Professional Documents
Culture Documents
This shape represents a This shape represents a This shape This shape represents a slicer.
slicer. Slicers are supported slicer. Slicers are supported represents a slicer. Slicers are supported in Excel
in Excel 2010 or later. in Excel 2010 or later. Slicers are 2010 or later.
supported in Excel
If the shape was modified in If the shape was modified 2010 or later. If the shape was modified in an
an earlier version of Excel, in an earlier version of earlier version of Excel, or if
or if the workbook was Excel, or if the workbook If the shape was the workbook was saved in
saved in Excel 2003 or was saved inCalendar
ExcelDate
2003 or12/25/2021
modified in an Calendar Days Excel 2003 30or earlier, the slicer
earlier, the slicer cannot be earlier, the slicer cannot be earlier version of cannot be used.
used. used. Excel, or if the
Duratio
Location Activity planned Start PPanned Endworkbook
n was Start
Actual Actual End
saved in Excel 2003
or earlier, the slicer
cannot be used.
' TK-22-458'! Access Door Cutting & Removal 30/10/22
Existing Bottom Plates & Old Soil Removal 6/4/2022 6/24/2022 21 5/23/2022 6/30/2022
Water Spraying & Compaction after Removal of 10/19/2022 10/22/2022 4 10/19/2022 10/22/2022
'Impervious-
667,668'! [IMPERVIOUS LINING WORKS] 9/13/2022 10/30/2022 48 9/13/2022 10/30/2022
[TANK DYKE WALL & KEY REPAIR WORKS] 10/8/2022 10/28/2022 21 10/5/2022 10/28/2022
Removal of Damaged Asphalt from Dyke & Key 10/8/2022 10/13/2022 6 10/5/2022 10/11/2022
Removal of Damaged Bitumen from Tank Skirti 10/9/2022 10/10/2022 2 10/9/2022 10/10/2022
Shuttering Works for Tank Foundation Repair 9/29/2022 10/2/2022 4 9/29/2022 10/2/2022
Water Spraying & Compaction after Removal of 9/22/2022 9/25/2022 4 9/22/2022 9/25/2022
Water Spraying & Levelling of New Gatch 10/2/2022 10/24/2022 20 10/2/2022 10/24/2022
'Impervious-
669,670'! [PREPARATORY WORKS] 10/22/2022 10/23/2022 2 10/22/2022 10/23/2022
Existing Bottom Plates & Old Soil Removal 12/9/2021 1/1/2022 24 12/9/2021 1/1/2022
Existing Bottom Plates & Old Soil Removal 8/5/2022 8/25/2022 21 6/22/2022 8/11/2022
Existing Bottom Plates & Old Soil Removal 5/2/2022 5/9/2022 8 4/20/2022 5/8/2022
'TK-29-042B'! Inspection of Tank Roof & Shell 10/26/2022 10/27/2022 2 10/26/2022 10/26/2022
Internal Sweep Blasting (Roof & Shell) 10/23/2022 10/25/2022 2 10/25/2022 10/25/2022
Existing Bottom Plates & Old Soil Removal 5/2/2022 5/24/2022 23 5/17/2022 6/26/2022
Tank Extrenal Fire line Coating Works 10/3/2022 10/13/2022 10 10/3/2022 10/26/2022
10/21/2022
11/20/2022
12/20/2022
1/24/2022
2/23/2022
3/25/2022
4/24/2022
5/24/2022
6/23/2022
7/23/2022
8/22/2022
9/21/2022
1/19/2023
2/18/2023
3/20/2023
4/19/2023
5/19/2023
6/18/2023
7/18/2023
8/17/2023
9/16/2023
Completion
#VALUE!###############################################################
1 1
1 1
1 1
1 1
(blank) 1
1
(blank)
1 1
(blank) 1 1
(blank)
(blank) 1
(blank) 1
(blank)
(blank)
1 1
1 1
1 1
1
1
1 1
1 1
1 1
(blank)
1 1
1 1
(blank)
(blank)
(blank)
(blank)
(blank) 1 1 1 1 1 1 1
1 1
1 1
1 1
1 1 1 1 1 1
1
1
1 1
1 1 1
1 1
1 1
(blank)
1 1
1
1
(blank)
(blank) 1 1
1 1
1 1
1 1 1
1 1 1
1
1
1 1
1 1
(blank)
1 1
(blank)
1
1 1
1 1
0.98
1 1
(blank) 1 1 1 1 1 1
1 1 1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1 1
1 1
(blank)
1
1
1 1
1 1 1
1 1
1
1
1 1
1 1
(blank) 1
(blank) 1
1
1
(blank) 1
1 1
1
10/16/2023
11/15/2023
M W F
12/15/2023
S
1/14/2024
T
2/13/2024
T
3/14/2024
4/13/2024
5/13/2024
6/12/2024
S M W F
7/12/2024
S
8/11/2024
T
9/10/2024
T
10/10/2024
11/9/2024
12/9/2024
1/8/2025
S M W F
2/7/2025
S
3/9/2025
T
4/8/2025
T
5/8/2025
6/7/2025
7/7/2025
8/6/2025
S M W F
9/5/2025
S
10/5/2025
T
11/4/2025
T
12/4/2025
1/3/2026
S M
#######################################################################################
2/2/2026
3/4/2026
W F
4/3/2026
S
5/3/2026
T
6/2/2026
T
7/2/2026
8/1/2026
8/31/2026
9/30/2026
S M W F
10/30/2026
S
11/29/2026
T
12/29/2026
T
1/28/2027
2/27/2027
3/29/2027
4/28/2027
S M W F
5/28/2027
S
6/27/2027
T
7/27/2027
T
8/26/2027
9/25/2027
10/25/2027
11/24/2027
S M W F
12/24/2027
S
1/23/2028
T
2/22/2028
T
3/23/2028
4/22/2028
5/22/2028
S M W
#######################################################################################
6/21/2028
F
7/21/2028
S
8/20/2028
T
9/19/2028
T
10/19/2028
11/18/2028
12/18/2028
1/17/2029 S M W F
2/16/2029
S
3/18/2029
T
4/17/2029
T
5/17/2029
6/16/2029
7/16/2029
8/15/2029
S M W F
9/14/2029
S
10/14/2029
T
11/13/2029
T
12/13/2029
1/12/2030
2/11/2030
3/13/2030
S M W F
4/12/2030
S
5/12/2030
T
6/11/2030
T
7/11/2030
8/10/2030
9/9/2030
10/9/2030
S M W F
#######################################################################################
11/8/2030
S
12/8/2030
T
1/7/2031
T
2/6/2031
3/8/2031
4/7/2031
5/7/2031
6/6/2031 S M W F
S
7/6/2031
T
8/5/2031
T
9/4/2031
10/4/2031
11/3/2031
12/3/2031
S M W F
1/2/2032
S
2/1/2032
T
3/2/2032
T
4/1/2032
5/1/2032
5/31/2032
6/30/2032
S M W F
7/30/2032
S
8/29/2032
T
9/28/2032
T
10/28/2032
11/27/2032
12/27/2032
1/26/2033
S M W F
2/25/2033
S
#######################################################################################
3/27/2033
T
4/26/2033
T
5/26/2033
6/25/2033
7/25/2033
8/24/2033
S M W F
9/23/2033
10/23/2033 S
T
11/22/2033
T
12/22/2033
1/21/2034
2/20/2034
3/22/2034
S M W F
4/21/2034
S
5/21/2034
T
6/20/2034
T
7/20/2034
8/19/2034
9/18/2034
10/18/2034
S M W F
11/17/2034
S
12/17/2034
T
1/16/2035
T
2/15/2035
3/17/2035
4/16/2035
5/16/2035
S M W F
6/15/2035
S
7/15/2035
T
#######################################################################################
8/14/2035
T
9/13/2035
10/13/2035
11/12/2035
12/12/2035
S M W F
1/11/2036
S
2/10/2036
3/11/2036 T
T
4/10/2036
5/10/2036
6/9/2036
7/9/2036
S M W F
8/8/2036
S
9/7/2036
T
10/7/2036
T
11/6/2036
12/6/2036
1/5/2037
2/4/2037
S M W F
3/6/2037
S
4/5/2037
T
5/5/2037
T
6/4/2037
7/4/2037
8/3/2037
9/2/2037
S M W F
10/2/2037
S
11/1/2037
T
12/1/2037
T
#######################################################################################
12/31/2037
1/30/2038
3/1/2038
3/31/2038
S M W F
4/30/2038
S
5/30/2038
T
6/29/2038
7/29/2038 T
8/28/2038
9/27/2038
10/27/2038
S M W F
11/26/2038
S
12/26/2038
T
1/25/2039
T
2/24/2039
3/26/2039
4/25/2039
5/25/2039
S M W F
6/24/2039
S
#########################################################
7/24/2039
Location
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
Content.Column1
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-458
TANK ROOF TYPE: Floating
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-460
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-667/668
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-669/670
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. :
TANK ROOF TYPE:
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. :
TANK ROOF TYPE:
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. :
TANK ROOF TYPE:
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-12-863
TANK ROOF TYPE:Fixed Roof
Works Executed Today :
Work Plan for Next Working Day :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-14-101
TANK ROOF TYPE:Fixed Roof
Works Executed Today :
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-253
TANK ROOF TYPE:Floating
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-264
TANK ROOF TYPE:Fixed
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-454
TANK ROOF TYPE: Cone
Works Executed Today :
Work Plan for Next Working Day :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-504
TANK ROOF TYPE:Floating Roof
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-509
TANK ROOF TYPE : Floating Roof
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-510
TANK ROOF TYPE:Cone
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-651
TANK ROOF TYPE:Dome
Works Executed Today :
Work Plan for Next Working Day :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. :
TANK ROOF TYPE:
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-34-406
TANK ROOF TYPE : Dome
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-34-424
TANK ROOF TYPE: Internal Roof/Dome
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-464
TANK ROOF TYPE:Floating
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-468
TANK ROOF TYPE:Floating Roof
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-534
TANK ROOF TYPE: Floating Roof
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-600
TANK ROOF TYPE:Fixed
Works Executed Today :
Work Plan for Next Working Day :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-671
TANK ROOF TYPE:Fixed Roof
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-703
TANK ROOF TYPE:Floating
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-63-703B
TANK ROOF TYPE: Fixed Roof
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-66-953
TANK ROOF TYPE:Fixed Roof
Works Executed Today :
Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-96-912
TANK ROOF TYPE:Fixed
Works Executed Today :
Supervisor:
Activity planned Start PPanned End
TASK DESCRIPTION
[PREPARATORY WORKS] 8/2/2021 0:00
Dead-Stock Transfer 8/2/2021 0:00 11/5/2021 0:00
Tank Blinding Works 11/6/2021 0:00 11/10/2021 0:00
Gas Freeing & Stripping 11/13/2021 0:00 11/17/2021 0:00
De-Sludging Works 11/18/2021 0:00 11/24/2021 0:00
Washing and Cleaning Works 11/24/2021 0:00 12/1/2021 0:00
Preliminary Inspection 12/2/2021 0:00 12/3/2021 0:00
Removal of Heat Detection Cable 12/27/2021 0:00 12/31/2021 0:00
External Scaffolding Erection 12/27/2021 0:00 1/4/2022 0:00
Internal Bottom Sweep Blasting 1/11/2022 0:00 1/31/2022 0:00
Inspection of Tank Bottom 2/20/2022 0:00 3/10/2022 0:00
Issuance of IAT(s) 3/12/2022 0:00 3/15/2022 0:00
Roof Seal Removal 6/11/2022 0:00 6/15/2022 0:00
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal 5/20/2022 0:00 5/23/2022 0:00
Existing Bottom Plates & Old Soil Removal 6/4/2022 0:00 6/24/2022 0:00
CP System Installation 9/18/2022 0:00 10/4/2022 0:00
Re-Bottoming Works 10/5/2022 0:00 10/30/2022 0:00
Access Door Reinstallation 10/31/2022 0:00 11/3/2022 0:00
NDT Works (DPT/Vacuum Box Test/RT) 11/4/2022 0:00 11/8/2022 0:00
Tank HydroTest 11/9/2022 0:00 12/3/2022 0:00
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 12/20/2022 0:00 1/14/2023 0:00
Roof Leg Pad Blasting & Coating 2/9/2023 0:00 2/26/2023 0:00
Tank Internal Blasting & Painting 2/9/2023 0:00 2/21/2023 0:00
U/G Piping Coating Works 12/14/2022 0:00 12/22/2022 0:00
External Scaffolding Removal 2/7/2023 0:00 2/13/2023 0:00
Tank Calibration 2/14/2023 0:00 2/16/2023 0:00
[HANDOVER WORKS]
Final Cleaning & Housekeeping 2/27/2023 0:00 3/3/2023 0:00
Tank Box-Up Works 2/27/2023 0:00 3/3/2023 0:00
De-Blinding 2/27/2023 0:00 3/3/2023 0:00
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 10/10/2022 0:00 10/11/2022 0:00
Site Survey Works 10/10/2022 0:00 10/11/2022 0:00
Permeability Test of Existing Soil 10/11/2022 0:00 10/11/2022 0:00
[IMPERVIOUS LINING WORKS] 10/12/2022 0:00 11/13/2022 0:00
Grading of Old Soil 10/12/2022 0:00 10/17/2022 0:00
Removal of Old Soil from Tank 10/15/2022 0:00 10/19/2022 0:00
Water Spraying & Compaction after Removal of Old Soil 10/19/2022 0:00 10/22/2022 0:00
Backfilling with New Gatch 10/23/2022 0:00 11/3/2022 0:00
Water Spraying & Levelling of New Gatch 10/29/2022 0:00 11/7/2022 0:00
Compaction of New Gatch 11/3/2022 0:00 11/12/2022 0:00
Final Permeability & Compaction Testing 11/13/2022 0:00 11/13/2022 0:00
[TANK FOUNDATION REPAIR WORKS] 10/29/2022 0:00 11/4/2022 0:00
Removal of Damaged Concrete Sections 10/29/2022 0:00 10/30/2022 0:00
Shuttering Works for Tank Foundation Repair 10/31/2022 0:00 11/1/2022 0:00
Concrete Casting & Curing Works 11/2/2022 0:00 11/3/2022 0:00
Final Paint Touch-Up Works 11/4/2022 0:00 11/4/2022 0:00
[TANK SKIRTING REPAIR WORKS] 11/5/2022 0:00 11/12/2022 0:00
Removal of Damaged Bitumen from Tank Skirting 11/5/2022 0:00 11/6/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 11/7/2022 0:00 11/8/2022 0:00
Application of MC-30 Capseal in Skirt Area 11/9/2022 0:00 11/10/2022 0:00
Application of Bitumen 11/11/2022 0:00 11/12/2022 0:00
[TANK DYKE WALL & KEY REPAIR WORKS] 11/4/2022 0:00 11/11/2022 0:00
Removal of Damaged Asphalt from Dyke & Key 11/4/2022 0:00 11/6/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 11/7/2022 0:00 11/9/2022 0:00
Application of MC-30 Capseal 11/10/2022 0:00 11/11/2022 0:00
Application of Bitumen 11/8/2022 0:00 11/11/2022 0:00
[STORM WATER DRAIN REPAIR WORKS] 10/17/2022 0:00 11/15/2022 0:00
Excavation of Burried Storm Water Drain 10/17/2022 0:00 10/18/2022 0:00
Removal Damaged Sections 10/18/2022 0:00 10/18/2022 0:00
Rebar Repair Works 11/11/2022 0:00 11/11/2022 0:00
Shuttering Works 11/12/2022 0:00 11/13/2022 0:00
Concrete Casting & Curing Works 11/14/2022 0:00 11/14/2022 0:00
Backfilling & Compaction Works in Adjacent Area 11/15/2022 0:00 11/15/2022 0:00
TASK DESCRIPTION
[PREPARATORY WORKS] 9/9/2022 0:00 9/10/2022 0:00
Site Survey Works 9/9/2022 0:00 9/10/2022 0:00
Permeability Test of Existing Soil 9/10/2022 0:00 9/10/2022 0:00
[IMPERVIOUS LINING WORKS] 9/13/2022 0:00 10/30/2022 0:00
Grading of Old Soil 9/13/2022 0:00 9/19/2022 0:00
Removal of Old Soil from Tank 9/16/2022 0:00 9/22/2022 0:00
Water Spraying & Compaction after Removal of Old Soil 9/22/2022 0:00 9/25/2022 0:00
Backfilling with New Gatch 9/26/2022 0:00 10/22/2022 0:00
Water Spraying & Levelling of New Gatch 10/2/2022 0:00 10/24/2022 0:00
Compaction of New Gatch 10/7/2022 0:00 10/29/2022 0:00
Final Permeability & Compaction Testing 10/23/2022 0:00 10/30/2022 0:00
[TANK FOUNDATION REPAIR WORKS] 9/27/2022 0:00 10/8/2022 0:00
Removal of Damaged Concrete Sections 9/27/2022 0:00 9/28/2022 0:00
Shuttering Works for Tank Foundation Repair 9/29/2022 0:00 10/2/2022 0:00
Concrete Casting & Curing Works 10/3/2022 0:00 10/6/2022 0:00
Final Paint Touch-Up Works 10/7/2022 0:00 10/8/2022 0:00
[TANK SKIRTING REPAIR WORKS] 10/9/2022 0:00 10/19/2022 0:00
Removal of Damaged Bitumen from Tank Skirting 10/9/2022 0:00 10/10/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 10/11/2022 0:00 10/13/2022 0:00
Application of MC-30 Capseal in Skirt Area 10/14/2022 0:00 10/15/2022 0:00
Application of Bitumen 10/16/2022 0:00 10/19/2022 0:00
[TANK DYKE WALL & KEY REPAIR WORKS] 10/8/2022 0:00 10/28/2022 0:00
Removal of Damaged Asphalt from Dyke & Key 10/8/2022 0:00 10/13/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 10/14/2022 0:00 10/21/2022 0:00
Application of MC-30 Capseal 10/19/2022 0:00 10/24/2022 0:00
Application of Bitumen 10/21/2022 0:00 10/28/2022 0:00
[STORM WATER DRAIN REPAIR WORKS] 10/17/2022 0:00 10/27/2022 0:00
Excavation of Burried Storm Water Drain 10/17/2022 0:00 10/19/2022 0:00
Removal Damaged Sections 10/18/2022 0:00 10/19/2022 0:00
Rebar Repair Works 10/20/2022 0:00 10/21/2022 0:00
Shuttering Works 10/22/2022 0:00 10/23/2022 0:00
Concrete Casting & Curing Works 10/24/2022 0:00 10/25/2022 0:00
Backfilling & Compaction Works in Adjacent Area 10/26/2022 0:00 10/27/2022 0:00
TASK DESCRIPTION
[PREPARATORY WORKS] 10/22/2022 0:00 10/23/2022 0:00
Site Survey Works 10/22/2022 0:00 10/23/2022 0:00
Permeability Test of Existing Soil 10/23/2022 0:00 10/23/2022 0:00
[IMPERVIOUS LINING WORKS] 10/23/2022 0:00 12/10/2022 0:00
Grading of Old Soil 10/24/2022 0:00 10/30/2022 0:00
Removal of Old Soil from Tank 10/27/2022 0:00 11/2/2022 0:00
Water Spraying & Compaction after Removal of Old Soil 11/2/2022 0:00 11/5/2022 0:00
Backfilling with New Gatch 11/6/2022 0:00 11/30/2022 0:00
Water Spraying & Levelling of New Gatch 11/12/2022 0:00 12/2/2022 0:00
Compaction of New Gatch 11/17/2022 0:00 12/9/2022 0:00
Final Permeability & Compaction Testing 10/23/2022 0:00 12/10/2022 0:00
[TANK FOUNDATION REPAIR WORKS] 11/14/2022 0:00 11/25/2022 0:00
Removal of Damaged Concrete Sections 11/14/2022 0:00 11/15/2022 0:00
Shuttering Works for Tank Foundation Repair 11/16/2022 0:00 11/19/2022 0:00
Concrete Casting & Curing Works 11/20/2022 0:00 11/23/2022 0:00
Final Paint Touch-Up Works 11/24/2022 0:00 11/25/2022 0:00
[TANK SKIRTING REPAIR WORKS] 11/26/2022 0:00 12/6/2022 0:00
Removal of Damaged Bitumen from Tank Skirting 11/26/2022 0:00 11/27/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 11/28/2022 0:00 11/30/2022 0:00
Application of MC-30 Capseal in Skirt Area 12/1/2022 0:00 12/2/2022 0:00
Application of Bitumen 12/3/2022 0:00 12/6/2022 0:00
[TANK DYKE WALL & KEY REPAIR WORKS] 11/18/2022 0:00 12/8/2022 0:00
Removal of Damaged Asphalt from Dyke & Key 11/18/2022 0:00 11/23/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 11/24/2022 0:00 12/1/2022 0:00
Application of MC-30 Capseal 11/29/2022 0:00 12/4/2022 0:00
Application of Bitumen 12/1/2022 0:00 12/8/2022 0:00
[STORM WATER DRAIN REPAIR WORKS] 11/26/2022 0:00 12/6/2022 0:00
Excavation of Burried Storm Water Drain 11/26/2022 0:00 11/28/2022 0:00
Removal Damaged Sections 11/27/2022 0:00 11/28/2022 0:00
Rebar Repair Works 11/29/2022 0:00 11/30/2022 0:00
Shuttering Works 12/1/2022 0:00 12/2/2022 0:00
Concrete Casting & Curing Works 12/3/2022 0:00 12/4/2022 0:00
Backfilling & Compaction Works in Adjacent Area 12/5/2022 0:00 12/6/2022 0:00
TASK DESCRIPTION
[PREPARATORY WORKS]
Site Survey Works
Permeability Test of Existing Soil
[IMPERVIOUS LINING WORKS]
Grading of Old Soil
Removal of Old Soil from Tank
Water Spraying & Compaction after Removal of Old Soil
Backfilling with New Gatch
Water Spraying & Levelling of New Gatch
Compaction of New Gatch
Final Permeability & Compaction Testing
[TANK FOUNDATION REPAIR WORKS]
Removal of Damaged Concrete Sections
Shuttering Works for Tank Foundation Repair
Concrete Casting & Curing Works
Final Paint Touch-Up Works
[TANK SKIRTING REPAIR WORKS]
Removal of Damaged Bitumen from Tank Skirting
Backfilling, Contouring and Compaction of New Gatch
Application of MC-30 Capseal in Skirt Area
Application of Bitumen
[TANK DYKE WALL & KEY REPAIR WORKS]
Removal of Damaged Asphalt from Dyke & Key
Backfilling, Contouring and Compaction of New Gatch
Application of MC-30 Capseal
Application of Bitumen
[STORM WATER DRAIN REPAIR WORKS]
Excavation of Burried Storm Water Drain
Removal Damaged Sections
Rebar Repair Works
Shuttering Works
Concrete Casting & Curing Works
Backfilling & Compaction Works in Adjacent Area
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting
Inspection of Tank
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping 9/9/2022 0:00 9/14/2022 0:00
De-Sludging Works 9/4/2022 0:00 9/8/2022 0:00
Washing and Cleaning Works 9/9/2022 0:00 9/14/2022 0:00
Preliminary Inspection 10/14/2022 0:00 10/14/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 9/21/2022 0:00 9/22/2022 0:00
Inspection of Tank Bottom 9/23/2022 0:00 9/24/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection 9/25/2022 0:00 9/26/2022 0:00
