Last Issue: 15-May-21 Internal

Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Pipe Saddle No.226 - 222 Start Finish


Pile Cap inc' Embedded Plate 08/06/2021 10/06/2021
Productivity
Cutting Plan Saddle 04/06/2021 05/06/2021
Fabrication Saddle 05/06/2021 07/06/2021 Fabrication Saddle 2 saddle/day
Instalation of Saddle 22/06/2021 23/06/2021 Installation of Pipe 2 Joint/day
Instalation of Pipe 24/06/2021 29/06/2021

Pipe Saddle No.222 - 218 Start Finish


Pile Cap inc' Embedded Plate 11/06/2021 13/06/2021
Cutting Plan Saddle 06/06/2021 07/06/2021
Fabrication Saddle 08/06/2021 10/06/2021
Instalation of Saddle 28/06/2021 29/06/2021
Instalation of Pipe 30/06/2021 05/07/2021

Pipe Saddle No.218 - 214 Start Finish


Pile Cap inc' Embedded Plate 14/06/2021 16/06/2021
Cutting Plan Saddle 08/06/2021 09/06/2021
Fabrication Saddle 10/06/2021 12/06/2021
Instalation of Saddle 01/07/2021 02/07/2021
Instalation of Pipe 06/07/2021 11/07/2021

Pipe Saddle No.214 - 210 Start Finish


Pile Cap inc' Embedded Plate 17/06/2021 19/06/2021
Cutting Plan Saddle 10/06/2021 11/06/2021
Fabrication Saddle 13/06/2021 15/06/2021
Instalation of Saddle 04/07/2021 05/07/2021
Instalation of Pipe 12/07/2021 17/07/2021

Pipe Saddle No.210 - 206 Start Finish


Pile Cap inc' Embedded Plate 20/06/2021 22/06/2021
Cutting Plan Saddle 12/06/2021 13/06/2021
Fabrication Saddle 16/06/2021 18/06/2021
Instalation of Saddle 07/07/2021 08/07/2021
Instalation of Pipe 18/07/2021 23/07/2021

Pipe Saddle No.206 - 202 Start Finish


Pile Cap inc' Embedded Plate 23/06/2021 25/06/2021
Cutting Plan Saddle 14/06/2021 15/06/2021
Fabrication Saddle 19/06/2021 21/06/2021
Instalation of Saddle 10/07/2021 11/07/2021
Instalation of Pipe 24/07/2021 29/07/2021

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 1 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Pipe Saddle No. 202 - 198 Start Finish


Pile Cap inc' Embedded Plate 26/06/2021 28/06/2021 Productivity
Cutting Plan Saddle 16/06/2021 17/06/2021 Fabrication Saddle 2 saddle/day
Fabrication Saddle 22/06/2021 24/06/2021
Installation of Pipe 2 Joint/day
Instalation of Saddle 13/07/2021 14/07/2021
Instalation of Pipe 30/07/2021 04/08/2021

Pipe Saddle No.198 -194 Start Finish


Pile Cap inc' Embedded Plate 29/06/2021 01/07/2021
Cutting Plan Saddle 18/06/2021 19/06/2021
Fabrication Saddle 25/06/2021 27/06/2021
Instalation of Saddle 16/07/2021 17/07/2021
Instalation of Pipe 05/08/2021 10/08/2021

Pipe Saddle No.198 - 194 Start Finish


Pile Cap inc' Embedded Plate 29/06/2021 01/07/2021
Cutting Plan Saddle 18/06/2021 19/06/2021
Fabrication Saddle 25/06/2021 27/06/2021
Instalation of Saddle 16/07/2021 17/07/2021
Instalation of Pipe 05/08/2021 10/08/2021

Pipe Saddle No.194 - 190 Start Finish


Pile Cap inc' Embedded Plate 02/07/2021 04/07/2021
Cutting Plan Saddle 20/06/2021 21/06/2021
Fabrication Saddle 28/06/2021 30/06/2021
Instalation of Saddle 19/07/2021 20/07/2021
Instalation of Pipe 11/08/2021 16/08/2021

Pipe Saddle No.190- 186 Start Finish


Pile Cap inc' Embedded Plate 05/07/2021 07/07/2021
Cutting Plan Saddle 22/06/2021 23/06/2021
Fabrication Saddle 01/07/2021 03/07/2021
Instalation of Saddle 22/07/2021 23/07/2021
Instalation of Pipe 17/08/2021 22/08/2021

