and Fabrication of Drinking Water & Demineralised Storage Tanks  rev 2
for Desicon Groups
Proposed Schedule of Work
ID Task Name Duration Start Finish 1 Jun '20 06 Jul '20 10 Aug '20 14 Sep '20 19 Oct '20 23 Nov '20 28 Dec '2
S S M T W T F S S M T W T F S
1 Drinking Water & Demineralised Storage Tanks for Desicon Groups 135 days Wed 15/07/20 Fri 18/12/20
2 Award of contract 0 days Wed 15/07/20 Wed 15/07/20 15/07
3 Detailed Engineering 42 days Wed 15/07/20 Tue 01/09/20
4 Preparing of detailed engineering w/c calculation notes 15 days Wed 15/07/20 Fri 31/07/20
5 Review and approval of detailed engineering and calculation notes 30 days Thu 23/07/20 Wed 26/08/20
6 Preparing of shop fabrication drawings from approved detailed engineering 15 days Tue 21/07/20 Thu 06/08/20
7 Approval of shop fabrication drawing for construction 30 days Wed 29/07/20 Tue 01/09/20
8 Procurement 117 days Mon 27/07/20 Wed 09/12/20
9 Local Procurement 24 days Mon 27/07/20 Sat 22/08/20
10 Place order for steel plates and profiles 5 days Mon 27/07/20 Fri 31/07/20
11 Receipt of order raw materials in NIVAFER yard 19 days Sat 01/08/20 Sat 22/08/20
12 Place order for gratings 5 days Sat 01/08/20 Thu 06/08/20
13 Receipt of gratings in NIVAFER yard 10 days Fri 07/08/20 Tue 18/08/20
14 Overseas Procurement 85 days Wed 02/09/20 Wed 09/12/20
15 Place order for Level Indicators 10 days Wed 02/09/20 Sat 12/09/20
16 Gathering and packaging Level Indicators for shipping 5 days Mon 14/09/20 Fri 18/09/20
17 Shipping and arrival at TINCAN Lagos 50 days Sat 19/09/20 Mon 16/11/20
18 Custom cleaning and delivery to NIVAFER yard 20 days Tue 17/11/20 Wed 09/12/20
19 Quality Activities 40 days Wed 15/07/20 Sat 29/08/20
20 Preparing and submission of VMDL for approval 10 days Wed 15/07/20 Sat 25/07/20
21 Approval of VMDL 5 days Mon 27/07/20 Fri 31/07/20
22 Submission of plans and procedures as per approved VMDL 15 days Sat 01/08/20 Tue 18/08/20
23 Approval of plans and procedures 5 days Wed 19/08/20 Mon 24/08/20
24 Welder's Qualification 3 days Tue 25/08/20 Thu 27/08/20
25 NDT on Welder's Qualification 2 days Fri 28/08/20 Sat 29/08/20
26 Material Inspection and release for fabrication 2 days Mon 24/08/20 Tue 25/08/20
27 Fabrication Works 68 days Wed 02/09/20 Thu 19/11/20
28 Drinking Water Storage Tank ‐ T 4503 68 days Wed 02/09/20 Thu 19/11/20
29 Mark & Cut bottom plate 10 days Wed 02/09/20 Sat 12/09/20
30 Mark, Cut & roll/bend shell plates 15 days Mon 14/09/20 Wed 30/09/20
31 Mark & Cut roof plates 8 days Thu 01/10/20 Fri 09/10/20
32 Fabrication of roof structures with central drum 20 days Sat 10/10/20 Mon 02/11/20
33 Fabrication of stair and roof handrail 10 days Sat 10/10/20 Wed 21/10/20

Task Project Summary Manual Task Start-only Deadline

Project: Drinking Water & Dem Split Inactive Task Duration-only Finish-only Progress
Date: Wed 22/07/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
Supply and Fabrication of Drinking Water & Demineralised Storage Tanks  rev 2
for Desicon Groups
Proposed Schedule of Work
ID Task Name Duration Start Finish 1 Jun '20 06 Jul '20 10 Aug '20 14 Sep '20 19 Oct '20 23 Nov '20 28 Dec '2
S S M T W T F S S M T W T F S
34 Fabricate Manholes and Nozzles 10 days Thu 22/10/20 Mon 02/11/20
35 Blasting and Priming 15 days Tue 03/11/20 Thu 19/11/20
36 Demineralised Storage Tank ‐ T 4602 56 days Mon 14/09/20 Tue 17/11/20
37 Mark & Cut bottom plate 7 days Mon 14/09/20 Mon 21/09/20
38 Mark, Cut & roll/bend shell plates 10 days Thu 01/10/20 Mon 12/10/20
39 Mark & Cut roof plates 7 days Tue 13/10/20 Tue 20/10/20
40 Fabrication of roof structures with central drum 18 days Wed 21/10/20 Tue 10/11/20
41 Fabricate stair and roof handrail 7 days Wed 21/10/20 Wed 28/10/20
42 Fabricate Manholes and Nozzles 7 days Thu 29/10/20 Thu 05/11/20
43 Blasting and Priming 6 days Wed 11/11/20 Tue 17/11/20
44 Structural Platform, Crossbridge, etc 32 days Fri 18/09/20 Sat 24/10/20
45 Cutting activities 2 days Fri 18/09/20 Sat 19/09/20
46 Fitup activities 6 days Mon 21/09/20 Sat 26/09/20
47 Welding activities 15 days Mon 28/09/20 Wed 14/10/20
48 NDT and release for painting 3 days Thu 15/10/20 Sat 17/10/20
49 Blasting and Priming 6 days Mon 19/10/20 Sat 24/10/20
50 Gratings Fabrication 30 days Thu 01/10/20 Wed 04/11/20
51 Post Fabrication Activities 9 days Fri 20/11/20 Mon 30/11/20
52 Tagging and packaging for delivery 3 days Fri 20/11/20 Mon 23/11/20
53 Close out of fabrication work (Ex‐works delivery) 0 days Mon 23/11/20 Mon 23/11/20 23/11
54 Signing of As‐Built documentation 6 days Tue 24/11/20 Mon 30/11/20
55 OPTIONAL SCOPE 6 days Tue 01/12/20 Mon 07/12/20
56 Delivery of prefab materials to Desicon yard, Port Harcourt 6 days Tue 01/12/20 Mon 07/12/20
57 Delivery of Level Indicator 8 days Thu 10/12/20 Fri 18/12/20
58 Inspection of indicators 2 days Thu 10/12/20 Fri 11/12/20
59 Delivery to Desicon yard, Port Harcourt (Optional scope) 6 days Sat 12/12/20 Fri 18/12/20

Task Project Summary Manual Task Start-only Deadline

Project: Drinking Water & Dem Split Inactive Task Duration-only Finish-only Progress
Date: Wed 22/07/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2