NHBRC - HOUSE GOVENDER - WORK SCHEDULE

ID Task Name Duration Start Finish November 21 December 01 December 11 December 21 January 01 January 11 January 21 February 01 February 11 February 21 March 01 March 11 March 21 April 01 April 11
11/24 12/01 12/08 12/15 12/22 12/29 01/05 01/12 01/19 01/26 02/02 02/09 02/16 02/23 03/01 03/08 03/15 03/22 03/29 04/05
1 House Govender Projects 82 days Wed 19/12/11 Thu 20/04/02

2 Site Handover 0 days Fri 19/12/13 Fri 19/12/13 12/13


3 Contract Award, Contractual Start date 0 days Fri 19/12/13 Fri 19/12/13 12/13
4 Time Risk Allowance -Contractors Holiday 17 days Fri 19/12/13 Sun 20/01/05

5 CONTRACTOR's FLOAT 3 days Mon 20/01/06 Wed 20/01/08

6 Indicative Actual Completion Date for Remedial Works and Contractor 0 days Wed 20/03/11 Wed 20/03/11 03/11
7 Contractual Completion Date- Remedial Works 30 days Thu 20/01/09 Wed 20/02/19

8 House Govender - Assessment of Remedial Works 26 days Mon 20/01/06 Mon 20/02/10

9 KEY DATE - NHBRC Provides Full Access to site after Signing of Contract 0 days Mon 20/01/06 Mon 20/01/06 01/06
10 Site Handover 1 day Mon 20/01/06 Mon 20/01/06

11 Site Investigation Determine the leaks 2 days Tue 20/01/07 Wed 20/01/08

12 Hold Points - Inspection by NHBRC on Site 0 days Thu 20/01/09 Thu 20/01/09 01/09
13 Submit draft report 8 days Thu 20/01/09 Mon 20/01/20

14 Hold Points - Comments by NHBRC on draft report before final report 0 days Tue 20/01/21 Tue 20/01/21 01/21
15 Submit Final REPORT Including BOQ 15 days Tue 20/01/21 Mon 20/02/10

16 Remedial Works Contractor 38 days Tue 20/02/11 Thu 20/04/02

17 Appointment of remedial work contractor 15 days Tue 20/02/11 Mon 20/03/02

18 Site Handover to Remedial work Contractor 5 days Tue 20/03/03 Mon 20/03/09

19 Completion 15 days Tue 20/03/10 Mon 20/03/30

20 Hand over to the Home Owner 3 days Tue 20/03/31 Thu 20/04/02

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: House Govender Work
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 19/12/11
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress