Summerdale II Renovation Project Schedule

ABC Renovation Pte Ltd

Project Start Date 30-Mar-20 17 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24
Project Lead Elaine 20 Jul 2020 27 Jul 2020 3 Aug 2020 10 Aug 2020 17 Aug 2020 24 Aug 2020 31 Aug 2020 7 Sep 2020
20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13

PREDECE % WORK
TASK START END M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
SSOR DONE DAYS

1 Planning - -

1.1 Concept planning and proposal 30-Mar-20 20-Apr-20 100% 16

1.2 Project Implementation Plan 13-Apr-20 15-Apr-20 60% 3

1.3 Preliminary design review 1.2 16-Apr-20 23-Apr-20 0% 6

1.4 Final design 24-Apr-20 1-May-20 0% 6

Preparation of drawings and


1.4.1 1.3 24-Apr-20 3-May-20 0% 6
document

1.4.2 Review 1.4.1 4-May-20 4-May-20 0% 1


2 Site Prep - -

2.1 Site access and associated permits 1.4.2 5-May-20 26-May-20 0% 16

Procurement of equipment and


2.2 1.4.2 5-May-20 5-Jun-20 0% 24
material

2.3 Dust control and surface protection 27-May-20 2-Jun-20 0% 5

2.4 Demolition 2.3 3-Jun-20 9-Jun-20 0% 5


2.5 Debris removal 2.4 10-Jun-20 14-Jun-20 0% 3

3 Plumbing, Sanitary and Gas - -

3.1 Drainage/ waste pipe/ vent pipe 2.5 15-Jun-20 23-Jun-20 0% 7

3.2 Water supply piping 2.5 15-Jun-20 23-Jun-20 0% 7

Diversion of gas pipe to new kitchen


3.3 2.5 15-Jun-20 23-Jun-20 0% 7
and gas water heater

3.4 Plumbing - fixtures and faucets 3.2 24-Jun-20 30-Jun-20 0% 5

4 Masonry - -
4.1 Wet Works 1-Jul-20 5-Jul-20 0% 3
4.2 Tiling 4.1 6-Jul-20 12-Jul-20 0% 5

5 Electrical - -
5.1 Wiring/ cabling 15-Jun-20 23-Jun-20 0% 7

Light fittings, fan, switches, socket


5.2 5.2 15-Jun-20 5-Jul-20 0% 15
outlets, etc.

6 Air-Conditioning - -

6.1 piping and installation of equipment 5.1 24-Jun-20 5-Jul-20 0% 8

7 Drywall/ Plaster/ flooring - -


7.1 Walls 24-Jun-20 2-Jul-20 0% 7
7.2 Ceiling 30-Jun-20 7-Jul-20 0% 6
7.3 Doors and windows 8-Jul-20 15-Jul-20 0% 6

7.4 Painting, wallpaper, feature walls 7.1 24-Jun-20 30-Jun-20 0% 5

7.5 Flooring 1-Jul-20 9-Jul-20 7

8 Carpentry - -
8.1 Manufacture 1-Jul-20 9-Jul-20 0% 7
8.2 Installation 8.1 10-Jul-20 18-Jul-20 6
9 Others - -

9.1 Installation of appliances 8.2 20-Jul-20 27-Jul-20 0% 6

9.2 Cleaning 9.1 28-Jul-20 4-Aug-20 0% 6


9.3 Furniture 9.2 5-Aug-20 12-Aug-20 0% 6
9.4 Inspection 9.3 13-Aug-20 20-Aug-20 0% 6
9.5 Final touch up 9.4 21-Aug-20 28-Aug-20 6
9.6 Handover 9.5 29-Aug-20 1-Sep-20 2