INITIAL WORK PROGRAM FOR IDP2 - PROPOSED NEW DEVELOPEMENT AT PENGERANG

ID Task Name Duration Start Finish 2020 2021


Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 IDP2 - PROPOSED NEW DEVELOPMENT 455 days 1 Jan '20 30 Sep '21
AT PENGERANG
2 PROJECT START 0 days 1 Jan '20 1 Jan '20 1/1
3 PRELIMINARIES 65 days 1 Jan '20 2 Apr '20
4 Site Surveying 10 days 1 Jan '20 14 Jan '20
5 Machinery Mobilization 5 days 15 Jan '20 21 Jan '20
6 ESCP Implementation 50 days 22 Jan '20 2 Apr '20
7 Making Wash Through 20 days 22 Jan '20 20 Feb '20
8 Making Drainage Inlet Protection 10 days 23 Feb '20 5 Mar '20
9 Making Temporary Sediment Basin 20 days 23 Feb '20 19 Mar '20
10 Installing Silt Fence 20 days 8 Mar '20 2 Apr '20
11 PHYSICAL WORKS 390 days 5 Apr '20 30 Sep '21
12 REMOVAL OF TREES 58 days 5 Apr '20 23 Jun '20
13 Cut Down A Tree 11 days 5 Apr '20 19 Apr '20
14 Tree Trunk Removal 17 days 20 Apr '20 12 May '20
15 Stump Removal 29 days 6 May '20 15 Jun '20
16 Stump Disposal 11 days 9 Jun '20 23 Jun '20
17 STRIPPING TOP SOIL 25 days 17 Jun '20 21 Jul '20
18 Stripping Top Soil 15 days 17 Jun '20 7 Jul '20
19 Top Soil Removal 15 days 1 Jul '20 21 Jul '20
20 CUT & FILL WORK 289 days 15 Jul '20 23 Aug '21
21 Cutting 82 days 15 Jul '20 5 Nov '20
22 Filling 187 days 29 Jul '20 15 Apr '21
23 Compacting 269 days 12 Aug '20 23 Aug '21
24 Grading 8 days 12 Aug '21 23 Aug '21
25 OTHER'S WORKS 53 days 20 Jul '21 30 Sep '21
26 Disposing Excess Soil Material 15 days 3 Aug '21 23 Aug '21
27 Slope Stabilization (Turfing) 53 days 20 Jul '21 30 Sep '21
28 PROJECT COMPLETE 0 days 30 Sep '21 30 Sep '21 30/9