Internal Sweep Blasting 9/27/2022 0:00 9/29/2022 0:00
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works 10/13/2021 0:00 11/12/2021 0:00
NDT Works (Vaccum Box/DPT) 11/13/2021 0:00 11/15/2021 0:00
Internal Scaffolding Removal 10/3/2022 0:00 10/5/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal 12/9/2021 0:00 1/1/2022 0:00
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 9/29/2021 0:00 10/9/2021 0:00
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
2022-24833
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest 8/13/2022 0:00 10/4/2022 0:00
[BLASTING & PAINTING WORKS]
Internal Blasting & Painting 11/26/2022 0:00 12/29/2022 0:00
Tank External Blasting & Painting 11/11/2022 0:00 11/25/2022 0:00
Tank Internal Blasting & Painting 12/19/2022 0:00
U/G Piping Coating Works
External Scaffolding Removal 11/27/2022 0:00 11/30/2022 0:00
Tank Calibration 12/30/2022 0:00 12/31/2022 0:00
[HANDOVER WORKS]
Final Cleaning & Housekeeping 12/30/2022 0:00 1/3/2023 0:00
Tank Box-Up Works 12/30/2022 0:00 1/3/2023 0:00
De-Blinding 12/30/2022 0:00 1/3/2023 0:00
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 1/5/2022 0:00 8/10/2022 0:00
Dead-Stock Transfer 1/5/2022 0:00 1/31/2022 0:00
Tank Blinding Works 2/1/2022 0:00 2/3/2022 0:00
Gas Freeing & Stripping 2/14/2022 0:00 2/20/2022 0:00
De-Sludging Works 2/21/2022 0:00 2/27/2022 0:00
Washing and Cleaning Works 2/28/2022 0:00 3/3/2022 0:00
Preliminary Inspection 3/4/2022 0:00 3/5/2022 0:00
External Scaffolding Erection 5/28/2022 0:00 6/5/2022 0:00
Removal of Heat Detection Cable 3/7/2022 0:00 3/10/2022 0:00
Removal of Roof Seal 3/10/2022 0:00 3/17/2022 0:00
Internal Sweep Blasting 4/1/2022 0:00 4/6/2022 0:00
Inspection of Tank 4/4/2022 0:00 4/15/2022 0:00
Issuance of IAT(s) 3/10/2022 0:00 8/10/2022 0:00
[MECHANICAL WORKS]
Re-Roofing Works 7/28/2022 0:00 8/4/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal 8/5/2022 0:00 8/25/2022 0:00
C.P. System Installation 10/27/2022 0:00 11/19/2022 0:00
Re-Bottoming Works 11/20/2022 0:00 12/31/2022 0:00
Access Door Reinstallation 1/1/2023 0:00 1/6/2023 0:00
NDT Works (DPT/Vacuum Box Test/RT) 1/1/2023 0:00 1/6/2023 0:00
Re-Installation of Roof Seal 1/7/2023 0:00 1/14/2023 0:00
Tank HydroTest 1/16/2023 0:00 2/15/2023 0:00
Opening of Roof Seal(If Required)
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 12/21/2022 0:00 2/25/2023 0:00
Roof Leg Pad Blasting & Coating 2/15/2023 0:00 3/22/2023 0:00
Tank Internal Blasting & Painting 3/18/2023 0:00 4/8/2023 0:00
U/G Piping Coating Works
External Scaffolding Removal 2/26/2022 0:00 3/10/2022 0:00
Tank Calibration 3/11/2022 0:00 3/13/2022 0:00
[HANDOVER WORKS]
Final Cleaning & Housekeeping 3/19/2023 0:00 3/24/2023 0:00
Tank Box-Up Works 3/19/2023 0:00 3/24/2023 0:00
De-Blinding 3/19/2023 0:00 3/24/2023 0:00
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works 8/1/2022 0:00 8/8/2022 0:00
Preliminary Inspection 8/8/2022 0:00 8/9/2022 0:00
External Scaffolding Erection 9/15/2021 0:00 9/24/2021 0:00
Internal Bottom Sweep Blasting 9/26/2021 0:00 10/6/2021 0:00
Inspection of Tank Bottom 10/7/2022 0:00 10/13/2022 0:00
Issuance of IAT(s) 10/7/2022 0:00 10/13/2022 0:00
Internal Scaffloding Erection 10/21/2021 0:00 11/7/2021 0:00
Internal Sweep Blasting 12/21/2021 0:00 1/23/2022 0:00
Inspection of Tank Roof & Shell 10/21/2021 0:00 11/7/2021 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal 9/8/2022 0:00 9/18/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest 10/23/2022 0:00 11/18/2022 0:00
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 11/20/2022 0:00 12/8/2022 0:00
Tank External Blasting & Painting 7/10/2022 0:00 8/22/2022 0:00
Tank internal Blasting & Painting 8/13/2022 0:00 9/7/2022 0:00
U/G Piping Coating Works 9/19/2022 0:00 12/2/2022 0:00
External Scaffolding Removal 12/3/2022 0:00 12/7/2022 0:00
Tank Calibration 12/3/2022 0:00 12/4/2022 0:00
[HANDOVER WORKS]
Final Cleaning & Housekeeping 12/3/2022 0:00 12/8/2022 0:00
Tank Box-Up Works 12/3/2022 0:00 12/8/2022 0:00
De-Blinding 12/3/2022 0:00 12/8/2022 0:00
[MATERIAL STATUS]
KNPC Material Supply:
TASK DESCRIPTION
[PREPARATORY WORKS] 4/22/2022 0:00
Dead-Stock Transfer 4/22/2022 0:00 4/29/2022 0:00
Tank Blinding Works 6/27/2022 0:00 6/30/2022 0:00
Gas Freeing & Stripping 4/30/2022 0:00 5/4/2022 0:00
De-Sludging Works 7/9/2022 0:00 7/15/2022 0:00
Washing and Cleaning Works 5/5/2022 0:00 5/6/2022 0:00
Preliminary Inspection 8/10/2022 0:00 8/15/2022 0:00
External Scaffolding Erection 10/5/2022 0:00 10/8/2022 0:00
Internal Bottom Sweep Blasting 7/31/2022 0:00 8/6/2022 0:00
Inspection of Tank Bottom 10/2/2022 0:00 10/4/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection 9/17/2022 0:00 9/23/2022 0:00
Internal Sweep Blasting 9/24/2022 0:00 9/29/2022 0:00
Inspection of Tank Roof & Shell 10/2/2022 0:00 10/4/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works 10/22/2022 0:00 11/13/2022 0:00
NDT Works (Vaccum Box/DPT) 11/22/2022 0:00 11/25/2022 0:00
Internal Scaffolding Removal 11/25/2022 0:00 12/6/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest 12/7/2022 0:00 12/22/2022 0:00
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 10/16/2021 0:00 2/15/2022 0:00
Dead-Stock Transfer 10/16/2021 0:00 10/20/2021 0:00
Tank Blinding Works 10/21/2021 0:00 10/24/2021 0:00
Gas Freeing & Stripping 11/28/2021 0:00 12/4/2021 0:00
De-Sludging Works 12/5/2021 0:00 12/7/2021 0:00
Washing and Cleaning Works 12/8/2021 0:00 12/12/2021 0:00
Preliminary Inspection 12/13/2021 0:00 12/13/2021 0:00
External Scaffolding Erection 2/12/2022 0:00 2/17/2022 0:00
Removal of Heat Detection Cable 12/9/2021 0:00 12/11/2021 0:00
Removal of Roof Seal 12/12/2021 0:00 12/17/2021 0:00
Internal Sweep Blasting 12/12/2021 0:00 1/2/2022 0:00
Inspection of Tank 1/3/2022 0:00 1/13/2022 0:00
Issuance of IAT(s) 2/10/2022 0:00 2/15/2022 0:00
[MECHANICAL WORKS] 5/5/2022 0:00 6/13/2022 0:00
Re-Roofing Works 5/5/2022 0:00 6/23/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal 5/2/2022 0:00 5/9/2022 0:00
C.P. System Installation
Re-Bottoming Works 4/15/2022 0:00 5/28/2022 0:00
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT) 6/20/2022 0:00 6/24/2022 0:00
Re-Installation of Roof Seal 12/1/2022 0:00 12/7/2022 0:00
