Construction Schedule for ME003 – Field Erected Fixed Roof Tanks

Mar 2021 Apr 2021 May 2021 Jun 2021 Jul 2021 Aug 2021 Sep 2021 Oct 2021 Nov 2021 Dec 2021 Jan 2022 Feb 2022 Mar 2022 Apr 2022 May 2022 Jun 2022 Jul 2022 Aug 2022 Sep 2022 Oct 2022 Nov 2022 Dec 2022 Jan 2023
ID Task Name Start Finish Duration
28/2 7/3 14/3 21/3 28/3 4/4 11/4 18/4 25/4 2/5 9/5 16/5 23/5 30/5 6/6 13/6 20/6 27/6 4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9 26/9 3/10 10/10 17/10 24/10 31/10 7/11 14/11 21/11 28/11 5/12 12/12 19/12 26/12 2/1 9/1 16/1 23/1 30/1 6/2 13/2 20/2 27/2 6/3 13/3 20/3 27/3 3/4 10/4 17/4 24/4 1/5 8/5 15/5 22/5 29/5 5/6 12/6 19/6 26/6 3/7 10/7 17/7 24/7 31/7 7/8 14/8 21/8 28/8 4/9 11/9 18/9 25/9 2/10 9/10 16/10 23/10 30/10 6/11 13/11 20/11 27/11 4/12 11/12 18/12 25/12 1/1 8/1 15/1 22/1

