ecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12, '20 May 3, '20
T W T F S S M T W T F S S M
0 DS MYANMAR PROJECT Update 69.5 days Feb 14 '20 May 2 '20
1 1 Work Shop 30 days Mar 15 '20 Apr 24 '20
2 1.1 Inner Pile Cap 16 days Mar 15 '20 Mar 30 '20
3 1.1.1 Rebar Installation 12 days Mar 15 '20 Mar 26 '20
4 1.1.2 Formwork installation 12 days Mar 16 '20 Mar 28 '20 3SS+2 days
5 1.1.3 Concrete casting 12 days Mar 18 '20 Mar 30 '20 4SS+2 days
6 1.1.4 Finished Inner Pile Cap 0 days Mar 29 '20 Mar 29 '20 5 Sun 3/29/20
7 1.2 Floor Slab 23 days Mar 21 '20 Apr 24 '20
8 1.2.1 Backfilling 8 days Mar 21 '20 Mar 29 '20 5SS+3 days
9 1.2.2 Compacting 8 days Mar 24 '20 Apr 1 '20 8SS+3 days
10 1.2.3 Lean Concrete 8 days Mar 27 '20 Apr 4 '20 9SS+3 days
11 1.2.4 Rebar Installation 10 days Mar 30 '20 Apr 20 '20 10SS+3 days
12 1.2.5 Formwork Installation 8 days Apr 2 '20 Apr 21 '20 11SS+3 days
13 1.2.6 Concrete Casting 8 days Apr 5 '20 Apr 24 '20 12SS+3 days
14 1.2.7 Finished Floor Slab 0 days Apr 24 '20 Apr 24 '20 13 Fri 4/24/20
15 2 Brick Trench B4 50 days Feb 14 '20 Apr 2 '20
16 2.1 Manhole G2 10 days Feb 14 '20 Feb 23 '20
17 2.1.1 Earth Wrok 2 days Feb 14 '20 Feb 15 '20
18 2.1.2 Lean 2 days Feb 15 '20 Feb 17 '20 17
19 2.1.3 Plain Concrete 2 days Feb 17 '20 Feb 19 '20 18
20 2.1.4 Brick work 4 days Feb 19 '20 Feb 23 '20 19
21 2.2 Trench 40 days Feb 23 '20 Apr 2 '20
22 2.2.1 Earth Wrok 2 days Feb 23 '20 Feb 25 '20 20
23 2.2.2 Lean 5 days Feb 25 '20 Mar 1 '20 22
24 2.2.3 Plain Concrete 5 days Mar 1 '20 Mar 6 '20 23
25 2.2.4 Brick work 14 days Mar 6 '20 Mar 19 '20 24
26 2.2.5 Plastering work 14 days Mar 19 '20 Apr 2 '20 25
27 2.2.6 Finished Brick Trench 0 days Apr 2 '20 Apr 2 '20 26 Thu 4/2/20
28 3 Storm Drain 9 days Mar 19 '20 Mar 28 '20
29 3.1 D800 Concrete Culvert 7 days Mar 19 '20 Mar 26 '20
30 3.1.1 D800 Concrete Pipe Laying 7 days Mar 19 '20 Mar 26 '20 25
31 3.2 D400 Concrete Culvert 2 days Mar 26 '20 Mar 28 '20
32 3.2.1 Earth Wrok 1 day Mar 26 '20 Mar 27 '20 30
33 3.2.2 D400 Concrete Pipe Laying 1 day Mar 27 '20 Mar 28 '20 32
34 3.2.3 Finished Storm Drain 0 days Mar 28 '20 Mar 28 '20 33 Sat 3/28/20
35 4 Waste Water Drain 20 days Mar 26 '20 Apr 25 '20
36 4.1 Earth Wrok 4 days Mar 26 '20 Mar 30 '20 30
37 4.2 River Shingle Laying 2 days Mar 30 '20 Apr 1 '20 36
38 4.3 Base Slab 2 days Apr 1 '20 Apr 3 '20 37
39 4.4 Wall 3 days Apr 3 '20 Apr 5 '20 38
40 4.5 Precast Slab 2 days Apr 6 '20 Apr 7 '20 39
Task Inactive Task Manual Summary Rollup External Milestone Progress
Page 1
ID Task Name Duration Start Finish Predecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12, '20 May 3, '20
T W T F S S M T W T F S S M
41 4.6 D200 PVC Pipe Laying 7 days Apr 8 '20 Apr 25 '20 40
42 4.7 Finished Waste Water Drain 0 days Apr 25 '20 Apr 25 '20 41 Sat 4/25/20
43 5 Fencing Work 64 days Feb 19 '20 May 1 '20
254 6 LPG 9 days Mar 23 '20 Mar 31 '20
255 6.1 Lean Concrete 1 day Mar 23 '20 Mar 23 '20
256 6.2 Rebar installation 2 days Mar 24 '20 Mar 25 '20 255
257 6.3 Formwork installation 2 days Mar 26 '20 Mar 27 '20 256
258 6.4 Concrete casting 4 hrs Mar 28 '20 Mar 28 '20 257
259 6.5 Floor Compaction 1.5 days Mar 28 '20 Mar 29 '20 258
260 6.6 Floor Slab rebar and formwork 1 day Mar 29 '20 Mar 30 '20 259
261 6.7 Floor Slab casting 1 day Mar 30 '20 Mar 31 '20 260
262 6.8 Finished LPG 0 days Mar 31 '20 Mar 31 '20 261 Tue 3/31/20
263 7 Gabage 11 days Mar 23 '20 Apr 2 '20
264 7.1 Earthwork Excavation 4 hrs Mar 23 '20 Mar 23 '20
265 7.2 Lean Concrete 4 hrs Mar 23 '20 Mar 23 '20 264
266 7.3 Rebar installation 1 day Mar 24 '20 Mar 24 '20 265
267 7.4 Formwork installation 1 day Mar 25 '20 Mar 25 '20 266
268 7.5 Concrete casting 4 hrs Mar 26 '20 Mar 26 '20 267
269 7.6 Floor Compaction 1.5 days Mar 26 '20 Mar 27 '20 268
270 7.7 Floor Slab rebar and formwork 1 day Mar 28 '20 Mar 28 '20 269
271 7.8 Floor Slab casting 0.5 days Mar 28 '20 Mar 29 '20 270
272 7.9 Column rebar installation 4 hrs Mar 29 '20 Mar 29 '20 271
273 7.10 Column formwork installation 4 hrs Mar 29 '20 Mar 30 '20 272
274 7.11 Column casting 4 hrs Mar 30 '20 Mar 30 '20 273
275 7.12 RB rebar installation 1 day Mar 30 '20 Mar 31 '20 274
276 7.13 RB formwork installation 1.5 days Mar 31 '20 Apr 2 '20 275
277 7.14 RB casting 0.5 days Apr 2 '20 Apr 2 '20 276
278 7.15 Finished Gabage 0 days Apr 2 '20 Apr 2 '20 277 Thu 4/2/20
279 8 Utility house 8 days Mar 23 '20 Mar 30 '20
280 8.1 Earthwork Excavation 1 day Mar 23 '20 Mar 23 '20
281 8.2 Lean Concrete 1 day Mar 24 '20 Mar 24 '20 280
282 8.3 Rebar installation 1 day Mar 25 '20 Mar 25 '20 281
283 8.4 Formwork installation 1 day Mar 26 '20 Mar 26 '20 282
284 8.5 Concrete casting 1 day Mar 27 '20 Mar 27 '20 283
285 8.6 Floor Compaction 1 day Mar 28 '20 Mar 28 '20 284
286 8.7 Floor Slab rebar and formwork 1 day Mar 28 '20 Mar 29 '20 285
287 8.8 Floor Slab casting 1 day Mar 29 '20 Mar 30 '20 286
288 8.9 Finished Utility house 0 days Mar 30 '20 Mar 30 '20 287 Mon 3/30/20
289 9 Pavement 21 days Mar 31 '20 May 2 '20
290 9.1 Subgrade preparation 10 days Mar 31 '20 Apr 21 '20 262
291 9.2 Laying Geotextile 5 days Apr 4 '20 Apr 20 '20 290SS+4 days
Task Inactive Task Manual Summary Rollup External Milestone Progress
Page 2
ID Task Name Duration Start Finish Predecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12, '20 May 3, '20
T W T F S S M T W T F S S M
292 9.3 Crushed stone compaction 6 days Apr 4 '20 Apr 21 '20 291SS
293 9.4 Laying PE sheet 5 days Apr 6 '20 Apr 22 '20 292SS+2 days
294 9.5 Rebar installation 5 days Apr 8 '20 Apr 24 '20 293SS+2 days
295 9.6 Formwork installation 10 days Apr 21 '20 May 1 '20 294SS+2 days
296 9.7 Concrete casting 10 days Apr 22 '20 May 2 '20 295SS+1 day
297 9.8 Finished Pavement 0 days May 2 '20 May 2 '20 296 Sat 5/2/20
298 10 Guard house 8 days Mar 30 '20 Apr 7 '20
299 10.1 Earthwork Excavation 1 day Mar 30 '20 Mar 31 '20 287
300 10.2 Lean Concrete 1 day Mar 31 '20 Apr 1 '20 299
301 10.3 Rebar installation 1 day Apr 1 '20 Apr 2 '20 300
302 10.4 Formwork installation 1 day Apr 2 '20 Apr 3 '20 301
303 10.5 Concrete casting 1 day Apr 3 '20 Apr 4 '20 302
304 10.6 Floor Compaction 1 day Apr 4 '20 Apr 5 '20 303
305 10.7 Floor Slab rebar and formwork 1 day Apr 5 '20 Apr 6 '20 304
306 10.8 Floor Slab casting 1 day Apr 6 '20 Apr 7 '20 305
307 10.9 Finished guard house 0 days Apr 7 '20 Apr 7 '20 306 Tue 4/7/20
308 11 Bike shed 8 days Apr 7 '20 Apr 26 '20
309 11.1 Earthwork Excavation 1 day Apr 7 '20 Apr 8 '20 307
310 11.2 Lean Concrete 1 day Apr 8 '20 Apr 20 '20 309
311 11.3 Rebar installation 1 day Apr 20 '20 Apr 21 '20 310
312 11.4 Formwork installation 1 day Apr 21 '20 Apr 22 '20 311
313 11.5 Concrete casting 1 day Apr 22 '20 Apr 23 '20 312
314 11.6 Floor Compaction 1 day Apr 23 '20 Apr 24 '20 313
315 11.7 Floor Slab rebar and formwork 1 day Apr 24 '20 Apr 25 '20 314
316 11.8 Floor Slab casting 1 day Apr 25 '20 Apr 26 '20 315
317 11.9 Finished bike shed 0 days Apr 26 '20 Apr 26 '20 316 Sun 4/26/20
318 12 Electric house 14 days Apr 2 '20 Apr 27 '20
319 12.1 Earthwork Excavation 1 day Apr 2 '20 Apr 3 '20 278
320 12.2 Lean Concrete 1 day Apr 3 '20 Apr 4 '20 319
321 12.3 Rebar installation 1 day Apr 4 '20 Apr 5 '20 320
322 12.4 Formwork installation 1 day Apr 5 '20 Apr 6 '20 321
323 12.5 Concrete casting 1 day Apr 6 '20 Apr 7 '20 322
324 12.6 Floor Compaction 1 day Apr 7 '20 Apr 8 '20 323
325 12.7 Floor Slab rebar and formwork 1 day Apr 8 '20 Apr 20 '20 324
326 12.8 Floor Slab casting 1 day Apr 20 '20 Apr 21 '20 325
327 12.9 Column rebar installation 1 day Apr 21 '20 Apr 22 '20 326
328 12.10 Column formwork installation 1 day Apr 22 '20 Apr 23 '20 327
329 12.11 Column casting 1 day Apr 23 '20 Apr 24 '20 328
330 12.12 RB rebar installation 1 day Apr 24 '20 Apr 25 '20 329
331 12.13 RB formwork installation 1 day Apr 25 '20 Apr 26 '20 330
332 12.14 RB casting 1 day Apr 26 '20 Apr 27 '20 331
Task Inactive Task Manual Summary Rollup External Milestone Progress
Page 3
ID Task Name Duration Start Finish Predecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12, '20 May 3, '20
T W T F S S M T W T F S S M
333 12.15 Finished electric house 0 days Apr 27 '20 Apr 27 '20 332 Mon 4/27/20
334 13 Tuck scale 6 days Apr 7 '20 Apr 24 '20
335 13.1 Earthwork Excavation 1 day Apr 7 '20 Apr 8 '20 307
336 13.2 Lean Concrete 1 day Apr 8 '20 Apr 20 '20 335
337 13.3 Rebar installation 2 days Apr 20 '20 Apr 22 '20 336
338 13.4 Formwork installation 1 day Apr 22 '20 Apr 23 '20 337
339 13.5 Concrete casting 1 day Apr 23 '20 Apr 24 '20 338