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 2 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Pipe Saddle No.186- 182 Start Finish


Productivity
Pile Cap inc' Embedded Plate 08/07/2021 10/07/2021
Cutting Plan Saddle 24/06/2021 25/06/2021 Fabrication Saddle 2 saddle/day
Fabrication Saddle 04/07/2021 06/07/2021 Installation of Pipe 2 Joint/day
Instalation of Saddle 25/07/2021 26/07/2021
Instalation of Pipe 23/08/2021 28/08/2021

Pipe Saddle No.182- 178 Start Finish


Pile Cap inc' Embedded Plate 11/07/2021 13/07/2021
Cutting Plan Saddle 26/06/2021 27/06/2021
Fabrication Saddle 07/07/2021 09/07/2021
Instalation of Saddle 28/07/2021 29/07/2021
Instalation of Pipe 29/08/2021 03/09/2021

Pipe Saddle No.178- 174 Start Finish


Pile Cap inc' Embedded Plate 14/07/2021 16/07/2021
Cutting Plan Saddle 28/06/2021 29/06/2021
Fabrication Saddle 10/07/2021 12/07/2021
Instalation of Saddle 31/07/2021 01/08/2021
Instalation of Pipe 04/09/2021 09/09/2021

Pipe Saddle No.174- 170 Start Finish


Pile Cap inc' Embedded Plate 17/07/2021 19/07/2021
Cutting Plan Saddle 30/06/2021 01/07/2021
Fabrication Saddle 13/07/2021 15/07/2021
Instalation of Saddle 03/08/2021 04/08/2021
Instalation of Pipe 10/09/2021 15/09/2021

Pipe Saddle No.170- 166 Start Finish


Pile Cap inc' Embedded Plate 20/07/2021 22/07/2021
Cutting Plan Saddle 02/07/2021 03/07/2021
Fabrication Saddle 16/07/2021 18/07/2021
Instalation of Saddle 05/08/2021 06/08/2021
Instalation of Pipe 16/09/2021 21/09/2021

Pipe Saddle No.166- 162 Start Finish


Pile Cap inc' Embedded Plate 23/07/2021 25/07/2021
Cutting Plan Saddle 04/07/2021 05/07/2021
Fabrication Saddle 19/07/2021 21/07/2021
Instalation of Saddle 09/08/2021 10/08/2021
Instalation of Pipe 22/09/2021 27/09/2021

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 3 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Pipe Saddle No.162- 158 Start Finish


Pile Cap inc' Embedded Plate 26/07/2021 28/07/2021 Productivity
Cutting Plan Saddle 06/07/2021 07/07/2021 Fabrication Saddle 2 saddle/day
Fabrication Saddle 22/07/2021 24/07/2021
Installation of Pipe 2 Joint/day
Instalation of Saddle 12/08/2021 13/08/2021
Instalation of Pipe 28/09/2021 03/10/2021

Pipe Saddle No.158- 154 Start Finish


Pile Cap inc' Embedded Plate 29/07/2021 31/07/2021
Cutting Plan Saddle 08/07/2021 09/07/2021
Fabrication Saddle 25/07/2021 27/07/2021
Instalation of Saddle 15/08/2021 16/08/2021
Instalation of Pipe 04/10/2021 09/10/2021

Pipe Saddle No.154- 150 Start Finish


Pile Cap inc' Embedded Plate 01/08/2021 03/08/2021
Cutting Plan Saddle 10/07/2021 11/07/2021
Fabrication Saddle 28/07/2021 30/07/2021
Instalation of Saddle 18/08/2021 19/08/2021
Instalation of Pipe 10/10/2021 15/10/2021

Pipe Saddle No.150- 146 Start Finish


Pile Cap inc' Embedded Plate 04/08/2021 06/08/2021
Cutting Plan Saddle 12/07/2021 13/07/2021
Fabrication Saddle 31/07/2021 02/08/2021
Instalation of Saddle 21/08/2021 22/08/2021
Instalation of Pipe 16/10/2021 21/10/2021

Pipe Saddle No.146- 142 Start Finish


Pile Cap inc' Embedded Plate 07/08/2021 09/08/2021
Cutting Plan Saddle 14/07/2021 15/07/2021
Fabrication Saddle 03/08/2021 05/08/2021
Instalation of Saddle 24/08/2021 25/08/2021
Instalation of Pipe 22/10/2021 27/10/2021

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 4 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Pipe Saddle No.142- 138 Start Finish


Pile Cap inc' Embedded Plate 10/08/2021 12/08/2021 Productivity
Cutting Plan Saddle 16/07/2021 17/07/2021
Fabrication Saddle 2 saddle/day
Fabrication Saddle 06/08/2021 08/08/2021
Instalation of Saddle 27/08/2021 28/08/2021
Installation of Pipe 2 Joint/day
Instalation of Pipe 28/10/2021 02/11/2021

Pipe Saddle No.138- 134 Start Finish


Pile Cap inc' Embedded Plate 13/08/2021 15/08/2021
Cutting Plan Saddle 18/07/2021 19/07/2021
Fabrication Saddle 09/08/2021 11/08/2021
Instalation of Saddle 30/08/2021 31/08/2021
Instalation of Pipe 03/11/2021 08/11/2021

Pipe Saddle No.134- 130 Start Finish


Pile Cap inc' Embedded Plate 16/08/2021 18/08/2021
Cutting Plan Saddle 20/07/2021 21/07/2021
Fabrication Saddle 12/08/2021 14/08/2021
Instalation of Saddle 02/09/2021 03/09/2021
Instalation of Pipe 09/11/2021 14/11/2021

Pipe Saddle No.130- 126 Start Finish


Pile Cap inc' Embedded Plate 19/08/2021 21/08/2021
Cutting Plan Saddle 22/07/2021 23/07/2021
Fabrication Saddle 15/08/2021 17/08/2021
Instalation of Saddle 05/09/2021 06/09/2021
Instalation of Pipe 15/11/2021 20/11/2021

Pipe Saddle No.126 - 122 Start Finish


Pile Cap inc' Embedded Plate 22/08/2021 24/08/2021
Cutting Plan Saddle 24/07/2021 25/07/2021
Fabrication Saddle 18/08/2021 20/08/2021
Instalation of Saddle 08/09/2021 09/09/2021
Instalation of Pipe 21/11/2021 26/11/2021

Pipe Saddle No.122 - 118 Start Finish


Pile Cap inc' Embedded Plate 25/08/2021 27/08/2021
Cutting Plan Saddle 26/07/2021 27/07/2021
Fabrication Saddle 21/08/2021 23/08/2021
Instalation of Saddle 11/09/2021 12/09/2021
Instalation of Pipe 27/11/2021 02/12/2021

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 5 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Productivity
Pipe Saddle No.118- 114 Start Finish
Fabrication Saddle 2 saddle/day
Pile Cap inc' Embedded Plate 28/08/2021 30/08/2021
Cutting Plan Saddle 28/07/2021 29/07/2021 Installation of Pipe 2 Joint/day
Fabrication Saddle 24/08/2021 26/08/2021
Instalation of Saddle 14/09/2021 15/09/2021
Instalation of Pipe 03/12/2021 08/12/2021

Pipe Saddle No.108 - 114 Start Finish


Pile Cap inc' Embedded Plate 11/11/2021 14/11/2021
Cutting Plan Saddle 16/09/2021 18/09/2021
Fabrication Saddle 07/11/2021 10/11/2021
Instalation of Saddle 29/11/2021 01/12/2021
Instalation of Pipe 10/02/2022 17/02/2022

Pipe Saddle No.104 - 108 Start Finish


Pile Cap inc' Embedded Plate 08/11/2021 10/11/2021
Cutting Plan Saddle 14/09/2021 15/09/2021
Fabrication Saddle 04/11/2021 06/11/2021
Instalation of Saddle 25/11/2021 26/11/2021
Instalation of Pipe 04/02/2022 09/02/2022

Pipe Saddle No.100 - 104 Start Finish


Pile Cap inc' Embedded Plate 05/11/2021 07/11/2021
Cutting Plan Saddle 12/09/2021 13/09/2021
Fabrication Saddle 01/11/2021 03/11/2021
Instalation of Saddle 22/11/2021 23/11/2021
Instalation of Pipe 29/01/2022 03/02/2022

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 6 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Pipe Saddle No.96 - 100 Start Finish Productivity


Pile Cap inc' Embedded Plate 02/11/2021 04/11/2021 Fabrication Saddle 2 saddle/day
Cutting Plan Saddle 10/09/2021 11/09/2021
Installation of Pipe 2 Joint/day
Fabrication Saddle 29/10/2021 31/10/2021
Instalation of Saddle 19/11/2021 20/11/2021
Instalation of Pipe 23/01/2022 28/01/2022

Pipe Saddle No.92 - 96 Start Finish


Pile Cap inc' Embedded Plate 30/10/2021 01/11/2021
Cutting Plan Saddle 08/09/2021 09/09/2021
Fabrication Saddle 26/10/2021 28/10/2021
Instalation of Saddle 16/11/2021 17/11/2021
Instalation of Pipe 17/01/2022 22/01/2022

Pipe Saddle No.88 - 92 Start Finish


Pile Cap inc' Embedded Plate 27/10/2021 29/10/2021
Cutting Plan Saddle 06/09/2021 07/09/2021
Fabrication Saddle 23/10/2021 25/10/2021
Instalation of Saddle 14/11/2021 15/11/2021
Instalation of Pipe 11/01/2022 16/01/2022

Pipe Saddle No.84 - 88 Start Finish


Pile Cap inc' Embedded Plate 24/10/2021 26/10/2021
Cutting Plan Saddle 04/09/2021 05/09/2021
Fabrication Saddle 20/10/2021 22/10/2021
Instalation of Saddle 12/11/2021 13/11/2021
Instalation of Pipe 05/01/2022 10/01/2022

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 7 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Productivity
Pipe Saddle No.80 - 84 Start Finish
Fabrication Saddle 2 saddle/day
Pile Cap inc' Embedded Plate 21/10/2021 23/10/2021
Cutting Plan Saddle 02/09/2021 03/09/2021
Installation of Pipe 2 Joint/day
Fabrication Saddle 17/10/2021 19/10/2021
Instalation of Saddle 10/11/2021 11/11/2021
Instalation of Pipe 30/12/2021 04/01/2022

Pipe Saddle No.76 - 80 Start Finish


Pile Cap inc' Embedded Plate 18/10/2021 20/10/2021
Cutting Plan Saddle 31/08/2021 01/09/2021
Fabrication Saddle 14/10/2021 16/10/2021
Instalation of Saddle 08/11/2021 09/11/2021
Instalation of Pipe 24/12/2021 29/12/2021

Pipe Saddle No.72 - 76 Start Finish


Pile Cap inc' Embedded Plate 15/10/2021 17/10/2021
Cutting Plan Saddle 29/08/2021 30/08/2021
Fabrication Saddle 11/10/2021 13/10/2021
Instalation of Saddle 06/11/2021 07/11/2021
Instalation of Pipe 18/12/2021 23/12/2021

Pipe Saddle No.68 - 72 Start Finish


Pile Cap inc' Embedded Plate 12/10/2021 14/10/2021
Cutting Plan Saddle 27/08/2021 28/08/2021
Fabrication Saddle 08/10/2021 10/10/2021
Instalation of Saddle 29/10/2021 30/10/2021
Instalation of Pipe 12/12/2021 17/12/2021

Pipe Saddle No.64 - 68 Start Finish


Pile Cap inc' Embedded Plate 09/10/2021 11/10/2021
Cutting Plan Saddle 25/08/2021 26/08/2021
Fabrication Saddle 05/10/2021 07/10/2021
Instalation of Saddle 26/10/2021 27/10/2021
Instalation of Pipe 06/12/2021 11/12/2021

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 8 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Pipe Saddle No.52-56 Start Finish Pipe Saddle No.56-60 Start Finish Pipe Saddle No.60 - 64 Start Finish
Pile Cap inc' Embedded Plate 30/09/2021 02/10/2021 Pile Cap inc' Embedded Plate 03/10/2021 05/10/2021 Pile Cap inc' Embedded Plate 06/10/2021 08/10/2021
Cutting Plan Saddle 19/08/2021 20/08/2021 Cutting Plan Saddle 21/08/2021 22/08/2021 Cutting Plan Saddle 23/08/2021 24/08/2021
Fabrication Saddle 26/09/2021 28/09/2021 Fabrication Saddle 29/09/2021 01/10/2021 Fabrication Saddle 02/10/2021 04/10/2021
Instalation of Saddle 17/10/2021 18/10/2021 Instalation of Saddle 20/10/2021 21/10/2021 Instalation of Saddle 23/10/2021 24/10/2021
Instalation of Pipe 18/11/2021 23/11/2021 Instalation of Pipe 24/11/2021 29/11/2021 Instalation of Pipe 30/11/2021 05/12/2021

Productivity
Fabrication Saddle 2 saddle/day
Installation of Pipe 2 Joint/day

Pipe Saddle No.36-40 Start Finish Pipe Saddle No.44-48 Start Finish Pipe Saddle No.48-52 Start Finish
Pile Cap inc' Embedded Plate 18/09/2021 20/09/2021 Pile Cap inc' Embedded Plate 24/09/2021 26/09/2021 Pile Cap inc' Embedded Plate 27/09/2021 29/09/2021
Cutting Plan Saddle 11/08/2021 12/08/2021 Cutting Plan Saddle 15/08/2021 16/08/2021 Cutting Plan Saddle 17/08/2021 18/08/2021
Fabrication Saddle 14/09/2021 16/09/2021 Fabrication Saddle 20/09/2021 22/09/2021 Fabrication Saddle 23/09/2021 25/09/2021
Instalation of Saddle 05/10/2021 06/10/2021 Instalation of Saddle 11/10/2021 12/10/2021 Instalation of Saddle 14/10/2021 15/10/2021
Instalation of Pipe 25/10/2021 30/10/2021 Instalation of Pipe 06/11/2021 11/11/2021 Instalation of Pipe 12/11/2021 17/11/2021

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 9 of 10 Approved by: ALB
Last Issue: 15-May-21 Internal
Rev: 0
FL3B PROJECT
WATER TREATMENT PLANT STICK DIAGRAM

Pipe Saddle No.32-36 Start Finish


Pile Cap inc' Embedded Plate 15/09/2021 17/09/2021
Cutting Plan Saddle 09/08/2021 10/08/2021 Productivity
Fabrication Saddle 11/09/2021 13/09/2021
Fabrication Saddle 2 saddle/day
Instalation of Saddle 02/10/2021 03/10/2021
Instalation of Pipe 19/10/2021 24/10/2021 Installation of Pipe 2 Joint/day

Pipe Saddle No.28-32 Start Finish


Pile Cap inc' Embedded Plate 12/09/2021 14/09/2021
Cutting Plan Saddle 07/08/2021 08/08/2021
Fabrication Saddle 08/09/2021 10/09/2021
Instalation of Saddle 29/09/2021 30/09/2021
Instalation of Pipe 13/10/2021 18/10/2021

Pipe Saddle No.24-28 Start Finish


Pile Cap inc' Embedded Plate 06/09/2021 08/09/2021
Cutting Plan Saddle 03/08/2021 04/08/2021
Fabrication Saddle 02/09/2021 04/09/2021
Instalation of Saddle 23/09/2021 24/09/2021
Instalation of Pipe 01/10/2021 06/10/2021

Pipe Saddle No.20-24 Start Finish


Pile Cap inc' Embedded Plate 06/09/2021 08/09/2021
Cutting Plan Saddle 03/08/2021 04/08/2021
Fabrication Saddle 02/09/2021 04/09/2021
Instalation of Saddle 23/09/2021 24/09/2021
Instalation of Pipe 01/10/2021 06/10/2021

Pipe Saddle No.16- 20 Start Finish


Pile Cap inc' Embedded Plate 03/09/2021 05/09/2021
Cutting Plan Saddle 01/08/2021 02/08/2021
Fabrication Saddle 30/08/2021 01/09/2021
Instalation of Saddle 20/09/2021 21/09/2021
Instalation of Pipe 25/09/2021 30/09/2021

Pipe Saddle No. 12- 16 Start Finish


Pile Cap inc' Embedded Plate 31/08/2021 02/09/2021
Cutting Plan Saddle 30/07/2021 31/07/2021
Fabrication Saddle 27/08/2021 29/08/2021
Instalation of Saddle 17/09/2021 18/09/2021
Instalation of Pipe 19/09/2021 24/09/2021

Checked by: YA, DPK, EDP, SP, JMD


Prepared by: SPS Page 10 of 10 Approved by: ALB