Tank HydroTest 5/29/2022 0:00 6/13/2022 0:00
[BLASTING & PAINTING WORKS] 10/13/2022 0:00 12/13/2022 0:00
Tank External Blasting & Painting 10/13/2022 0:00 12/7/2022 0:00
Roof Leg Pad Blasting & Coating 10/7/2022 0:00 10/21/2022 0:00
Tank Internal Blasting & Painting 11/3/2022 0:00 11/30/2022 0:00
U/G Piping Coating Works
External Scaffolding Removal 12/8/2022 0:00 12/12/2022 0:00
Tank Calibration 12/13/2022 0:00 12/13/2022 0:00
[HANDOVER WORKS] 12/8/2022 0:00 12/16/2022 0:00
Final Cleaning & Housekeeping 12/8/2022 0:00 12/12/2022 0:00
Tank Box-Up Works 12/13/2022 0:00 12/13/2022 0:00
De-Blinding 12/14/2022 0:00 12/16/2022 0:00
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 9/7/2022 0:00
Dead-Stock Transfer 9/7/2022 0:00 9/9/2022 0:00
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 9/23/2022 0:00
Dead-Stock Transfer 9/23/2022 0:00 9/25/2022 0:00
Tank Blinding Works
Gas Freeing & Stripping 9/26/2022 0:00 9/29/2022 0:00
De-Sludging Works 9/30/2022 0:00 10/2/2022 0:00
Washing and Cleaning Works 11/29/2022 0:00 12/2/2022 0:00
Preliminary Inspection
External Scaffolding Erection 11/5/2022 0:00 11/15/2022 0:00
Internal Bottom Sweep Blasting 11/1/2022 0:00 11/17/2022 0:00
Inspection of Tank Bottom 11/18/2022 0:00 11/20/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection
External Sweep Blasting 11/21/2022 0:00 11/22/2022 0:00
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer 5/22/2022 0:00 5/27/2022 0:00
Tank Blinding Works 6/14/2022 0:00 6/23/2022 0:00
Gas Freeing & Stripping 6/28/2022 0:00 7/8/2022 0:00
De-Sludging Works 7/7/2022 0:00 7/15/2022 0:00
Washing and Cleaning Works 6/28/2022 0:00 7/8/2022 0:00
Preliminary Inspection 8/21/2022 0:00 8/21/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 8/23/2022 0:00 9/23/2022 0:00
Inspection of Tank Bottom 9/24/2022 0:00 9/30/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting 8/22/2022 0:00 8/29/2022 0:00
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping 10/15/2022 0:00 10/16/2022 0:00
De-Sludging Works
Washing and Cleaning Works 10/17/2022 0:00 10/18/2022 0:00
Preliminary Inspection 10/18/2022 0:00 10/18/2022 0:00
External Scaffolding Erection 10/23/2022 0:00 10/25/2022 0:00
Internal Bottom Sweep Blasting 11/5/2022 0:00 11/8/2022 0:00
Inspection of Tank Bottom 11/9/2022 0:00 11/10/2022 0:00
Issuance of IAT(s) 10/19/2022 0:00 10/19/2022 0:00
Internal Scaffloding Erection 10/19/2022 0:00 10/19/2022 0:00
Internal Sweep Blasting (Roof & Shell) 10/23/2022 0:00 10/25/2022 0:00
Inspection of Tank Roof & Shell 10/26/2022 0:00 10/27/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 10/23/2022 0:00 10/25/2022 0:00
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works 5/16/2022 0:00 5/16/2022 0:00
Gas Freeing & Stripping 9/3/2022 0:00 9/7/2022 0:00
De-Sludging Works 8/26/2022 0:00 9/2/2022 0:00
Washing and Cleaning Works 9/8/2022 0:00 9/13/2022 0:00
Preliminary Inspection 9/14/2022 0:00 9/16/2022 0:00
External Scaffolding Erection 11/25/2022 0:00 12/6/2022 0:00
Internal Bottom Sweep Blasting 10/16/2022 0:00 10/23/2022 0:00
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 3/20/2022 0:00
Dead-Stock Transfer 3/20/2022 0:00 3/26/2022 0:00
Tank Blinding Works
Gas Freeing & Stripping 4/3/2022 0:00 4/7/2022 0:00
De-Sludging Works 4/8/2022 0:00 4/12/2022 0:00
Washing and Cleaning Works 4/13/2022 0:00 4/17/2022 0:00
Preliminary Inspection 8/4/2022 0:00 8/4/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 8/16/2022 0:00 8/26/2022 0:00
Inspection of Tank Bottom 8/27/2022 0:00 9/6/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
TASK DESCRIPTION
[PREPARATORY WORKS] 11/5/2021 0:00 6/15/2022 0:00
Dead-Stock Transfer 11/5/2021 0:00 11/17/2021 0:00
Tank Blinding Works 12/20/2021 0:00 12/24/2021 0:00
Gas Freeing & Stripping 1/3/2022 0:00 1/10/2022 0:00
De-Sludging Works 1/11/2022 0:00 1/19/2022 0:00
Washing and Cleaning Works 1/20/2022 0:00 1/25/2022 0:00
Preliminary Inspection 1/26/2022 0:00 1/28/2022 0:00
External Scaffolding Erection 4/11/2022 0:00 5/26/2022 0:00
Removal of Heat Detection Cable 2/13/2022 0:00 2/17/2022 0:00
Removal of Roof Seal 2/18/2022 0:00 2/26/2022 0:00
Internal Sweep Blasting 2/27/2022 0:00 3/10/2022 0:00
Inspection of Tank 3/11/2022 0:00 3/21/2022 0:00
Issuance of IAT(s) 2/10/2022 0:00 6/15/2022 0:00
[MECHANICAL WORKS] 5/22/2022 0:00 9/15/2022 0:00
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works 5/22/2022 0:00 5/27/2022 0:00
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT) 6/1/2022 0:00 6/2/2022 0:00
Re-Installation of Roof Seal
Tank HydroTest 7/1/2022 0:00 9/15/2022 0:00
[BLASTING & PAINTING WORKS] 9/8/2022 0:00 11/29/2022 0:00
Tank External Blasting & Painting 9/8/2022 0:00 10/30/2022 0:00
Roof Leg Pad Blasting & Coating 10/11/2022 0:00 11/18/2022 0:00
Tank Internal Blasting & Painting 11/15/2022 0:00 12/7/2022 0:00
U/G Piping Coating Works 10/21/2022 0:00 10/29/2022 0:00
External Scaffolding Removal 10/21/2022 0:00 10/27/2022 0:00
Tank Calibration 11/20/2022 0:00 11/29/2022 0:00
[HANDOVER WORKS] 11/30/2022 0:00 12/5/2022 0:00
Final Cleaning & Housekeeping 11/30/2022 0:00 12/5/2022 0:00
Tank Box-Up Works 11/30/2022 0:00 12/5/2022 0:00
De-Blinding 12/4/2022 0:00 12/10/2022 0:00
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 7/14/2022 0:00
Dead-Stock Transfer 7/14/2022 0:00 7/19/2022 0:00
Tank Blinding Works 7/27/2022 0:00 7/30/2022 0:00
Gas Freeing & Stripping 8/11/2022 0:00 8/15/2022 0:00
De-Sludging Works 8/16/2022 0:00 8/22/2022 0:00
Washing and Cleaning Works 8/23/2022 0:00 8/28/2022 0:00
Preliminary Inspection 8/25/2022 0:00 8/27/2022 0:00
External Scaffolding Erection
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting 9/20/2022 0:00 10/5/2022 0:00
Inspection of Tank 10/6/2022 0:00 10/8/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 8/10/2022 0:00
Dead-Stock Transfer 8/10/2022 0:00 8/20/2022 0:00
Tank Blinding Works 8/24/2022 0:00 8/29/2022 0:00
Gas Freeing & Stripping 9/1/2022 0:00 9/8/2022 0:00
De-Sludging Works 9/9/2022 0:00 9/13/2022 0:00
Washing and Cleaning Works 9/14/2022 0:00 9/20/2022 0:00
Preliminary Inspection 10/14/2022 0:00 10/15/2022 0:00
External Scaffolding Erection 11/10/2022 0:00 11/23/2022 0:00
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting 10/20/2022 0:00 11/7/2022 0:00
