TUGAS BESAR I

PERENCANAAN PENGENDALIAN PROYEK

Dosen :
Ali Sunandar, S.ST, MT

Disusun oleh :
Indra Subagja
NIM : 41117320032

Fakultas Teknik
Jurusan Teknik Sipil
2019/2020
TABEL PERHITUNGAN FLOAT/SLACK
Early Late Slack
NO Task Name Duration Predecessors
Early Start Early Finish Late Start Late Finish Free Indepd Total
1 Project Jalan Baru 97 days 4/8/2020 0 7/14/2020 97 4/8/2020 0 7/14/2020 97 0 0 0
2 Kuari 35 days 4/8/2020 0 5/13/2020 35 4/8/2020 0 7/14/2020 97 0 0 62
3 Install Stone Crusher 30 days 4/8/2020 0 5/8/2020 30 4/8/2020 0 5/8/2020 30 0 0 0
4 Install AMP (Aspalt Mixing Plant) 12 days 3FS-10 days 4/28/2020 20 5/10/2020 32 4/28/2020 20 5/10/2020 32 0 0 0
5 Install Cool Bin 7 days 4/28/2020 20 5/5/2020 27 5/3/2020 25 5/10/2020 32 0 -5 5
6 Install Dust Collector 12 days 4/28/2020 20 5/10/2020 32 4/28/2020 20 5/10/2020 32 0 0 0
7 Install Hot Screen 11 days 4/28/2020 20 5/9/2020 31 4/29/2020 21 5/10/2020 32 0 -1 1
8 Install Timbangan 11 days 4/28/2020 20 5/9/2020 31 4/29/2020 21 5/10/2020 32 0 -1 1
9 Install Mixer 7 days 4/28/2020 20 5/5/2020 27 5/3/2020 25 5/10/2020 32 0 -5 5
10 Mixing Agregat 2 days 3FS+1 day 5/11/2020 33 5/13/2020 35 7/12/2020 95 7/14/2020 97 0 -62 62
11 Mixing Aspalt 2 days 4FS+1 day 5/11/2020 33 5/13/2020 35 7/12/2020 95 7/14/2020 97 0 -62 62
12 Konturksi Jalan 71 days 5/3/2020 25 7/13/2020 96 5/3/2020 25 7/14/2020 97 0 0 1
13 STA 1+000 70 days 5/3/2020 25 7/12/2020 95 5/3/2020 25 7/14/2020 97 0 0 2
14 Existing Jalan 7 days 4FS-1 wk 5/3/2020 25 5/10/2020 32 5/3/2020 25 5/10/2020 32 0 0 0
15 Galian& Timbunan 10 days 14SS 5/3/2020 25 5/13/2020 35 5/3/2020 25 5/13/2020 35 0 0 0
16 Pengamparan Agregat B 5 days 15 5/13/2020 35 5/18/2020 40 5/13/2020 35 5/18/2020 40 0 0 0
17 Pengamparan Agregat A 3 days 16FS+1 day 5/19/2020 41 5/22/2020 44 5/19/2020 41 5/22/2020 44 0 0 0
18 Bahu Jalan 7 days 17 5/22/2020 44 5/29/2020 51 5/22/2020 44 5/29/2020 51 0 0 0
19 Primecoat 2 days 21SS-1 hr 6/24/2020 77 6/26/2020 79 7/12/2020 95 7/14/2020 97 0 -18 18
20 Takecoat 1 day 22SS-1 hr 7/1/2020 84 7/2/2020 85 7/13/2020 96 7/14/2020 97 0 -12 12
Pengamparan Aspal - Binder
