ID Task Task Name Duration Baseline Start Baseline Finish Start Finish Total Slack Predecessors

Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022
Mode D J F M A M J J A S O N D J F M A M J J A S O N D J F M
0 Building Projects in Limbang District Proposed 534 days 7/1/2020 19/12/2021 7/1/2020 17/1/2022 0 days
Upgrading of Existing Limbang District Council Depot
On Lot 541 Block 4, Pandaruan land District
Buangsiol, Limbang Division
1 1 Commencement Project 1 day 7/1/2020 7/1/2020 7/1/2020 7/1/2020 16 days
2 1.1 PRELIMINIRIES AND GENERALLY 454 days 10/1/2020 2/10/2021 10/1/2020 2/10/2021 77 days
3 1.2 DEMOLITION WORKS 57 days 29/1/2020 16/4/2020 29/1/2020 16/4/2020 0 days
4 1.2.1 Existing single storey shed 4 days 29/1/2020 3/2/2020 29/1/2020 3/2/2020 66 days
5 1.2.2 Existing single strorey buffalo slaughter 21 days 4/2/2020 3/3/2020 4/2/2020 3/3/2020 457 days 4
6 1.2.3 Existing single storey old quarters 12 days 4/3/2020 19/3/2020 4/3/2020 19/3/2020 457 days 5
7 1.2.4 Existing chainlink fencing 6 days 20/3/2020 27/3/2020 20/3/2020 27/3/2020 457 days 6
8 1.2.5 Existing ground level tank including grubbing 8 days 30/3/2020 8/4/2020 30/3/2020 8/4/2020 457 days 7
up all foundations
9 1.2.6 Existing 2 nos of manhole including grubbing 6 days 9/4/2020 16/4/2020 9/4/2020 16/4/2020 457 days 8
up all foundations
10 1.3 Site Clearing 56 days 4/2/2020 21/4/2020 4/2/2020 21/4/2020 0 days
11 1.3.1 Site Clearing at whole area 19 days 4/2/2020 28/2/2020 4/2/2020 28/2/2020 66 days 4
12 1.3.2 Site clearing after Demolization area 19 days 2/3/2020 26/3/2020 2/3/2020 26/3/2020 458 days 11
13 1.3.3 Site Clearing at Upgrading Area 18 days 27/3/2020 21/4/2020 27/3/2020 21/4/2020 458 days 12
14 1.4 New Quarters 456 days 2/3/2020 27/9/2021 2/3/2020 23/11/2021 0 days
15 1.4.1 Survey Work 4 days 2/3/2020 5/3/2020 2/3/2020 5/3/2020 66 days 11
16 1.4.2 Earth Filling to PPL 1.3m 174 days 30/9/2020 31/5/2021 30/9/2020 31/5/2021 167 days 15FS+150 days
17 1.4.3 Piling Works 9 days 8/6/2020 18/6/2020 8/6/2020 18/6/2020 0 days 15
18 1.4.3.1 Quarters A 3 days 8/6/2020 10/6/2020 8/6/2020 10/6/2020 146 days 15
19 1.4.3.2 Quarters B 3 days 11/6/2020 15/6/2020 11/6/2020 15/6/2020 146 days 18
20 1.4.3.3 Quarters C 3 days 16/6/2020 18/6/2020 16/6/2020 18/6/2020 416 days 19
21 1.4.4 Work Below Finish Floor Level 24 days 29/12/2020 29/1/2021 29/12/2020 29/1/2021 0 days
22 1.4.4.1 Quarters A 6 days 29/12/2020 5/1/2021 29/12/2020 5/1/2021 4 days 19
23 1.4.4.2 Quarters B 7 days 9/1/2021 18/1/2021 9/1/2021 18/1/2021 2 days 22
24 1.4.4.3 Quarters C 7 days 21/1/2021 29/1/2021 21/1/2021 29/1/2021 0 days 23
25 1.4.5 Frame 21 days 21/1/2021 18/2/2021 21/1/2021 18/2/2021 0 days 21
26 1.4.5.1 Quarters A 7 days 21/1/2021 29/1/2021 21/1/2021 29/1/2021 120 days 24SS