Inspection of Tank 11/8/2022 0:00 11/10/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 11/3/2020 0:00 2/6/2021 0:00
Dead-Stock Transfer
Tank Blinding Works 11/3/2020 0:00 11/5/2020 0:00
Gas Freeing & Stripping 11/7/2020 0:00 11/14/2020 0:00
De-Sludging Works 11/15/2020 0:00 11/17/2020 0:00
Washing and Cleaning Works 11/18/2020 0:00 11/23/2020 0:00
Preliminary Inspection 11/24/2020 0:00 11/24/2020 0:00
External Scaffolding Erection 4/8/2021 0:00 4/15/2021 0:00
Internal Bottom Sweep Blasting 4/12/2021 0:00 4/28/2021 0:00
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection 3/26/2021 0:00 4/10/2021 0:00
Internal Sweep Blasting 11/26/2020 0:00 1/16/2021 0:00
Inspection of Tank Roof & Shell 1/18/2021 0:00 1/28/2021 0:00
Issuance of IAT(s) 1/30/2021 0:00 2/6/2021 0:00
[MECHANICAL WORKS] 11/27/2021 0:00 10/14/2022 0:00
Re-Roofing Works 11/27/2021 0:00 1/6/2022 0:00
NDT Works (Vaccum Box/DPT) 1/7/2022 0:00 1/11/2022 0:00
Internal Scaffolding Removal 8/30/2021 0:00 9/11/2021 0:00
Access Door Cutting & Removal 1/5/2022 0:00 1/6/2022 0:00
Existing Bottom Plates & Old Soil Removal 5/2/2022 0:00 5/24/2022 0:00
CP System Installation 5/25/2022 0:00 6/15/2022 0:00
Re-Bottoming Works 6/25/2022 0:00 9/16/2022 0:00
Access Door Reinstallation 9/17/2022 0:00 9/20/2022 0:00
NDT Works (DPT/Vacuum Box Test/RT) 9/15/2022 0:00 9/19/2022 0:00
Tank HydroTest 9/20/2022 0:00 10/14/2022 0:00
[BLASTING & PAINTING WORKS] 10/10/2021 0:00 12/19/2022 0:00
Tank External Blasting & Painting 10/4/2022 0:00 12/11/2022 0:00
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting 10/24/2022 0:00 11/25/2022 0:00
U/G Piping Coating Works 10/18/2022 0:00 11/5/2022 0:00
External Scaffolding Removal 12/12/2022 0:00 12/19/2022 0:00
Tank Calibration 12/19/2022 0:00 12/19/2022 0:00
[HANDOVER WORKS] 12/15/2022 0:00 12/27/2022 0:00
Final Cleaning & Housekeeping 12/9/2022 0:00 12/15/2022 0:00
Tank Box-Up Works 12/16/2022 0:00 12/18/2022 0:00
De-Blinding 12/19/2022 0:00 12/21/2022 0:00
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 6/25/2022 0:00
Dead-Stock Transfer 6/25/2022 0:00 6/30/2022 0:00
Tank Blinding Works
Gas Freeing & Stripping 8/4/2022 0:00 8/7/2022 0:00
De-Sludging Works 8/8/2022 0:00 8/14/2022 0:00
Washing and Cleaning Works 8/15/2022 0:00 8/20/2022 0:00
Preliminary Inspection 8/10/2022 0:00 8/11/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 8/24/2022 0:00 9/10/2022 0:00
Inspection of Tank Bottom 9/11/2022 0:00 9/23/2022 0:00
Issuance of IAT(s) 8/21/2022 0:00 9/28/2022 0:00
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 4/11/2022 0:00
Dead Stock Transfer 4/11/2022 0:00 4/17/2022 0:00
Blinding 6/16/2022 0:00 6/19/2022 0:00
Gas Freeing & Stripping 6/25/2022 0:00 6/30/2022 0:00
De-Sludging 7/1/2022 0:00 7/8/2022 0:00
Washing and Cleaning 7/9/2022 0:00 7/16/2022 0:00
Preliminary Inspection 7/17/2022 0:00 7/18/2022 0:00
External Scaffolding Erection 6/28/2022 0:00 7/3/2022 0:00
Bottom Sweep Blasting 7/19/2022 0:00 8/8/2022 0:00
Inspection of Tank Bottom 9/1/2022 0:00 9/12/2022 0:00
Issuance of IAT 9/1/2022 0:00 9/12/2022 0:00
Internal Scaffloding Erection 9/22/2022 0:00 11/4/2022 0:00
Internal Sweep Blasting 11/5/2022 0:00 11/27/2022 0:00
Inspection of Tank 11/28/2022 0:00 12/3/2022 0:00
Issuance of IAT
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Internal Scaffloding Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 11/28/2022 0:00 12/2/2022 0:00
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works 8/15/2022 0:00 8/18/2022 0:00
Gas Freeing & Stripping 8/15/2022 0:00 8/18/2022 0:00
De-Sludging Works
Washing and Cleaning Works 8/19/2022 0:00 8/24/2022 0:00
Preliminary Inspection 8/25/2022 0:00 8/27/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 9/12/2022 0:00 9/18/2022 0:00
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection 11/5/2022 0:00 11/17/2022 0:00
Internal Sweep Blasting 11/18/2022 0:00 11/26/2022 0:00
Inspection of Tank Roof & Shell 11/27/2022 0:00 11/29/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
2022-24833
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 5/23/2022 0:00 6/14/2022 0:00
Dead-Stock Transfer
Tank Blinding Works 5/23/2022 0:00 5/23/2022 0:00
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection 6/12/2022 0:00 6/14/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 7/30/2022 0:00 8/11/2022 0:00
Inspection of Tank Bottom 6/19/2022 0:00 6/25/2022 0:00
Issuance of IAT(s) 7/25/2022 0:00 9/6/2022 0:00
Internal Scaffloding Erection 7/15/2022 0:00 7/22/2022 0:00
Internal Sweep Blasting 7/30/2022 0:00 8/11/2022 0:00
Inspection of Tank Roof & Shell 6/12/2022 0:00 6/14/2022 0:00
Issuance of IAT(s) 6/12/2022 0:00 6/14/2022 0:00
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal 9/29/2022 0:00 10/2/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works 9/7/2022 0:00 9/11/2022 0:00
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting 10/3/2022 0:00 10/18/2022 0:00
Tank internal Blasting & Painting
Tank Extrenal Fire line Coating Works 10/3/2022 0:00 10/13/2022 0:00
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping 10/27/2022 0:00 10/30/2022 0:00
Tank Box-Up Works 10/27/2022 0:00 10/30/2022 0:00
De-Blinding 10/27/2022 0:00 10/30/2022 0:00
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 4/25/2022 0:00 8/6/2022 0:00
Dead-Stock Transfer 5/6/2022 0:00 5/7/2022 0:00
Tank Blinding Works 5/8/2022 0:00 5/8/2022 0:00
Gas Freeing & Stripping 4/25/2022 0:00 5/2/2022 0:00
De-Sludging Works 5/3/2022 0:00 5/10/2022 0:00
Washing and Cleaning Works 5/16/2022 0:00 5/20/2022 0:00
Preliminary Inspection 5/21/2022 0:00 5/22/2022 0:00
External Scaffolding Erection 5/27/2022 0:00 6/1/2022 0:00
Internal Bottom Sweep Blasting 6/27/2022 0:00 7/3/2022 0:00
Inspection of Tank Bottom 7/8/2022 0:00 7/14/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection 7/15/2022 0:00 7/22/2022 0:00
Internal Sweep Blasting 7/23/2022 0:00 7/29/2022 0:00
Inspection of Tank Roof & Shell 8/2/2022 0:00 8/6/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS] 10/10/2022 0:00 10/16/2022 0:00
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal 10/10/2022 0:00 10/16/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS] 9/24/2022 0:00 11/16/2022 0:00
