OWNER : Mr. & Mrs. De Rosa


PROJECT: PROPOSED TWO-STOREY (2) HOUSE

LOCATION : 148 Villa Catalina, San Agustin 3 Dasmariñas City, Cavite

Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21


TASK START FINISH DURATION
28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14
Project Approvals 9/27/2020 10/4/2020 6d
Planning and Formulation 10/5/2020 10/16/2020 6d
Space Planning 10/5/2020 10/12/2020 6d
Facilities Programming 10/8/2020 10/15/2020 6d
Capital Planning 10/9/2020 10/16/2020 6d
Capital Budgeting 10/9/2020 10/16/2020 6d
Preliminary Design 10/17/2020 11/13/2020 20 d
Design Planning 10/17/2020 10/24/2020 6d
Reviewed by Stakeholders 10/25/2020 11/1/2020 6d
Works out Major Design Elements 11/2/2020 11/9/2020 6d
Finish of Planning and Design 11/13/2020 11/13/2020 1d
Bidding 11/19/2020 12/4/2020 11 d
Construction Process 12/7/2020 6/17/2021 136 d
Marking the Layout 12/7/2020 12/24/2020 11 d
Exacavation of Footings 12/24/2020 1/8/2021 11 d
Reinforcement 1/8/2021 2/1/2021 18 d
Back Filling & Compaction 2/6/2021 2/18/2021 8d
Staging 2/20/2021 3/6/2021 11 d
Electrical Works 3/7/2021 3/22/2021 11 d
Window Fixing 3/22/2021 4/4/2021 9d
Tiles Flooring 4/4/2021 4/12/2021 6d
Plumbing Pipe Installation 4/12/2021 4/29/2021 11 d
Ceiling Installation 4/29/2021 5/10/2021 9d
Paintings 5/10/2021 5/22/2021 8d
Finishes/Fixtures 5/22/2021 5/30/2021 6d
Garden Works 5/31/2021 6/17/2021 11 d
Construction Closeout 6/18/2021 6/19/2021 1d