27 1.4.5.2 Quarters B 7 days 1/2/2021 9/2/2021 1/2/2021 9/2/2021 239 days 26
28 1.4.5.3 Quarters C 7 days 10/2/2021 18/2/2021 10/2/2021 18/2/2021 239 days 27
29 1.4.6 Upper Floor 23 days 1/2/2021 3/3/2021 1/2/2021 3/3/2021 0 days
30 1.4.6.1 Quarters A 7 days 1/2/2021 9/2/2021 1/2/2021 9/2/2021 120 days 26
31 1.4.6.2 Quarters B 7 days 10/2/2021 18/2/2021 10/2/2021 18/2/2021 120 days 30
32 1.4.6.3 Quarters C 7 days 19/2/2021 1/3/2021 19/2/2021 1/3/2021 120 days 31
33 1.4.7 Roof 36 days 11/5/2021 29/6/2021 11/5/2021 29/6/2021 9 days
34 1.4.7.1 Notice of Material Delivery Delay due to MCO
61 days
3.0 NA NA 24/5/2021 16/8/2021 0 days
35 1.4.7.2 Quarters A 12 days 11/5/2021 26/5/2021 17/8/2021 1/9/2021 0 days 32,34

Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: Building Projects in Lim
Milestone Inactive Summary Start-only Critical Progress
Date: 1/8/2022
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline

Page 1
ID Task Task Name Duration Baseline Start Baseline Finish Start Finish Total Slack Predecessors
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022
Mode D J F M A M J J A S O N D J F M A M J J A S O N D J F M
36 1.4.7.3 Quarters B 12 days 27/5/2021 11/6/2021 2/9/2021 17/9/2021 0 days 35
37 1.4.7.4 Quarters C 12 days 14/6/2021 29/6/2021 20/9/2021 3/10/2021 0 days 36
38 1.4.8 Wall Construction 54 days 2/3/2021 14/5/2021 2/3/2021 14/5/2021 18 days
39 1.4.8.1 Quarters A 18 days 2/3/2021 25/3/2021 2/3/2021 25/3/2021 163 days 32
40 1.4.8.2 Quarters B 18 days 26/3/2021 20/4/2021 26/3/2021 20/4/2021 163 days 39
41 1.4.8.3 Quarters C 18 days 21/4/2021 14/5/2021 21/4/2021 14/5/2021 163 days 40
42 1.4.9 Windows 23 days 6/4/2021 6/5/2021 6/4/2021 6/5/2021 0 days
43 1.4.9.1 Quarters A 5 days 6/4/2021 12/4/2021 6/4/2021 12/4/2021 192 days 39SS+7 days
44 1.4.9.2 Quarters B 5 days 19/4/2021 23/4/2021 19/4/2021 23/4/2021 188 days 43
45 1.4.9.3 Quarters C 5 days 30/4/2021 6/5/2021 30/4/2021 6/5/2021 184 days 44
46 1.4.10 Doors 15 days 17/5/2021 4/6/2021 17/5/2021 4/6/2021 163 days
47 1.4.10.1 Quarters A 5 days 17/5/2021 21/5/2021 17/5/2021 21/5/2021 163 days 41
48 1.4.10.2 Quarters B 5 days 24/5/2021 28/5/2021 24/5/2021 28/5/2021 163 days 47
49 1.4.10.3 Quarters C 5 days 31/5/2021 4/6/2021 31/5/2021 4/6/2021 163 days 48
50 1.4.11 Floor Finishes 27 days 5/6/2021 14/7/2021 2/9/2021 6/10/2021 6 days
51 1.4.11.1 Quarters A 9 days 5/6/2021 16/6/2021 2/9/2021 14/9/2021 6 days 35
52 1.4.11.2 Quarters B 9 days 21/6/2021 1/7/2021 15/9/2021 27/9/2021 6 days 51
53 1.4.11.3 Quarters C 9 days 2/7/2021 14/7/2021 28/9/2021 6/10/2021 73 days 52
54 1.4.12 Ceiling Finishes 30 days 14/7/2021 24/8/2021 4/10/2021 12/11/2021 0 days
55 1.4.12.1 Quarters A 10 days 14/7/2021 27/7/2021 4/10/2021 15/10/2021 0 days 37
56 1.4.12.2 Quarters B 10 days 28/7/2021 10/8/2021 18/10/2021 29/10/2021 0 days 55
57 1.4.12.3 Quarters C 10 days 11/8/2021 24/8/2021 1/11/2021 12/11/2021 0 days 56
58 1.4.13 Wall Finishes 30 days 22/7/2021 1/9/2021 28/9/2021 4/11/2021 6 days
59 1.4.13.1 Quarters A 10 days 22/7/2021 4/8/2021 28/9/2021 7/10/2021 6 days 52
60 1.4.13.2 Quarters B 10 days 5/8/2021 18/8/2021 8/10/2021 21/10/2021 6 days 59
61 1.4.13.3 Quarters C 10 days 19/8/2021 1/9/2021 22/10/2021 4/11/2021 6 days 60
62 1.4.14 Sanitary Fittings 13 days 31/8/2021 27/9/2021 5/11/2021 23/11/2021 0 days 58
63 1.4.14.1 Quarters A 7 days 31/8/2021 8/9/2021 15/11/2021 23/11/2021 0 days 57
64 1.4.14.2 Quarters B 7 days 9/9/2021 17/9/2021 5/11/2021 15/11/2021 6 days 60
65 1.4.14.3 Quarters C 7 days 18/9/2021 27/9/2021 5/11/2021 15/11/2021 6 days 61
66 1.5 Upgrading Works 49 days 21/9/2020 26/11/2020 21/9/2020 26/11/2020 0 days
67 1.5.1 Existing Strorage for Authority 39 days 21/9/2020 12/11/2020 21/9/2020 12/11/2020 309 days
68 1.5.2 Existing Car and Lorry Porch 10 days 13/11/2020 26/11/2020 13/11/2020 26/11/2020 299 days
69 1.6 Earthwork 76 days 17/5/2021 30/8/2021 17/5/2021 30/8/2021 0 days
101 1.7 Sewerage Works 25 days 3/5/2021 4/6/2021 3/5/2021 4/6/2021 0 days
102 1.7.1 Trench Excavation & Piling Work 4 days 3/5/2021 6/5/2021 3/5/2021 6/5/2021 184 days 9
103 1.7.2 Laying & Install 100mm dia. Sewer pipe 8 days 5/5/2021 14/5/2021 5/5/2021 14/5/2021 163 days 102SS+2 days
104 1.7.3 Construction of Brick Manhole 6 days 17/5/2021 24/5/2021 17/5/2021 24/5/2021 163 days 103
105 1.7.4 Supply & Install Septic Tank ES3 4 days 25/5/2021 28/5/2021 25/5/2021 28/5/2021 163 days 104
106 1.7.5 Testing of Sewerage System 3 days 31/5/2021 2/6/2021 31/5/2021 2/6/2021 163 days 105

Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: Building Projects in Lim
Milestone Inactive Summary Start-only Critical Progress
Date: 1/8/2022
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline

Page 2
ID Task Task Name Duration Baseline Start Baseline Finish Start Finish Total Slack Predecessors
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Half 1, 2022
Mode D J F M A M J J A S O N D J F M A M J J A S O N D J F M
107 1.7.6 Backfilled 2 days 3/6/2021 4/6/2021 3/6/2021 4/6/2021 163 days 106
108 1.8 Water reticulation 23 days 5/7/2021 4/8/2021 5/7/2021 4/8/2021 0 days
109 1.8.1 Trench Excavation 4 days 5/7/2021 8/7/2021 5/7/2021 8/7/2021 58 days
110 1.8.2 Laying 160mm dia HDPE PN 12.5 pipe 10 days 9/7/2021 22/7/2021 9/7/2021 22/7/2021 58 days 109
111 1.8.3 Installation of Sluive Valve with Chamber 3 days 23/7/2021 27/7/2021 23/7/2021 27/7/2021 120 days 110
112 1.8.4 Installation 100mm dia. Pillar Hydrant 3 days 28/7/2021 30/7/2021 28/7/2021 30/7/2021 120 days 111
complete with Chamber
113 1.8.5 Connectiong to existing Water Meter 2 days 2/8/2021 3/8/2021 2/8/2021 3/8/2021 120 days 112