1 BWRO Product Tank A (D-337-01 A) 3/3/2021 2/17/2022 302d

2 Foundation Handover 3/3/2021 3/18/2021 14d

3 Installation Bottom & Anular Plate 3/19/2021 4/12/2021 21d

4 Installation Upper Shell c/w nozzle 4/13/2021 5/6/2021 21d

Installation Rafter / Girder & Coloumn


5 5/7/2021 5/22/2021 14d
Post

6 Installation Roof Plate c/w nozzle 5/24/2021 6/16/2021 21d

7 Installation Lower Shell c/w nozzle 6/17/2021 10/16/2021 105d

8 Other Tank Accessories 10/18/2021 11/2/2021 14d

9 Painting 1st Step 11/3/2021 11/26/2021 21d

10 Hydrostatic Test 11/27/2021 1/6/2022 35d

11 Painting Final Step 1/7/2022 2/8/2022 28d

Tank Cleaning, Preservation & Final


12 2/9/2022 2/14/2022 5d
Inspect

13 MDR & Commissioning Document 2/15/2022 2/17/2022 3d

14 BWRO Product Tank B (D-337-01 B) 3/3/2021 2/25/2022 309d

15 Foundation Handover 3/3/2021 3/26/2021 21d

16 Installation Bototm & Anular Plate 3/27/2021 4/20/2021 21d

17 Installation Upper Shell c/w nozzle 4/21/2021 5/14/2021 21d

Installation Rafter / Girder & Coloumn


18 5/15/2021 5/31/2021 14d
Post

19 Installation Roof Plate c/w nozzle 6/1/2021 6/24/2021 21d

20 Installation Lower Shell c/w nozzle 6/25/2021 10/25/2021 105d

21 Other Tank Accessories 10/26/2021 11/10/2021 14d

22 Painting 1st Step 11/11/2021 12/4/2021 21d

23 Hydrostatic Test 12/6/2021 1/14/2022 35d

24 Painting Final Step 1/15/2022 2/16/2022 28d

Tank Cleaning, Presevation & Final


25 2/17/2022 2/22/2022 5d
Inspect

26 MDR & Commissioning Document 2/23/2022 2/25/2022 3d

27 Cooled Hot Condensate Tank A (D-337-03 A) 3/9/2021 12/28/2021 253d

28 Foundation Handover 3/9/2021 4/9/2021 28d

29 Installation Bottom & Anular Plate 4/10/2021 4/26/2021 14d

30 Installation Upper Shell c/w nozzle 4/27/2021 5/20/2021 21d

Installation Rafter / Girder & Coloumn


31 5/21/2021 6/5/2021 14d
Post

32 Installation Roof Plate c/w nozzle 6/7/2021 6/22/2021 14d

33 Installation Lower Shell c/w nozzle 6/23/2021 10/14/2021 98d

34 Other Tank Accessories 10/15/2021 10/30/2021 14d

35 Painting 1st Step 11/1/2021 11/8/2021 7d

36 Hydrostatic Test 11/9/2021 12/2/2021 21d

37 Painting Final Step 12/3/2021 12/18/2021 14d

Tank Cleaning, Preservation & Final


38 12/20/2021 12/24/2021 5d
Inspect

39 MDR & Commissioning Document 12/25/2021 12/28/2021 3d

40 Cooled Hot Condensate Tank B (D-337-03 B) 3/9/2021 1/5/2022 260d

41 Foundation Handover 3/9/2021 4/17/2021 35d

42 Installation Bottom & Anular Plate 4/19/2021 5/4/2021 14d

43 Installation Upper Shell c/w nozzle 5/5/2021 5/28/2021 21d

Installation Rafter / Girder & Coloumn


44 5/29/2021 6/14/2021 14d
Post

45 Installation Roof Plate c/w nozzle 6/15/2021 6/30/2021 14d

46 Installation Lower Shell c/w nozzle 7/1/2021 10/22/2021 98d

47 Other Tank Accessories 10/23/2021 11/8/2021 14d

48 Painting 1st Step 11/9/2021 11/16/2021 7d

49 Hydrostatic Test 11/17/2021 12/10/2021 21d

50 Painting Final Step 12/11/2021 12/27/2021 14d

Tank Cleaning, Preservation & Final


51 12/28/2021 1/1/2022 5d
Inspect

52 MDR & Commissioning Document 1/3/2022 1/5/2022 3d

53 Demineralized Water Tank A (D-337-02 A) 3/16/2021 2/24/2022 297d

54 Foundation Handover 3/16/2021 4/24/2021 35d

55 Installation Bottom & Anular Plate 4/26/2021 5/13/2021 16d

56 Installation Upper Shell c/w nozzle 5/14/2021 5/25/2021 10d

Installation Rafter / Girder & Coloumn


57 5/26/2021 6/10/2021 14d
Post

58 Installation Roof Plate c/w nozzle 6/11/2021 7/13/2021 28d

59 Installation Lower Shell c/w nozzle 7/14/2021 11/8/2021 101d

60 Other Tank Accessories 11/9/2021 11/19/2021 10d

61 Painting 1st Step 11/20/2021 12/10/2021 18d

62 Hydrostatic Tes 12/11/2021 1/22/2022 37d

63 Painting Final Step 1/24/2022 2/15/2022 20d

Tank Cleaning, Preservation & Final


64 2/16/2022 2/21/2022 5d
Inspect

65 MDR & Commissioning Document 2/22/2022 2/24/2022 3d

66 Demineralized Water Tank B (D-337-02 B) 3/16/2021 3/4/2022 304d

67 Foundation Handover 3/16/2021 5/3/2021 42d

68 Installation Bottom & Anular Plate 5/4/2021 5/21/2021 16d

69 Installation Upper Shell c/w nozzle 5/22/2021 6/2/2021 10d

Installation Rafter / Girder & Coloumn


70 6/3/2021 6/18/2021 14d
Post
68 Installation Bottom & Anular Plate 5/4/2021 5/21/2021 16d

69 Installation Upper Shell c/w nozzle 5/22/2021 6/2/2021 10d

Installation Rafter / Girder & Coloumn


70 6/3/2021 6/18/2021 14d
Post

71 Installation Roof Plate c/w nozzle 6/19/2021 7/21/2021 28d

72 Installation Lower Shell c/w nozzle 7/22/2021 11/16/2021 101d

73 Other Tank Accessories 11/17/2021 11/27/2021 10d

74 Painting 1st Step 11/29/2021 12/18/2021 18d

75 Hydrostatic Test 12/20/2021 1/31/2022 37d

76 Painting Final Step 2/1/2022 2/23/2022 20d

Tank Cleaning, Preservation & Final


77 2/24/2022 3/1/2022 5d
Inspect

78 MDR & Commissioning Document 3/2/2022 3/4/2022 3d

79 SWRO Product Tank A (D-337-05 A) 4/29/2021 12/2/2021 187d

80 Foundatiion Handover 4/29/2021 5/14/2021 14d

81 Installation Bottom & Anular Plate 5/15/2021 5/26/2021 10d

82 Installation Upper Shell c/w nozzle 5/27/2021 6/9/2021 12d

Installation Rafter / Girder & Coloumn


83 6/10/2021 6/25/2021 14d
Post

84 Installation Roof Plate c/w nozzle 6/26/2021 7/9/2021 12d

85 Installation Lower Shell c/w nozzle 7/10/2021 9/29/2021 70d

86 Other Tank Accessories 9/30/2021 10/13/2021 12d

87 Painting 1st Step 10/14/2021 10/21/2021 7d

88 Hydrostatic Test 10/22/2021 11/6/2021 14d

89 Painting Final Step 11/8/2021 11/23/2021 14d

Tank Cleaning, Preservation & Final


90 11/24/2021 11/29/2021 5d
Inspect

91 MDR & Commissioning Document 11/30/2021 12/2/2021 3d

92 SWRO Product Tank B (D-337-05 B) 5/29/2021 2/3/2022 215d

93 Foundation Handover 5/29/2021 7/16/2021 42d

94 Installation Bottom & Anular Plate 7/17/2021 7/28/2021 10d

95 Installation Upper Shell c/w nozzle 7/29/2021 8/11/2021 12d

Installation Rafter / Girder & Coloumn


96 8/12/2021 8/27/2021 14d
Post

97 Installation Roof Plate c/w nozzle 8/28/2021 9/10/2021 12d

98 Installation Lower Shell c/w nozzle 9/11/2021 12/1/2021 70d

99 Other Tank Accessories 12/2/2021 12/15/2021 12d

100 Painting 1st Step 12/16/2021 12/23/2021 7d

101 Hydrostatioc Test 12/24/2021 1/8/2022 14d

102 Painting Final Step 1/10/2022 1/25/2022 14d

Tank Cleaning, Preservation & Final


103 1/26/2022 1/31/2022 5d
Inspect

104 MDR & Commissioning Document 2/1/2022 2/3/2022 3d

105 Portable Water Tank (D-337-06) 5/3/2021 9/14/2021 116d

106 Foundation Handover 5/3/2021 5/26/2021 21d

107 Installation Bottom & Anular Plate 5/27/2021 6/3/2021 7d

108 Installation Upper Shell c/w nozzle 6/4/2021 6/8/2021 4d

Installation Rafter / Girder & Coloumn


109 6/9/2021 6/18/2021 9d
Post

110 Installation Roof Plate c/w nozzle 6/19/2021 6/26/2021 7d

111 Installation Lower Shell c/w nozzle 6/28/2021 7/29/2021 28d

112 Other Tank Accessories 7/30/2021 8/6/2021 7d

113 Finishing 8/7/2021 8/12/2021 5d

114 Hydrostatic Test 8/13/2021 8/21/2021 8d

115 Final Painting 8/23/2021 9/4/2021 12d

Tank Cleaning, Preservation & Final


116 9/6/2021 9/10/2021 5d
Inspect

117 MDR & Commissioning Document 9/11/2021 9/14/2021 3d

118 Ultrafiltration Product Tank A (D-337-04 A) 6/11/2021 3/11/2022 235d

119 Foundation handover 6/11/2021 7/5/2021 21d

120 Installation Bottom & Anular Plate 7/6/2021 7/16/2021 10d

121 Installation Upper Shell c/w nozzle 7/17/2021 7/27/2021 9d

Installation Rafter / Girder & Coloumn


122 7/28/2021 8/20/2021 21d
Post

123 Installation Roof Plate c/w nozzle 8/21/2021 9/10/2021 18d

124 Installation Lower Shell c/w nozzle 9/11/2021 12/27/2021 92d