Internal Roof Blasting & Painting 9/24/2022 0:00 9/28/2022 0:00
Tank External Blasting & Painting
Tank internal Blasting & Painting 9/29/2022 0:00 11/16/2022 0:00
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS] 11/16/2022 0:00 11/24/2022 0:00
Final Cleaning & Housekeeping 11/16/2022 0:00 11/18/2022 0:00
Tank Box-Up Works 11/19/2022 0:00 11/21/2022 0:00
De-Blinding 11/22/2022 0:00 11/24/2022 0:00
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS]
2022-24833
IAT#
IAT#
IAT#
Duration Actual Start Actual End Completion
8/2/2021 0:00
96 8/2/2021 0:00 8/2/2021 0:00 1
5 11/5/2021 0:00 11/10/2021 0:00 1
5 11/13/2002 0:00 11/18/2021 0:00 1
7 11/20/2021 0:00 11/24/2021 0:00 1
8 11/25/2021 0:00 12/4/2021 0:00 1
2 12/5/2021 0:00 12/5/2021 0:00 1
5 12/29/2021 0:00 12/30/2021 0:00 1
9 2/28/2022 0:00 3/8/2022 0:00 1
21 12/27/2021 0:00 2/24/2022 0:00 1
19 3/29/2022 0:00 4/10/2022 0:00 1
4 12/26/2021 0:00 5/8/2022 0:00 1
5 6/21/2022 0:00 6/25/2022 0:00 1
10/10/2022 0:00
2 10/10/2022 0:00 10/11/2022 0:00
2 10/10/2022 0:00 10/11/2022 0:00 1
1 10/11/2022 0:00 10/11/2022 0:00 1
33 10/12/2022 0:00
5 10/12/2022 0:00 10/17/2022 0:00 1
4 10/15/2022 0:00 10/19/2022 0:00 1
4 10/19/2022 0:00 10/22/2022 0:00 1
12 10/23/2022 0:00 0.7
10 10/29/2022 0:00 0.6
10
1
7
2
2
2
1
8
2
2
2
2
8
3
3
2
4
30
2 1
1 1
1
2
1
1
9/9/2022 0:00
10/22/2022 0:00
34
15
4
1
5
5
5
4
1/5/2022 0:00
8 8/16/2022 0:00 1
66
35
21
12
2
6
6
6
8 8/1/2022 0:00 8/10/2022 0:00 1
2 8/11/2022 0:00 8/11/2022 0:00 1
10 9/15/2021 0:00 9/24/2021 0:00 1
10 9/26/2021 0:00 10/6/2021 0:00 1
6 10/7/2022 0:00 10/13/2022 0:00 1
7 10/7/2022 0:00 10/13/2022 0:00 1
17 10/21/2021 0:00 11/7/2021 0:00 1
33 1/2/2022 0:00 1/14/2022 0:00 1
17 10/21/2021 0:00 11/7/2021 0:00 1
11 1
18
43 7/10/2022 0:00 8/22/2022 0:00 1
25 8/13/2022 0:00 9/7/2022 0:00 1
74 1
4
1
4/22/2022 0:00
15
5
1
8
5
1
2
10
16
2
1
5/22/2022 0:00
32 8/23/2022 0:00
7 9/12/2022 0:00
19 0.5
3
11/3/2020 0:00
32
19
8
1
11
7
2
2
6/25/2022 0:00
4
4 8/13/2022 0:00 8/16/2022 0:00 1
4 8/13/2022 0:00 8/16/2022 0:00 1
12
8
2
5/23/2022 0:00
4 10/26/2022 0:00
4
4
4/25/2022 0:00
53
2 5/8/2022 0:00 5/8/2022 0:00 1
1 5/8/2022 0:00 5/8/2022 0:00 1
8 4/25/2022 0:00 5/2/2022 0:00 1
8 6/8/2022 0:00 6/12/2022 0:00 1
5 6/14/2022 0:00 6/15/2022 0:00 1
2 6/17/2022 0:00 6/17/2022 0:00 1
6 6/13/2022 0:00 6/18/2022 0:00 1
7 6/27/2022 0:00 7/5/2022 0:00 1
7 7/27/2022 0:00 7/31/2022 0:00 1
6
2
2
2
Remarks
REPORT DATE:
REMARKS
Inclement Weather
44880
REMARKS
Inclement Weather
44864
REMARKS
Inclement Weather
44905
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
Dhruvil Vaniyawala
REPORT DATE:
REMARKS
Water Draining is very slow(Level - 7.47m)
REMARKS
Inclement Weather
Dhruvil Vaniyawala
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
12" line to be installed at south east side
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
Dhruvil Vaniyawala
REPORT DATE:
REMARKS
New IAT received
REMARKS
Inclement Weather
Dhruvil Vaniyawala
REPORT DATE:
REMARKS
REPORT DATE:
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
Inclement Weather
Dhruvil Vaniyawala
REPORT DATE:
REMARKS
Inspection delayed and started on 20-Sep-22 (One person only available for Inspection)
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
Water draining in progress
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
Inclement Weather
REPORT DATE:
REMARKS
Inclement Weather
Dhruvil Vaniyawala
REPORT DATE:
REMARKS
New IAT received on 25-Jul-22
REMARKS
Inclement Weather
REPORT DATE:
44889
REMARKS
Bottom and 1st shell remaining
REMARKS
Inclement Weather
Dhruvil Vaniyawala
DAILY PROGRESS REPORT
TANK ROOF TYPE:Floating DIA (M) :64.62 HEIGHT (M): 19.50 PRODUCT: LFO
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
TANK ROOF TYPE:Dome DIA (M) :36.576 HEIGHT (M): 14.6304 PRODUCT: DIESEL OIL
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Cone DIA (M) :18.288 HEIGHT (M): 12.192 PRODUCT: HGO/WAXY
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Internal Roof/Dome DIA (M) : 67.056 HEIGHT (M): 22.2504 PRODUCT: Gasoline
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE:Floating DIA (M) :48.768 HEIGHT (M): 14.6304 PRODUCT: NAPTHA
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
TANK ROOF TYPE:Fixed DIA (M) :58.15 HEIGHT (M): 58.15 PRODUCT: F/Water
[PREPARATORY WORKS]
Dead-Stock Transfer NA
Tank Blinding Works NA
Gas Freeing & Stripping NA
De-Sludging Works NA
Washing and Cleaning Works 1-Aug-22 8-Aug-22 8 1-Aug-22 10-Aug-22 100%
Preliminary Inspection 8-Aug-22 9-Aug-22 2 11-Aug-22 11-Aug-22 100%
External Scaffolding Erection 15-Sep-21 24-Sep-21 10 15-Sep-21 24-Sep-21 100%
Internal Bottom Sweep Blasting 26-Sep-21 6-Oct-21 10 26-Sep-21 6-Oct-21 100%
Inspection of Tank Bottom 7-Oct-22 13-Oct-22 6 7-Oct-22 13-Oct-22 100%
Issuance of IAT(s) 7-Oct-22 13-Oct-22 7 7-Oct-22 13-Oct-22 100%
Internal Scaffloding Erection 21-Oct-21 7-Nov-21 17 21-Oct-21 7-Nov-21 100%
Internal Sweep Blasting 21-Dec-21 23-Jan-22 33 2-Jan-22 14-Jan-22 100%
Inspection of Tank Roof & Shell 21-Oct-21 7-Nov-21 17 21-Oct-21 7-Nov-21 100%
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works NA
NDT Works (Vaccum Box/DPT) NA
Internal Scaffolding Removal 8-Sep-22 18-Sep-22 11 100%
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal NA
CP System Installation NA
Re-Bottoming Works NA
Access Door Reinstallation NA
NDT Works (DPT/Vacuum Box Test/RT) NA
Tank HydroTest 23-Oct-22 18-Nov-22 27 23-Oct-22 38%
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 20-Nov-22 8-Dec-22 18
Tank External Blasting & Painting 10-Jul-22 22-Aug-22 43 10-Jul-22 22-Aug-22 100%
Tank internal Blasting & Painting 13-Aug-22 7-Sep-22 25 13-Aug-22 7-Sep-22 100%
U/G Piping Coating Works 19-Sep-22 2-Dec-22 74 100%
External Scaffolding Removal 3-Dec-22 7-Dec-22 4
Tank Calibration 3-Dec-22 4-Dec-22 1
[HANDOVER WORKS]
Final Cleaning & Housekeeping 3-Dec-22 8-Dec-22
Tank Box-Up Works 3-Dec-22 8-Dec-22
De-Blinding 3-Dec-22 8-Dec-22
[TDS & TFS WORKS]
Mechanical Repair & Coating 12" line to be installed at south east side
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE:Floating DIA (M) :43.8912 HEIGHT (M): 19.5072 PRODUCT: MOGAS
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