21 3 days 30 6/24/2020 77 6/27/2020 80 6/24/2020 77 6/27/2020 80 0 0 0
Course
Pengamparan Aspal - Wearing
22 2 days 33FS+1 day 7/1/2020 84 7/3/2020 86 7/1/2020 84 7/3/2020 86 0 0 0
Course
23 Gorong Gorong 7 days 22FS+2 day 7/5/2020 88 7/12/2020 95 7/7/2020 90 7/14/2020 97 0 -2 2
24 Pasang Batu Penahan Dinding 5 days 23SS 7/5/2020 88 7/10/2020 93 7/9/2020 92 7/14/2020 97 0 -4 4
25 STA 2+000 64 days 5/10/2020 32 7/13/2020 96 5/29/2020 51 7/14/2020 97 0 -19 1
26 Existing Jalan 7 days 14 5/10/2020 32 5/17/2020 39 6/11/2020 64 6/18/2020 71 0 -32 32
27 Galian& Timbunan 10 days 18 5/29/2020 51 6/8/2020 61 5/29/2020 51 6/8/2020 61 0 0 0
28 Pengamparan Agregat B 5 days 27 6/8/2020 61 6/13/2020 66 6/8/2020 61 6/13/2020 66 0 0 0
29 Pengamparan Agregat A 3 days 28FS+1 day 6/14/2020 67 6/17/2020 70 6/14/2020 67 6/17/2020 70 0 0 0
30 Bahu Jalan 7 days 29 6/17/2020 70 6/24/2020 77 6/17/2020 70 6/24/2020 77 0 0 0
31 Primecoat 2 days 33SS-1 hr 6/27/2020 80 6/29/2020 82 7/12/2020 95 7/14/2020 97 0 -15 15
32 Takecoat 1 day 34SS-1 hr 7/3/2020 86 7/4/2020 87 7/13/2020 96 7/14/2020 97 0 -10 10
Pengamparan Aspal - Binder
33 3 days 21 6/27/2020 80 6/30/2020 83 6/27/2020 80 6/30/2020 83 0 0 0
Course
Pengamparan Aspal - Wearing
34 2 days 22 7/3/2020 86 7/5/2020 88 7/3/2020 86 7/5/2020 88 0 0 0
Course
35 Gorong Gorong 5 days 34FS+2 day 7/7/2020 90 7/12/2020 95 7/8/2020 91 7/13/2020 96 0 -1 1
36 Pasang Batu Penahan Dinding 6 days 35SS 7/7/2020 90 7/13/2020 96 7/8/2020 91 7/14/2020 97 0 -1 1
37 Kontruksi Jembatan 52 days 5/17/2020 39 7/8/2020 91 6/18/2020 71 7/14/2020 97 0 -32 6
38 Pondasi Spoon pile 6 days 5/17/2020 39 5/23/2020 45 6/18/2020 71 7/14/2020 97 0 -32 52
39 Bor 2 days 26 5/17/2020 39 5/19/2020 41 6/18/2020 71 6/20/2020 73 0 -32 32
40 Pembesian 3 days 39SS+1 day 5/18/2020 40 5/21/2020 43 6/19/2020 72 6/22/2020 75 0 -32 32
41 Pembuatan Beksiting 2 days 40SS 5/18/2020 40 5/20/2020 42 7/12/2020 95 7/14/2020 97 0 -55 55
42 Pengecoran 1 day 40FS+1 day 5/22/2020 44 5/23/2020 45 6/23/2020 76 6/24/2020 77 0 -32 32
43 Sheet Pile 4 days 5/24/2020 46 5/28/2020 50 6/25/2020 78 7/14/2020 97 0 -32 47
44 Pembesian 3 days 42FS+1 day 5/24/2020 46 5/27/2020 49 6/25/2020 78 6/28/2020 81 0 -32 32
45 Pembuatan Beksiting 2 days 44SS 5/24/2020 46 5/26/2020 48 7/12/2020 95 7/14/2020 97 0 -49 49
46 Pengecoran 1 day 44 5/27/2020 49 5/28/2020 50 6/28/2020 81 6/29/2020 82 0 -32 32
47 Abutment 4 days 5/29/2020 51 6/2/2020 55 6/30/2020 83 7/14/2020 97 0 -32 42
48 Pembesian 3 days 46FS+1 day 5/29/2020 51 6/1/2020 54 6/30/2020 83 7/3/2020 86 0 -32 32
49 Pembuatan Beksiting 2 days 48SS 5/29/2020 51 5/31/2020 53 7/12/2020 95 7/14/2020 97 0 -44 44
50 Pengecoran 1 day 48 6/1/2020 54 6/2/2020 55 7/3/2020 86 7/4/2020 87 0 -32 32
51 Kolom 4 days 6/3/2020 56 6/7/2020 60 7/5/2020 88 7/14/2020 97 0 -32 37
52 Pembesian 3 days 50FS+1 day 6/3/2020 56 6/6/2020 59 7/5/2020 88 7/8/2020 91 0 -32 32
53 Pembuatan Beksiting 2 days 52SS 6/3/2020 56 6/5/2020 58 7/12/2020 95 7/14/2020 97 0 -39 39
54 Pengecoran 1 day 52 6/6/2020 59 6/7/2020 60 7/8/2020 91 7/9/2020 92 0 -32 32
55 Girder 1 day 6/11/2020 64 6/12/2020 65 7/13/2020 96 7/14/2020 97 0 -32 32
56 Erection Girder 1 day 54FS+4 days 6/11/2020 64 6/12/2020 65 7/13/2020 96 7/14/2020 97 0 -32 32
57 Expantion Joint 1 day 34FF 7/4/2020 87 7/5/2020 88 7/13/2020 96 7/14/2020 97 0 -9 9
58 Railling 2 days 34FS+1 day 7/6/2020 89 7/8/2020 91 7/12/2020 95 7/14/2020 97 0 -6 6
59 Finishing 11 days 7/3/2020 86 7/14/2020 97 7/6/2020 89 7/14/2020 97 0 -3 0
60 STA 1+000 4 days 7/6/2020 89 7/10/2020 93 7/6/2020 89 7/13/2020 96 0 0 3
61 Trotoar 4 days 34FS+1 day 7/6/2020 89 7/10/2020 93 7/6/2020 89 7/10/2020 93 0 0 0
62 Marka Jalan 2 days 61SS+1 day 7/7/2020 90 7/9/2020 92 7/10/2020 93 7/12/2020 95 0 -3 3
63 Pemasangan Rambu 1 day 62SS 7/7/2020 90 7/8/2020 91 7/12/2020 95 7/13/2020 96 0 -5 5
64 STA 2+000 6 days 7/8/2020 91 7/14/2020 97 7/10/2020 93 7/14/2020 97 0 -2 0
65 Trotoar 4 days 61 7/10/2020 93 7/14/2020 97 7/10/2020 93 7/14/2020 97 0 0 0
66 Marka Jalan 2 days 62 7/9/2020 92 7/11/2020 94 7/12/2020 95 7/14/2020 97 0 -3 3
67 Pemasangan Rambu 1 day 63 7/8/2020 91 7/9/2020 92 7/13/2020 96 7/14/2020 97 0 -5 5
68 Mobilisasi Alat Berat 2 days 34FF 7/3/2020 86 7/5/2020 88 7/12/2020 95 7/14/2020 97 0 -9 9
PDM METHOD
Tugas Besar 1 (Indra Subagja 41117320032)

0 0 97 0 0 12
Project Jalan Baru 1 Install AMP (Aspalt Mixing Plant) 4
0 0 20 20
97 97 32 32

0 2 70 0 0 7 0 0 10 0 0 5 0 0 3 0 0 7
STA 1+000 13 Existing Jalan 14 Galian& Timbunan 15 Pengamparan Agregat B 16 Pengamparan Agregat A 17 Bahu Jalan 18
25 25 25 25 25 25 35 35 41 41 44 44
95 97 32 32 35 35 40 40 44 44 51 51

0 1 64 0 0 10 0 0 5 0 0 3 0 0 7
STA 2+000 25 Galian& Timbunan 27 Pengamparan Agregat B 28 Pengamparan Agregat A 29 Bahu Jalan 30
32 51 51 51 61 61 67 67 70 70
96 97 61 61 66 66 70 70 77 77

0 32 7 0 0 3 0 0 3 0 0 2 0 0 2
Existing Jalan 26 Pengamparan Aspal - Binder Course
21 Pengamparan Aspal - Binder Course
33 Pengamparan Aspal - Wearing Course
22 Pengamparan Aspal - Wearing Course
34
32 64 77 77 80 80 84 84 86 86
39 71 80 80 83 83 86 86 88 88

0 0 4 0 0 4
Trotoar 61 Trotoar 65
89 89 93 93
93 93 97 97

0 52 6 0 47 4 0 42 4 0 37 4 0 32 1
Pondasi Spoon pile 38 Sheet Pile 43 Abutment 47 Kolom 51 Girder 55
39 71 46 78 51 83 56 88 64 96
45 97 50 97 55 97 60 97 65 97

FF Simple formula to calculate Free Float is ES (of successor) – EF of current activity


TF Simple formula to calculate total float is our usual formula i.e. LS (Late Start) – ES (Early Start) or LF (Late, Finish) – EF (Early Finish)

Forward Pass Calculate Early Dates hence the Free Float & FF TF DUR
Total Duration of the Project As longest Path ACTIVITY NAME No
ES EF
Backword Pass Calculates the Late Dates hence the Total Floats LS LF
& Critical Path of the Project
CPM METHOD
Tugas Besar 1 (Indra Subagja 41117320032)

4
0 12
0 1
0 12 12
14 15 16 17 18 27 28
19 10 5 3 7 10 5
1 1 1 1 1 1 1
7 19 10 10 5 5 3 3 7 7 10 10 5 5

29 30 21
3 7 3
1 1 1
3 3 7 7 3 3 33
6
2
3 6 22
8
3
2 8 34
10
4
2 10 61
14
5
4 14 65
18
6
4 18

26 38 43 47 51 55
7 6 4 4 4 1
1 1 1 1 1 1
7 7 6 6 4 4 4 4 4 4 1 1

Legend : No Table
EF
No
D LF
ID Task Mode Task Name Duration Start Finish Apr '20 May '20 Jun '20 Jul '20
22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19
1 Project Jalan Baru 97 days 4/8/2020 7/14/2020
2 Kuari 35 days 4/8/2020 5/13/2020
3 Install Stone Crusher 30 days 4/8/2020 5/8/2020
4 Install AMP (Aspalt Mixing Plant)
12 days 4/28/2020 5/10/2020
5 Install Cool Bin 7 days 4/28/2020 5/5/2020
6 Install Dust Collector 12 days 4/28/2020 5/10/2020
7 Install Hot Screen 11 days 4/28/2020 5/9/2020
8 Install Timbangan 11 days 4/28/2020 5/9/2020
9 Install Mixer 7 days 4/28/2020 5/5/2020
10 Mixing Agregat 2 days 5/11/2020 5/13/2020
11 Mixing Aspalt 2 days 5/11/2020 5/13/2020
12 Konturksi Jalan 71 days 5/3/2020 7/13/2020
13 STA 1+000 70 days 5/3/2020 7/12/2020
14 Existing Jalan 7 days 5/3/2020 5/10/2020
15 Galian& Timbunan 10 days 5/3/2020 5/13/2020
16 Pengamparan Agregat B 5 days 5/13/2020 5/18/2020
17 Pengamparan Agregat A 3 days 5/19/2020 5/22/2020
18 Bahu Jalan 7 days 5/22/2020 5/29/2020
19 Primecoat 2 days 6/24/2020 6/26/2020
20 Takecoat 1 day 7/1/2020 7/2/2020
21 Pengamparan Aspal - 3 days 6/24/2020 6/27/2020
Binder Course
22 Pengamparan Aspal - 2 days 7/1/2020 7/3/2020
Wearing Course
23 Gorong Gorong 7 days 7/5/2020 7/12/2020
24 Pasang Batu Penahan Dinding
5 days 7/5/2020 7/10/2020
25 STA 2+000 64 days 5/10/2020 7/13/2020
26 Existing Jalan 7 days 5/10/2020 5/17/2020
27 Galian& Timbunan 10 days 5/29/2020 6/8/2020
28 Pengamparan Agregat B 5 days 6/8/2020 6/13/2020
Project: Perencanaan Jalan Baru Critical Split Summary Critical
Date: 4/9/2020 Task Project Summary