125 Other Tank Accessories 12/28/2021 1/7/2022 10d

126 Painting 1st Step 1/8/2022 1/15/2022 7d

127 Hydrostatic Test 1/17/2022 2/5/2022 18d

128 Painting Final Step 2/7/2022 3/2/2022 21d

Tank Cleaning, Preservation & Final


129 3/3/2022 3/8/2022 5d
Inspect

130 MDR & Commissioning Document 3/9/2022 3/11/2022 3d

131 Ultrafiltration Product Tank B (D-337-04 B) 6/11/2021 3/28/2022 249d

132 Foundation Handover 6/11/2021 7/21/2021 35d

133 Installation Bottom & Anular Plate 7/22/2021 8/2/2021 10d

134 Installation Upper Shell c/w nozzle 8/3/2021 8/12/2021 9d

Installation Rafter / Girder & Coloumn


135 8/13/2021 9/6/2021 21d
Post

136 Installation Roof Plate c/w nozzle 9/7/2021 9/27/2021 18d

137 Installation Lower Shell c/w nozzle 9/28/2021 1/12/2022 92d

138 Other Tank Accessories 1/13/2022 1/24/2022 10d

139 Painting 1st Step 1/25/2022 2/1/2022 7d

140 Hydrostatic Test 2/2/2022 2/22/2022 18d

141 Painting Final Step 2/23/2022 3/18/2022 21d

Tank Cleaning, Preservation & Final


142 3/19/2022 3/24/2022 5d
Inspect

143 MDR & Commisioning Document 3/25/2022 3/28/2022 3d

144 Diesel Oil Daily Storage Tank A (D-331-01 A) 6/21/2021 11/4/2021 118d

145 Foundation Handover 6/21/2021 6/28/2021 7d

146 Installation Bottom & Anular Plate 6/29/2021 7/5/2021 6d

147 Installation Upper Shell c/w nozzle 7/6/2021 7/14/2021 8d

Installation Rafter / Girder & Coloumn


148 7/15/2021 8/2/2021 16d
145 Foundation Handover 6/21/2021 6/28/2021 7d

146 Installation Bottom & Anular Plate 6/29/2021 7/5/2021 6d

147 Installation Upper Shell c/w nozzle 7/6/2021 7/14/2021 8d

Installation Rafter / Girder & Coloumn


148 7/15/2021 8/2/2021 16d
Post

149 Installation Roof Plate c/w nozzle 8/3/2021 8/10/2021 7d

150 Installation Lower Shell c/w nozzle 8/11/2021 9/20/2021 35d

151 Other Tank Accessories 9/21/2021 9/28/2021 7d

152 Finishing 9/29/2021 10/2/2021 4d

153 Hydrotest 10/4/2021 10/12/2021 8d

154 Final Painting 10/13/2021 10/26/2021 12d

Tank Cleaning, Preservation & Final


155 10/27/2021 11/1/2021 5d
Inspect

156 MDR & Commissioning Document 11/2/2021 11/4/2021 3d

157 Diesel Oil Daily Storage Tank B (D-331-01 B) 6/21/2021 11/4/2021 118d

158 Foundation Handover 6/21/2021 6/28/2021 7d

159 Installation Bottom & Anular Plate 6/29/2021 7/5/2021 6d

160 Installation Upper Shell c/w nozzle 7/6/2021 7/14/2021 8d

Installation Rafter / Girder & Coloumn


161 7/15/2021 8/2/2021 16d
Post

162 Installation Roof Plate c/w nozzle 8/3/2021 8/10/2021 7d

163 Installation Lower Shell c/w nozzle 8/11/2021 9/20/2021 35d

164 Other Tank Accessories 9/21/2021 9/28/2021 7d

165 Finishing 9/29/2021 10/2/2021 4d

166 Hydrotest 10/4/2021 10/12/2021 8d

167 Final Painting 10/13/2021 10/26/2021 12d

Tank Cleaning, Preservation & Final


168 10/27/2021 11/1/2021 5d
Inspect

169 MDR & Commissioning Document 11/2/2021 11/4/2021 3d

170 Caustic Tank (D-325-01) 8/4/2021 1/12/2022 139d

171 Foundation Handover 8/4/2021 8/11/2021 7d

172 Installation Bototm & Anular Plate 8/12/2021 8/19/2021 7d

173 Installation Upper Shell c/w nozzle 8/20/2021 9/4/2021 14d

Installation Rafter / Girder & Coloumn


174 9/6/2021 9/13/2021 7d
Post

175 Installation Roof Plate c/w nozzle 9/14/2021 9/21/2021 7d

176 Installation Lower Shell c/w Nozzle 9/22/2021 10/15/2021 21d

177 Other Tank Accessories 10/16/2021 11/1/2021 14d

178 PWHT 11/2/2021 11/17/2021 14d

179 Internal Coil 11/18/2021 12/3/2021 14d

180 Finishing 12/4/2021 12/11/2021 7d

181 Hydrotest 12/13/2021 12/20/2021 7d

182 Final Painting 12/21/2021 1/3/2022 12d

Tank Cleaning, Preservation & Final


183 1/4/2022 1/8/2022 5d
Inspect

184 MDR & Commissioning Document 1/10/2022 1/12/2022 3d

185 Sour Water Storage Tank (D-167-01) 10/25/2021 7/19/2022 230d

186 Foundation Handover 10/25/2021 11/25/2021 28d

187 Installation Bottom & Anular Plate 11/26/2021 12/8/2021 11d

188 Installation Upper Shell c/w nozzle 12/9/2021 12/20/2021 10d

Installation Rafter / Girder & Coloumn


189 12/21/2021 1/5/2022 14d
Post

190 Installation Roof Plate c/w nozzle 1/6/2022 1/29/2022 21d

191 Installation Lower Shell c/w nozzle 1/31/2022 4/21/2022 70d

192 Other Tank Accessories 4/22/2022 5/7/2022 14d

193 Painting 1st Step 5/9/2022 5/16/2022 7d

194 Hydrostatic Test 5/17/2022 6/15/2022 26d

195 Final Painting 6/16/2022 7/9/2022 21d

Tank Cleaning, Preservation & Final


196 7/11/2022 7/15/2022 5d
Inspect

197 MDR & Commissioning Document 7/16/2022 7/19/2022 3d

198 Spent Acid Storage Tank (D-065-03) 11/8/2021 4/28/2022 148d

199 Foundation Handover 11/8/2021 12/17/2021 35d

200 Installation Bottom & Anular Plate 12/18/2021 12/25/2021 7d

201 Installation Upper Shell c/w nozzle 12/27/2021 1/6/2022 10d

Installation Rafter / Girder & Coloumn


202 1/7/2022 1/18/2022 10d
Post

203 Installation Roof Plate c/w nozzle 1/19/2022 1/26/2022 7d

204 Installation Lower Shell c/w nozzle 1/27/2022 3/2/2022 30d

205 Other Tank Accessories 3/3/2022 3/18/2022 14d

206 Finishing 3/19/2022 3/26/2022 7d

207 Hydrostatic Test 3/28/2022 4/5/2022 8d

208 Final Painting 4/6/2022 4/19/2022 12d

Tank Cleaning, Preservation & Final


209 4/20/2022 4/25/2022 5d
Inspect

210 MDR & Commissioning Document 4/26/2022 4/28/2022 3d

211 Fresh Acid Storage Tank (D-065-01) 11/18/2021 4/22/2022 134d

212 Foundation Handover 11/18/2021 12/11/2021 21d

213 Installation Bottom & Anular Plate 12/13/2021 12/20/2021 7d

214 Installation Upper Shell c/w nozzle 12/21/2021 12/31/2021 10d

215 Installation Rafter / Girder & Coloum Post 1/1/2022 1/12/2022 10d

216 Installation Roof Plate c/w nozzle 1/13/2022 1/20/2022 7d

217 Installation Lower Shell c/w nozzle 1/21/2022 2/24/2022 30d

218 Other Tank Accessories 2/25/2022 3/12/2022 14d

219 Finishing 3/14/2022 3/21/2022 7d

220 Hydrostatic Test 3/22/2022 3/30/2022 8d

221 Final Painting 3/31/2022 4/13/2022 12d

Tank Cleaning, Preservation & Final


222 4/14/2022 4/19/2022 5d
Inspect

223 MDR & Commissioning Document 4/20/2022 4/22/2022 3d

224 Fresh / Spent Acid Storage Tank (D-065-02) 1/11/2022 6/15/2022 134d

225 Foundation Handover 1/11/2022 2/3/2022 21d


Tank Cleaning, Preservation & Final
222 4/14/2022 4/19/2022 5d
Inspect

223 MDR & Commissioning Document 4/20/2022 4/22/2022 3d

224 Fresh / Spent Acid Storage Tank (D-065-02) 1/11/2022 6/15/2022 134d

225 Foundation Handover 1/11/2022 2/3/2022 21d

226 Installation Bottom & Anular Plate 2/4/2022 2/11/2022 7d

227 Installation Upper Shell c/w nozzle 2/12/2022 2/23/2022 10d

Installation Rafter / Girder & Coloumn


228 2/24/2022 3/7/2022 10d
Post

229 Installation Roof Plate c/w nozzle 3/8/2022 3/15/2022 7d

230 Installation Lower Shell c/w nozzle 3/16/2022 4/19/2022 30d

231 Other Tank Accessories 4/20/2022 5/5/2022 14d

232 Finishing 5/6/2022 5/13/2022 7d

233 Hydrostatic Test 5/14/2022 5/23/2022 8d

234 Final Painting 5/24/2022 6/6/2022 12d

Tank Cleaning, Preservation & Final


235 6/7/2022 6/11/2022 5d
Inspect

236 MDR & Commissioning Document 6/13/2022 6/15/2022 3d

237 Caustic Tank (A-052-10-D1) 4/5/2022 9/1/2022 129d

238 Foundation Handover 4/5/2022 4/28/2022 21d

239 Installation Bottom & Anular Plate 4/29/2022 5/5/2022 6d

240 Installation Upper Shell c/w nozzle 5/6/2022 5/20/2022 13d

241 Installation Rafter / Girder & Structure 5/21/2022 5/30/2022 8d

242 Installation Roof Plate c/w nozzle 5/31/2022 6/6/2022 6d

243 Installation Lower Shell c/w nozzle 6/7/2022 7/11/2022 30d

244 Other Tank Accessories 7/12/2022 7/19/2022 7d

245 PWHT 7/20/2022 8/4/2022 14d

246 Hydrostatic Test 8/5/2022 8/13/2022 8d

247 Final Painting 8/15/2022 8/27/2022 12d

Tank Cleaning, Preservation & Final


248 8/29/2022 8/31/2022 3d
Inspect

249 MDR & Commissioning Document 9/1/2022 9/1/2022 1d

250 Caustic Dilution Tank (D-082-01) 5/19/2022 9/8/2022 97d

251 Foundation Handover 5/19/2022 5/21/2022 3d

252 Installation Bottom & Anular Plate 5/23/2022 5/28/2022 6d

253 Installation Upper Shell c/w nozzle 5/30/2022 6/6/2022 7d

254 Installation Rafter / Girder & structure 6/7/2022 6/15/2022 8d

255 Installation Roof Plate c/w nozzle 6/16/2022 6/22/2022 6d

256 Installation Lower Shell c/w nozzle 6/23/2022 7/16/2022 21d

257 Other Tank Accessories 7/18/2022 7/25/2022 7d

258 PWHT 7/26/2022 8/10/2022 14d

259 Hydrostatic Test 8/11/2022 8/18/2022 7d

260 Final Painting 8/19/2022 8/30/2022 10d

Tank Cleaning, Preservation & Final


261 8/31/2022 9/5/2022 5d
Inspect

262 MDR & Commissioning Document 9/6/2022 9/8/2022 3d

263 Sour Water Storage Tank (D-067-01) 5/30/2022 12/26/2022 181d

264 Foundation Handover 5/30/2022 6/1/2022 3d

265 Installation Bottom & Anular Plate 6/2/2022 6/13/2022 10d

266 Installation Upper Shell c/w nozzle 6/14/2022 6/21/2022 7d

267 Installation Rafter / Girder & Structure 6/22/2022 7/7/2022 14d

268 Installation Roof Plate c/w nozzle 7/8/2022 8/1/2022 21d

269 Installation Lower Shell c/w nozzle 8/2/2022 10/3/2022 54d

270 Other Tank Accessories 10/4/2022 10/14/2022 10d

271 Finishing 10/15/2022 10/20/2022 5d

272 Hydrostatic test 10/21/2022 11/22/2022 28d

273 Final Painting 11/23/2022 12/16/2022 21d

Tank Cleaning, Preservation & Final


274 12/17/2022 12/22/2022 5d
Inspect

275 MDR & Commissioning Document 12/23/2022 12/26/2022 3d

276 Water Stilling Tank (D-334-01) 8/9/2022 12/16/2022 112d

277 Foundation Handover 8/9/2022 8/16/2022 7d

278 Installation Bottom & Anular Plate 8/17/2022 8/27/2022 10d

279 Installation Upper Shell c/w nozzle 8/29/2022 9/5/2022 7d

280 Installation Rafter / Girder & Structure 9/6/2022 9/13/2022 7d

281 Installation Stiffener 9/14/2022 10/7/2022 21d

282 Installation Lower Plate 10/8/2022 11/3/2022 23d

283 Other Tank Accessories 11/4/2022 11/12/2022 8d

284 Finishing 11/14/2022 11/16/2022 3d

285 Hydrostatic Test 11/17/2022 11/25/2022 8d

286 Final Painting 11/26/2022 12/7/2022 10d

Tank Cleaning, Preservation & Final


287 12/8/2022 12/13/2022 5d
Inspect

288 MDR & Commissioning Document 12/14/2022 12/16/2022 3d