TANK ROOF TYPE:Fixed DIA (M) :43.8912 HEIGHT (M): 14.6304 PRODUCT: HSD
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
TANK ROOF TYPE:Fixed Roof DIA (M) :4.9 HEIGHT (M): 6.09 PRODUCT: Bitumen
[PREPARATORY WORKS]
Dead-Stock Transfer NA
Tank Blinding Works NA
Gas Freeing & Stripping 9-Sep-22 14-Sep-22 6 13-Sep-22 14-Sep-22 100%
De-Sludging Works 4-Sep-22 8-Sep-22 5 8-Sep-22 12-Sep-22 100%
Washing and Cleaning Works 9-Sep-22 14-Sep-22 6 13-Sep-22 14-Sep-22
Preliminary Inspection 14-Oct-22 14-Oct-22 1 13-Oct-22 13-Oct-22 100%
External Scaffolding Erection
Internal Bottom Sweep Blasting 21-Sep-22 22-Sep-22 2 21-Sep-22 21-Sep-22 100%
Inspection of Tank Bottom 23-Sep-22 24-Sep-22 2 13-Oct-22 13-Oct-22 100%
Issuance of IAT(s)
Internal Scaffloding Erection 25-Sep-22 26-Sep-22 2 27-Sep-22 27-Sep-22 100%
Internal Sweep Blasting 27-Sep-22 29-Sep-22 3 29-Sep-22 29-Sep-22 100%
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works 13-Oct-21 12-Nov-21 31 13-Oct-21 12-Nov-21
NDT Works (Vaccum Box/DPT) 13-Nov-21 15-Nov-21 3 13-Nov-21 15-Nov-21
Internal Scaffolding Removal 3-Oct-22 5-Oct-22 3 6-Oct-22 6-Oct-22 100%
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal 9-Dec-21 1-Jan-22 24 9-Dec-21 1-Jan-22 100%
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 29-Sep-21 9-Oct-21 11 29-Sep-21 9-Oct-21
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating 15-Mar-22 18-Mar-22
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
2022-24833
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE:Fixed Roof DIA (M) :17.983 HEIGHT (M): 10.973 PRODUCT:
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works NA
NDT Works (Vaccum Box/DPT) NA
Internal Scaffolding Removal NA
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal NA
CP System Installation NA
Re-Bottoming Works NA
Access Door Reinstallation NA
NDT Works (DPT/Vacuum Box Test/RT) NA
Tank HydroTest 13-Aug-22 4-Oct-22 53 3-Sep-22 62% Water Draining is very slow(Level - 7.47m)
[BLASTING & PAINTING WORKS]
Internal Blasting & Painting 26-Nov-22 29-Dec-22 34
Tank External Blasting & Painting 11-Nov-22 25-Nov-22 15
U/G Piping Coating Works
External Scaffolding Removal 27-Nov-22 30-Nov-22 4
Tank Calibration 30-Dec-22 31-Dec-22 1
[HANDOVER WORKS]
Final Cleaning & Housekeeping 30-Dec-22 3-Jan-23 5
Tank Box-Up Works 30-Dec-22 3-Jan-23 5
De-Blinding 30-Dec-22 3-Jan-23 5
[TDS & TFS WORKS]
Mechanical Repair & Coating 19-Dec-22 22-Dec-22 4
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE : Floating Roof DIA (M) :15.24 HEIGHT (M): 13.4112 PRODUCT: ATK
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE:Cone DIA (M) :10.668 HEIGHT (M): 10.9728 PRODUCT: MOGAS
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE : Dome DIA (M) :49.69 HEIGHT (M): 19.51 PRODUCT: PROPANE
[PREPARATORY WORKS]
Dead-Stock Transfer NA
Tank Blinding Works 16-May-22 16-May-22 16-May-22 16-May-22 100%
Gas Freeing & Stripping 3-Sep-22 7-Sep-22 4 17-Sep-22 25-Sep-22 100%
De-Sludging Works 26-Aug-22 2-Sep-22 7 26-Aug-22 15-Sep-22 100%
Washing and Cleaning Works 8-Sep-22 13-Sep-22 5 26-Sep-22 6-Oct-22 100%
Preliminary Inspection 14-Sep-22 16-Sep-22 2 9-Oct-22 9-Oct-22 100%
External Scaffolding Erection 25-Nov-22 6-Dec-22 11
Internal Bottom Sweep Blasting 16-Oct-22 23-Oct-22 7 16-Oct-22 22-Oct-22 100% Awaiting Inspection from 25-Oct-22
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Fixed Roof DIA (M) : HEIGHT (M): PRODUCT:
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works 15-Aug-22 18-Aug-22 4 13-Aug-22 16-Aug-22 100%
Gas Freeing & Stripping 15-Aug-22 18-Aug-22 4 13-Aug-22 16-Aug-22 100%
De-Sludging Works
Washing and Cleaning Works 19-Aug-22 24-Aug-22 6 17-Aug-22 3-Sep-22 100%
Preliminary Inspection 25-Aug-22 27-Aug-22 3 4-Sep-22 4-Sep-22 100% New IAT received on 06-Sep-22
External Scaffolding Erection
Internal Bottom Sweep Blasting 12-Sep-22 18-Sep-22 7 10-Sep-22 18-Sep-22 100%
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection 5-Nov-22 17-Nov-22 12
Internal Sweep Blasting 18-Nov-22 26-Nov-22 8
Inspection of Tank Roof & Shell 27-Nov-22 29-Nov-22 2
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
2022-24833
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE:Fixed DIA (M) : HEIGHT (M): PRODUCT: SOUR WATER
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
2022-24833
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping 15-Oct-22 16-Oct-22 2
De-Sludging Works
Washing and Cleaning Works 17-Oct-22 18-Oct-22 2 17-Oct-22 17-Oct-22 100%
Preliminary Inspection 18-Oct-22 18-Oct-22 1 18-Oct-22 18-Oct-22 100%
External Scaffolding Erection 23-Oct-22 25-Oct-22 3
Internal Bottom Sweep Blasting 5-Nov-22 8-Nov-22 4
Inspection of Tank Bottom 9-Nov-22 10-Nov-22 2
Issuance of IAT(s) 19-Oct-22 19-Oct-22 1 19-Oct-22 19-Oct-22 New IAT received on 19-Oct-22
Internal Scaffloding Erection 19-Oct-22 19-Oct-22 1 19-Oct-22 19-Oct-22 100%
Internal Sweep Blasting (Roof & Shell) 23-Oct-22 25-Oct-22 2 25-Oct-22 25-Oct-22 100%
Inspection of Tank Roof & Shell 26-Oct-22 27-Oct-22 2 26-Oct-22 26-Oct-22 100%
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 23-Oct-22 25-Oct-22 3 24-Oct-22 30%
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE:Fixed Roof DIA (M) : HEIGHT (M): PRODUCT: GASOIL
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE:Fixed Roof DIA (M) :29.016 HEIGHT (M): 15.24 PRODUCT: SEA WATER
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
TANK ROOF TYPE: Floating Roof DIA (M) :49.866 HEIGHT (M): 19.507 PRODUCT: ATK
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
TANK ROOF TYPE:Floating Roof DIA (M) :4.14528 HEIGHT (M): 19.5072 PRODUCT: NAPTHA
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
TANK ROOF TYPE:Floating Roof DIA (M) :24.384 HEIGHT (M): 12.192 PRODUCT: KEROSENE
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
TANK ROOF TYPE: Floating DIA (M) :43.90 HEIGHT (M): 17.07 PRODUCT: KLD
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting
Inspection of Tank
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:
[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS
IAT#
IAT#
IAT#
IAT#
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:
Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks: