ID Task Name DurationStart Finish Jul '20 Aug '20 Sep '20

S 14/06 S 21/06 S 28/06 S 05/07 S 12/07 S 19/07 S 26/07 S 02/08 S 09/08 S 16/08 S 23/08 S 30/08 S 06/09
0 JADWAL PEKERJAAN DECK 85 19 11
SLAB, BRIDGE PARAPET DAN days June September
ASHPALT 2020 2020
1 DN LINE 56 days19 June 13
2020
August 2020
2 PEKERJAAN PERSIAPAN 1 day 19 June 192020
June 2020
3 Mobilisasi & Demobilisasi 1 day 19 June 192020
June 2020
4 Pemasangan support safety 3 days 19 June 21 June
net di atas tol Sumo 2020 2020
5 Pasang Scaffolding gantung 6 2 days 22 June 23 June
titik & pasang jaring 2020 2020
6 PEKERJAAN BETON 39 days20 June 28
2020
July 2020
7 Beton Struktur kelas B ( 13 06 July 18 July
Deck Slab ) days 2020 2020
8 Pengecoran Tahap 1 1 day 06 July 2020
06 July 2020
9 Pengecoran Tahap 2 1 day 12 July 2020
12 July 2020
10 Pengecoran Tahap 3 1 day 18 July 2020
18 July 2020
11 Beton Struktur kelas B ( 3 days 26 July 28 July
Parapet ) 2020 2020
12 Floor deck Slab 9 days 20 June 28
2020
June 2020
13 Antar girder 5 days 20 June 24
2020
June 2020
14 Dalam Girder 4 days 25 June 28
2020
June 2020
15 Kantilever 5 days 20 June 24
2020
June 2020
16 Bongkar bekisting kantilever6 days 19 July 2020
24 July 2020
17 Baja tulangan Ulir ( Deck 7 days 25 01 July
Slab & Parapet ) June 2020
18 Pembesian Slab 7 days 25 June 01
2020
July 2020
19 Pembesian Parapet 7 days 19 July 2020
25 July 2020
20 Pipa Utilitas dia. 4 " kelas 6 days 19 July 24 July
AW 2020 2020
21 PEKERJAAN ASPHALT ( 2 days 12 13
L=167,5 m. W=2x15,15 m ) August August
22 Bitumen Lapis pengikat ( 1 day 12 12
Tack Coat) August August
23 Asphalt Concrete wearing 1 day 13 13
course August August
24 PEKERJAAN DRAINASE 27 02 July 28 July
days 2020 2020
25 Box Deckdrain tipe 1 4 days 02 July 2020
05 July 2020
26 Pipa PVC 6 " Vertikal & 4 days 25 July 28 July
Horizontal 2020 2020
27
28 UP LINE 85 19 11
days June September
29 Pemasangan support safety 3 days 19 June 21 June
net di atas tol Sumo 2020 2020
30 Pasang Scaffolding gantung 6 2 days 22 June 23 June
titik & pasang jaring 2020 2020
31 PEKERJAAN BETON 39 19 July 26
days 2020 August
32 Beton Struktur kelas B ( 13 04 16
Deck Slab ) days August August
33 Pengecoran Tahap 1 1 day 04 04
August August
34 Pengecoran Tahap 2 1 day 10 10
August August
35 Pengecoran Tahap 3 1 day 16 16
August August
36 Beton Struktur kelas B ( 3 days 24 26
Parapet ) August August
37 Floor deck Slab 9 days 19 July 2020
27 July 2020
38 Antar girder 5 days 19 July 2020
23 July 2020
39 Dalam Girder 4 days 24 July 2020
27 July 2020
40 Kantilever 5 days 19 July 2020
23 July 2020
41 Bongkar bekisting 6 days 17 22
kantilever August August
42 Baja tulangan Ulir ( Deck 7 days 24 July 30 July
Slab & Parapet ) 2020 2020
43 Pembesian Slab 7 days 24 July 2020
30 July 2020
44 Pembesian Parapet 7 days 17 23
August August
45 Pipa Utilitas dia. 4 " kelas 6 days 17 22
AW August August
46 PEKERJAAN ASPHALT ( 2 days 10 11
L=167,5 m. W=2x15,15 m ) SeptemberSeptember
47 Bitumen Lapis pengikat ( 1 day 10 10
Tack Coat) SeptemberSeptember
48 Asphalt Concrete wearing 1 day 11 11
course SeptemberSeptember
49 PEKERJAAN DRAINASE 27 31 July 26
days 2020 August
50 Box Deckdrain tipe 1 4 days 31 July 03
2020 August
51 Pipa PVC 6 " Vertikal & 4 days 23 26
Horizontal August August

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary
JADWAL PEKERJAAN DECK SLAB, BRIDGE PARAPET DAN ASHPALT Milestone Inactive Milestone Start-only

Date: 22 June 2020 Summary Inactive Summary Finish-only


Project Summary Manual Task Deadline
External Tasks Duration-only Progress