Jan '21
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
1,200%
1,000%
800%
600%
400%
200%
Peak Units: 600% 600% 400% 800% 800% 600% 1,200% 600% 600% 800% 800% 800% 1,000% 1,000% 600% 400%
L Overallocated: Allocated:
Page 3
2108Project.mpp
Mar '20 Apr '20 May '20 Jun '20
1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
600%
500%
400%
300%
200%
100%
Page 1
2108Project.mpp
Jul '20 Aug '20 Sep '20 Oct '20
21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4
600%
500%
400%
300%
200%
100%
Peak Units:
O Overallocated: Allocated:
Page 2
2108Project.mpp
Nov '20 Dec '20 Jan '21
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
600%
500%
400%
300%
200%
100%
Peak Units:
O Overallocated: Allocated:
Page 3
2108Project.mpp
Mar '20 Apr '20 May '20 Jun '20
1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
900%
800%
700%
600%
500%
400%
300%
200%
100%
Page 1
2108Project.mpp
Jul '20 Aug '20 Sep '20 Oct '20
21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4
900%
800%
700%
600%
500%
400%
300%
200%
100%
Page 2
2108Project.mpp
Nov '20 Dec '20 Jan '21
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
900%
800%
700%
600%
500%
400%
300%
200%
100%
Page 3
2108Project.mpp
Mar '20 Apr '20 May '20 Jun '20
1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
600%
500%
400%
300%
200%
100%
Peak Units: 400% 400% 400% 400% 500% 500% 400% 400%
S Overallocated: Allocated:
Page 1
2108Project.mpp
Jul '20 Aug '20 Sep '20 Oct '20
21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4
600%
500%
400%
300%
200%
100%
Peak Units: 500% 500% 400% 400% 500% 500% 400% 400%
S Overallocated: Allocated:
Page 2
2108Project.mpp
Nov '20 Dec '20 Jan '21
11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
600%
500%
400%
300%
200%
100%
Page 3
2108Project.mpp
ID Resource Name Mar 8, '20
Details
M T W T F S S M T
1 L Cost $3,883.52 $3,883.52 $3,883.52 $3,883.52 $3,883.52 $3,883.52 $5,825.28
2 O Cost $7,282.08
3 Ca Cost
4 S Cost
5 Co Cost
6 E Cost
7 P Cost
8 B Cost
Page 1
2108Project.mpp
Page 2
2108Project.mpp
Page 3
2108Project.mpp
Page 4
2108Project.mpp
Page 5
2108Project.mpp
Page 6
2108Project.mpp
Page 7
2108Project.mpp
Page 8
2108Project.mpp
Page 9
2108Project.mpp
Page 10
2108Project.mpp
Page 11
2108Project.mpp
Page 12
2108Project.mpp
Page 13
2108Project.mpp
Page 14
2108Project.mpp
Page 15
2108Project.mpp
Page 16
2108Project.mpp
Page 17
2108Project.mpp
Page 18
2108Project.mpp
Page 19
2108Project.mpp
Page 20
2108Project.mpp
Page 21
2108Project.mpp
Page 22
2108Project.mpp
Page 23
2108Project.mpp
Page 24
2108Project.mpp
Page 25
2108Project.mpp
Page 26
2108Project.mpp
Page 27
2108Project.mpp
Page 28
2108Project.mpp
Page 29
2108Project.mpp
Page 30
2108Project.mpp
Page 31
2108Project.mpp
Page 32
2108Project.mpp
Page 33
2108Project.mpp
Page 34
2108Project.mpp
Page 35
2108Project.mpp
Page 36
2108Project.mpp
Page 37
2108Project.mpp
Page 38
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 1
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 2
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 3
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 4
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 5
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 6
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 7
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 8
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 9
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 10
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 11
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 12
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 13
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 14
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 15
Cash Flow as of Sun 12/1/19
2108Project.mpp
Page 16
Cash Flow as of Sun 12/1/19
2108Project.mpp
Total
Mobilisation $23,301.12
Site Grading $131,073.60
Foundation Excavation $237,873.60
Foundation $898,304.00
Install 1st Floor Column Reinforcement Bars $70,430.40
Set up 1st Floor Column Formwork $63,877.76
Set up 1st Floor Beam and Slab Formwork $71,644.80
Install 1st Floor Beam and Slab Reinforcement Bars $56,344.32
Install In-floor Utilities (E&M) for 1st Floor $62,346.24
Pour and Cure 1st Floor Columns, Beams and Slab $117,886.08
Strip 1st Floor Formwork $35,822.40
Install 2nd Floor Column Reinforcement Bars $70,430.40
Set up 2nd Floor Column Formwork $63,877.76
Set up 2nd Floor Beam and Slab Formwork $71,644.80
Install 2nd Floor Beam and Slab Reinforcement Bars $56,344.32
Install In-floor Utilities (E&M) for 2nd Floor $62,346.24
Pour and Cure 2nd Floor Slab & Columns $117,886.08
Strip 2nd Floor Formwork $35,822.40
Install 3rd Floor Column Reinforcement Bars $70,430.40
Set up 3rd Floor Column Formwork $63,877.76
Set up 3rd Floor Beam and Slab Formwork $71,644.80
Install 3rd Floor Beam and Slab Reinforcement Bars $56,344.32
Install In-floor Utilities (E&M) for 3rd Floor $62,346.24
Pour and Cure 3rd Floor Slab & Columns $117,886.08
Strip 3rd Floor Formwork $35,822.40
Install 4th Floor Column Reinforcement Bars $70,430.40
Set up 4th Floor Column Formwork $63,877.76
Set up 4th Floor Beam and Slab Formwork $54,168.96
Install c Floor Beam and Slab Reinforcement Bars $56,344.32
Install In-floor Utilities (E&M) for 4th Floor $62,346.24
Pour and Cure 4th Floor Slab & Columns $117,886.08
Strip 4th Floor Formwork $35,822.40
1st Floor External and Internal Walls $62,523.84
2nd Floor External and Internal Walls $62,523.84
3rd Floor External and Internal Walls $62,523.84
Page 17
Cash Flow as of Sun 12/1/19
2108Project.mpp
Total
4th Floor External and Internal Walls $62,523.84
Roof Works $331,519.68
1st Doors & Windows $95,816.64
2nd Doors & Windows $95,816.64
3rd Doors & Windows $95,816.64
4th Doors & Windows $95,816.64
1st Floor Indoor Decoration $163,422.72
2nd Floor Indoor Decoration $163,422.72
3rd Floor Indoor Decoration $163,422.72
4th Floor Indoor Decoration $163,422.72
Clean up & vacate site $23,301.12
Final check $5,825.28
Total $4,834,183.36
Page 18
Budget Report as of Sun 12/1/19
2108Project.mpp
ID Task Name Fixed Cost Fixed Cost Accrual Total Cost Baseline Variance Actual
Page 1
Budget Report as of Sun 12/1/19
2108Project.mpp
ID Task Name Fixed Cost Fixed Cost Accrual Total Cost Baseline Variance Actual
32 Strip 4th Floor Formwork $0.00 Prorated $35,822.40 $0.00 $35,822.40 $0.00
1 Mobilisation $0.00 Prorated $23,301.12 $0.00 $23,301.12 $0.00
46 Clean up & vacate site $0.00 Prorated $23,301.12 $0.00 $23,301.12 $0.00
47 Final check $0.00 Prorated $5,825.28 $0.00 $5,825.28 $0.00
$0.00 $4,834,183.36 $0.00 $4,834,183.36 $0.00
Page 2
Budget Report as of Sun 12/1/19
2108Project.mpp
Remaining
$898,304.00
$331,519.68
$237,873.60
$163,422.72
$163,422.72
$163,422.72
$163,422.72
$131,073.60
$117,886.08
$117,886.08
$117,886.08
$117,886.08
$95,816.64
$95,816.64
$95,816.64
$95,816.64
$71,644.80
$71,644.80
$71,644.80
$70,430.40
$70,430.40
$70,430.40
$70,430.40
$63,877.76
$63,877.76
$63,877.76
$63,877.76
$62,523.84
$62,523.84
$62,523.84
$62,523.84
$62,346.24
$62,346.24
$62,346.24
$62,346.24
$56,344.32
$56,344.32
$56,344.32
$56,344.32
$54,168.96
$35,822.40
$35,822.40
$35,822.40
Page 3
Budget Report as of Sun 12/1/19
2108Project.mpp
Remaining
$35,822.40
$23,301.12
$23,301.12
$5,825.28
$4,834,183.36
Page 4