Page 1
ID Task Mode Task Name Duration Start Finish Apr '20 May '20 Jun '20 Jul '20
22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19
29 Pengamparan Agregat A 3 days 6/14/2020 6/17/2020
30 Bahu Jalan 7 days 6/17/2020 6/24/2020
31 Primecoat 2 days 6/27/2020 6/29/2020
32 Takecoat 1 day 7/3/2020 7/4/2020
33 Pengamparan Aspal - 3 days 6/27/2020 6/30/2020
Binder Course
34 Pengamparan Aspal - 2 days 7/3/2020 7/5/2020
Wearing Course
35 Gorong Gorong 5 days 7/7/2020 7/12/2020
36 Pasang Batu Penahan Dinding
6 days 7/7/2020 7/13/2020
37 Kontruksi Jembatan 52 days 5/17/2020 7/8/2020
38 Pondasi Spoon pile 6 days 5/17/2020 5/23/2020
39 Bor 2 days 5/17/2020 5/19/2020
40 Pembesian 3 days 5/18/2020 5/21/2020
41 Pembuatan Beksiting 2 days 5/18/2020 5/20/2020
42 Pengecoran 1 day 5/22/2020 5/23/2020
43 Sheet Pile 4 days 5/24/2020 5/28/2020
44 Pembesian 3 days 5/24/2020 5/27/2020
45 Pembuatan Beksiting 2 days 5/24/2020 5/26/2020
46 Pengecoran 1 day 5/27/2020 5/28/2020
47 Abutment 4 days 5/29/2020 6/2/2020
48 Pembesian 3 days 5/29/2020 6/1/2020
49 Pembuatan Beksiting 2 days 5/29/2020 5/31/2020
50 Pengecoran 1 day 6/1/2020 6/2/2020
51 Kolom 4 days 6/3/2020 6/7/2020
52 Pembesian 3 days 6/3/2020 6/6/2020
53 Pembuatan Beksiting 2 days 6/3/2020 6/5/2020
54 Pengecoran 1 day 6/6/2020 6/7/2020
55 Girder 1 day 6/11/2020 6/12/2020
56 Erection Girder 1 day 6/11/2020 6/12/2020
Project: Perencanaan Jalan Baru Critical Split Summary Critical
Date: 4/9/2020 Task Project Summary

Page 2
ID Task Mode Task Name Duration Start Finish Apr '20 May '20 Jun '20 Jul '20
22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19
57 Expantion Joint 1 day 7/4/2020 7/5/2020
58 Railling 2 days 7/6/2020 7/8/2020
59 Finishing 11 days 7/3/2020 7/14/2020
60 STA 1+000 4 days 7/6/2020 7/10/2020
61 Trotoar 4 days 7/6/2020 7/10/2020
62 Marka Jalan 2 days 7/7/2020 7/9/2020
63 Pemasangan Rambu 1 day 7/7/2020 7/8/2020
64 STA 2+000 6 days 7/8/2020 7/14/2020
65 Trotoar 4 days 7/10/2020 7/14/2020
66 Marka Jalan 2 days 7/9/2020 7/11/2020
67 Pemasangan Rambu 1 day 7/8/2020 7/9/2020
68 Mobilisasi Alat Berat 2 days 7/3/2020 7/5/2020

Project: Perencanaan Jalan Baru Critical Split Summary Critical


Date: 4/9/2020 Task Project Summary

Page 3