ID Task Name Duration Start Finish Predecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12,

ecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12, '20 May 3, '20
T W T F S S M T W T F S S M
0 DS MYANMAR PROJECT Update 69.5 days Feb 14 '20 May 2 '20
1 1 Work Shop 30 days Mar 15 '20 Apr 24 '20
2 1.1 Inner Pile Cap 16 days Mar 15 '20 Mar 30 '20
3 1.1.1 Rebar Installation 12 days Mar 15 '20 Mar 26 '20
4 1.1.2 Formwork installation 12 days Mar 16 '20 Mar 28 '20 3SS+2 days
5 1.1.3 Concrete casting 12 days Mar 18 '20 Mar 30 '20 4SS+2 days
6 1.1.4 Finished Inner Pile Cap 0 days Mar 29 '20 Mar 29 '20 5 Sun 3/29/20
7 1.2 Floor Slab 23 days Mar 21 '20 Apr 24 '20
8 1.2.1 Backfilling 8 days Mar 21 '20 Mar 29 '20 5SS+3 days
9 1.2.2 Compacting 8 days Mar 24 '20 Apr 1 '20 8SS+3 days
10 1.2.3 Lean Concrete 8 days Mar 27 '20 Apr 4 '20 9SS+3 days
11 1.2.4 Rebar Installation 10 days Mar 30 '20 Apr 20 '20 10SS+3 days
12 1.2.5 Formwork Installation 8 days Apr 2 '20 Apr 21 '20 11SS+3 days
13 1.2.6 Concrete Casting 8 days Apr 5 '20 Apr 24 '20 12SS+3 days
14 1.2.7 Finished Floor Slab 0 days Apr 24 '20 Apr 24 '20 13 Fri 4/24/20
15 2 Brick Trench B4 50 days Feb 14 '20 Apr 2 '20
16 2.1 Manhole G2 10 days Feb 14 '20 Feb 23 '20
17 2.1.1 Earth Wrok 2 days Feb 14 '20 Feb 15 '20
18 2.1.2 Lean 2 days Feb 15 '20 Feb 17 '20 17
19 2.1.3 Plain Concrete 2 days Feb 17 '20 Feb 19 '20 18
20 2.1.4 Brick work 4 days Feb 19 '20 Feb 23 '20 19
21 2.2 Trench 40 days Feb 23 '20 Apr 2 '20
22 2.2.1 Earth Wrok 2 days Feb 23 '20 Feb 25 '20 20
23 2.2.2 Lean 5 days Feb 25 '20 Mar 1 '20 22
24 2.2.3 Plain Concrete 5 days Mar 1 '20 Mar 6 '20 23
25 2.2.4 Brick work 14 days Mar 6 '20 Mar 19 '20 24
26 2.2.5 Plastering work 14 days Mar 19 '20 Apr 2 '20 25
27 2.2.6 Finished Brick Trench 0 days Apr 2 '20 Apr 2 '20 26 Thu 4/2/20
28 3 Storm Drain 9 days Mar 19 '20 Mar 28 '20
29 3.1 D800 Concrete Culvert 7 days Mar 19 '20 Mar 26 '20
30 3.1.1 D800 Concrete Pipe Laying 7 days Mar 19 '20 Mar 26 '20 25
31 3.2 D400 Concrete Culvert 2 days Mar 26 '20 Mar 28 '20
32 3.2.1 Earth Wrok 1 day Mar 26 '20 Mar 27 '20 30
33 3.2.2 D400 Concrete Pipe Laying 1 day Mar 27 '20 Mar 28 '20 32
34 3.2.3 Finished Storm Drain 0 days Mar 28 '20 Mar 28 '20 33 Sat 3/28/20
35 4 Waste Water Drain 20 days Mar 26 '20 Apr 25 '20
36 4.1  Earth Wrok 4 days Mar 26 '20 Mar 30 '20 30
37 4.2 River Shingle Laying 2 days Mar 30 '20 Apr 1 '20 36
38 4.3 Base Slab 2 days Apr 1 '20 Apr 3 '20 37
39 4.4 Wall  3 days Apr 3 '20 Apr 5 '20 38
40 4.5 Precast Slab 2 days Apr 6 '20 Apr 7 '20 39
Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: DS MYANMAR PROJEC
Milestone Inactive Summary Start-only Baseline Slippage
Date: Mar 20 '20
Summary Manual Task Finish-only Baseline Milestone

Project Summary Duration-only External Tasks Baseline Summary

Page 1
ID Task Name Duration Start Finish Predecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12, '20 May 3, '20
T W T F S S M T W T F S S M
41 4.6 D200 PVC Pipe Laying 7 days Apr 8 '20 Apr 25 '20 40
42 4.7 Finished Waste Water Drain 0 days Apr 25 '20 Apr 25 '20 41 Sat 4/25/20
43 5 Fencing Work 64 days Feb 19 '20 May 1 '20
254 6 LPG 9 days Mar 23 '20 Mar 31 '20
255 6.1 Lean Concrete 1 day Mar 23 '20 Mar 23 '20
256 6.2 Rebar installation 2 days Mar 24 '20 Mar 25 '20 255
257 6.3 Formwork installation 2 days Mar 26 '20 Mar 27 '20 256
258 6.4 Concrete casting 4 hrs Mar 28 '20 Mar 28 '20 257
259 6.5 Floor Compaction 1.5 days Mar 28 '20 Mar 29 '20 258
260 6.6 Floor Slab rebar and formwork 1 day Mar 29 '20 Mar 30 '20 259
261 6.7 Floor Slab casting 1 day Mar 30 '20 Mar 31 '20 260
262 6.8 Finished LPG 0 days Mar 31 '20 Mar 31 '20 261 Tue 3/31/20
263 7 Gabage 11 days Mar 23 '20 Apr 2 '20
264 7.1 Earthwork Excavation 4 hrs Mar 23 '20 Mar 23 '20
265 7.2 Lean Concrete 4 hrs Mar 23 '20 Mar 23 '20 264
266 7.3 Rebar installation 1 day Mar 24 '20 Mar 24 '20 265
267 7.4 Formwork installation 1 day Mar 25 '20 Mar 25 '20 266
268 7.5 Concrete casting 4 hrs Mar 26 '20 Mar 26 '20 267
269 7.6 Floor Compaction 1.5 days Mar 26 '20 Mar 27 '20 268
270 7.7 Floor Slab rebar and formwork 1 day Mar 28 '20 Mar 28 '20 269
271 7.8 Floor Slab casting 0.5 days Mar 28 '20 Mar 29 '20 270
272 7.9 Column rebar installation 4 hrs Mar 29 '20 Mar 29 '20 271
273 7.10 Column formwork installation 4 hrs Mar 29 '20 Mar 30 '20 272
274 7.11 Column casting 4 hrs Mar 30 '20 Mar 30 '20 273
275 7.12 RB rebar installation 1 day Mar 30 '20 Mar 31 '20 274
276 7.13 RB formwork installation 1.5 days Mar 31 '20 Apr 2 '20 275
277 7.14 RB casting 0.5 days Apr 2 '20 Apr 2 '20 276
278 7.15 Finished Gabage 0 days Apr 2 '20 Apr 2 '20 277 Thu 4/2/20
279 8 Utility house 8 days Mar 23 '20 Mar 30 '20
280 8.1 Earthwork Excavation 1 day Mar 23 '20 Mar 23 '20
281 8.2 Lean Concrete 1 day Mar 24 '20 Mar 24 '20 280
282 8.3 Rebar installation 1 day Mar 25 '20 Mar 25 '20 281
283 8.4 Formwork installation 1 day Mar 26 '20 Mar 26 '20 282
284 8.5 Concrete casting 1 day Mar 27 '20 Mar 27 '20 283
285 8.6 Floor Compaction 1 day Mar 28 '20 Mar 28 '20 284
286 8.7 Floor Slab rebar and formwork 1 day Mar 28 '20 Mar 29 '20 285
287 8.8 Floor Slab casting 1 day Mar 29 '20 Mar 30 '20 286
288 8.9 Finished Utility house 0 days Mar 30 '20 Mar 30 '20 287 Mon 3/30/20
289 9 Pavement 21 days Mar 31 '20 May 2 '20
290 9.1  Subgrade preparation 10 days Mar 31 '20 Apr 21 '20 262
291 9.2  Laying Geotextile 5 days Apr 4 '20 Apr 20 '20 290SS+4 days
Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: DS MYANMAR PROJEC
Milestone Inactive Summary Start-only Baseline Slippage
Date: Mar 20 '20
Summary Manual Task Finish-only Baseline Milestone

Project Summary Duration-only External Tasks Baseline Summary

Page 2
ID Task Name Duration Start Finish Predecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12, '20 May 3, '20
T W T F S S M T W T F S S M
292 9.3  Crushed stone compaction 6 days Apr 4 '20 Apr 21 '20 291SS
293 9.4  Laying PE sheet 5 days Apr 6 '20 Apr 22 '20 292SS+2 days
294 9.5  Rebar installation 5 days Apr 8 '20 Apr 24 '20 293SS+2 days
295 9.6  Formwork installation 10 days Apr 21 '20 May 1 '20 294SS+2 days
296 9.7  Concrete casting 10 days Apr 22 '20 May 2 '20 295SS+1 day
297 9.8  Finished Pavement 0 days May 2 '20 May 2 '20 296 Sat 5/2/20
298 10 Guard house 8 days Mar 30 '20 Apr 7 '20
299 10.1 Earthwork Excavation 1 day Mar 30 '20 Mar 31 '20 287
300 10.2 Lean Concrete 1 day Mar 31 '20 Apr 1 '20 299
301 10.3 Rebar installation 1 day Apr 1 '20 Apr 2 '20 300
302 10.4 Formwork installation 1 day Apr 2 '20 Apr 3 '20 301
303 10.5 Concrete casting 1 day Apr 3 '20 Apr 4 '20 302
304 10.6 Floor Compaction 1 day Apr 4 '20 Apr 5 '20 303
305 10.7 Floor Slab rebar and formwork 1 day Apr 5 '20 Apr 6 '20 304
306 10.8 Floor Slab casting 1 day Apr 6 '20 Apr 7 '20 305
307 10.9 Finished guard house 0 days Apr 7 '20 Apr 7 '20 306 Tue 4/7/20
308 11 Bike shed 8 days Apr 7 '20 Apr 26 '20
309 11.1 Earthwork Excavation 1 day Apr 7 '20 Apr 8 '20 307
310 11.2 Lean Concrete 1 day Apr 8 '20 Apr 20 '20 309
311 11.3 Rebar installation 1 day Apr 20 '20 Apr 21 '20 310
312 11.4 Formwork installation 1 day Apr 21 '20 Apr 22 '20 311
313 11.5 Concrete casting 1 day Apr 22 '20 Apr 23 '20 312
314 11.6 Floor Compaction 1 day Apr 23 '20 Apr 24 '20 313
315 11.7 Floor Slab rebar and formwork 1 day Apr 24 '20 Apr 25 '20 314
316 11.8 Floor Slab casting 1 day Apr 25 '20 Apr 26 '20 315
317 11.9 Finished bike shed 0 days Apr 26 '20 Apr 26 '20 316 Sun 4/26/20
318 12 Electric house 14 days Apr 2 '20 Apr 27 '20
319 12.1 Earthwork Excavation 1 day Apr 2 '20 Apr 3 '20 278
320 12.2 Lean Concrete 1 day Apr 3 '20 Apr 4 '20 319
321 12.3 Rebar installation 1 day Apr 4 '20 Apr 5 '20 320
322 12.4 Formwork installation 1 day Apr 5 '20 Apr 6 '20 321
323 12.5 Concrete casting 1 day Apr 6 '20 Apr 7 '20 322
324 12.6 Floor Compaction 1 day Apr 7 '20 Apr 8 '20 323
325 12.7 Floor Slab rebar and formwork 1 day Apr 8 '20 Apr 20 '20 324
326 12.8 Floor Slab casting 1 day Apr 20 '20 Apr 21 '20 325
327 12.9 Column rebar installation 1 day Apr 21 '20 Apr 22 '20 326
328 12.10 Column formwork installation 1 day Apr 22 '20 Apr 23 '20 327
329 12.11 Column casting 1 day Apr 23 '20 Apr 24 '20 328
330 12.12 RB rebar installation 1 day Apr 24 '20 Apr 25 '20 329
331 12.13 RB formwork installation 1 day Apr 25 '20 Apr 26 '20 330
332 12.14 RB casting 1 day Apr 26 '20 Apr 27 '20 331
Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: DS MYANMAR PROJEC
Milestone Inactive Summary Start-only Baseline Slippage
Date: Mar 20 '20
Summary Manual Task Finish-only Baseline Milestone

Project Summary Duration-only External Tasks Baseline Summary

Page 3
ID Task Name Duration Start Finish Predecessors Feb 9, '20 Mar 1, '20 Mar 22, '20 Apr 12, '20 May 3, '20
T W T F S S M T W T F S S M
333 12.15 Finished electric house 0 days Apr 27 '20 Apr 27 '20 332 Mon 4/27/20
334 13 Tuck scale 6 days Apr 7 '20 Apr 24 '20
335 13.1 Earthwork Excavation 1 day Apr 7 '20 Apr 8 '20 307
336 13.2 Lean Concrete 1 day Apr 8 '20 Apr 20 '20 335
337 13.3 Rebar installation 2 days Apr 20 '20 Apr 22 '20 336
338 13.4 Formwork installation 1 day Apr 22 '20 Apr 23 '20 337
339 13.5 Concrete casting 1 day Apr 23 '20 Apr 24 '20 338

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: DS MYANMAR PROJEC
Milestone Inactive Summary Start-only Baseline Slippage
Date: Mar 20 '20
Summary Manual Task Finish-only Baseline Milestone

Project Summary Duration-only External Tasks Baseline Summary