114 1.8.6 Testing & Commissioning 1 day 4/8/2021 4/8/2021 4/8/2021 4/8/2021 120 days 113
115 1.9 Fencing and Gate Works 22 days 4/8/2021 2/9/2021 4/8/2021 2/9/2021 0 days
116 1.9.1 Piling Works 7 days 4/8/2021 12/8/2021 4/8/2021 12/8/2021 89 days 100
117 1.9.2 Fencing and Gates 15 days 13/8/2021 2/9/2021 13/8/2021 2/9/2021 89 days 116
118 1.10 Turfing 10 days 3/9/2021 16/9/2021 3/9/2021 16/9/2021 89 days 117
119 1.11 Electrical Services 47 days 30/6/2021 2/9/2021 30/6/2021 2/9/2021 81 days
120 1.11.1 Laying the submain cable from sesco meter 12 days 30/6/2021 15/7/2021 30/6/2021 15/7/2021 81 days 33
cabinet to DB
121 1.11.2 Final sub circuit for lighting, fan and power point
12 days 16/7/2021 2/8/2021 16/7/2021 2/8/2021 81 days 120
122 1.11.3 To supply and installed sesco meter cabinet 10 days 3/8/2021 16/8/2021 3/8/2021 16/8/2021 81 days 121
and distribution board.
123 1.11.4 To supply and installed all the fan and lighting 13
fittings
days 17/8/2021 2/9/2021 17/8/2021 2/9/2021 99 days 122
124 1.12 Mechanical Services 81 days 23/7/2021 27/10/2021 23/7/2021 10/11/2021 48 days
125 1.12.1 Fire Fighting Extinguisher 4 days 11/10/2021 14/10/2021 5/11/2021 10/11/2021 48 days
126 1.12.1.1 portable fire extinguisher 4 days 11/10/2021 14/10/2021 5/11/2021 10/11/2021 48 days 58
127 1.12.2 Cold Water Services 71 days 23/7/2021 27/10/2021 23/7/2021 27/10/2021 58 days
128 1.12.2.1 Tapping off cold water pipe from 12 days 23/7/2021 9/8/2021 23/7/2021 9/8/2021 58 days 110
external hydrant pipe to water tap and all the
129 quarters.
1.12.2.2 Supply and install 150 gallon HDPE roof tank5 days 10/8/2021 16/8/2021 10/8/2021 16/8/2021 58 days 128
130 1.12.2.3 HDPE pipe works 14 days 17/8/2021 3/9/2021 17/8/2021 3/9/2021 58 days 129
131 1.12.2.4 Sanitary Plumbing Services 10 days 14/10/2021 27/10/2021 14/10/2021 27/10/2021 58 days
132 1.12.2.4.1 UPVC, Soil, waste and vent pipe to 10 days 14/10/2021 27/10/2021 14/10/2021 27/10/2021 58 days 130FS+30
all sanitary wares. days
133 2 Completion Project 74 days 6/10/2021 19/12/2021 6/10/2021 17/1/2022 0 days
134 2.1 SESCO Energize 4 days 6/10/2021 11/10/2021 6/10/2021 11/10/2021 69 days
135 2.2 LAKU Management & Bomba Inspection and Testing30 days 27/10/2021 7/12/2021 24/11/2021 4/1/2022 0 days 63,64,65
136 2.3 Overal T&C (inclusive Infra M&E Works) 30 days 28/10/2021 8/12/2021 24/11/2021 4/1/2022 8 days 122,63,64,65
137 2.4 Demobilization 8 days 9/12/2021 18/12/2021 5/1/2022 14/1/2022 0 days 135
138 2.5 Handling Over Project 1 day 19/12/2021 19/12/2021 17/1/2022 17/1/2022 0 days 137,134,135,136

Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: Building Projects in Lim
Milestone Inactive Summary Start-only Critical Progress
Date: 1/8/2022
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline