PROJECT GANTT CHART

This shape represents a This shape represents a This shape This shape represents a slicer.
slicer. Slicers are supported slicer. Slicers are supported represents a slicer. Slicers are supported in Excel
in Excel 2010 or later. in Excel 2010 or later. Slicers are 2010 or later.
supported in Excel
If the shape was modified in If the shape was modified 2010 or later. If the shape was modified in an
an earlier version of Excel, in an earlier version of earlier version of Excel, or if
or if the workbook was Excel, or if the workbook If the shape was the workbook was saved in
saved in Excel 2003 or was saved inCalendar
ExcelDate
2003 or12/25/2021
modified in an Calendar Days Excel 2003 30or earlier, the slicer
earlier, the slicer cannot be earlier, the slicer cannot be earlier version of cannot be used.
used. used. Excel, or if the
Duratio
Location Activity planned Start PPanned Endworkbook
n was Start
Actual Actual End
saved in Excel 2003
or earlier, the slicer
cannot be used.
' TK-22-458'! Access Door Cutting & Removal 30/10/22

CP System Installation 9/18/2022 10/4/2022 17 9/18/2022 10/18/2022

Dead-Stock Transfer 8/2/2021 11/5/2021 96 8/2/2021 8/2/2021

De-Sludging Works 11/18/2021 11/24/2021 7 11/20/2021 11/24/2021

Existing Bottom Plates & Old Soil Removal 6/4/2022 6/24/2022 21 5/23/2022 6/30/2022

External Scaffolding Erection 12/27/2021 1/4/2022 9 2/28/2022 3/8/2022

Gas Freeing & Stripping 11/13/2021 11/17/2021 5 11/13/2002 11/18/2021

Inspection of Tank Bottom 2/20/2022 3/10/2022 19 3/29/2022 4/10/2022

Internal Bottom Sweep Blasting 1/11/2022 1/31/2022 21 12/27/2021 2/24/2022

Issuance of IAT(s) 3/12/2022 3/15/2022 4 12/26/2021 5/8/2022

Preliminary Inspection 12/2/2021 12/3/2021 2 12/5/2021 12/5/2021

Removal of Heat Detection Cable 12/27/2021 12/31/2021 5 12/29/2021 12/30/2021

Roof Seal Removal 6/11/2022 6/15/2022 5 6/21/2022 6/25/2022

Tank Blinding Works 11/6/2021 11/10/2021 5 11/5/2021 11/10/2021

Tank External Blasting & Painting 12/20/2022 1/14/2023 26 2/22/2022 2/24/2022

Washing and Cleaning Works 11/24/2021 12/1/2021 8 11/25/2021 12/4/2021


'Impervious-460'! [PREPARATORY WORKS] 10/10/2022 10/11/2022 2 10/10/2022 10/11/2022

Grading of Old Soil 10/12/2022 10/17/2022 5 10/12/2022 10/17/2022

Permeability Test of Existing Soil 10/11/2022 10/11/2022 1 10/11/2022 10/11/2022

Removal of Old Soil from Tank 10/15/2022 10/19/2022 4 10/15/2022 10/19/2022

Site Survey Works 10/10/2022 10/11/2022 2 10/10/2022 10/11/2022

Water Spraying & Compaction after Removal of 10/19/2022 10/22/2022 4 10/19/2022 10/22/2022

'Impervious-
667,668'! [IMPERVIOUS LINING WORKS] 9/13/2022 10/30/2022 48 9/13/2022 10/30/2022

[PREPARATORY WORKS] 9/9/2022 9/10/2022 2 9/9/2022 9/10/2022

[STORM WATER DRAIN REPAIR WORKS] 10/17/2022 10/27/2022 11 10/17/2022 10/27/2022

[TANK DYKE WALL & KEY REPAIR WORKS] 10/8/2022 10/28/2022 21 10/5/2022 10/28/2022

[TANK FOUNDATION REPAIR WORKS] 9/27/2022 10/8/2022 12 9/27/2022 10/8/2022

[TANK SKIRTING REPAIR WORKS] 10/9/2022 10/19/2022 11 10/9/2022 10/19/2022

Application of Bitumen 10/16/2022 10/19/2022 4 10/16/2022 10/19/2022

Application of MC-30 Capseal 10/19/2022 10/24/2022 6 10/17/2022 10/22/2022

Application of MC-30 Capseal in Skirt Area 10/14/2022 10/15/2022 2 10/14/2022 10/15/2022

Backfilling & Compaction Works in Adjacent Ar 10/26/2022 10/27/2022 2 10/26/2022 10/27/2022

Backfilling with New Gatch 9/26/2022 10/22/2022 24 9/26/2022 10/22/2022

Backfilling, Contouring and Compaction of Ne 10/11/2022 10/13/2022 3 10/11/2022 10/13/2022

10/14/2022 10/21/2022 8 10/12/2022 10/19/2022

Concrete Casting & Curing Works 10/3/2022 10/6/2022 4 10/3/2022 10/6/2022

10/24/2022 10/25/2022 2 10/24/2022 10/25/2022

Excavation of Burried Storm Water Drain 10/17/2022 10/19/2022 3 10/17/2022 10/19/2022


Final Paint Touch-Up Works 10/7/2022 10/8/2022 2 10/7/2022 10/8/2022

Grading of Old Soil 9/13/2022 9/19/2022 6 9/13/2022 9/19/2022

Permeability Test of Existing Soil 9/10/2022 9/10/2022 1 9/10/2022 9/10/2022

Rebar Repair Works 10/20/2022 10/21/2022 2 10/20/2022 10/21/2022

Removal Damaged Sections 10/18/2022 10/19/2022 2 10/18/2022 10/19/2022

Removal of Damaged Asphalt from Dyke & Key 10/8/2022 10/13/2022 6 10/5/2022 10/11/2022

Removal of Damaged Bitumen from Tank Skirti 10/9/2022 10/10/2022 2 10/9/2022 10/10/2022

Removal of Damaged Concrete Sections 9/27/2022 9/28/2022 2 9/27/2022 9/28/2022

Removal of Old Soil from Tank 9/16/2022 9/22/2022 6 9/16/2022 9/22/2022

Shuttering Works 10/22/2022 10/23/2022 2 10/22/2022 10/23/2022

Shuttering Works for Tank Foundation Repair 9/29/2022 10/2/2022 4 9/29/2022 10/2/2022

Site Survey Works 9/9/2022 9/10/2022 2 9/9/2022 9/10/2022

Water Spraying & Compaction after Removal of 9/22/2022 9/25/2022 4 9/22/2022 9/25/2022

Water Spraying & Levelling of New Gatch 10/2/2022 10/24/2022 20 10/2/2022 10/24/2022

'Impervious-
669,670'! [PREPARATORY WORKS] 10/22/2022 10/23/2022 2 10/22/2022 10/23/2022

Permeability Test of Existing Soil 10/23/2022 10/23/2022 1 10/23/2022 10/23/2022

Site Survey Works 10/22/2022 10/23/2022 2 10/22/2022 10/23/2022

'TK-12-863'! De-Sludging Works 9/4/2022 9/8/2022 5 9/8/2022 9/12/2022

Existing Bottom Plates & Old Soil Removal 12/9/2021 1/1/2022 24 12/9/2021 1/1/2022

Gas Freeing & Stripping 9/9/2022 9/14/2022 6 9/13/2022 9/14/2022

Inspection of Tank Bottom 9/23/2022 9/24/2022 2 10/13/2022 10/13/2022

Internal Bottom Sweep Blasting 9/21/2022 9/22/2022 2 9/21/2022 9/21/2022


Internal Roof Blasting & Painting 9/29/2021 10/9/2021 11 9/29/2021 10/9/2021

Internal Scaffloding Erection 9/25/2022 9/26/2022 2 9/27/2022 9/27/2022

Internal Scaffolding Removal 10/3/2022 10/5/2022 3 10/6/2022 10/6/2022

Internal Sweep Blasting 9/27/2022 9/29/2022 3 9/29/2022 9/29/2022

NDT Works (Vaccum Box/DPT) 11/13/2021 11/15/2021 3 11/13/2021 11/15/2021

Preliminary Inspection 10/14/2022 10/14/2022 1 10/13/2022 10/13/2022

Re-Roofing Works 10/13/2021 11/12/2021 31 10/13/2021 11/12/2021

Washing and Cleaning Works 9/9/2022 9/14/2022 6 9/13/2022 9/14/2022

'TK-22-253'! [PREPARATORY WORKS] 1/5/2022 8/10/2022 243 1/5/2022 8/10/2022

Dead-Stock Transfer 1/5/2022 1/31/2022 27 1/5/2022 1/31/2022

De-Sludging Works 2/21/2022 2/27/2022 7 2/21/2022 2/27/2022

Existing Bottom Plates & Old Soil Removal 8/5/2022 8/25/2022 21 6/22/2022 8/11/2022

External Scaffolding Erection 5/28/2022 6/5/2022 9 5/28/2022 6/5/2022

Gas Freeing & Stripping 2/14/2022 2/20/2022 7 2/15/2022 2/20/2022

Inspection of Tank 4/4/2022 4/15/2022 12 5/8/2022 6/3/2022

Internal Sweep Blasting 4/1/2022 4/6/2022 6 4/2/2022 4/3/2022

Issuance of IAT(s) 3/10/2022 8/10/2022 154 3/10/2022 8/10/2022

Preliminary Inspection 3/4/2022 3/5/2022 2 3/6/2022 3/6/2022

Removal of Heat Detection Cable 3/7/2022 3/10/2022 4 3/11/2022 3/20/2022

Removal of Roof Seal 3/10/2022 3/17/2022 8 3/21/2022 3/31/2022

Tank Blinding Works 2/1/2022 2/3/2022 3 2/6/2022 2/6/2022

Washing and Cleaning Works 2/28/2022 3/3/2022 4 2/28/2022 3/2/2022

'TK-22-264'! External Scaffolding Erection 9/15/2021 9/24/2021 10 9/15/2021 9/24/2021


Inspection of Tank Bottom 10/7/2022 10/13/2022 6 10/7/2022 10/13/2022

Inspection of Tank Roof & Shell 10/21/2021 11/7/2021 17 10/21/2021 11/7/2021

Internal Bottom Sweep Blasting 9/26/2021 10/6/2021 10 9/26/2021 10/6/2021

Internal Scaffloding Erection 10/21/2021 11/7/2021 17 10/21/2021 11/7/2021

Internal Sweep Blasting 12/21/2021 1/23/2022 33 1/2/2022 1/14/2022

Issuance of IAT(s) 10/7/2022 10/13/2022 7 10/7/2022 10/13/2022

Preliminary Inspection 8/8/2022 8/9/2022 2 8/11/2022 8/11/2022

Tank External Blasting & Painting 7/10/2022 8/22/2022 43 7/10/2022 8/22/2022

Tank Internal Blasting & Painting 8/13/2022 9/7/2022 25 8/13/2022 9/7/2022

Washing and Cleaning Works 8/1/2022 8/8/2022 8 8/1/2022 8/10/2022

'TK-22-454'! Dead-Stock Transfer 4/22/2022 4/29/2022 8 4/23/2022 4/27/2022

De-Sludging Works 7/9/2022 7/15/2022 7 7/17/2022 7/20/2022

External Scaffolding Erection 10/5/2022 10/8/2022 4 8/28/2022 8/29/2022

Gas Freeing & Stripping 4/30/2022 5/4/2022 5 5/8/2022 7/20/2022

HydroTest 10/5/2022 10/7/2022 3 8/1/2022 8/1/2022

Inspection of Tank Bottom 10/2/2022 10/4/2022 3 10/4/2022 10/4/2022

Inspection of Tank Roof & Shell 10/2/2022 10/4/2022 2 10/3/2022 10/4/2022

Internal Bottom Sweep Blasting 7/31/2022 8/6/2022 7 7/31/2022 8/15/2022

Internal Scaffloding Erection 9/17/2022 9/23/2022 7 9/20/2022 9/24/2022

Internal Scaffolding Removal 11/25/2022 12/6/2022 10 9/20/2022 9/24/2022

Internal Sweep Blasting 9/24/2022 9/29/2022 6 9/26/2022 10/2/2022

Mechanical Repair & Coating 10/5/2022 10/7/2022 3 8/1/2022 8/1/2022


Preliminary Inspection 8/10/2022 8/15/2022 6 8/19/2022 8/19/2022

Service Test 10/5/2022 10/7/2022 3 8/1/2022 8/1/2022

Tank Blinding Works 6/27/2022 6/30/2022 4 6/25/2022 6/25/2022

Washing and Cleaning Works 5/5/2022 5/6/2022 2 7/21/2022 7/21/2022

'TK-22-504'! [PREPARATORY WORKS] 10/16/2021 2/15/2022 79 10/16/2021 4/13/2022

Dead-Stock Transfer 10/16/2021 10/20/2021 5 10/16/2021 10/19/2021

De-Sludging Works 12/5/2021 12/7/2021 3 12/1/2021 12/2/2021

Existing Bottom Plates & Old Soil Removal 5/2/2022 5/9/2022 8 4/20/2022 5/8/2022

External Scaffolding Erection 2/12/2022 2/17/2022 6 2/14/2022 2/20/2022

Gas Freeing & Stripping 11/28/2021 12/4/2021 7 11/28/2021 11/30/2021

HydroTest 8/1/2022 8/10/2022 10 8/1/2022 8/11/2022

Inspection of Tank 1/3/2022 1/13/2022 11 3/22/2022 4/3/2022

Internal Sweep Blasting 12/12/2021 1/2/2022 22 1/5/2022 1/21/2022

Issuance of IAT(s) 2/10/2022 2/15/2022 6 12/13/2021 4/13/2022

Mechanical Repair & Coating 8/1/2022 8/10/2022 10 8/1/2022 8/11/2022

NDT Works (DPT/Vacuum Box Test/RT) 6/20/2022 6/24/2022 4 7/3/2022 7/7/2022

Preliminary Inspection 12/13/2021 12/13/2021 1 12/13/2021 12/13/2021

Re-Bottoming Works 4/15/2022 5/28/2022 44 5/7/2022 7/2/2022

Removal of Heat Detection Cable 12/9/2021 12/11/2021 3 1/4/2022 1/4/2022

Removal of Roof Seal 12/12/2021 12/17/2021 6 12/28/2021 1/3/2022

Re-Roofing Works 5/5/2022 6/23/2022 50 5/10/2022 6/9/2022

Service Test 8/1/2022 8/10/2022 10 8/1/2022 8/11/2022

Tank Blinding Works 10/21/2021 10/24/2021 4 10/27/2021 10/27/2021


Tank HydroTest 5/29/2022 6/13/2022 16 9/1/2022 9/20/2022

Washing and Cleaning Works 12/8/2021 12/12/2021 5 12/2/2021 12/6/2021

'TK-22-509'! Dead-Stock Transfer 9/7/2022 9/9/2022 3 9/8/2022 9/9/2022

'TK-22-510'! Dead-Stock Transfer 9/23/2022 9/25/2022 3 9/23/2022 9/26/2022

De-Sludging Works 9/30/2022 10/2/2022 3 10/4/2022 10/5/2022

Gas Freeing & Stripping 9/26/2022 9/29/2022 4 10/1/2022 10/3/2022

Washing and Cleaning Works 11/29/2022 12/2/2022 4 10/4/2022 10/5/2022

'TK-22-651'! Dead-Stock Transfer 5/22/2022 5/27/2022 6 5/30/2022 6/20/2022

De-Sludging Works 7/7/2022 7/15/2022 9 7/8/2022 8/16/2022

Gas Freeing & Stripping 6/28/2022 7/8/2022 11 8/2/2022 8/19/2022

Internal Sweep Blasting 8/22/2022 8/29/2022 8 8/23/2022 9/12/2022

Preliminary Inspection 8/21/2022 8/21/2022 (blank) 8/21/2022 8/21/2022

Tank Blinding Works 6/14/2022 6/23/2022 8 6/25/2022 6/25/2022

Washing and Cleaning Works 6/28/2022 7/8/2022 11 8/2/2022 8/19/2022

'TK-29-042B'! Inspection of Tank Roof & Shell 10/26/2022 10/27/2022 2 10/26/2022 10/26/2022

Internal Scaffloding Erection 10/19/2022 10/19/2022 1 10/19/2022 10/19/2022

Internal Sweep Blasting (Roof & Shell) 10/23/2022 10/25/2022 2 10/25/2022 10/25/2022

Issuance of IAT(s) 10/19/2022 10/19/2022 1 10/19/2022 10/19/2022

Preliminary Inspection 10/18/2022 10/18/2022 1 10/18/2022 10/18/2022

Washing and Cleaning Works 10/17/2022 10/18/2022 2 10/17/2022 10/17/2022

'TK-34-406'! De-Sludging Works 8/26/2022 9/2/2022 7 8/26/2022 9/15/2022

Gas Freeing & Stripping 9/3/2022 9/7/2022 4 9/17/2022 9/25/2022


Internal Bottom Sweep Blasting 10/16/2022 10/23/2022 7 10/16/2022 10/22/2022

Preliminary Inspection 9/14/2022 9/16/2022 2 10/9/2022 10/9/2022

Tank Blinding Works 5/16/2022 5/16/2022 (blank) 5/16/2022 5/16/2022

Washing and Cleaning Works 9/8/2022 9/13/2022 5 9/26/2022 10/6/2022

'TK-34-424'! Dead-Stock Transfer 3/20/2022 3/26/2022 7 3/26/2022 5/22/2022

De-Sludging Works 4/8/2022 4/12/2022 5 6/26/2022 7/16/2022

Gas Freeing & Stripping 4/3/2022 4/7/2022 5 6/2/2022 6/6/2022

Inspection of Tank Bottom 8/27/2022 9/6/2022 11 8/25/2022 9/1/2022

Internal Bottom Sweep Blasting 8/16/2022 8/26/2022 11 8/16/2022 8/24/2022

Preliminary Inspection 8/4/2022 8/4/2022 1 8/7/2022 8/7/2022

Washing and Cleaning Works 4/13/2022 4/17/2022 5 7/21/2022 8/3/2022

'TK-61-464'! [PREPARATORY WORKS] 11/5/2021 6/15/2022 253 11/5/2021 6/15/2022

Dead-Stock Transfer 11/5/2021 11/17/2021 13 11/5/2021 12/20/2021

De-Sludging Works 1/11/2022 1/19/2022 9 1/12/2022 1/21/2022

External Scaffolding Erection 4/11/2022 5/26/2022 46 4/11/2022 5/26/2022

Gas Freeing & Stripping 1/3/2022 1/10/2022 8 1/4/2022 1/11/2022

HydroTest 7/1/2022 9/15/2022 16 7/18/2022 9/22/2022

Inspection of Tank 3/11/2022 3/21/2022 11 4/11/2022 4/21/2022

Internal Sweep Blasting 2/27/2022 3/10/2022 12 2/27/2022 3/12/2022

Issuance of IAT(s) 2/10/2022 6/15/2022 126 2/10/2022 6/15/2022

Mechanical Repair & Coating 7/23/2022 7/30/2022 8 6/15/2022 6/20/2022

NDT Works (DPT/Vacuum Box Test/RT) 6/1/2022 6/2/2022 2 6/7/2022 6/7/2022

Preliminary Inspection 1/26/2022 1/28/2022 3 2/7/2022 2/7/2022


Re-Bottoming Works 5/22/2022 5/27/2022 6 6/3/2022 6/6/2022

Removal of Heat Detection Cable 2/13/2022 2/17/2022 5 2/28/2022 2/28/2022

Removal of Roof Seal 2/18/2022 2/26/2022 9 2/28/2022 3/6/2022

Tank Blinding Works 12/20/2021 12/24/2021 5 12/22/2021 12/23/2021

Tank HydroTest 7/1/2022 9/15/2022 77 6/28/2022 7/10/2022

Washing and Cleaning Works 1/20/2022 1/25/2022 6 1/21/2022 2/6/2022

'TK-61-468'! Dead-Stock Transfer 7/14/2022 7/19/2022 6 7/21/2022 7/26/2022

De-Sludging Works 8/16/2022 8/22/2022 7 8/14/2022 8/21/2022

Gas Freeing & Stripping 8/11/2022 8/15/2022 5 8/23/2022 8/23/2022

Internal Sweep Blasting 9/20/2022 10/5/2022 16 9/20/2022 10/5/2022

Preliminary Inspection 8/25/2022 8/27/2022 3 9/6/2022 9/6/2022

Tank Blinding Works 7/27/2022 7/30/2022 4 8/1/2022 8/3/2022

Washing and Cleaning Works 8/23/2022 8/28/2022 6 8/24/2022 9/5/2022

'TK-61-534'! Dead-Stock Transfer 8/10/2022 8/20/2022 11 8/13/2022 8/18/2022

De-Sludging Works 9/9/2022 9/13/2022 5 9/5/2022 9/11/2022

Gas Freeing & Stripping 9/1/2022 9/8/2022 8 9/5/2022 9/11/2022

Preliminary Inspection 10/14/2022 10/15/2022 2 10/16/2022 10/16/2022

Tank Blinding Works 8/24/2022 8/29/2022 6 8/26/2022 8/29/2022

Washing and Cleaning Works 9/14/2022 9/20/2022 7 9/12/2022 9/15/2022

'TK-61-600'! [PREPARATORY WORKS] 11/3/2020 2/6/2021 133 11/3/2020 7/4/2022

Access Door Cutting & Removal 1/5/2022 1/6/2022 2 5/13/2022 5/15/2022

Access Door Reinstallation 9/17/2022 9/20/2022 3 9/27/2022 9/29/2022


CP System Installation 5/25/2022 6/15/2022 22 6/27/2022 8/11/2022

De-Sludging Works 11/15/2020 11/17/2020 3 11/13/2020 11/14/2020

Existing Bottom Plates & Old Soil Removal 5/2/2022 5/24/2022 23 5/17/2022 6/26/2022

External Scaffolding Erection 4/8/2021 4/15/2021 8 4/8/2021 4/15/2021

Gas Freeing & Stripping 11/7/2020 11/14/2020 8 11/7/2020 11/12/2020

Inspection of Tank Roof & Shell 1/18/2021 1/28/2021 11 1/27/2021 2/15/2021

Internal Bottom Sweep Blasting 4/12/2021 4/28/2021 17 5/9/2021 5/26/2021

Internal Scaffloding Erection 3/26/2021 4/10/2021 16 4/17/2021 5/8/2021

Internal Scaffolding Removal 8/30/2021 9/11/2021 13 4/24/2022 5/11/2022

Internal Sweep Blasting 11/26/2020 1/16/2021 52 11/26/2020 1/16/2021

Issuance of IAT(s) 1/30/2021 2/6/2021 8 3/23/2021 7/4/2022

NDT Works (DPT/Vacuum Box Test/RT) 9/15/2022 9/19/2022 5 9/26/2022 10/1/2022

NDT Works (Vaccum Box/DPT) 1/7/2022 1/11/2022 5 9/25/2022 10/2/2022

Preliminary Inspection 11/24/2020 11/24/2020 1 11/17/2020 11/17/2020

Re-Bottoming Works 6/25/2022 9/16/2022 45 8/12/2022 9/26/2022

Re-Roofing Works 11/27/2021 1/6/2022 41 1/9/2022 9/28/2022

Tank Blinding Works 11/3/2020 11/5/2020 3 11/3/2020 11/5/2020

Washing and Cleaning Works 11/18/2020 11/23/2020 6 11/13/2020 11/15/2020

'TK-61-671'! Dead-Stock Transfer 6/25/2022 6/30/2022 6 7/10/2022 7/14/2022

De-Sludging Works 8/8/2022 8/14/2022 7 8/3/2022 8/6/2022

Gas Freeing & Stripping 8/4/2022 8/7/2022 4 8/2/2022 8/7/2022

Internal Bottom Sweep Blasting 8/24/2022 9/10/2022 (blank) 8/20/2022 9/7/2022

Preliminary Inspection 8/10/2022 8/11/2022 2 8/14/2022 8/14/2022


Washing and Cleaning Works 8/15/2022 8/20/2022 6 8/6/2022 8/9/2022

'TK-61-703'! Blinding 6/16/2022 6/19/2022 4 6/16/2022 6/19/2022

Bottom Sweep Blasting 7/19/2022 8/8/2022 21 7/19/2022 8/31/2022

Dead Stock Transfer 4/11/2022 4/17/2022 7 4/11/2022 4/17/2022

De-Sludging 7/1/2022 7/8/2022 8 7/2/2022 7/8/2022

External Scaffolding Erection 6/28/2022 7/3/2022 6 6/28/2022 7/3/2022

Gas Freeing & Stripping 6/25/2022 6/30/2022 6 6/25/2022 6/30/2022

Inspection of Tank Bottom 9/1/2022 9/12/2022 12 9/20/2022 9/27/2022

Issuance of IAT 9/1/2022 9/12/2022 12 9/20/2022 9/27/2022

Preliminary Inspection 7/17/2022 7/18/2022 2 7/17/2022 7/17/2022

Washing and Cleaning 7/9/2022 7/16/2022 8 7/12/2022 7/17/2022

'TK-63-703B'! Gas Freeing & Stripping 8/15/2022 8/18/2022 4 8/13/2022 8/16/2022

Internal Bottom Sweep Blasting 9/12/2022 9/18/2022 7 9/10/2022 9/18/2022

Preliminary Inspection 8/25/2022 8/27/2022 3 9/4/2022 9/4/2022

Tank Blinding Works 8/15/2022 8/18/2022 4 8/13/2022 8/16/2022

Washing and Cleaning Works 8/19/2022 8/24/2022 6 8/17/2022 9/3/2022

'TK-66-953'! [PREPARATORY WORKS] 5/23/2022 6/14/2022 95 5/23/2022 7/3/2022

Inspection of Tank Bottom 6/19/2022 6/25/2022 7 9/1/2022 9/5/2022

Inspection of Tank Roof & Shell 6/12/2022 6/14/2022 3 6/23/2022 7/3/2022

Internal Bottom Sweep Blasting 7/30/2022 8/11/2022 13 8/3/2022 8/22/2022

Internal Scaffloding Erection 7/15/2022 7/22/2022 8 8/15/2022 8/27/2022

Internal Scaffolding Removal 9/29/2022 10/2/2022 4 9/19/2022 9/20/2022


Internal Sweep Blasting 7/30/2022 8/11/2022 13 8/3/2022 8/22/2022

Issuance of IAT(s) 6/12/2022 6/14/2022 3 6/23/2022 7/3/2022

7/25/2022 9/6/2022 44 7/25/2022 9/6/2022

Preliminary Inspection 6/12/2022 6/14/2022 3 6/23/2022 7/3/2022

Re-Bottoming Works 9/7/2022 9/11/2022 5 9/7/2022 9/7/2022

Tank Blinding Works 5/23/2022 5/11/22 1 5/23/2022 5/23/2022

Tank External Blasting & Painting 10/3/2022 10/18/2022 16 10/3/2022 10/18/2022

Tank Extrenal Fire line Coating Works 10/3/2022 10/13/2022 10 10/3/2022 10/26/2022

'TK-96-912'! Dead-Stock Transfer 5/6/2022 5/7/2022 2 5/8/2022 5/8/2022

De-Sludging Works 5/3/2022 5/10/2022 8 6/8/2022 6/12/2022

External Scaffolding Erection 5/27/2022 6/1/2022 6 6/13/2022 6/18/2022

Gas Freeing & Stripping 4/25/2022 5/2/2022 8 4/25/2022 5/2/2022

Inspection of Tank Bottom 7/8/2022 7/14/2022 7 7/27/2022 7/31/2022

Inspection of Tank Roof & Shell 8/2/2022 8/6/2022 4 9/19/2022 9/19/2022

Internal Bottom Sweep Blasting 6/27/2022 7/3/2022 7 6/27/2022 7/5/2022

Internal Roof Blasting & Painting 9/24/2022 9/28/2022 4 9/22/2022 10/2/2022

Internal Scaffloding Erection 7/15/2022 7/22/2022 7 8/15/2022 8/27/2022

Internal Scaffolding Removal 10/10/2022 10/16/2022 6 10/19/2022 10/23/2022

Internal Sweep Blasting 7/23/2022 7/29/2022 6 9/3/2022 9/15/2022

Preliminary Inspection 5/21/2022 5/22/2022 2 6/17/2022 6/17/2022

Tank Blinding Works 5/8/2022 5/8/2022 1 5/8/2022 5/8/2022

Washing and Cleaning Works 5/16/2022 5/20/2022 5 6/14/2022 6/15/2022


This shape represents a slicer.
Slicers are supported in Excel
2010 or later.

f the shape was modified in an


earlier version of Excel, or if
he workbook was saved in
Excel 2003 or earlier, the slicer S M W F S T T S M W F S T T S M W F S T T S
cannot be used. 12/25/2021

10/21/2022
11/20/2022
12/20/2022
1/24/2022
2/23/2022
3/25/2022
4/24/2022
5/24/2022
6/23/2022
7/23/2022
8/22/2022
9/21/2022

1/19/2023
2/18/2023
3/20/2023
4/19/2023
5/19/2023
6/18/2023
7/18/2023
8/17/2023
9/16/2023
Completion

#VALUE!###############################################################

1 1

1 1

1 1

1 1

(blank) 1

1
(blank)

1 1

(blank) 1 1

(blank)

(blank) 1

(blank) 1

(blank)

(blank)

1 1

1 1

1 1

1
1

1 1

1 1

1 1

(blank)

1 1

1 1
(blank)

(blank)

(blank)

(blank)

(blank) 1 1 1 1 1 1 1

1 1

1 1

1 1

1 1 1 1 1 1

1
1

1 1

1 1 1

1 1

1 1

(blank)

1 1

1
1

(blank)

(blank) 1 1

1 1

1 1

1 1 1

1 1 1

1
1

1 1

1 1

(blank)

1 1

(blank)

1
1 1

1 1

0.98

1 1

(blank) 1 1 1 1 1 1

1 1 1

1 1 1

1 1 1 1 1

1 1

1
1 1

1 1

1 1 1

1 1

1 1

1 1

(blank)

1
1

1 1

1 1 1

1 1

1
1

1 1

1 1

(blank) 1

(blank) 1

1
1

(blank) 1

1 1

1
10/16/2023
11/15/2023

M W F
12/15/2023

S
1/14/2024

T
2/13/2024

T
3/14/2024
4/13/2024
5/13/2024
6/12/2024
S M W F

7/12/2024
S

8/11/2024
T

9/10/2024
T

10/10/2024
11/9/2024
12/9/2024
1/8/2025
S M W F

2/7/2025
S

3/9/2025
T

4/8/2025
T

5/8/2025
6/7/2025
7/7/2025
8/6/2025
S M W F

9/5/2025
S

10/5/2025
T

11/4/2025
T

12/4/2025
1/3/2026
S M

#######################################################################################

2/2/2026
3/4/2026

W F
4/3/2026

S
5/3/2026

T
6/2/2026

T
7/2/2026
8/1/2026
8/31/2026
9/30/2026
S M W F

10/30/2026
S

11/29/2026
T

12/29/2026
T

1/28/2027
2/27/2027
3/29/2027
4/28/2027
S M W F

5/28/2027
S

6/27/2027
T

7/27/2027
T

8/26/2027
9/25/2027
10/25/2027
11/24/2027
S M W F

12/24/2027
S

1/23/2028
T

2/22/2028
T

3/23/2028
4/22/2028
5/22/2028
S M W

#######################################################################################

6/21/2028
F
7/21/2028

S
8/20/2028

T
9/19/2028

T
10/19/2028
11/18/2028
12/18/2028
1/17/2029 S M W F
2/16/2029
S

3/18/2029
T

4/17/2029
T

5/17/2029
6/16/2029
7/16/2029
8/15/2029
S M W F

9/14/2029
S

10/14/2029
T

11/13/2029
T

12/13/2029
1/12/2030
2/11/2030
3/13/2030
S M W F

4/12/2030
S

5/12/2030
T

6/11/2030
T

7/11/2030
8/10/2030
9/9/2030
10/9/2030
S M W F

#######################################################################################

11/8/2030
S
12/8/2030

T
1/7/2031

T
2/6/2031
3/8/2031
4/7/2031
5/7/2031
6/6/2031 S M W F
S
7/6/2031
T

8/5/2031
T

9/4/2031
10/4/2031
11/3/2031
12/3/2031
S M W F

1/2/2032
S

2/1/2032
T

3/2/2032
T

4/1/2032
5/1/2032
5/31/2032
6/30/2032
S M W F

7/30/2032
S

8/29/2032
T

9/28/2032
T

10/28/2032
11/27/2032
12/27/2032
1/26/2033
S M W F

2/25/2033
S

#######################################################################################

3/27/2033
T
4/26/2033

T
5/26/2033
6/25/2033
7/25/2033
8/24/2033

S M W F
9/23/2033
10/23/2033 S
T
11/22/2033
T

12/22/2033
1/21/2034
2/20/2034
3/22/2034
S M W F

4/21/2034
S

5/21/2034
T

6/20/2034
T

7/20/2034
8/19/2034
9/18/2034
10/18/2034
S M W F

11/17/2034
S

12/17/2034
T

1/16/2035
T

2/15/2035
3/17/2035
4/16/2035
5/16/2035
S M W F

6/15/2035
S

7/15/2035
T

#######################################################################################

8/14/2035
T
9/13/2035
10/13/2035
11/12/2035
12/12/2035

S M W F
1/11/2036

S
2/10/2036
3/11/2036 T
T
4/10/2036
5/10/2036
6/9/2036
7/9/2036
S M W F

8/8/2036
S

9/7/2036
T

10/7/2036
T

11/6/2036
12/6/2036
1/5/2037
2/4/2037
S M W F

3/6/2037
S

4/5/2037
T

5/5/2037
T

6/4/2037
7/4/2037
8/3/2037
9/2/2037
S M W F

10/2/2037
S

11/1/2037
T

12/1/2037
T

#######################################################################################

12/31/2037
1/30/2038
3/1/2038
3/31/2038

S M W F
4/30/2038

S
5/30/2038

T
6/29/2038
7/29/2038 T
8/28/2038
9/27/2038
10/27/2038
S M W F

11/26/2038
S

12/26/2038
T

1/25/2039
T

2/24/2039
3/26/2039
4/25/2039
5/25/2039
S M W F

6/24/2039
S

#########################################################

7/24/2039
Location
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
' TK-22-458'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-460'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-667,668'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-669,670'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'Impervious-Edited'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Fixed Sample (Edited)'!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK Floating Sample(Edited) '!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-12-863'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-14-101'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-253'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-264'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-454'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-504'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-509'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-510'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-22-651'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-29-042B'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-406'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-34-424'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-464'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-468'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-534'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-600'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-671'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-61-703'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-63-703B'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-66-953'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
'TK-96-912'!
Content.Column1

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-458
TANK ROOF TYPE: Floating
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-460
Works Executed Today :

Work Plan for Next Working Day :


Critical Activity if Any:
Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-667/668
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-669/670
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. :
TANK ROOF TYPE:
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. :
TANK ROOF TYPE:
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. :
TANK ROOF TYPE:
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-12-863
TANK ROOF TYPE:Fixed Roof
Works Executed Today :
Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-14-101
TANK ROOF TYPE:Fixed Roof
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:
Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-253
TANK ROOF TYPE:Floating
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-264
TANK ROOF TYPE:Fixed
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-454
TANK ROOF TYPE: Cone
Works Executed Today :
Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-504
TANK ROOF TYPE:Floating Roof
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-509
TANK ROOF TYPE : Floating Roof
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-510
TANK ROOF TYPE:Cone
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-651
TANK ROOF TYPE:Dome
Works Executed Today :
Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. :
TANK ROOF TYPE:
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:
Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-34-406
TANK ROOF TYPE : Dome
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-34-424
TANK ROOF TYPE: Internal Roof/Dome
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-464
TANK ROOF TYPE:Floating
Works Executed Today :

Work Plan for Next Working Day :


Critical Activity if Any:
Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-468
TANK ROOF TYPE:Floating Roof
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-534
TANK ROOF TYPE: Floating Roof
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-600
TANK ROOF TYPE:Fixed
Works Executed Today :
Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-671
TANK ROOF TYPE:Fixed Roof
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-703
TANK ROOF TYPE:Floating
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-63-703B
TANK ROOF TYPE: Fixed Roof
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-66-953
TANK ROOF TYPE:Fixed Roof
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:

Contract No : CA/4079
Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-96-912
TANK ROOF TYPE:Fixed
Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To :
Remarks:

Supervisor:
Activity planned Start PPanned End

TASK DESCRIPTION
[PREPARATORY WORKS] 8/2/2021 0:00
Dead-Stock Transfer 8/2/2021 0:00 11/5/2021 0:00
Tank Blinding Works 11/6/2021 0:00 11/10/2021 0:00
Gas Freeing & Stripping 11/13/2021 0:00 11/17/2021 0:00
De-Sludging Works 11/18/2021 0:00 11/24/2021 0:00
Washing and Cleaning Works 11/24/2021 0:00 12/1/2021 0:00
Preliminary Inspection 12/2/2021 0:00 12/3/2021 0:00
Removal of Heat Detection Cable 12/27/2021 0:00 12/31/2021 0:00
External Scaffolding Erection 12/27/2021 0:00 1/4/2022 0:00
Internal Bottom Sweep Blasting 1/11/2022 0:00 1/31/2022 0:00
Inspection of Tank Bottom 2/20/2022 0:00 3/10/2022 0:00
Issuance of IAT(s) 3/12/2022 0:00 3/15/2022 0:00
Roof Seal Removal 6/11/2022 0:00 6/15/2022 0:00
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal 5/20/2022 0:00 5/23/2022 0:00
Existing Bottom Plates & Old Soil Removal 6/4/2022 0:00 6/24/2022 0:00
CP System Installation 9/18/2022 0:00 10/4/2022 0:00
Re-Bottoming Works 10/5/2022 0:00 10/30/2022 0:00
Access Door Reinstallation 10/31/2022 0:00 11/3/2022 0:00
NDT Works (DPT/Vacuum Box Test/RT) 11/4/2022 0:00 11/8/2022 0:00
Tank HydroTest 11/9/2022 0:00 12/3/2022 0:00
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 12/20/2022 0:00 1/14/2023 0:00
Roof Leg Pad Blasting & Coating 2/9/2023 0:00 2/26/2023 0:00
Tank Internal Blasting & Painting 2/9/2023 0:00 2/21/2023 0:00
U/G Piping Coating Works 12/14/2022 0:00 12/22/2022 0:00
External Scaffolding Removal 2/7/2023 0:00 2/13/2023 0:00
Tank Calibration 2/14/2023 0:00 2/16/2023 0:00
[HANDOVER WORKS]
Final Cleaning & Housekeeping 2/27/2023 0:00 3/3/2023 0:00
Tank Box-Up Works 2/27/2023 0:00 3/3/2023 0:00
De-Blinding 2/27/2023 0:00 3/3/2023 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS] 10/10/2022 0:00 10/11/2022 0:00
Site Survey Works 10/10/2022 0:00 10/11/2022 0:00
Permeability Test of Existing Soil 10/11/2022 0:00 10/11/2022 0:00
[IMPERVIOUS LINING WORKS] 10/12/2022 0:00 11/13/2022 0:00
Grading of Old Soil 10/12/2022 0:00 10/17/2022 0:00
Removal of Old Soil from Tank 10/15/2022 0:00 10/19/2022 0:00
Water Spraying & Compaction after Removal of Old Soil 10/19/2022 0:00 10/22/2022 0:00
Backfilling with New Gatch 10/23/2022 0:00 11/3/2022 0:00
Water Spraying & Levelling of New Gatch 10/29/2022 0:00 11/7/2022 0:00
Compaction of New Gatch 11/3/2022 0:00 11/12/2022 0:00
Final Permeability & Compaction Testing 11/13/2022 0:00 11/13/2022 0:00
[TANK FOUNDATION REPAIR WORKS] 10/29/2022 0:00 11/4/2022 0:00
Removal of Damaged Concrete Sections 10/29/2022 0:00 10/30/2022 0:00
Shuttering Works for Tank Foundation Repair 10/31/2022 0:00 11/1/2022 0:00
Concrete Casting & Curing Works 11/2/2022 0:00 11/3/2022 0:00
Final Paint Touch-Up Works 11/4/2022 0:00 11/4/2022 0:00
[TANK SKIRTING REPAIR WORKS] 11/5/2022 0:00 11/12/2022 0:00
Removal of Damaged Bitumen from Tank Skirting 11/5/2022 0:00 11/6/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 11/7/2022 0:00 11/8/2022 0:00
Application of MC-30 Capseal in Skirt Area 11/9/2022 0:00 11/10/2022 0:00
Application of Bitumen 11/11/2022 0:00 11/12/2022 0:00
[TANK DYKE WALL & KEY REPAIR WORKS] 11/4/2022 0:00 11/11/2022 0:00
Removal of Damaged Asphalt from Dyke & Key 11/4/2022 0:00 11/6/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 11/7/2022 0:00 11/9/2022 0:00
Application of MC-30 Capseal 11/10/2022 0:00 11/11/2022 0:00
Application of Bitumen 11/8/2022 0:00 11/11/2022 0:00
[STORM WATER DRAIN REPAIR WORKS] 10/17/2022 0:00 11/15/2022 0:00
Excavation of Burried Storm Water Drain 10/17/2022 0:00 10/18/2022 0:00
Removal Damaged Sections 10/18/2022 0:00 10/18/2022 0:00
Rebar Repair Works 11/11/2022 0:00 11/11/2022 0:00
Shuttering Works 11/12/2022 0:00 11/13/2022 0:00
Concrete Casting & Curing Works 11/14/2022 0:00 11/14/2022 0:00
Backfilling & Compaction Works in Adjacent Area 11/15/2022 0:00 11/15/2022 0:00
TASK DESCRIPTION
[PREPARATORY WORKS] 9/9/2022 0:00 9/10/2022 0:00
Site Survey Works 9/9/2022 0:00 9/10/2022 0:00
Permeability Test of Existing Soil 9/10/2022 0:00 9/10/2022 0:00
[IMPERVIOUS LINING WORKS] 9/13/2022 0:00 10/30/2022 0:00
Grading of Old Soil 9/13/2022 0:00 9/19/2022 0:00
Removal of Old Soil from Tank 9/16/2022 0:00 9/22/2022 0:00
Water Spraying & Compaction after Removal of Old Soil 9/22/2022 0:00 9/25/2022 0:00
Backfilling with New Gatch 9/26/2022 0:00 10/22/2022 0:00
Water Spraying & Levelling of New Gatch 10/2/2022 0:00 10/24/2022 0:00
Compaction of New Gatch 10/7/2022 0:00 10/29/2022 0:00
Final Permeability & Compaction Testing 10/23/2022 0:00 10/30/2022 0:00
[TANK FOUNDATION REPAIR WORKS] 9/27/2022 0:00 10/8/2022 0:00
Removal of Damaged Concrete Sections 9/27/2022 0:00 9/28/2022 0:00
Shuttering Works for Tank Foundation Repair 9/29/2022 0:00 10/2/2022 0:00
Concrete Casting & Curing Works 10/3/2022 0:00 10/6/2022 0:00
Final Paint Touch-Up Works 10/7/2022 0:00 10/8/2022 0:00
[TANK SKIRTING REPAIR WORKS] 10/9/2022 0:00 10/19/2022 0:00
Removal of Damaged Bitumen from Tank Skirting 10/9/2022 0:00 10/10/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 10/11/2022 0:00 10/13/2022 0:00
Application of MC-30 Capseal in Skirt Area 10/14/2022 0:00 10/15/2022 0:00
Application of Bitumen 10/16/2022 0:00 10/19/2022 0:00
[TANK DYKE WALL & KEY REPAIR WORKS] 10/8/2022 0:00 10/28/2022 0:00
Removal of Damaged Asphalt from Dyke & Key 10/8/2022 0:00 10/13/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 10/14/2022 0:00 10/21/2022 0:00
Application of MC-30 Capseal 10/19/2022 0:00 10/24/2022 0:00
Application of Bitumen 10/21/2022 0:00 10/28/2022 0:00
[STORM WATER DRAIN REPAIR WORKS] 10/17/2022 0:00 10/27/2022 0:00
Excavation of Burried Storm Water Drain 10/17/2022 0:00 10/19/2022 0:00
Removal Damaged Sections 10/18/2022 0:00 10/19/2022 0:00
Rebar Repair Works 10/20/2022 0:00 10/21/2022 0:00
Shuttering Works 10/22/2022 0:00 10/23/2022 0:00
Concrete Casting & Curing Works 10/24/2022 0:00 10/25/2022 0:00
Backfilling & Compaction Works in Adjacent Area 10/26/2022 0:00 10/27/2022 0:00

TASK DESCRIPTION
[PREPARATORY WORKS] 10/22/2022 0:00 10/23/2022 0:00
Site Survey Works 10/22/2022 0:00 10/23/2022 0:00
Permeability Test of Existing Soil 10/23/2022 0:00 10/23/2022 0:00
[IMPERVIOUS LINING WORKS] 10/23/2022 0:00 12/10/2022 0:00
Grading of Old Soil 10/24/2022 0:00 10/30/2022 0:00
Removal of Old Soil from Tank 10/27/2022 0:00 11/2/2022 0:00
Water Spraying & Compaction after Removal of Old Soil 11/2/2022 0:00 11/5/2022 0:00
Backfilling with New Gatch 11/6/2022 0:00 11/30/2022 0:00
Water Spraying & Levelling of New Gatch 11/12/2022 0:00 12/2/2022 0:00
Compaction of New Gatch 11/17/2022 0:00 12/9/2022 0:00
Final Permeability & Compaction Testing 10/23/2022 0:00 12/10/2022 0:00
[TANK FOUNDATION REPAIR WORKS] 11/14/2022 0:00 11/25/2022 0:00
Removal of Damaged Concrete Sections 11/14/2022 0:00 11/15/2022 0:00
Shuttering Works for Tank Foundation Repair 11/16/2022 0:00 11/19/2022 0:00
Concrete Casting & Curing Works 11/20/2022 0:00 11/23/2022 0:00
Final Paint Touch-Up Works 11/24/2022 0:00 11/25/2022 0:00
[TANK SKIRTING REPAIR WORKS] 11/26/2022 0:00 12/6/2022 0:00
Removal of Damaged Bitumen from Tank Skirting 11/26/2022 0:00 11/27/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 11/28/2022 0:00 11/30/2022 0:00
Application of MC-30 Capseal in Skirt Area 12/1/2022 0:00 12/2/2022 0:00
Application of Bitumen 12/3/2022 0:00 12/6/2022 0:00
[TANK DYKE WALL & KEY REPAIR WORKS] 11/18/2022 0:00 12/8/2022 0:00
Removal of Damaged Asphalt from Dyke & Key 11/18/2022 0:00 11/23/2022 0:00
Backfilling, Contouring and Compaction of New Gatch 11/24/2022 0:00 12/1/2022 0:00
Application of MC-30 Capseal 11/29/2022 0:00 12/4/2022 0:00
Application of Bitumen 12/1/2022 0:00 12/8/2022 0:00
[STORM WATER DRAIN REPAIR WORKS] 11/26/2022 0:00 12/6/2022 0:00
Excavation of Burried Storm Water Drain 11/26/2022 0:00 11/28/2022 0:00
Removal Damaged Sections 11/27/2022 0:00 11/28/2022 0:00
Rebar Repair Works 11/29/2022 0:00 11/30/2022 0:00
Shuttering Works 12/1/2022 0:00 12/2/2022 0:00
Concrete Casting & Curing Works 12/3/2022 0:00 12/4/2022 0:00
Backfilling & Compaction Works in Adjacent Area 12/5/2022 0:00 12/6/2022 0:00

TASK DESCRIPTION
[PREPARATORY WORKS]
Site Survey Works
Permeability Test of Existing Soil
[IMPERVIOUS LINING WORKS]
Grading of Old Soil
Removal of Old Soil from Tank
Water Spraying & Compaction after Removal of Old Soil
Backfilling with New Gatch
Water Spraying & Levelling of New Gatch
Compaction of New Gatch
Final Permeability & Compaction Testing
[TANK FOUNDATION REPAIR WORKS]
Removal of Damaged Concrete Sections
Shuttering Works for Tank Foundation Repair
Concrete Casting & Curing Works
Final Paint Touch-Up Works
[TANK SKIRTING REPAIR WORKS]
Removal of Damaged Bitumen from Tank Skirting
Backfilling, Contouring and Compaction of New Gatch
Application of MC-30 Capseal in Skirt Area
Application of Bitumen
[TANK DYKE WALL & KEY REPAIR WORKS]
Removal of Damaged Asphalt from Dyke & Key
Backfilling, Contouring and Compaction of New Gatch
Application of MC-30 Capseal
Application of Bitumen
[STORM WATER DRAIN REPAIR WORKS]
Excavation of Burried Storm Water Drain
Removal Damaged Sections
Rebar Repair Works
Shuttering Works
Concrete Casting & Curing Works
Backfilling & Compaction Works in Adjacent Area
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting
Inspection of Tank
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping 9/9/2022 0:00 9/14/2022 0:00
De-Sludging Works 9/4/2022 0:00 9/8/2022 0:00
Washing and Cleaning Works 9/9/2022 0:00 9/14/2022 0:00
Preliminary Inspection 10/14/2022 0:00 10/14/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 9/21/2022 0:00 9/22/2022 0:00
Inspection of Tank Bottom 9/23/2022 0:00 9/24/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection 9/25/2022 0:00 9/26/2022 0:00
Internal Sweep Blasting 9/27/2022 0:00 9/29/2022 0:00
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works 10/13/2021 0:00 11/12/2021 0:00
NDT Works (Vaccum Box/DPT) 11/13/2021 0:00 11/15/2021 0:00
Internal Scaffolding Removal 10/3/2022 0:00 10/5/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal 12/9/2021 0:00 1/1/2022 0:00
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 9/29/2021 0:00 10/9/2021 0:00
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating 3/15/2022 0:00 3/18/2022 0:00
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
2022-24833
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest 8/13/2022 0:00 10/4/2022 0:00
[BLASTING & PAINTING WORKS]
Internal Blasting & Painting 11/26/2022 0:00 12/29/2022 0:00
Tank External Blasting & Painting 11/11/2022 0:00 11/25/2022 0:00
Tank Internal Blasting & Painting 12/19/2022 0:00
U/G Piping Coating Works
External Scaffolding Removal 11/27/2022 0:00 11/30/2022 0:00
Tank Calibration 12/30/2022 0:00 12/31/2022 0:00
[HANDOVER WORKS]
Final Cleaning & Housekeeping 12/30/2022 0:00 1/3/2023 0:00
Tank Box-Up Works 12/30/2022 0:00 1/3/2023 0:00
De-Blinding 12/30/2022 0:00 1/3/2023 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating 12/19/2022 0:00 12/22/2022 0:00
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 1/5/2022 0:00 8/10/2022 0:00
Dead-Stock Transfer 1/5/2022 0:00 1/31/2022 0:00
Tank Blinding Works 2/1/2022 0:00 2/3/2022 0:00
Gas Freeing & Stripping 2/14/2022 0:00 2/20/2022 0:00
De-Sludging Works 2/21/2022 0:00 2/27/2022 0:00
Washing and Cleaning Works 2/28/2022 0:00 3/3/2022 0:00
Preliminary Inspection 3/4/2022 0:00 3/5/2022 0:00
External Scaffolding Erection 5/28/2022 0:00 6/5/2022 0:00
Removal of Heat Detection Cable 3/7/2022 0:00 3/10/2022 0:00
Removal of Roof Seal 3/10/2022 0:00 3/17/2022 0:00
Internal Sweep Blasting 4/1/2022 0:00 4/6/2022 0:00
Inspection of Tank 4/4/2022 0:00 4/15/2022 0:00
Issuance of IAT(s) 3/10/2022 0:00 8/10/2022 0:00
[MECHANICAL WORKS]
Re-Roofing Works 7/28/2022 0:00 8/4/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal 8/5/2022 0:00 8/25/2022 0:00
C.P. System Installation 10/27/2022 0:00 11/19/2022 0:00
Re-Bottoming Works 11/20/2022 0:00 12/31/2022 0:00
Access Door Reinstallation 1/1/2023 0:00 1/6/2023 0:00
NDT Works (DPT/Vacuum Box Test/RT) 1/1/2023 0:00 1/6/2023 0:00
Re-Installation of Roof Seal 1/7/2023 0:00 1/14/2023 0:00
Tank HydroTest 1/16/2023 0:00 2/15/2023 0:00
Opening of Roof Seal(If Required)
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 12/21/2022 0:00 2/25/2023 0:00
Roof Leg Pad Blasting & Coating 2/15/2023 0:00 3/22/2023 0:00
Tank Internal Blasting & Painting 3/18/2023 0:00 4/8/2023 0:00
U/G Piping Coating Works
External Scaffolding Removal 2/26/2022 0:00 3/10/2022 0:00
Tank Calibration 3/11/2022 0:00 3/13/2022 0:00
[HANDOVER WORKS]
Final Cleaning & Housekeeping 3/19/2023 0:00 3/24/2023 0:00
Tank Box-Up Works 3/19/2023 0:00 3/24/2023 0:00
De-Blinding 3/19/2023 0:00 3/24/2023 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works 8/1/2022 0:00 8/8/2022 0:00
Preliminary Inspection 8/8/2022 0:00 8/9/2022 0:00
External Scaffolding Erection 9/15/2021 0:00 9/24/2021 0:00
Internal Bottom Sweep Blasting 9/26/2021 0:00 10/6/2021 0:00
Inspection of Tank Bottom 10/7/2022 0:00 10/13/2022 0:00
Issuance of IAT(s) 10/7/2022 0:00 10/13/2022 0:00
Internal Scaffloding Erection 10/21/2021 0:00 11/7/2021 0:00
Internal Sweep Blasting 12/21/2021 0:00 1/23/2022 0:00
Inspection of Tank Roof & Shell 10/21/2021 0:00 11/7/2021 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal 9/8/2022 0:00 9/18/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest 10/23/2022 0:00 11/18/2022 0:00
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 11/20/2022 0:00 12/8/2022 0:00
Tank External Blasting & Painting 7/10/2022 0:00 8/22/2022 0:00
Tank internal Blasting & Painting 8/13/2022 0:00 9/7/2022 0:00
U/G Piping Coating Works 9/19/2022 0:00 12/2/2022 0:00
External Scaffolding Removal 12/3/2022 0:00 12/7/2022 0:00
Tank Calibration 12/3/2022 0:00 12/4/2022 0:00
[HANDOVER WORKS]
Final Cleaning & Housekeeping 12/3/2022 0:00 12/8/2022 0:00
Tank Box-Up Works 12/3/2022 0:00 12/8/2022 0:00
De-Blinding 12/3/2022 0:00 12/8/2022 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:


[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS] 4/22/2022 0:00
Dead-Stock Transfer 4/22/2022 0:00 4/29/2022 0:00
Tank Blinding Works 6/27/2022 0:00 6/30/2022 0:00
Gas Freeing & Stripping 4/30/2022 0:00 5/4/2022 0:00
De-Sludging Works 7/9/2022 0:00 7/15/2022 0:00
Washing and Cleaning Works 5/5/2022 0:00 5/6/2022 0:00
Preliminary Inspection 8/10/2022 0:00 8/15/2022 0:00
External Scaffolding Erection 10/5/2022 0:00 10/8/2022 0:00
Internal Bottom Sweep Blasting 7/31/2022 0:00 8/6/2022 0:00
Inspection of Tank Bottom 10/2/2022 0:00 10/4/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection 9/17/2022 0:00 9/23/2022 0:00
Internal Sweep Blasting 9/24/2022 0:00 9/29/2022 0:00
Inspection of Tank Roof & Shell 10/2/2022 0:00 10/4/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works 10/22/2022 0:00 11/13/2022 0:00
NDT Works (Vaccum Box/DPT) 11/22/2022 0:00 11/25/2022 0:00
Internal Scaffolding Removal 11/25/2022 0:00 12/6/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest 12/7/2022 0:00 12/22/2022 0:00
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating 10/5/2022 0:00 10/7/2022 0:00
HydroTest 10/5/2022 0:00 10/7/2022 0:00
Service Test 10/5/2022 0:00 10/7/2022 0:00

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 10/16/2021 0:00 2/15/2022 0:00
Dead-Stock Transfer 10/16/2021 0:00 10/20/2021 0:00
Tank Blinding Works 10/21/2021 0:00 10/24/2021 0:00
Gas Freeing & Stripping 11/28/2021 0:00 12/4/2021 0:00
De-Sludging Works 12/5/2021 0:00 12/7/2021 0:00
Washing and Cleaning Works 12/8/2021 0:00 12/12/2021 0:00
Preliminary Inspection 12/13/2021 0:00 12/13/2021 0:00
External Scaffolding Erection 2/12/2022 0:00 2/17/2022 0:00
Removal of Heat Detection Cable 12/9/2021 0:00 12/11/2021 0:00
Removal of Roof Seal 12/12/2021 0:00 12/17/2021 0:00
Internal Sweep Blasting 12/12/2021 0:00 1/2/2022 0:00
Inspection of Tank 1/3/2022 0:00 1/13/2022 0:00
Issuance of IAT(s) 2/10/2022 0:00 2/15/2022 0:00
[MECHANICAL WORKS] 5/5/2022 0:00 6/13/2022 0:00
Re-Roofing Works 5/5/2022 0:00 6/23/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal 5/2/2022 0:00 5/9/2022 0:00
C.P. System Installation
Re-Bottoming Works 4/15/2022 0:00 5/28/2022 0:00
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT) 6/20/2022 0:00 6/24/2022 0:00
Re-Installation of Roof Seal 12/1/2022 0:00 12/7/2022 0:00
Tank HydroTest 5/29/2022 0:00 6/13/2022 0:00
[BLASTING & PAINTING WORKS] 10/13/2022 0:00 12/13/2022 0:00
Tank External Blasting & Painting 10/13/2022 0:00 12/7/2022 0:00
Roof Leg Pad Blasting & Coating 10/7/2022 0:00 10/21/2022 0:00
Tank Internal Blasting & Painting 11/3/2022 0:00 11/30/2022 0:00
U/G Piping Coating Works
External Scaffolding Removal 12/8/2022 0:00 12/12/2022 0:00
Tank Calibration 12/13/2022 0:00 12/13/2022 0:00
[HANDOVER WORKS] 12/8/2022 0:00 12/16/2022 0:00
Final Cleaning & Housekeeping 12/8/2022 0:00 12/12/2022 0:00
Tank Box-Up Works 12/13/2022 0:00 12/13/2022 0:00
De-Blinding 12/14/2022 0:00 12/16/2022 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating 8/1/2022 0:00 8/10/2022 0:00
HydroTest 8/1/2022 0:00 8/10/2022 0:00
Service Test 8/1/2022 0:00 8/10/2022 0:00

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 9/7/2022 0:00
Dead-Stock Transfer 9/7/2022 0:00 9/9/2022 0:00
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS] 9/23/2022 0:00
Dead-Stock Transfer 9/23/2022 0:00 9/25/2022 0:00
Tank Blinding Works
Gas Freeing & Stripping 9/26/2022 0:00 9/29/2022 0:00
De-Sludging Works 9/30/2022 0:00 10/2/2022 0:00
Washing and Cleaning Works 11/29/2022 0:00 12/2/2022 0:00
Preliminary Inspection
External Scaffolding Erection 11/5/2022 0:00 11/15/2022 0:00
Internal Bottom Sweep Blasting 11/1/2022 0:00 11/17/2022 0:00
Inspection of Tank Bottom 11/18/2022 0:00 11/20/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection
External Sweep Blasting 11/21/2022 0:00 11/22/2022 0:00
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:


[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer 5/22/2022 0:00 5/27/2022 0:00
Tank Blinding Works 6/14/2022 0:00 6/23/2022 0:00
Gas Freeing & Stripping 6/28/2022 0:00 7/8/2022 0:00
De-Sludging Works 7/7/2022 0:00 7/15/2022 0:00
Washing and Cleaning Works 6/28/2022 0:00 7/8/2022 0:00
Preliminary Inspection 8/21/2022 0:00 8/21/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 8/23/2022 0:00 9/23/2022 0:00
Inspection of Tank Bottom 9/24/2022 0:00 9/30/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting 8/22/2022 0:00 8/29/2022 0:00
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping 10/15/2022 0:00 10/16/2022 0:00
De-Sludging Works
Washing and Cleaning Works 10/17/2022 0:00 10/18/2022 0:00
Preliminary Inspection 10/18/2022 0:00 10/18/2022 0:00
External Scaffolding Erection 10/23/2022 0:00 10/25/2022 0:00
Internal Bottom Sweep Blasting 11/5/2022 0:00 11/8/2022 0:00
Inspection of Tank Bottom 11/9/2022 0:00 11/10/2022 0:00
Issuance of IAT(s) 10/19/2022 0:00 10/19/2022 0:00
Internal Scaffloding Erection 10/19/2022 0:00 10/19/2022 0:00
Internal Sweep Blasting (Roof & Shell) 10/23/2022 0:00 10/25/2022 0:00
Inspection of Tank Roof & Shell 10/26/2022 0:00 10/27/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 10/23/2022 0:00 10/25/2022 0:00
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works 5/16/2022 0:00 5/16/2022 0:00
Gas Freeing & Stripping 9/3/2022 0:00 9/7/2022 0:00
De-Sludging Works 8/26/2022 0:00 9/2/2022 0:00
Washing and Cleaning Works 9/8/2022 0:00 9/13/2022 0:00
Preliminary Inspection 9/14/2022 0:00 9/16/2022 0:00
External Scaffolding Erection 11/25/2022 0:00 12/6/2022 0:00
Internal Bottom Sweep Blasting 10/16/2022 0:00 10/23/2022 0:00
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS] 3/20/2022 0:00
Dead-Stock Transfer 3/20/2022 0:00 3/26/2022 0:00
Tank Blinding Works
Gas Freeing & Stripping 4/3/2022 0:00 4/7/2022 0:00
De-Sludging Works 4/8/2022 0:00 4/12/2022 0:00
Washing and Cleaning Works 4/13/2022 0:00 4/17/2022 0:00
Preliminary Inspection 8/4/2022 0:00 8/4/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 8/16/2022 0:00 8/26/2022 0:00
Inspection of Tank Bottom 8/27/2022 0:00 9/6/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:


[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS] 11/5/2021 0:00 6/15/2022 0:00
Dead-Stock Transfer 11/5/2021 0:00 11/17/2021 0:00
Tank Blinding Works 12/20/2021 0:00 12/24/2021 0:00
Gas Freeing & Stripping 1/3/2022 0:00 1/10/2022 0:00
De-Sludging Works 1/11/2022 0:00 1/19/2022 0:00
Washing and Cleaning Works 1/20/2022 0:00 1/25/2022 0:00
Preliminary Inspection 1/26/2022 0:00 1/28/2022 0:00
External Scaffolding Erection 4/11/2022 0:00 5/26/2022 0:00
Removal of Heat Detection Cable 2/13/2022 0:00 2/17/2022 0:00
Removal of Roof Seal 2/18/2022 0:00 2/26/2022 0:00
Internal Sweep Blasting 2/27/2022 0:00 3/10/2022 0:00
Inspection of Tank 3/11/2022 0:00 3/21/2022 0:00
Issuance of IAT(s) 2/10/2022 0:00 6/15/2022 0:00
[MECHANICAL WORKS] 5/22/2022 0:00 9/15/2022 0:00
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works 5/22/2022 0:00 5/27/2022 0:00
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT) 6/1/2022 0:00 6/2/2022 0:00
Re-Installation of Roof Seal
Tank HydroTest 7/1/2022 0:00 9/15/2022 0:00
[BLASTING & PAINTING WORKS] 9/8/2022 0:00 11/29/2022 0:00
Tank External Blasting & Painting 9/8/2022 0:00 10/30/2022 0:00
Roof Leg Pad Blasting & Coating 10/11/2022 0:00 11/18/2022 0:00
Tank Internal Blasting & Painting 11/15/2022 0:00 12/7/2022 0:00
U/G Piping Coating Works 10/21/2022 0:00 10/29/2022 0:00
External Scaffolding Removal 10/21/2022 0:00 10/27/2022 0:00
Tank Calibration 11/20/2022 0:00 11/29/2022 0:00
[HANDOVER WORKS] 11/30/2022 0:00 12/5/2022 0:00
Final Cleaning & Housekeeping 11/30/2022 0:00 12/5/2022 0:00
Tank Box-Up Works 11/30/2022 0:00 12/5/2022 0:00
De-Blinding 12/4/2022 0:00 12/10/2022 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating 7/23/2022 0:00 7/30/2022 0:00
HydroTest 7/1/2022 0:00 9/15/2022 0:00
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 7/14/2022 0:00
Dead-Stock Transfer 7/14/2022 0:00 7/19/2022 0:00
Tank Blinding Works 7/27/2022 0:00 7/30/2022 0:00
Gas Freeing & Stripping 8/11/2022 0:00 8/15/2022 0:00
De-Sludging Works 8/16/2022 0:00 8/22/2022 0:00
Washing and Cleaning Works 8/23/2022 0:00 8/28/2022 0:00
Preliminary Inspection 8/25/2022 0:00 8/27/2022 0:00
External Scaffolding Erection
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting 9/20/2022 0:00 10/5/2022 0:00
Inspection of Tank 10/6/2022 0:00 10/8/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 8/10/2022 0:00
Dead-Stock Transfer 8/10/2022 0:00 8/20/2022 0:00
Tank Blinding Works 8/24/2022 0:00 8/29/2022 0:00
Gas Freeing & Stripping 9/1/2022 0:00 9/8/2022 0:00
De-Sludging Works 9/9/2022 0:00 9/13/2022 0:00
Washing and Cleaning Works 9/14/2022 0:00 9/20/2022 0:00
Preliminary Inspection 10/14/2022 0:00 10/15/2022 0:00
External Scaffolding Erection 11/10/2022 0:00 11/23/2022 0:00
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting 10/20/2022 0:00 11/7/2022 0:00
Inspection of Tank 11/8/2022 0:00 11/10/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:
Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS] 11/3/2020 0:00 2/6/2021 0:00
Dead-Stock Transfer
Tank Blinding Works 11/3/2020 0:00 11/5/2020 0:00
Gas Freeing & Stripping 11/7/2020 0:00 11/14/2020 0:00
De-Sludging Works 11/15/2020 0:00 11/17/2020 0:00
Washing and Cleaning Works 11/18/2020 0:00 11/23/2020 0:00
Preliminary Inspection 11/24/2020 0:00 11/24/2020 0:00
External Scaffolding Erection 4/8/2021 0:00 4/15/2021 0:00
Internal Bottom Sweep Blasting 4/12/2021 0:00 4/28/2021 0:00
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection 3/26/2021 0:00 4/10/2021 0:00
Internal Sweep Blasting 11/26/2020 0:00 1/16/2021 0:00
Inspection of Tank Roof & Shell 1/18/2021 0:00 1/28/2021 0:00
Issuance of IAT(s) 1/30/2021 0:00 2/6/2021 0:00
[MECHANICAL WORKS] 11/27/2021 0:00 10/14/2022 0:00
Re-Roofing Works 11/27/2021 0:00 1/6/2022 0:00
NDT Works (Vaccum Box/DPT) 1/7/2022 0:00 1/11/2022 0:00
Internal Scaffolding Removal 8/30/2021 0:00 9/11/2021 0:00
Access Door Cutting & Removal 1/5/2022 0:00 1/6/2022 0:00
Existing Bottom Plates & Old Soil Removal 5/2/2022 0:00 5/24/2022 0:00
CP System Installation 5/25/2022 0:00 6/15/2022 0:00
Re-Bottoming Works 6/25/2022 0:00 9/16/2022 0:00
Access Door Reinstallation 9/17/2022 0:00 9/20/2022 0:00
NDT Works (DPT/Vacuum Box Test/RT) 9/15/2022 0:00 9/19/2022 0:00
Tank HydroTest 9/20/2022 0:00 10/14/2022 0:00
[BLASTING & PAINTING WORKS] 10/10/2021 0:00 12/19/2022 0:00
Tank External Blasting & Painting 10/4/2022 0:00 12/11/2022 0:00
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting 10/24/2022 0:00 11/25/2022 0:00
U/G Piping Coating Works 10/18/2022 0:00 11/5/2022 0:00
External Scaffolding Removal 12/12/2022 0:00 12/19/2022 0:00
Tank Calibration 12/19/2022 0:00 12/19/2022 0:00
[HANDOVER WORKS] 12/15/2022 0:00 12/27/2022 0:00
Final Cleaning & Housekeeping 12/9/2022 0:00 12/15/2022 0:00
Tank Box-Up Works 12/16/2022 0:00 12/18/2022 0:00
De-Blinding 12/19/2022 0:00 12/21/2022 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 6/25/2022 0:00
Dead-Stock Transfer 6/25/2022 0:00 6/30/2022 0:00
Tank Blinding Works
Gas Freeing & Stripping 8/4/2022 0:00 8/7/2022 0:00
De-Sludging Works 8/8/2022 0:00 8/14/2022 0:00
Washing and Cleaning Works 8/15/2022 0:00 8/20/2022 0:00
Preliminary Inspection 8/10/2022 0:00 8/11/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 8/24/2022 0:00 9/10/2022 0:00
Inspection of Tank Bottom 9/11/2022 0:00 9/23/2022 0:00
Issuance of IAT(s) 8/21/2022 0:00 9/28/2022 0:00
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 4/11/2022 0:00
Dead Stock Transfer 4/11/2022 0:00 4/17/2022 0:00
Blinding 6/16/2022 0:00 6/19/2022 0:00
Gas Freeing & Stripping 6/25/2022 0:00 6/30/2022 0:00
De-Sludging 7/1/2022 0:00 7/8/2022 0:00
Washing and Cleaning 7/9/2022 0:00 7/16/2022 0:00
Preliminary Inspection 7/17/2022 0:00 7/18/2022 0:00
External Scaffolding Erection 6/28/2022 0:00 7/3/2022 0:00
Bottom Sweep Blasting 7/19/2022 0:00 8/8/2022 0:00
Inspection of Tank Bottom 9/1/2022 0:00 9/12/2022 0:00
Issuance of IAT 9/1/2022 0:00 9/12/2022 0:00
Internal Scaffloding Erection 9/22/2022 0:00 11/4/2022 0:00
Internal Sweep Blasting 11/5/2022 0:00 11/27/2022 0:00
Inspection of Tank 11/28/2022 0:00 12/3/2022 0:00
Issuance of IAT
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Internal Scaffloding Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 11/28/2022 0:00 12/2/2022 0:00
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works 8/15/2022 0:00 8/18/2022 0:00
Gas Freeing & Stripping 8/15/2022 0:00 8/18/2022 0:00
De-Sludging Works
Washing and Cleaning Works 8/19/2022 0:00 8/24/2022 0:00
Preliminary Inspection 8/25/2022 0:00 8/27/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 9/12/2022 0:00 9/18/2022 0:00
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection 11/5/2022 0:00 11/17/2022 0:00
Internal Sweep Blasting 11/18/2022 0:00 11/26/2022 0:00
Inspection of Tank Roof & Shell 11/27/2022 0:00 11/29/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
2022-24833
IAT#
IAT#
IAT#

TASK DESCRIPTION
[PREPARATORY WORKS] 5/23/2022 0:00 6/14/2022 0:00
Dead-Stock Transfer
Tank Blinding Works 5/23/2022 0:00 5/23/2022 0:00
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection 6/12/2022 0:00 6/14/2022 0:00
External Scaffolding Erection
Internal Bottom Sweep Blasting 7/30/2022 0:00 8/11/2022 0:00
Inspection of Tank Bottom 6/19/2022 0:00 6/25/2022 0:00
Issuance of IAT(s) 7/25/2022 0:00 9/6/2022 0:00
Internal Scaffloding Erection 7/15/2022 0:00 7/22/2022 0:00
Internal Sweep Blasting 7/30/2022 0:00 8/11/2022 0:00
Inspection of Tank Roof & Shell 6/12/2022 0:00 6/14/2022 0:00
Issuance of IAT(s) 6/12/2022 0:00 6/14/2022 0:00
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal 9/29/2022 0:00 10/2/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works 9/7/2022 0:00 9/11/2022 0:00
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting 10/3/2022 0:00 10/18/2022 0:00
Tank internal Blasting & Painting
Tank Extrenal Fire line Coating Works 10/3/2022 0:00 10/13/2022 0:00
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping 10/27/2022 0:00 10/30/2022 0:00
Tank Box-Up Works 10/27/2022 0:00 10/30/2022 0:00
De-Blinding 10/27/2022 0:00 10/30/2022 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
IAT#
IAT#
IAT#
IAT#
TASK DESCRIPTION
[PREPARATORY WORKS] 4/25/2022 0:00 8/6/2022 0:00
Dead-Stock Transfer 5/6/2022 0:00 5/7/2022 0:00
Tank Blinding Works 5/8/2022 0:00 5/8/2022 0:00
Gas Freeing & Stripping 4/25/2022 0:00 5/2/2022 0:00
De-Sludging Works 5/3/2022 0:00 5/10/2022 0:00
Washing and Cleaning Works 5/16/2022 0:00 5/20/2022 0:00
Preliminary Inspection 5/21/2022 0:00 5/22/2022 0:00
External Scaffolding Erection 5/27/2022 0:00 6/1/2022 0:00
Internal Bottom Sweep Blasting 6/27/2022 0:00 7/3/2022 0:00
Inspection of Tank Bottom 7/8/2022 0:00 7/14/2022 0:00
Issuance of IAT(s)
Internal Scaffloding Erection 7/15/2022 0:00 7/22/2022 0:00
Internal Sweep Blasting 7/23/2022 0:00 7/29/2022 0:00
Inspection of Tank Roof & Shell 8/2/2022 0:00 8/6/2022 0:00
Issuance of IAT(s)
[MECHANICAL WORKS] 10/10/2022 0:00 10/16/2022 0:00
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal 10/10/2022 0:00 10/16/2022 0:00
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS] 9/24/2022 0:00 11/16/2022 0:00
Internal Roof Blasting & Painting 9/24/2022 0:00 9/28/2022 0:00
Tank External Blasting & Painting
Tank internal Blasting & Painting 9/29/2022 0:00 11/16/2022 0:00
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS] 11/16/2022 0:00 11/24/2022 0:00
Final Cleaning & Housekeeping 11/16/2022 0:00 11/18/2022 0:00
Tank Box-Up Works 11/19/2022 0:00 11/21/2022 0:00
De-Blinding 11/22/2022 0:00 11/24/2022 0:00

[TDS & TFS WORKS]


Mechanical Repair & Coating
HydroTest
Service Test

[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS]
2022-24833
IAT#
IAT#
IAT#
Duration Actual Start Actual End Completion

8/2/2021 0:00
96 8/2/2021 0:00 8/2/2021 0:00 1
5 11/5/2021 0:00 11/10/2021 0:00 1
5 11/13/2002 0:00 11/18/2021 0:00 1
7 11/20/2021 0:00 11/24/2021 0:00 1
8 11/25/2021 0:00 12/4/2021 0:00 1
2 12/5/2021 0:00 12/5/2021 0:00 1
5 12/29/2021 0:00 12/30/2021 0:00 1
9 2/28/2022 0:00 3/8/2022 0:00 1
21 12/27/2021 0:00 2/24/2022 0:00 1
19 3/29/2022 0:00 4/10/2022 0:00 1
4 12/26/2021 0:00 5/8/2022 0:00 1
5 6/21/2022 0:00 6/25/2022 0:00 1

4 5/17/2022 0:00 5/22/2022 0:00 1


21 5/23/2022 0:00 6/30/2022 0:00 1
17 9/18/2022 0:00 10/18/2022 0:00 1
25 5/23/2022 0:00 0.1
3
4
24

26 2/22/2022 0:00 2/24/2022 0:00


18
13
9
7
3
4
4
4

10/10/2022 0:00
2 10/10/2022 0:00 10/11/2022 0:00
2 10/10/2022 0:00 10/11/2022 0:00 1
1 10/11/2022 0:00 10/11/2022 0:00 1
33 10/12/2022 0:00
5 10/12/2022 0:00 10/17/2022 0:00 1
4 10/15/2022 0:00 10/19/2022 0:00 1
4 10/19/2022 0:00 10/22/2022 0:00 1
12 10/23/2022 0:00 0.7
10 10/29/2022 0:00 0.6
10
1
7
2
2
2
1
8
2
2
2
2
8
3
3
2
4
30
2 1
1 1
1
2
1
1
9/9/2022 0:00

2 9/9/2022 0:00 9/10/2022 0:00


2 9/9/2022 0:00 9/10/2022 0:00 1
1 9/10/2022 0:00 9/10/2022 0:00 1
48 9/13/2022 0:00 10/30/2022 0:00
6 9/13/2022 0:00 9/19/2022 0:00 1
6 9/16/2022 0:00 9/22/2022 0:00 1
4 9/22/2022 0:00 9/25/2022 0:00 1
24 9/26/2022 0:00 10/22/2022 0:00 1
20 10/2/2022 0:00 10/24/2022 0:00 1
20 10/7/2022 0:00 0.85
2 10/23/2022 0:00 0.5
12 9/27/2022 0:00 10/8/2022 0:00
2 9/27/2022 0:00 9/28/2022 0:00 1
4 9/29/2022 0:00 10/2/2022 0:00 1
4 10/3/2022 0:00 10/6/2022 0:00 1
2 10/7/2022 0:00 10/8/2022 0:00 1
11 10/9/2022 0:00 10/19/2022 0:00
2 10/9/2022 0:00 10/10/2022 0:00 1
3 10/11/2022 0:00 10/13/2022 0:00 1
2 10/14/2022 0:00 10/15/2022 0:00 1
4 10/16/2022 0:00 10/19/2022 0:00 1
21 10/5/2022 0:00 10/28/2022 0:00
6 10/5/2022 0:00 10/11/2022 0:00 1
8 10/12/2022 0:00 10/19/2022 0:00 1
6 10/17/2022 0:00 10/22/2022 0:00 1
8 10/21/2022 0:00 0.85
11 10/17/2022 0:00 10/27/2022 0:00
3 10/17/2022 0:00 10/19/2022 0:00 1
2 10/18/2022 0:00 10/19/2022 0:00 1
2 10/20/2022 0:00 10/21/2022 0:00 1
2 10/22/2022 0:00 10/23/2022 0:00 1
2 10/24/2022 0:00 10/25/2022 0:00 1
2 10/26/2022 0:00 10/27/2022 0:00 1

10/22/2022 0:00

2 10/22/2022 0:00 10/23/2022 0:00


2 10/22/2022 0:00 10/23/2022 0:00 1
1 10/23/2022 0:00 10/23/2022 0:00 1
49
6 10/24/2022 0:00 0.5
6
4
22
18
20
1
12
2
4
4
2
11
2
3
2
4
21
6
8
6
8
11
3
2
2
2
2
2
6 9/13/2022 0:00 9/14/2022 0:00 1
5 9/8/2022 0:00 9/12/2022 0:00 1
6 9/13/2022 0:00 9/14/2022 0:00
1 10/13/2022 0:00 10/13/2022 0:00 1

2 9/21/2022 0:00 9/21/2022 0:00 1


2 10/13/2022 0:00 10/13/2022 0:00 1

2 9/27/2022 0:00 9/27/2022 0:00 1


3 9/29/2022 0:00 9/29/2022 0:00 1

31 10/13/2021 0:00 11/12/2021 0:00


3 11/13/2021 0:00 11/15/2021 0:00
3 10/6/2022 0:00 10/6/2022 0:00 1

24 12/9/2021 0:00 1/1/2022 0:00 1

11 9/29/2021 0:00 10/9/2021 0:00


53 9/3/2022 0:00 0.62

34
15

4
1

5
5
5

4
1/5/2022 0:00

243 1/5/2022 0:00 8/10/2022 0:00


27 1/5/2022 0:00 1/31/2022 0:00 1
3 2/6/2022 0:00 2/6/2022 0:00 1
7 2/15/2022 0:00 2/20/2022 0:00 1
7 2/21/2022 0:00 2/27/2022 0:00 1
4 2/28/2022 0:00 3/2/2022 0:00 1
2 3/6/2022 0:00 3/6/2022 0:00 1
9 5/28/2022 0:00 6/5/2022 0:00 1
4 3/11/2022 0:00 3/20/2022 0:00 1
8 3/21/2022 0:00 3/31/2022 0:00 1
6 4/2/2022 0:00 4/3/2022 0:00 1
12 5/8/2022 0:00 6/3/2022 0:00 1
154 3/10/2022 0:00 8/10/2022 0:00 1

8 8/16/2022 0:00 1

21 6/22/2022 0:00 8/11/2022 0:00 1


22 0.05
40
5
4
7
30

66
35
21

12
2

6
6
6
8 8/1/2022 0:00 8/10/2022 0:00 1
2 8/11/2022 0:00 8/11/2022 0:00 1
10 9/15/2021 0:00 9/24/2021 0:00 1
10 9/26/2021 0:00 10/6/2021 0:00 1
6 10/7/2022 0:00 10/13/2022 0:00 1
7 10/7/2022 0:00 10/13/2022 0:00 1
17 10/21/2021 0:00 11/7/2021 0:00 1
33 1/2/2022 0:00 1/14/2022 0:00 1
17 10/21/2021 0:00 11/7/2021 0:00 1

11 1

27 10/23/2022 0:00 0.38

18
43 7/10/2022 0:00 8/22/2022 0:00 1
25 8/13/2022 0:00 9/7/2022 0:00 1
74 1
4
1
4/22/2022 0:00

8 4/23/2022 0:00 4/27/2022 0:00 1


4 6/25/2022 0:00 6/25/2022 0:00
5 5/8/2022 0:00 7/20/2022 0:00 1
7 7/17/2022 0:00 7/20/2022 0:00
2 7/21/2022 0:00 7/21/2022 0:00 1
6 8/19/2022 0:00 8/19/2022 0:00 1
4 8/28/2022 0:00 8/29/2022 0:00 1
7 7/31/2022 0:00 8/15/2022 0:00 1
3 10/4/2022 0:00 10/4/2022 0:00 1
7/28/2022 0:00
7 9/20/2022 0:00 9/24/2022 0:00 1
6 9/26/2022 0:00 10/2/2022 0:00 1
2 10/3/2022 0:00 10/4/2022 0:00 1

23 10/18/2022 0:00 0.15


4
10 9/20/2022 0:00 9/24/2022 0:00 1

15

3 8/1/2022 0:00 8/1/2022 0:00 1


3 8/1/2022 0:00 8/1/2022 0:00 1
3 8/1/2022 0:00 8/1/2022 0:00 1
10/16/2021 0:00

79 10/16/2021 0:00 4/13/2022 0:00


5 10/16/2021 0:00 10/19/2021 0:00 1
4 10/27/2021 0:00 10/27/2021 0:00 1
7 11/28/2021 0:00 11/30/2021 0:00 1
3 12/1/2021 0:00 12/2/2021 0:00 1
5 12/2/2021 0:00 12/6/2021 0:00 1
1 12/13/2021 0:00 12/13/2021 0:00 1
6 2/14/2022 0:00 2/20/2022 0:00 1
3 1/4/2022 0:00 1/4/2022 0:00 1
6 12/28/2021 0:00 1/3/2022 0:00 1
22 1/5/2022 0:00 1/21/2022 0:00 1
11 3/22/2022 0:00 4/3/2022 0:00 1
6 12/13/2021 0:00 4/13/2022 0:00 1
122
50 5/10/2022 0:00 6/9/2022 0:00 1

8 4/20/2022 0:00 5/8/2022 0:00 1

44 5/7/2022 0:00 7/2/2022 0:00 1

4 7/3/2022 0:00 7/7/2022 0:00 1


6
16 9/1/2022 0:00 9/20/2022 0:00 1
103
55 10/16/2022 0:00 0.45
14 10/5/2022 0:00 0.97
28

5
1
8
5
1
2

10 8/1/2022 0:00 8/11/2022 0:00 1


10 8/1/2022 0:00 8/11/2022 0:00 1
10 8/1/2022 0:00 8/11/2022 0:00 1
9/7/2022 0:00

3 9/8/2022 0:00 9/9/2022 0:00 1


9/23/2022 0:00

3 9/23/2022 0:00 9/26/2022 0:00 1

4 10/1/2022 0:00 10/3/2022 0:00 1


3 10/4/2022 0:00 10/5/2022 0:00 1
4 10/4/2022 0:00 10/5/2022 0:00 1

10
16
2

1
5/22/2022 0:00

6 5/30/2022 0:00 6/20/2022 0:00 1


8 6/25/2022 0:00 6/25/2022 0:00 1
11 8/2/2022 0:00 8/19/2022 0:00 1
9 7/8/2022 0:00 8/16/2022 0:00 1
11 8/2/2022 0:00 8/19/2022 0:00 1
8/21/2022 0:00 8/21/2022 0:00

32 8/23/2022 0:00
7 9/12/2022 0:00

8 8/23/2022 0:00 9/12/2022 0:00 1


2

2 10/17/2022 0:00 10/17/2022 0:00 1


1 10/18/2022 0:00 10/18/2022 0:00 1
3
4
2
1 10/19/2022 0:00 10/19/2022 0:00
1 10/19/2022 0:00 10/19/2022 0:00 1
2 10/25/2022 0:00 10/25/2022 0:00 1
2 10/26/2022 0:00 10/26/2022 0:00 1
3 10/24/2022 0:00 0.3
5/16/2022 0:00 5/16/2022 0:00 1
4 9/17/2022 0:00 9/25/2022 0:00 1
7 8/26/2022 0:00 9/15/2022 0:00 1
5 9/26/2022 0:00 10/6/2022 0:00 1
2 10/9/2022 0:00 10/9/2022 0:00 1
11
7 10/16/2022 0:00 10/22/2022 0:00 1
3/20/2022 0:00

7 3/26/2022 0:00 5/22/2022 0:00 1


5 6/2/2022 0:00 6/6/2022 0:00 1
5 6/26/2022 0:00 7/16/2022 0:00 1
5 7/21/2022 0:00 8/3/2022 0:00 1
1 8/7/2022 0:00 8/7/2022 0:00 1

11 8/16/2022 0:00 8/24/2022 0:00 1


11 8/25/2022 0:00 9/1/2022 0:00 0.98
11/5/2021 0:00

253 11/5/2021 0:00 6/15/2022 0:00


13 11/5/2021 0:00 12/20/2021 0:00 1
5 12/22/2021 0:00 12/23/2021 0:00 1
8 1/4/2022 0:00 1/11/2022 0:00 1
9 1/12/2022 0:00 1/21/2022 0:00 1
6 1/21/2022 0:00 2/6/2022 0:00 1
3 2/7/2022 0:00 2/7/2022 0:00 1
46 4/11/2022 0:00 5/26/2022 0:00 1
5 2/28/2022 0:00 2/28/2022 0:00 1
9 2/28/2022 0:00 3/6/2022 0:00 1
12 2/27/2022 0:00 3/12/2022 0:00 1
11 4/11/2022 0:00 4/21/2022 0:00 1
126 2/10/2022 0:00 6/15/2022 0:00 1
93
6 6/3/2022 0:00 6/6/2022 0:00 1

2 6/7/2022 0:00 6/7/2022 0:00 1

77 6/28/2022 0:00 7/10/2022 0:00 1


286
133 9/8/2022 0:00 0.7
39 10/11/2022 0:00 0.52
22
9 1
7
10
18
6
6
6

8 6/15/2022 0:00 6/20/2022 0:00 1


16 7/18/2022 0:00 9/22/2022 0:00 1
7/14/2022 0:00

6 7/21/2022 0:00 7/26/2022 0:00 1


4 8/1/2022 0:00 8/3/2022 0:00 1
5 8/23/2022 0:00 8/23/2022 0:00 1
7 8/14/2022 0:00 8/21/2022 0:00 1
6 8/24/2022 0:00 9/5/2022 0:00 1
3 9/6/2022 0:00 9/6/2022 0:00 1

16 9/20/2022 0:00 10/5/2022 0:00 1


3 10/26/2022 0:00 0.25
8/13/2022 0:00
8/13/2022 0:00
11 8/13/2022 0:00 8/18/2022 0:00 1
6 8/26/2022 0:00 8/29/2022 0:00 1
8 9/5/2022 0:00 9/11/2022 0:00 1
5 9/5/2022 0:00 9/11/2022 0:00 1
7 9/12/2022 0:00 9/15/2022 0:00 1
2 10/16/2022 0:00 10/16/2022 0:00 1
13

19 0.5
3
11/3/2020 0:00

133 11/3/2020 0:00 7/4/2022 0:00

3 11/3/2020 0:00 11/5/2020 0:00 1


8 11/7/2020 0:00 11/12/2020 0:00 1
3 11/13/2020 0:00 11/14/2020 0:00 1
6 11/13/2020 0:00 11/15/2020 0:00 1
1 11/17/2020 0:00 11/17/2020 0:00 1
8 4/8/2021 0:00 4/15/2021 0:00 1
17 5/9/2021 0:00 5/26/2021 0:00 1
16 4/17/2021 0:00 5/8/2021 0:00 1
52 11/26/2020 0:00 1/16/2021 0:00 1
11 1/27/2021 0:00 2/15/2021 0:00 1
8 3/23/2021 0:00 7/4/2022 0:00 1
183 1/9/2022 0:00
41 1/9/2022 0:00 9/28/2022 0:00 1
5 9/25/2022 0:00 10/2/2022 0:00 1
13 4/24/2022 0:00 5/11/2022 0:00 1
2 5/13/2022 0:00 5/15/2022 0:00 1
23 5/17/2022 0:00 6/26/2022 0:00 1
22 6/27/2022 0:00 8/11/2022 0:00 1
45 8/12/2022 0:00 9/26/2022 0:00 1
3 9/27/2022 0:00 9/29/2022 0:00 1
5 9/26/2022 0:00 10/1/2022 0:00 1
24 10/9/2022 0:00 0.65
210 10/6/2022 0:00
68 10/6/2022 0:00 0.2

32
19
8
1
11
7
2
2
6/25/2022 0:00

6 7/10/2022 0:00 7/14/2022 0:00 1

4 8/2/2022 0:00 8/7/2022 0:00 1


7 8/3/2022 0:00 8/6/2022 0:00 1
6 8/6/2022 0:00 8/9/2022 0:00 1
2 8/14/2022 0:00 8/14/2022 0:00 1

8/20/2022 0:00 9/7/2022 0:00 1


4/11/2022 0:00

7 4/11/2022 0:00 4/17/2022 0:00 1


4 6/16/2022 0:00 6/19/2022 0:00 1
6 6/25/2022 0:00 6/30/2022 0:00 1
8 7/2/2022 0:00 7/8/2022 0:00 1
8 7/12/2022 0:00 7/17/2022 0:00 1
2 7/17/2022 0:00 7/17/2022 0:00 1
6 6/28/2022 0:00 7/3/2022 0:00 1
21 7/19/2022 0:00 8/31/2022 0:00 1
12 9/20/2022 0:00 9/27/2022 0:00 1
12 9/20/2022 0:00 9/27/2022 0:00 1
21 9/28/2022 0:00 0.8
22
5

4
4 8/13/2022 0:00 8/16/2022 0:00 1
4 8/13/2022 0:00 8/16/2022 0:00 1

6 8/17/2022 0:00 9/3/2022 0:00 1


3 9/4/2022 0:00 9/4/2022 0:00 1

7 9/10/2022 0:00 9/18/2022 0:00 1

12
8
2
5/23/2022 0:00

95 5/23/2022 0:00 7/3/2022 0:00

1 5/23/2022 0:00 5/23/2022 0:00 1

3 6/23/2022 0:00 7/3/2022 0:00 1

13 8/3/2022 0:00 8/22/2022 0:00 1


7 9/1/2022 0:00 9/5/2022 0:00
44 7/25/2022 0:00 9/6/2022 0:00
8 8/15/2022 0:00 8/27/2022 0:00 1
13 8/3/2022 0:00 8/22/2022 0:00 1
3 6/23/2022 0:00 7/3/2022 0:00 1
3 6/23/2022 0:00 7/3/2022 0:00 1

4 9/19/2022 0:00 9/20/2022 0:00 1

5 9/7/2022 0:00 9/7/2022 0:00 1

16 10/3/2022 0:00 10/18/2022 0:00 1

10 10/3/2022 0:00 10/26/2022 0:00 1

4 10/26/2022 0:00
4
4
4/25/2022 0:00

53
2 5/8/2022 0:00 5/8/2022 0:00 1
1 5/8/2022 0:00 5/8/2022 0:00 1
8 4/25/2022 0:00 5/2/2022 0:00 1
8 6/8/2022 0:00 6/12/2022 0:00 1
5 6/14/2022 0:00 6/15/2022 0:00 1
2 6/17/2022 0:00 6/17/2022 0:00 1
6 6/13/2022 0:00 6/18/2022 0:00 1
7 6/27/2022 0:00 7/5/2022 0:00 1
7 7/27/2022 0:00 7/31/2022 0:00 1

7 8/15/2022 0:00 8/27/2022 0:00 1


6 9/3/2022 0:00 9/15/2022 0:00 1
4 9/19/2022 0:00 9/19/2022 0:00 1

6 10/19/2022 0:00 10/23/2022 0:00 1


52
4 9/22/2022 0:00 10/2/2022 0:00 1

48 10/3/2022 0:00 0.65

6
2
2
2
Remarks

REPORT DATE:

REMARKS

Due to Rain water logging in dyke wall

Preliminary IAT received on 26/12/21

Junction box Installation and termination pending

Service test to be done


REMARKS

Inclement Weather

44880

REMARKS
Inclement Weather

44864

REMARKS
Inclement Weather

44905

REMARKS
Inclement Weather

REPORT DATE:

REMARKS
Inclement Weather

REPORT DATE:

REMARKS
REMARKS

Inclement Weather

REPORT DATE:
REMARKS
REMARKS

Inclement Weather

REPORT DATE:

REMARKS
REMARKS
Inclement Weather

Dhruvil Vaniyawala

REPORT DATE:

REMARKS
Water Draining is very slow(Level - 7.47m)

REMARKS

Inclement Weather
Dhruvil Vaniyawala

REPORT DATE:

REMARKS

Delayed in receiving CTRA


Blindlist received on 8-2-22
Cleaning CTRA received on 13-2-22

Delayed by Electrical Maintenance


Due to Heat detection cable

Due to Non Availabilty of ISCO manpower

Cp initial Backfilling for Ribbon laying in progress


TFS repair in progress

REMARKS

Inclement Weather

REPORT DATE:

REMARKS
12" line to be installed at south east side
REMARKS

Inclement Weather

REPORT DATE:

REMARKS

Blinding delayed due to high level of product in the tank

Due to dumping issue of sludge in MAB

Received Inspection clearance on 17-Sep-22


New
Roof IAT received
plate cutting on 18-Oct-22
complete waiting for
Painting IAT for plates and structure

REMARKS
Inclement Weather

REPORT DATE:

REMARKS

Manpower used for Shutdown Scaffold work


Delayed by Electrical Maintenance
Due to Heat detection Cable
Due to Heat detection Cable
Due to Non Availabilty of ISCO manpower
Roof External Blasting ongoing
Delayed by Electrical Maintenance

REMARKS

Inclement Weather

REPORT DATE:
REMARKS
REMARKS

Inclement Weather

Dhruvil Vaniyawala

REPORT DATE:

REMARKS
New IAT received
REMARKS

Inclement Weather

Dhruvil Vaniyawala

REPORT DATE:

REMARKS

Due to dumping issue of sludge in MAB

Awaiting Inspection from 12-Sep-22


REMARKS
Inclement Weather

REPORT DATE:

REMARKS

New IAT received on 19-Oct-22


REMARKS

Inclement Weather
REPORT DATE:

REMARKS

Awaiting Inspection from 25-Oct-22


REMARKS

Inclement Weather

Dhruvil Vaniyawala

REPORT DATE:

REMARKS
Inspection delayed and started on 20-Sep-22 (One person only available for Inspection)
REMARKS

Inclement Weather

REPORT DATE:

REMARKS

Delayed by Electrical Maintenance


Due to Heat detection Cable

Sample Poin IAT issued on 16-6-22


Hydrotest delay due to low pressure in Fire hydrant

REMARKS
Inclement Weather

REPORT DATE:

REMARKS

New IAT received on 11-Sep-22


REMARKS

Inclement Weather

REPORT DATE:
REMARKS
REMARKS

Inclement Weather

REPORT DATE:

REMARKS
Water draining in progress

Roof External Blasting ongoing

REMARKS
Inclement Weather

REPORT DATE:

REMARKS

New IAT received on 15-Aug-22

Awaiting Inspection (Offered for 08-Sep-22)


REMARKS

Inclement Weather
REPORT DATE:

REMARKS

Blindlist received on 19-6-22


REMARKS

Inclement Weather

REPORT DATE:
REMARKS

New IAT received on 06-Sep-22


REMARKS

Inclement Weather

Dhruvil Vaniyawala

REPORT DATE:

REMARKS
New IAT received on 25-Jul-22

IAT Received on 06-09-22

REMARKS
Inclement Weather

REPORT DATE:

44889

REMARKS
Bottom and 1st shell remaining

REMARKS
Inclement Weather

Dhruvil Vaniyawala
DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 355445,359849,360930 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-703 START DATE: 11-Apr-22 END DATE:

TANK ROOF TYPE:Floating DIA (M) :64.62 HEIGHT (M): 19.50 PRODUCT: LFO

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 11-Apr-22


Dead Stock Transfer 11-Apr-22 17-Apr-22 7 11-Apr-22 17-Apr-22 100%
Blinding 16-Jun-22 19-Jun-22 4 16-Jun-22 19-Jun-22 100% Blindlist received on 19-6-22
Gas Freeing & Stripping 25-Jun-22 30-Jun-22 6 25-Jun-22 30-Jun-22 100%
De-Sludging 1-Jul-22 8-Jul-22 8 2-Jul-22 8-Jul-22 100%
Washing and Cleaning 9-Jul-22 16-Jul-22 8 12-Jul-22 17-Jul-22 100%
Preliminary Inspection 17-Jul-22 18-Jul-22 2 17-Jul-22 17-Jul-22 100%
External Scaffolding Erection 28-Jun-22 3-Jul-22 6 28-Jun-22 3-Jul-22 100%
Bottom Sweep Blasting 19-Jul-22 8-Aug-22 21 19-Jul-22 31-Aug-22 100%
Inspection of Tank Bottom 1-Sep-22 12-Sep-22 12 20-Sep-22 27-Sep-22 100%
Issuance of IAT 1-Sep-22 12-Sep-22 12 20-Sep-22 27-Sep-22 100%
Internal Scaffloding Erection 22-Sep-22 4-Nov-22 21 28-Sep-22 80%
Internal Sweep Blasting 5-Nov-22 27-Nov-22 22
Inspection of Tank 28-Nov-22 3-Dec-22 5
Issuance of IAT
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Internal Scaffloding Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 28-Nov-22 2-Dec-22 4
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 357548,362414 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-651 START DATE: 22-May-22 END DATE:

TANK ROOF TYPE:Dome DIA (M) :36.576 HEIGHT (M): 14.6304 PRODUCT: DIESEL OIL

TASK DESCRIPTION PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION REMARKS


START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS]
Dead-Stock Transfer 22-May-22 27-May-22 6 30-May-22 20-Jun-22 100%
Tank Blinding Works 14-Jun-22 23-Jun-22 8 25-Jun-22 25-Jun-22 100%
Gas Freeing & Stripping 28-Jun-22 8-Jul-22 11 2-Aug-22 19-Aug-22 100%
De-Sludging Works 7-Jul-22 15-Jul-22 9 8-Jul-22 16-Aug-22 100% Due to dumping issue of sludge in MAB
Washing and Cleaning Works 28-Jun-22 8-Jul-22 11 2-Aug-22 19-Aug-22 100%
Preliminary Inspection 21-Aug-22 21-Aug-22 21-Aug-22 21-Aug-22
External Scaffolding Erection NA
Internal Bottom Sweep Blasting 23-Aug-22 23-Sep-22 32 23-Aug-22
Inspection of Tank Bottom 24-Sep-22 30-Sep-22 7 12-Sep-22
Issuance of IAT(s) NA
Internal Scaffloding Erection NA
Internal Sweep Blasting 22-Aug-22 29-Aug-22 8 23-Aug-22 12-Sep-22 100% Awaiting Inspection from 12-Sep-22
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 360929,355793 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-454 START DATE: 22-Apr-22 END DATE:

TANK ROOF TYPE: Cone DIA (M) :18.288 HEIGHT (M): 12.192 PRODUCT: HGO/WAXY

TASK DESCRIPTION PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION REMARKS


START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS] 22-Apr-22
Dead-Stock Transfer 22-Apr-22 29-Apr-22 8 23-Apr-22 27-Apr-22 100%
Tank Blinding Works 27-Jun-22 30-Jun-22 4 25-Jun-22 25-Jun-22 Blinding delayed due to high level of product in the tank
Gas Freeing & Stripping 30-Apr-22 4-May-22 5 8-May-22 20-Jul-22 100%
De-Sludging Works 9-Jul-22 15-Jul-22 7 17-Jul-22 20-Jul-22 Due to dumping issue of sludge in MAB
Washing and Cleaning Works 5-May-22 6-May-22 2 21-Jul-22 21-Jul-22 100%
Preliminary Inspection 10-Aug-22 15-Aug-22 6 19-Aug-22 19-Aug-22 100%
External Scaffolding Erection 5-Oct-22 8-Oct-22 4 28-Aug-22 29-Aug-22 100%
Internal Bottom Sweep Blasting 31-Jul-22 6-Aug-22 7 31-Jul-22 15-Aug-22 100%
Inspection of Tank Bottom 2-Oct-22 4-Oct-22 3 4-Oct-22 4-Oct-22 100% Received Inspection clearance on 17-Sep-22
Issuance of IAT(s) 28-Jul-22
Internal Scaffloding Erection 17-Sep-22 23-Sep-22 7 20-Sep-22 24-Sep-22 100%
Internal Sweep Blasting 24-Sep-22 29-Sep-22 6 26-Sep-22 2-Oct-22 100%
Inspection of Tank Roof & Shell 2-Oct-22 4-Oct-22 2 3-Oct-22 4-Oct-22 100% New IAT received on 18-Oct-22
Roof plate cutting complete waiting for
Issuance of IAT(s) Painting IAT for plates and structure
[MECHANICAL WORKS]
Re-Roofing Works 22-Oct-22 13-Nov-22 23 18-Oct-22 15%
NDT Works (Vaccum Box/DPT) 22-Nov-22 25-Nov-22 4
Internal Scaffolding Removal 25-Nov-22 6-Dec-22 10 20-Sep-22 24-Sep-22 100%
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal NA
CP System Installation NA
Re-Bottoming Works NA
Access Door Reinstallation NA
NDT Works (DPT/Vacuum Box Test/RT) NA
Tank HydroTest 7-Dec-22 22-Dec-22 15
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating 5-Oct-22 7-Oct-22 3 1-Aug-22 1-Aug-22 100%
HydroTest 5-Oct-22 7-Oct-22 3 1-Aug-22 1-Aug-22 100%
Service Test 5-Oct-22 7-Oct-22 3 1-Aug-22 1-Aug-22 100%
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 280671,287251,354417,361452 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-34-424 START DATE: 20-Mar-22 END DATE:

TANK ROOF TYPE: Internal Roof/Dome DIA (M) : 67.056 HEIGHT (M): 22.2504 PRODUCT: Gasoline

TASK DESCRIPTION PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION REMARKS


START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS] 20-Mar-22
Dead-Stock Transfer 20-Mar-22 26-Mar-22 7 26-Mar-22 22-May-22 100%
Tank Blinding Works
Gas Freeing & Stripping 3-Apr-22 7-Apr-22 5 2-Jun-22 6-Jun-22 100%
De-Sludging Works 8-Apr-22 12-Apr-22 5 26-Jun-22 16-Jul-22 100%
Washing and Cleaning Works 13-Apr-22 17-Apr-22 5 21-Jul-22 3-Aug-22 100%
Preliminary Inspection 4-Aug-22 4-Aug-22 1 7-Aug-22 7-Aug-22 100%
External Scaffolding Erection
Internal Bottom Sweep Blasting 16-Aug-22 26-Aug-22 11 16-Aug-22 24-Aug-22 100%
Inspection delayed and started on 20-
Inspection of Tank Bottom 27-Aug-22 6-Sep-22 11 25-Aug-22 1-Sep-22 98% Sep-22 (One person only available for
Inspection)
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 350835,355000,364885 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-253 START DATE: 5-Jan-22 END DATE:

TANK ROOF TYPE:Floating DIA (M) :48.768 HEIGHT (M): 14.6304 PRODUCT: NAPTHA

TASK DESCRIPTION PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION REMARKS


START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS] 5-Jan-22 10-Aug-22 243 5-Jan-22 10-Aug-22
Dead-Stock Transfer 5-Jan-22 31-Jan-22 27 5-Jan-22 31-Jan-22 100%
Tank Blinding Works 1-Feb-22 3-Feb-22 3 6-Feb-22 6-Feb-22 100% Delayed in receiving CTRA
Gas Freeing & Stripping 14-Feb-22 20-Feb-22 7 15-Feb-22 20-Feb-22 100% Blindlist received on 8-2-22
De-Sludging Works 21-Feb-22 27-Feb-22 7 21-Feb-22 27-Feb-22 100% Cleaning CTRA received on 13-2-22
Washing and Cleaning Works 28-Feb-22 3-Mar-22 4 28-Feb-22 2-Mar-22 100%
Preliminary Inspection 4-Mar-22 5-Mar-22 2 6-Mar-22 6-Mar-22 100%
External Scaffolding Erection 28-May-22 5-Jun-22 9 28-May-22 5-Jun-22 100%
Removal of Heat Detection Cable 7-Mar-22 10-Mar-22 4 11-Mar-22 20-Mar-22 100% Delayed by Electrical Maintenance
Removal of Roof Seal 10-Mar-22 17-Mar-22 8 21-Mar-22 31-Mar-22 100% Due to Heat detection cable
Internal Sweep Blasting 1-Apr-22 6-Apr-22 6 2-Apr-22 3-Apr-22 100%
Inspection of Tank 4-Apr-22 15-Apr-22 12 8-May-22 3-Jun-22 100% Due to Non Availabilty of ISCO manpower
Issuance of IAT(s) 10-Mar-22 10-Aug-22 154 10-Mar-22 10-Aug-22 100%
[MECHANICAL WORKS]
Re-Roofing Works 28-Jul-22 4-Aug-22 8 16-Aug-22 100%
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal 5-Aug-22 25-Aug-22 21 22-Jun-22 11-Aug-22 100%
C.P. System Installation 27-Oct-22 19-Nov-22 22 5% Cp initial Backfilling for Ribbon laying in progress
Re-Bottoming Works 20-Nov-22 31-Dec-22 40
Access Door Reinstallation 1-Jan-23 6-Jan-23 5
NDT Works (DPT/Vacuum Box Test/RT) 1-Jan-23 6-Jan-23 4
Re-Installation of Roof Seal 7-Jan-23 14-Jan-23 7
Tank HydroTest 16-Jan-23 15-Feb-23 30
Opening of Roof Seal(If Required)
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 21-Dec-22 25-Feb-23 66
Roof Leg Pad Blasting & Coating 15-Feb-23 22-Mar-23 35
Tank Internal Blasting & Painting 18-Mar-23 8-Apr-23 21
U/G Piping Coating Works
External Scaffolding Removal 26-Feb-22 10-Mar-22 12
Tank Calibration 11-Mar-22 13-Mar-22 2
[HANDOVER WORKS]
Final Cleaning & Housekeeping 19-Mar-23 24-Mar-23 6
Tank Box-Up Works 19-Mar-23 24-Mar-23 6
De-Blinding 19-Mar-23 24-Mar-23 6
[TDS & TFS WORKS]
Mechanical Repair & Coating TFS repair in progress
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 340896,342651,350830,355796 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-264 START DATE: END DATE:

TANK ROOF TYPE:Fixed DIA (M) :58.15 HEIGHT (M): 58.15 PRODUCT: F/Water

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS]
Dead-Stock Transfer NA
Tank Blinding Works NA
Gas Freeing & Stripping NA
De-Sludging Works NA
Washing and Cleaning Works 1-Aug-22 8-Aug-22 8 1-Aug-22 10-Aug-22 100%
Preliminary Inspection 8-Aug-22 9-Aug-22 2 11-Aug-22 11-Aug-22 100%
External Scaffolding Erection 15-Sep-21 24-Sep-21 10 15-Sep-21 24-Sep-21 100%
Internal Bottom Sweep Blasting 26-Sep-21 6-Oct-21 10 26-Sep-21 6-Oct-21 100%
Inspection of Tank Bottom 7-Oct-22 13-Oct-22 6 7-Oct-22 13-Oct-22 100%
Issuance of IAT(s) 7-Oct-22 13-Oct-22 7 7-Oct-22 13-Oct-22 100%
Internal Scaffloding Erection 21-Oct-21 7-Nov-21 17 21-Oct-21 7-Nov-21 100%
Internal Sweep Blasting 21-Dec-21 23-Jan-22 33 2-Jan-22 14-Jan-22 100%
Inspection of Tank Roof & Shell 21-Oct-21 7-Nov-21 17 21-Oct-21 7-Nov-21 100%
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works NA
NDT Works (Vaccum Box/DPT) NA
Internal Scaffolding Removal 8-Sep-22 18-Sep-22 11 100%
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal NA
CP System Installation NA
Re-Bottoming Works NA
Access Door Reinstallation NA
NDT Works (DPT/Vacuum Box Test/RT) NA
Tank HydroTest 23-Oct-22 18-Nov-22 27 23-Oct-22 38%
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 20-Nov-22 8-Dec-22 18
Tank External Blasting & Painting 10-Jul-22 22-Aug-22 43 10-Jul-22 22-Aug-22 100%
Tank internal Blasting & Painting 13-Aug-22 7-Sep-22 25 13-Aug-22 7-Sep-22 100%
U/G Piping Coating Works 19-Sep-22 2-Dec-22 74 100%
External Scaffolding Removal 3-Dec-22 7-Dec-22 4
Tank Calibration 3-Dec-22 4-Dec-22 1
[HANDOVER WORKS]
Final Cleaning & Housekeeping 3-Dec-22 8-Dec-22
Tank Box-Up Works 3-Dec-22 8-Dec-22
De-Blinding 3-Dec-22 8-Dec-22
[TDS & TFS WORKS]
Mechanical Repair & Coating 12" line to be installed at south east side
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 350834,352983,357630,359853,361083 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-464 START DATE: 5-Nov-21 END DATE:

TANK ROOF TYPE:Floating DIA (M) :43.8912 HEIGHT (M): 19.5072 PRODUCT: MOGAS

TASK DESCRIPTION PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION REMARKS


START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS] 5-Nov-21 15-Jun-22 253 5-Nov-21 15-Jun-22
Dead-Stock Transfer 5-Nov-21 17-Nov-21 13 5-Nov-21 20-Dec-21 100%
Tank Blinding Works 20-Dec-21 24-Dec-21 5 22-Dec-21 23-Dec-21 100%
Gas Freeing & Stripping 3-Jan-22 10-Jan-22 8 4-Jan-22 11-Jan-22 100%
De-Sludging Works 11-Jan-22 19-Jan-22 9 12-Jan-22 21-Jan-22 100%
Washing and Cleaning Works 20-Jan-22 25-Jan-22 6 21-Jan-22 6-Feb-22 100%
Preliminary Inspection 26-Jan-22 28-Jan-22 3 7-Feb-22 7-Feb-22 100%
External Scaffolding Erection 11-Apr-22 26-May-22 46 11-Apr-22 26-May-22 100%
Removal of Heat Detection Cable 13-Feb-22 17-Feb-22 5 28-Feb-22 28-Feb-22 100% Delayed by Electrical Maintenance
Removal of Roof Seal 18-Feb-22 26-Feb-22 9 28-Feb-22 6-Mar-22 100% Due to Heat detection Cable
Internal Sweep Blasting 27-Feb-22 10-Mar-22 12 27-Feb-22 12-Mar-22 100%
Inspection of Tank 11-Mar-22 21-Mar-22 11 11-Apr-22 21-Apr-22 100%
Issuance of IAT(s) 10-Feb-22 15-Jun-22 126 10-Feb-22 15-Jun-22 100% Sample Poin IAT issued on 16-6-22
[MECHANICAL WORKS] 22-May-22 15-Sep-22 93
Re-Roofing Works NA
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal NA
C.P. System Installation NA
Re-Bottoming Works 22-May-22 27-May-22 6 3-Jun-22 6-Jun-22 100%
Access Door Reinstallation NA
NDT Works (DPT/Vacuum Box Test/RT) 1-Jun-22 2-Jun-22 2 7-Jun-22 7-Jun-22 100%
Re-Installation of Roof Seal
Tank HydroTest 1-Jul-22 15-Sep-22 77 28-Jun-22 10-Jul-22 100% Hydrotest delay due to low pressure in Fire hydrant
[BLASTING & PAINTING WORKS] 8-Sep-22 29-Nov-22 286
Tank External Blasting & Painting 8-Sep-22 30-Oct-22 133 8-Sep-22 70%
Roof Leg Pad Blasting & Coating 11-Oct-22 18-Nov-22 39 11-Oct-22 52%
Tank Internal Blasting & Painting 15-Nov-22 7-Dec-22 22
U/G Piping Coating Works 21-Oct-22 29-Oct-22 9 100%
External Scaffolding Removal 21-Oct-22 27-Oct-22 7
Tank Calibration 20-Nov-22 29-Nov-22 10
[HANDOVER WORKS] 30-Nov-22 5-Dec-22 18
Final Cleaning & Housekeeping 30-Nov-22 5-Dec-22 6
Tank Box-Up Works 30-Nov-22 5-Dec-22 6
De-Blinding 4-Dec-22 10-Dec-22 6
[TDS & TFS WORKS]
Mechanical Repair & Coating 23-Jul-22 30-Jul-22 8 15-Jun-22 20-Jun-22 100%
HydroTest 1-Jul-22 15-Sep-22 16 18-Jul-22 22-Sep-22 100%
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 327461,328607,363335,364253,345183 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-600 START DATE: 3-Nov-20 END DATE:

TANK ROOF TYPE:Fixed DIA (M) :43.8912 HEIGHT (M): 14.6304 PRODUCT: HSD

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 3-Nov-20 6-Feb-21 133 3-Nov-20 4-Jul-22


Dead-Stock Transfer NA
Tank Blinding Works 3-Nov-20 5-Nov-20 3 3-Nov-20 5-Nov-20 100%
Gas Freeing & Stripping 7-Nov-20 14-Nov-20 8 7-Nov-20 12-Nov-20 100%
De-Sludging Works 15-Nov-20 17-Nov-20 3 13-Nov-20 14-Nov-20 100%
Washing and Cleaning Works 18-Nov-20 23-Nov-20 6 13-Nov-20 15-Nov-20 100%
Preliminary Inspection 24-Nov-20 24-Nov-20 1 17-Nov-20 17-Nov-20 100%
External Scaffolding Erection 8-Apr-21 15-Apr-21 8 8-Apr-21 15-Apr-21 100%
Internal Bottom Sweep Blasting 12-Apr-21 28-Apr-21 17 9-May-21 26-May-21 100%
Inspection of Tank Bottom NA
Issuance of IAT(s) NA
Internal Scaffloding Erection 26-Mar-21 10-Apr-21 16 17-Apr-21 8-May-21 100%
Internal Sweep Blasting 26-Nov-20 16-Jan-21 52 26-Nov-20 16-Jan-21 100%
Inspection of Tank Roof & Shell 18-Jan-21 28-Jan-21 11 27-Jan-21 15-Feb-21 100%
Issuance of IAT(s) 30-Jan-21 6-Feb-21 8 23-Mar-21 4-Jul-22 100%
[MECHANICAL WORKS] 27-Nov-21 14-Oct-22 183 9-Jan-22
Re-Roofing Works 27-Nov-21 6-Jan-22 41 9-Jan-22 28-Sep-22 100%
NDT Works (Vaccum Box/DPT) 7-Jan-22 11-Jan-22 5 25-Sep-22 2-Oct-22 100%
Internal Scaffolding Removal 30-Aug-21 11-Sep-21 13 24-Apr-22 11-May-22 100%
Access Door Cutting & Removal 5-Jan-22 6-Jan-22 2 13-May-22 15-May-22 100%
Existing Bottom Plates & Old Soil Removal 2-May-22 24-May-22 23 17-May-22 26-Jun-22 100%
CP System Installation 25-May-22 15-Jun-22 22 27-Jun-22 11-Aug-22 100%
Re-Bottoming Works 25-Jun-22 16-Sep-22 45 12-Aug-22 26-Sep-22 100%
Access Door Reinstallation 17-Sep-22 20-Sep-22 3 27-Sep-22 29-Sep-22 100%
NDT Works (DPT/Vacuum Box Test/RT) 15-Sep-22 19-Sep-22 5 26-Sep-22 1-Oct-22 100%
Tank HydroTest 20-Sep-22 14-Oct-22 24 9-Oct-22 65% Water draining in progress
[BLASTING & PAINTING WORKS] 10-Oct-21 19-Dec-22 210 6-Oct-22
Tank External Blasting & Painting 4-Oct-22 11-Dec-22 68 6-Oct-22 20% Roof External Blasting ongoing
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting 24-Oct-22 25-Nov-22 32
U/G Piping Coating Works 18-Oct-22 5-Nov-22 19
External Scaffolding Removal 12-Dec-22 19-Dec-22 8
Tank Calibration 19-Dec-22 19-Dec-22 1
[HANDOVER WORKS] 15-Dec-22 27-Dec-22 11
Final Cleaning & Housekeeping 9-Dec-22 15-Dec-22 7
Tank Box-Up Works 16-Dec-22 18-Dec-22 2
De-Blinding 19-Dec-22 21-Dec-22 2
[TDS & TFS WORKS]
Mechanical Repair & Coating Na
HydroTest Na
Service Test Na
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 363330,364252 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-12-863 START DATE: END DATE:

TANK ROOF TYPE:Fixed Roof DIA (M) :4.9 HEIGHT (M): 6.09 PRODUCT: Bitumen

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS]
Dead-Stock Transfer NA
Tank Blinding Works NA
Gas Freeing & Stripping 9-Sep-22 14-Sep-22 6 13-Sep-22 14-Sep-22 100%
De-Sludging Works 4-Sep-22 8-Sep-22 5 8-Sep-22 12-Sep-22 100%
Washing and Cleaning Works 9-Sep-22 14-Sep-22 6 13-Sep-22 14-Sep-22
Preliminary Inspection 14-Oct-22 14-Oct-22 1 13-Oct-22 13-Oct-22 100%
External Scaffolding Erection
Internal Bottom Sweep Blasting 21-Sep-22 22-Sep-22 2 21-Sep-22 21-Sep-22 100%
Inspection of Tank Bottom 23-Sep-22 24-Sep-22 2 13-Oct-22 13-Oct-22 100%
Issuance of IAT(s)
Internal Scaffloding Erection 25-Sep-22 26-Sep-22 2 27-Sep-22 27-Sep-22 100%
Internal Sweep Blasting 27-Sep-22 29-Sep-22 3 29-Sep-22 29-Sep-22 100%
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works 13-Oct-21 12-Nov-21 31 13-Oct-21 12-Nov-21
NDT Works (Vaccum Box/DPT) 13-Nov-21 15-Nov-21 3 13-Nov-21 15-Nov-21
Internal Scaffolding Removal 3-Oct-22 5-Oct-22 3 6-Oct-22 6-Oct-22 100%
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal 9-Dec-21 1-Jan-22 24 9-Dec-21 1-Jan-22 100%
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 29-Sep-21 9-Oct-21 11 29-Sep-21 9-Oct-21
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating 15-Mar-22 18-Mar-22
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

2022-24833
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer: Dhruvil Vaniyawala


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 356125,357540,360597,361453 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-14-101 START DATE: END DATE:

TANK ROOF TYPE:Fixed Roof DIA (M) :17.983 HEIGHT (M): 10.973 PRODUCT:

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works NA
NDT Works (Vaccum Box/DPT) NA
Internal Scaffolding Removal NA
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal NA
CP System Installation NA
Re-Bottoming Works NA
Access Door Reinstallation NA
NDT Works (DPT/Vacuum Box Test/RT) NA
Tank HydroTest 13-Aug-22 4-Oct-22 53 3-Sep-22 62% Water Draining is very slow(Level - 7.47m)
[BLASTING & PAINTING WORKS]
Internal Blasting & Painting 26-Nov-22 29-Dec-22 34
Tank External Blasting & Painting 11-Nov-22 25-Nov-22 15
U/G Piping Coating Works
External Scaffolding Removal 27-Nov-22 30-Nov-22 4
Tank Calibration 30-Dec-22 31-Dec-22 1
[HANDOVER WORKS]
Final Cleaning & Housekeeping 30-Dec-22 3-Jan-23 5
Tank Box-Up Works 30-Dec-22 3-Jan-23 5
De-Blinding 30-Dec-22 3-Jan-23 5
[TDS & TFS WORKS]
Mechanical Repair & Coating 19-Dec-22 22-Dec-22 4
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer: Dhruvil Vaniyawala


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-509 START DATE: 7-Sep-22 END DATE:

TANK ROOF TYPE : Floating Roof DIA (M) :15.24 HEIGHT (M): 13.4112 PRODUCT: ATK

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 7-Sep-22


Dead-Stock Transfer 7-Sep-22 9-Sep-22 3 8-Sep-22 9-Sep-22 100%
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer: Dhruvil Vaniyawala


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 364247 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-510 START DATE: 23-Sep-22 END DATE:

TANK ROOF TYPE:Cone DIA (M) :10.668 HEIGHT (M): 10.9728 PRODUCT: MOGAS

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 23-Sep-22


Dead-Stock Transfer 23-Sep-22 25-Sep-22 3 23-Sep-22 26-Sep-22 100%
Tank Blinding Works NA
Gas Freeing & Stripping 26-Sep-22 29-Sep-22 4 1-Oct-22 3-Oct-22 100%
De-Sludging Works 30-Sep-22 2-Oct-22 3 4-Oct-22 5-Oct-22 100%
Washing and Cleaning Works 29-Nov-22 2-Dec-22 4 4-Oct-22 5-Oct-22 100%
Preliminary Inspection NA New IAT received
External Scaffolding Erection 5-Nov-22 15-Nov-22 10
Internal Bottom Sweep Blasting 1-Nov-22 17-Nov-22 16
Inspection of Tank Bottom 18-Nov-22 20-Nov-22 2
Issuance of IAT(s)
Internal Scaffloding Erection
External Sweep Blasting 21-Nov-22 22-Nov-22 1
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer: Dhruvil Vaniyawala


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 363328 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-34-406 START DATE: END DATE:

TANK ROOF TYPE : Dome DIA (M) :49.69 HEIGHT (M): 19.51 PRODUCT: PROPANE

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS]
Dead-Stock Transfer NA
Tank Blinding Works 16-May-22 16-May-22 16-May-22 16-May-22 100%
Gas Freeing & Stripping 3-Sep-22 7-Sep-22 4 17-Sep-22 25-Sep-22 100%
De-Sludging Works 26-Aug-22 2-Sep-22 7 26-Aug-22 15-Sep-22 100%
Washing and Cleaning Works 8-Sep-22 13-Sep-22 5 26-Sep-22 6-Oct-22 100%
Preliminary Inspection 14-Sep-22 16-Sep-22 2 9-Oct-22 9-Oct-22 100%
External Scaffolding Erection 25-Nov-22 6-Dec-22 11
Internal Bottom Sweep Blasting 16-Oct-22 23-Oct-22 7 16-Oct-22 22-Oct-22 100% Awaiting Inspection from 25-Oct-22
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer: Dhruvil Vaniyawala


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 361064 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-63-703B START DATE: END DATE:

TANK ROOF TYPE: Fixed Roof DIA (M) : HEIGHT (M): PRODUCT:

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works 15-Aug-22 18-Aug-22 4 13-Aug-22 16-Aug-22 100%
Gas Freeing & Stripping 15-Aug-22 18-Aug-22 4 13-Aug-22 16-Aug-22 100%
De-Sludging Works
Washing and Cleaning Works 19-Aug-22 24-Aug-22 6 17-Aug-22 3-Sep-22 100%
Preliminary Inspection 25-Aug-22 27-Aug-22 3 4-Sep-22 4-Sep-22 100% New IAT received on 06-Sep-22
External Scaffolding Erection
Internal Bottom Sweep Blasting 12-Sep-22 18-Sep-22 7 10-Sep-22 18-Sep-22 100%
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection 5-Nov-22 17-Nov-22 12
Internal Sweep Blasting 18-Nov-22 26-Nov-22 8
Inspection of Tank Roof & Shell 27-Nov-22 29-Nov-22 2
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

2022-24833
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer: Dhruvil Vaniyawala


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 355794,359854,364246 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-96-912 START DATE: 25-Apr-22 END DATE: 24-Nov-22

TANK ROOF TYPE:Fixed DIA (M) : HEIGHT (M): PRODUCT: SOUR WATER

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 25-Apr-22 6-Aug-22 53


Dead-Stock Transfer 6-May-22 7-May-22 2 8-May-22 8-May-22 100%
Tank Blinding Works 8-May-22 8-May-22 1 8-May-22 8-May-22 100%
Gas Freeing & Stripping 25-Apr-22 2-May-22 8 25-Apr-22 2-May-22 100%
De-Sludging Works 3-May-22 10-May-22 8 8-Jun-22 12-Jun-22 100%
Washing and Cleaning Works 16-May-22 20-May-22 5 14-Jun-22 15-Jun-22 100%
Preliminary Inspection 21-May-22 22-May-22 2 17-Jun-22 17-Jun-22 100%
External Scaffolding Erection 27-May-22 1-Jun-22 6 13-Jun-22 18-Jun-22 100%
Internal Bottom Sweep Blasting 27-Jun-22 3-Jul-22 7 27-Jun-22 5-Jul-22 100%
Inspection of Tank Bottom 8-Jul-22 14-Jul-22 7 27-Jul-22 31-Jul-22 100%
Issuance of IAT(s) NA
Internal Scaffloding Erection 15-Jul-22 22-Jul-22 7 15-Aug-22 27-Aug-22 100%
Internal Sweep Blasting 23-Jul-22 29-Jul-22 6 3-Sep-22 15-Sep-22 100%
Inspection of Tank Roof & Shell 2-Aug-22 6-Aug-22 4 19-Sep-22 19-Sep-22 100%
Issuance of IAT(s) NA
[MECHANICAL WORKS] 10-Oct-22 16-Oct-22 6
Re-Roofing Works NA
NDT Works (Vaccum Box/DPT) NA
Internal Scaffolding Removal 10-Oct-22 16-Oct-22 6 19-Oct-22 23-Oct-22 100%
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal NA
CP System Installation NA
Re-Bottoming Works NA
Access Door Reinstallation NA
NDT Works (DPT/Vacuum Box Test/RT) NA
Tank HydroTest NA
[BLASTING & PAINTING WORKS] 24-Sep-22 16-Nov-22 52
Internal Roof Blasting & Painting 24-Sep-22 28-Sep-22 4 22-Sep-22 2-Oct-22 100%
Tank External Blasting & Painting NA
Tank internal Blasting & Painting 29-Sep-22 16-Nov-22 48 3-Oct-22 65% Bottom and 1st shell remaining
U/G Piping Coating Works NA
External Scaffolding Removal
Tank Calibration NA
[HANDOVER WORKS] 16-Nov-22 24-Nov-22 6
Final Cleaning & Housekeeping 16-Nov-22 18-Nov-22 2
Tank Box-Up Works 19-Nov-22 21-Nov-22 2
De-Blinding 22-Nov-22 24-Nov-22 2
[TDS & TFS WORKS]
Mechanical Repair & Coating NA
HydroTest NA
Service Test NA
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

2022-24833
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer: Dhruvil Vaniyawala


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : START DATE: END DATE:

TANK ROOF TYPE: DIA (M) : HEIGHT (M): PRODUCT:

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping 15-Oct-22 16-Oct-22 2
De-Sludging Works
Washing and Cleaning Works 17-Oct-22 18-Oct-22 2 17-Oct-22 17-Oct-22 100%
Preliminary Inspection 18-Oct-22 18-Oct-22 1 18-Oct-22 18-Oct-22 100%
External Scaffolding Erection 23-Oct-22 25-Oct-22 3
Internal Bottom Sweep Blasting 5-Nov-22 8-Nov-22 4
Inspection of Tank Bottom 9-Nov-22 10-Nov-22 2
Issuance of IAT(s) 19-Oct-22 19-Oct-22 1 19-Oct-22 19-Oct-22 New IAT received on 19-Oct-22
Internal Scaffloding Erection 19-Oct-22 19-Oct-22 1 19-Oct-22 19-Oct-22 100%
Internal Sweep Blasting (Roof & Shell) 23-Oct-22 25-Oct-22 2 25-Oct-22 25-Oct-22 100%
Inspection of Tank Roof & Shell 26-Oct-22 27-Oct-22 2 26-Oct-22 26-Oct-22 100%
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting 23-Oct-22 25-Oct-22 3 24-Oct-22 30%
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 360598,362415,310870 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-671 START DATE: 25-Jun-22 END DATE:

TANK ROOF TYPE:Fixed Roof DIA (M) : HEIGHT (M): PRODUCT: GASOIL

TASK DESCRIPTION PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION REMARKS


START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS] 25-Jun-22
Dead-Stock Transfer 25-Jun-22 30-Jun-22 6 10-Jul-22 14-Jul-22 100%
Tank Blinding Works NA
Gas Freeing & Stripping 4-Aug-22 7-Aug-22 4 2-Aug-22 7-Aug-22 100%
De-Sludging Works 8-Aug-22 14-Aug-22 7 3-Aug-22 6-Aug-22 100%
Washing and Cleaning Works 15-Aug-22 20-Aug-22 6 6-Aug-22 9-Aug-22 100%
Preliminary Inspection 10-Aug-22 11-Aug-22 2 14-Aug-22 14-Aug-22 100% New IAT received on 15-Aug-22
External Scaffolding Erection
Internal Bottom Sweep Blasting 24-Aug-22 10-Sep-22 20-Aug-22 7-Sep-22 100%
Inspection of Tank Bottom 11-Sep-22 23-Sep-22 Awaiting Inspection (Offered for 08-Sep-22)
Issuance of IAT(s) 21-Aug-22 28-Sep-22
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 357542,360932,364245 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-66-953 START DATE: 23-May-22 END DATE:

TANK ROOF TYPE:Fixed Roof DIA (M) :29.016 HEIGHT (M): 15.24 PRODUCT: SEA WATER

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 23-May-22 14-Jun-22 95 23-May-22 3-Jul-22


Dead-Stock Transfer NA
Tank Blinding Works 23-May-22 23-May-22 1 23-May-22 23-May-22 100%
Gas Freeing & Stripping NA
De-Sludging Works NA
Washing and Cleaning Works NA
Preliminary Inspection 12-Jun-22 14-Jun-22 3 23-Jun-22 3-Jul-22 100%
External Scaffolding Erection NA
Internal Bottom Sweep Blasting 30-Jul-22 11-Aug-22 13 3-Aug-22 22-Aug-22 100%
Inspection of Tank Bottom 19-Jun-22 25-Jun-22 7 1-Sep-22 5-Sep-22
Issuance of IAT(s) 25-Jul-22 6-Sep-22 44 25-Jul-22 6-Sep-22
Internal Scaffloding Erection 15-Jul-22 22-Jul-22 8 15-Aug-22 27-Aug-22 100%
Internal Sweep Blasting 30-Jul-22 11-Aug-22 13 3-Aug-22 22-Aug-22 100% New IAT received on 25-Jul-22
Inspection of Tank Roof & Shell 12-Jun-22 14-Jun-22 3 23-Jun-22 3-Jul-22 100%
Issuance of IAT(s) 12-Jun-22 14-Jun-22 3 23-Jun-22 3-Jul-22 100% IAT Received on 06-09-22
[MECHANICAL WORKS]
Re-Roofing Works Na
NDT Works (Vaccum Box/DPT) Na
Internal Scaffolding Removal 29-Sep-22 2-Oct-22 4 19-Sep-22 20-Sep-22 100%
Access Door Cutting & Removal Na
Existing Bottom Plates & Old Soil Removal Na
CP System Installation Na
Re-Bottoming Works 7-Sep-22 11-Sep-22 5 7-Sep-22 7-Sep-22 100%
Access Door Reinstallation Na
NDT Works (DPT/Vacuum Box Test/RT) Na
Tank HydroTest Na
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting Na
Tank External Blasting & Painting 3-Oct-22 18-Oct-22 16 3-Oct-22 18-Oct-22 100%
Tank internal Blasting & Painting
Tank Extrenal Fire line Coating Works 3-Oct-22 13-Oct-22 10 3-Oct-22 26-Oct-22 100%
External Scaffolding Removal Na
Tank Calibration Na
[HANDOVER WORKS]
Final Cleaning & Housekeeping 27-Oct-22 30-Oct-22 4 26-Oct-22
Tank Box-Up Works 27-Oct-22 30-Oct-22 4
De-Blinding 27-Oct-22 30-Oct-22 4
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 361450,364097 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-534 START DATE: 13-Aug-22 END DATE:

TANK ROOF TYPE: Floating Roof DIA (M) :49.866 HEIGHT (M): 19.507 PRODUCT: ATK

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 10-Aug-22 13-Aug-22


Dead-Stock Transfer 10-Aug-22 20-Aug-22 11 13-Aug-22 18-Aug-22 100%
Tank Blinding Works 24-Aug-22 29-Aug-22 6 26-Aug-22 29-Aug-22 100%
Gas Freeing & Stripping 1-Sep-22 8-Sep-22 8 5-Sep-22 11-Sep-22 100%
De-Sludging Works 9-Sep-22 13-Sep-22 5 5-Sep-22 11-Sep-22 100%
Washing and Cleaning Works 14-Sep-22 20-Sep-22 7 12-Sep-22 15-Sep-22 100%
Preliminary Inspection 14-Oct-22 15-Oct-22 2 16-Oct-22 16-Oct-22 100%
External Scaffolding Erection 10-Nov-22 23-Nov-22 13
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting 20-Oct-22 7-Nov-22 19 50%
Inspection of Tank 8-Nov-22 10-Nov-22 3
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 360599,363334 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-468 START DATE: 14-Jul-22 END DATE:

TANK ROOF TYPE:Floating Roof DIA (M) :4.14528 HEIGHT (M): 19.5072 PRODUCT: NAPTHA

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 14-Jul-22


Dead-Stock Transfer 14-Jul-22 19-Jul-22 6 21-Jul-22 26-Jul-22 100%
Tank Blinding Works 27-Jul-22 30-Jul-22 4 1-Aug-22 3-Aug-22 100%
Gas Freeing & Stripping 11-Aug-22 15-Aug-22 5 23-Aug-22 23-Aug-22 100%
De-Sludging Works 16-Aug-22 22-Aug-22 7 14-Aug-22 21-Aug-22 100%
Washing and Cleaning Works 23-Aug-22 28-Aug-22 6 24-Aug-22 5-Sep-22 100% New IAT received on 11-Sep-22
Preliminary Inspection 25-Aug-22 27-Aug-22 3 6-Sep-22 6-Sep-22 100%
External Scaffolding Erection
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting 20-Sep-22 5-Oct-22 16 20-Sep-22 5-Oct-22 100%
Inspection of Tank 6-Oct-22 8-Oct-22 3 26-Oct-22 25%
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 350836,356625,361083,364251,345871 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-504 START DATE: 16-Oct-21 END DATE:

TANK ROOF TYPE:Floating Roof DIA (M) :24.384 HEIGHT (M): 12.192 PRODUCT: KEROSENE

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 16-Oct-21 15-Feb-22 79 16-Oct-21 13-Apr-22


Dead-Stock Transfer 16-Oct-21 20-Oct-21 5 16-Oct-21 19-Oct-21 100%
Tank Blinding Works 21-Oct-21 24-Oct-21 4 27-Oct-21 27-Oct-21 100%
Gas Freeing & Stripping 28-Nov-21 4-Dec-21 7 28-Nov-21 30-Nov-21 100%
De-Sludging Works 5-Dec-21 7-Dec-21 3 1-Dec-21 2-Dec-21 100%
Washing and Cleaning Works 8-Dec-21 12-Dec-21 5 2-Dec-21 6-Dec-21 100%
Preliminary Inspection 13-Dec-21 13-Dec-21 1 13-Dec-21 13-Dec-21 100%
External Scaffolding Erection 12-Feb-22 17-Feb-22 6 14-Feb-22 20-Feb-22 100% Manpower used for Shutdown Scaffold work
Removal of Heat Detection Cable 9-Dec-21 11-Dec-21 3 4-Jan-22 4-Jan-22 100% Delayed by Electrical Maintenance
Removal of Roof Seal 12-Dec-21 17-Dec-21 6 28-Dec-21 3-Jan-22 100% Due to Heat detection Cable
Internal Sweep Blasting 12-Dec-21 2-Jan-22 22 5-Jan-22 21-Jan-22 100% Due to Heat detection Cable
Inspection of Tank 3-Jan-22 13-Jan-22 11 22-Mar-22 3-Apr-22 100% Due to Non Availabilty of ISCO manpower
Issuance of IAT(s) 10-Feb-22 15-Feb-22 6 13-Dec-21 13-Apr-22 100%
[MECHANICAL WORKS] 5-May-22 13-Jun-22 122
Re-Roofing Works 5-May-22 23-Jun-22 50 10-May-22 9-Jun-22 100%
Access Door Cutting & Removal NA
Existing Bottom Plates & Old Soil Removal 2-May-22 9-May-22 8 20-Apr-22 8-May-22 100%
C.P. System Installation NA
Re-Bottoming Works 15-Apr-22 28-May-22 44 7-May-22 2-Jul-22 100%
Access Door Reinstallation NA
NDT Works (DPT/Vacuum Box Test/RT) 20-Jun-22 24-Jun-22 4 3-Jul-22 7-Jul-22 100%
Re-Installation of Roof Seal 1-Dec-22 7-Dec-22 6
Tank HydroTest 29-May-22 13-Jun-22 16 1-Sep-22 20-Sep-22 100%
[BLASTING & PAINTING WORKS] 13-Oct-22 13-Dec-22 103
Tank External Blasting & Painting 13-Oct-22 7-Dec-22 55 16-Oct-22 45% Roof External Blasting ongoing
Roof Leg Pad Blasting & Coating 7-Oct-22 21-Oct-22 14 5-Oct-22 97% Delayed by Electrical Maintenance
Tank Internal Blasting & Painting 3-Nov-22 30-Nov-22 28
U/G Piping Coating Works NA
External Scaffolding Removal 8-Dec-22 12-Dec-22 5
Tank Calibration 13-Dec-22 13-Dec-22 1
[HANDOVER WORKS] 8-Dec-22 16-Dec-22 8
Final Cleaning & Housekeeping 8-Dec-22 12-Dec-22 5
Tank Box-Up Works 13-Dec-22 13-Dec-22 1
De-Blinding 14-Dec-22 16-Dec-22 2
[TDS & TFS WORKS]
Mechanical Repair & Coating 1-Aug-22 10-Aug-22 10 1-Aug-22 11-Aug-22 100%
HydroTest 1-Aug-22 10-Aug-22 10 1-Aug-22 11-Aug-22 100%
Service Test 1-Aug-22 10-Aug-22 10 1-Aug-22 11-Aug-22 100%
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 341226,350837,364249,345870 REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-22-458 START DATE: END DATE:

TANK ROOF TYPE: Floating DIA (M) :43.90 HEIGHT (M): 17.07 PRODUCT: KLD

TASK DESCRIPTION PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION REMARKS


START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS] 2-Aug-21 2-Aug-21
Dead-Stock Transfer 2-Aug-21 5-Nov-21 96 2-Aug-21 2-Aug-21 100%
Tank Blinding Works 6-Nov-21 10-Nov-21 5 5-Nov-21 10-Nov-21 100%
Gas Freeing & Stripping 13-Nov-21 17-Nov-21 5 13-Nov-02 18-Nov-21 100%
De-Sludging Works 18-Nov-21 24-Nov-21 7 20-Nov-21 24-Nov-21 100%
Washing and Cleaning Works 24-Nov-21 1-Dec-21 8 25-Nov-21 4-Dec-21 100%
Preliminary Inspection 2-Dec-21 3-Dec-21 2 5-Dec-21 5-Dec-21 100%
Removal of Heat Detection Cable 27-Dec-21 31-Dec-21 5 29-Dec-21 30-Dec-21 100%
External Scaffolding Erection 27-Dec-21 4-Jan-22 9 28-Feb-22 8-Mar-22 100% Due to Rain water logging in dyke wall
Internal Bottom Sweep Blasting 11-Jan-22 31-Jan-22 21 27-Dec-21 24-Feb-22 100%
Inspection of Tank Bottom 20-Feb-22 10-Mar-22 19 29-Mar-22 10-Apr-22 100%
Issuance of IAT(s) 12-Mar-22 15-Mar-22 4 26-Dec-21 8-May-22 100% Preliminary IAT received on 26/12/21
Roof Seal Removal 11-Jun-22 15-Jun-22 5 21-Jun-22 25-Jun-22 100%
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works NA
NDT Works (Vaccum Box/DPT) NA
Internal Scaffolding Removal NA
Access Door Cutting & Removal 20-May-22 23-May-22 4 17-May-22 22-May-22 100%
Existing Bottom Plates & Old Soil Removal 4-Jun-22 24-Jun-22 21 23-May-22 30-Jun-22 100%
CP System Installation 18-Sep-22 4-Oct-22 17 18-Sep-22 18-Oct-22 100% Junction box Installation and termination pending
Re-Bottoming Works 5-Oct-22 30-Oct-22 25 23-May-22 10%
Access Door Reinstallation 31-Oct-22 3-Nov-22 3
NDT Works (DPT/Vacuum Box Test/RT) 4-Nov-22 8-Nov-22 4
Tank HydroTest 9-Nov-22 3-Dec-22 24 Service test to be done
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting 20-Dec-22 14-Jan-23 26 22-Feb-22 24-Feb-22
Roof Leg Pad Blasting & Coating 9-Feb-23 26-Feb-23 18
Tank Internal Blasting & Painting 9-Feb-23 21-Feb-23 13
U/G Piping Coating Works 14-Dec-22 22-Dec-22 9
External Scaffolding Removal 7-Feb-23 13-Feb-23 7
Tank Calibration 14-Feb-23 16-Feb-23 3
[HANDOVER WORKS]
Final Cleaning & Housekeeping 27-Feb-23 3-Mar-23 4
Tank Box-Up Works 27-Feb-23 3-Mar-23 4
De-Blinding 27-Feb-23 3-Mar-23 4
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 363336, 364882 REPORT DATE: 25-OCT-2022


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-667/668 Start Date: 9/Sep/22 End Date: 30/Oct/22

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS] 9-Sep-22 10-Sep-22 2 9-Sep-22 10-Sep-22


Site Survey Works 9-Sep-22 10-Sep-22 2 9-Sep-22 10-Sep-22 100%
Permeability Test of Existing Soil 10-Sep-22 10-Sep-22 1 10-Sep-22 10-Sep-22 100%
[IMPERVIOUS LINING WORKS] 13-Sep-22 30-Oct-22 48 13-Sep-22 30-Oct-22
Grading of Old Soil 13-Sep-22 19-Sep-22 6 13-Sep-22 19-Sep-22 100%
Removal of Old Soil from Tank 16-Sep-22 22-Sep-22 6 16-Sep-22 22-Sep-22 100%
Water Spraying & Compaction after Removal of Old Soil 22-Sep-22 25-Sep-22 4 22-Sep-22 25-Sep-22 100%
Backfilling with New Gatch 26-Sep-22 22-Oct-22 24 26-Sep-22 22-Oct-22 100%
Water Spraying & Levelling of New Gatch 2-Oct-22 24-Oct-22 20 2-Oct-22 24-Oct-22 100%
Compaction of New Gatch 7-Oct-22 29-Oct-22 20 7-Oct-22 85%
Final Permeability & Compaction Testing 23-Oct-22 30-Oct-22 2 23-Oct-22 50%
[TANK FOUNDATION REPAIR WORKS] 27-Sep-22 8-Oct-22 12 27-Sep-22 8-Oct-22
Removal of Damaged Concrete Sections 27-Sep-22 28-Sep-22 2 27-Sep-22 28-Sep-22 100%
Shuttering Works for Tank Foundation Repair 29-Sep-22 2-Oct-22 4 29-Sep-22 2-Oct-22 100%
Concrete Casting & Curing Works 3-Oct-22 6-Oct-22 4 3-Oct-22 6-Oct-22 100%
Final Paint Touch-Up Works 7-Oct-22 8-Oct-22 2 7-Oct-22 8-Oct-22 100%
[TANK SKIRTING REPAIR WORKS] 9-Oct-22 19-Oct-22 11 9-Oct-22 19-Oct-22
Removal of Damaged Bitumen from Tank Skirting 9-Oct-22 10-Oct-22 2 9-Oct-22 10-Oct-22 100%
Backfilling, Contouring and Compaction of New Gatch 11-Oct-22 13-Oct-22 3 11-Oct-22 13-Oct-22 100%
Application of MC-30 Capseal in Skirt Area 14-Oct-22 15-Oct-22 2 14-Oct-22 15-Oct-22 100%
Application of Bitumen 16-Oct-22 19-Oct-22 4 16-Oct-22 19-Oct-22 100%
[TANK DYKE WALL & KEY REPAIR WORKS] 8-Oct-22 28-Oct-22 21 5-Oct-22 28-Oct-22
Removal of Damaged Asphalt from Dyke & Key 8-Oct-22 13-Oct-22 6 5-Oct-22 11-Oct-22 100%
Backfilling, Contouring and Compaction of New Gatch 14-Oct-22 21-Oct-22 8 12-Oct-22 19-Oct-22 100%
Application of MC-30 Capseal 19-Oct-22 24-Oct-22 6 17-Oct-22 22-Oct-22 100%
Application of Bitumen 21-Oct-22 28-Oct-22 8 21-Oct-22 85%
[STORM WATER DRAIN REPAIR WORKS] 17-Oct-22 27-Oct-22 11 17-Oct-22 27-Oct-22
Excavation of Burried Storm Water Drain 17-Oct-22 19-Oct-22 3 17-Oct-22 19-Oct-22 100%
Removal Damaged Sections 18-Oct-22 19-Oct-22 2 18-Oct-22 19-Oct-22 100%
Rebar Repair Works 20-Oct-22 21-Oct-22 2 20-Oct-22 21-Oct-22 100%
Shuttering Works 22-Oct-22 23-Oct-22 2 22-Oct-22 23-Oct-22 100%
Concrete Casting & Curing Works 24-Oct-22 25-Oct-22 2 24-Oct-22 25-Oct-22 100%
Backfilling & Compaction Works in Adjacent Area 26-Oct-22 27-Oct-22 2 26-Oct-22 27-Oct-22 100%

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:

Format No.CA/4079/002 Rev.0


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 364464 REPORT DATE: 25-OCT-2022


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-460 Start Date: 10/Oct/22 End Date: 15/Nov/22

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION REMARKS
START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS] 10-Oct-22 11-Oct-22 2 10-Oct-22 11-Oct-22
Site Survey Works 10-Oct-22 11-Oct-22 2 10-Oct-22 11-Oct-22 100%
Permeability Test of Existing Soil 11-Oct-22 11-Oct-22 1 11-Oct-22 11-Oct-22 100%
[IMPERVIOUS LINING WORKS] 12-Oct-22 13-Nov-22 33 12-Oct-22
Grading of Old Soil 12-Oct-22 17-Oct-22 5 12-Oct-22 17-Oct-22 100%
Removal of Old Soil from Tank 15-Oct-22 19-Oct-22 4 15-Oct-22 19-Oct-22 100%
Water Spraying & Compaction after Removal of Old Soil 19-Oct-22 22-Oct-22 4 19-Oct-22 22-Oct-22 100%
Backfilling with New Gatch 23-Oct-22 3-Nov-22 12 23-Oct-22 70%
Water Spraying & Levelling of New Gatch 29-Oct-22 7-Nov-22 10 29-Oct-22 60%
Compaction of New Gatch 3-Nov-22 12-Nov-22 10
Final Permeability & Compaction Testing 13-Nov-22 13-Nov-22 1
[TANK FOUNDATION REPAIR WORKS] 29-Oct-22 4-Nov-22 7
Removal of Damaged Concrete Sections 29-Oct-22 30-Oct-22 2
Shuttering Works for Tank Foundation Repair 31-Oct-22 1-Nov-22 2
Concrete Casting & Curing Works 2-Nov-22 3-Nov-22 2
Final Paint Touch-Up Works 4-Nov-22 4-Nov-22 1
[TANK SKIRTING REPAIR WORKS] 5-Nov-22 12-Nov-22 8
Removal of Damaged Bitumen from Tank Skirting 5-Nov-22 6-Nov-22 2
Backfilling, Contouring and Compaction of New Gatch 7-Nov-22 8-Nov-22 2
Application of MC-30 Capseal in Skirt Area 9-Nov-22 10-Nov-22 2
Application of Bitumen 11-Nov-22 12-Nov-22 2
[TANK DYKE WALL & KEY REPAIR WORKS] 4-Nov-22 11-Nov-22 8
Removal of Damaged Asphalt from Dyke & Key 4-Nov-22 6-Nov-22 3
Backfilling, Contouring and Compaction of New Gatch 7-Nov-22 9-Nov-22 3
Application of MC-30 Capseal 10-Nov-22 11-Nov-22 2
Application of Bitumen 8-Nov-22 11-Nov-22 4
[STORM WATER DRAIN REPAIR WORKS] 17-Oct-22 15-Nov-22 30
Excavation of Burried Storm Water Drain 17-Oct-22 18-Oct-22 2 100%
Removal Damaged Sections 18-Oct-22 18-Oct-22 1 100%
Rebar Repair Works 11-Nov-22 11-Nov-22 1
Shuttering Works 12-Nov-22 13-Nov-22 2
Concrete Casting & Curing Works 14-Nov-22 14-Nov-22 1
Backfilling & Compaction Works in Adjacent Area 15-Nov-22 15-Nov-22 1

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:

Format No.CA/4079/002 Rev.0


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): 364465 REPORT DATE: 25-OCT-2022


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : TK-61-669/670 Start Date: 22/Oct/22 End Date: 10/Dec/22

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION REMARKS
START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS] 22-Oct-22 23-Oct-22 2 22-Oct-22 23-Oct-22
Site Survey Works 22-Oct-22 23-Oct-22 2 22-Oct-22 23-Oct-22 100%
Permeability Test of Existing Soil 23-Oct-22 23-Oct-22 1 23-Oct-22 23-Oct-22 100%
[IMPERVIOUS LINING WORKS] 23-Oct-22 10-Dec-22 49
Grading of Old Soil 24-Oct-22 30-Oct-22 6 24-Oct-22 50%
Removal of Old Soil from Tank 27-Oct-22 2-Nov-22 6
Water Spraying & Compaction after Removal of Old Soil 2-Nov-22 5-Nov-22 4
Backfilling with New Gatch 6-Nov-22 30-Nov-22 22
Water Spraying & Levelling of New Gatch 12-Nov-22 2-Dec-22 18
Compaction of New Gatch 17-Nov-22 9-Dec-22 20
Final Permeability & Compaction Testing 23-Oct-22 10-Dec-22 1
[TANK FOUNDATION REPAIR WORKS] 14-Nov-22 25-Nov-22 12
Removal of Damaged Concrete Sections 14-Nov-22 15-Nov-22 2
Shuttering Works for Tank Foundation Repair 16-Nov-22 19-Nov-22 4
Concrete Casting & Curing Works 20-Nov-22 23-Nov-22 4
Final Paint Touch-Up Works 24-Nov-22 25-Nov-22 2
[TANK SKIRTING REPAIR WORKS] 26-Nov-22 6-Dec-22 11
Removal of Damaged Bitumen from Tank Skirting 26-Nov-22 27-Nov-22 2
Backfilling, Contouring and Compaction of New Gatch 28-Nov-22 30-Nov-22 3
Application of MC-30 Capseal in Skirt Area 1-Dec-22 2-Dec-22 2
Application of Bitumen 3-Dec-22 6-Dec-22 4
[TANK DYKE WALL & KEY REPAIR WORKS] 18-Nov-22 8-Dec-22 21
Removal of Damaged Asphalt from Dyke & Key 18-Nov-22 23-Nov-22 6
Backfilling, Contouring and Compaction of New Gatch 24-Nov-22 1-Dec-22 8
Application of MC-30 Capseal 29-Nov-22 4-Dec-22 6
Application of Bitumen 1-Dec-22 8-Dec-22 8
[STORM WATER DRAIN REPAIR WORKS] 26-Nov-22 6-Dec-22 11
Excavation of Burried Storm Water Drain 26-Nov-22 28-Nov-22 3
Removal Damaged Sections 27-Nov-22 28-Nov-22 2
Rebar Repair Works 29-Nov-22 30-Nov-22 2
Shuttering Works 1-Dec-22 2-Dec-22 2
Concrete Casting & Curing Works 3-Dec-22 4-Dec-22 2
Backfilling & Compaction Works in Adjacent Area 5-Dec-22 6-Dec-22 2

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:

Format No.CA/4079/002 Rev.0


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : START DATE: END DATE:

TANK ROOF TYPE: DIA (M) : HEIGHT (M): PRODUCT:

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Removal of Heat Detection Cable
Removal of Roof Seal
Internal Sweep Blasting
Inspection of Tank
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
C.P. System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Re-Installation of Roof Seal
Tank HydroTest
[BLASTING & PAINTING WORKS]
Tank External Blasting & Painting
Roof Leg Pad Blasting & Coating
Tank Internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:


Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : START DATE: END DATE:

TANK ROOF TYPE: DIA (M) : HEIGHT (M): PRODUCT:

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION START FINISH (DAYS) START FINISH % REMARKS

[PREPARATORY WORKS]
Dead-Stock Transfer
Tank Blinding Works
Gas Freeing & Stripping
De-Sludging Works
Washing and Cleaning Works
Preliminary Inspection
External Scaffolding Erection
Internal Bottom Sweep Blasting
Inspection of Tank Bottom
Issuance of IAT(s)
Internal Scaffloding Erection
Internal Sweep Blasting
Inspection of Tank Roof & Shell
Issuance of IAT(s)
[MECHANICAL WORKS]
Re-Roofing Works
NDT Works (Vaccum Box/DPT)
Internal Scaffolding Removal
Access Door Cutting & Removal
Existing Bottom Plates & Old Soil Removal
CP System Installation
Re-Bottoming Works
Access Door Reinstallation
NDT Works (DPT/Vacuum Box Test/RT)
Tank HydroTest
[BLASTING & PAINTING WORKS]
Internal Roof Blasting & Painting
Tank External Blasting & Painting
Tank internal Blasting & Painting
U/G Piping Coating Works
External Scaffolding Removal
Tank Calibration
[HANDOVER WORKS]
Final Cleaning & Housekeeping
Tank Box-Up Works
De-Blinding
[TDS & TFS WORKS]
Mechanical Repair & Coating
HydroTest
Service Test
[MATERIAL STATUS]
KNPC Material Supply:

Vendor Material Supply:

[IAT STATUS] INSPECTION HANDOVER DATE INSPECTION START DATE IAT ISSUE DATE DURATION REMARKS

IAT#
IAT#
IAT#
IAT#

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:


DAILY PROGRESS REPORT

Contract No : CA/4079 CPO(s): REPORT DATE:


Project Name : Tank Cleaning, Repair, Fiber Glassing & Painting Works at Refinery & Gas Liquid Production Facilities
Contractor Name : M/s. Al Magwa Engineering & Contracting Company WLL
Location : MAA Refinery
TANK NO. : START DATE: END DATE:

TANK ROOF TYPE: DIA (M) : HEIGHT (M): PRODUCT:

PLANNED PLANNED DUR ACTUAL ACTUAL COMPLETION


TASK DESCRIPTION REMARKS
START FINISH (DAYS) START FINISH %
[PREPARATORY WORKS]
Site Survey Works
Permeability Test of Existing Soil
[IMPERVIOUS LINING WORKS]
Grading of Old Soil
Removal of Old Soil from Tank
Water Spraying & Compaction after Removal of Old Soil
Backfilling with New Gatch
Water Spraying & Levelling of New Gatch
Compaction of New Gatch
Final Permeability & Compaction Testing
[TANK FOUNDATION REPAIR WORKS]
Removal of Damaged Concrete Sections
Shuttering Works for Tank Foundation Repair
Concrete Casting & Curing Works
Final Paint Touch-Up Works
[TANK SKIRTING REPAIR WORKS]
Removal of Damaged Bitumen from Tank Skirting
Backfilling, Contouring and Compaction of New Gatch
Application of MC-30 Capseal in Skirt Area
Application of Bitumen
[TANK DYKE WALL & KEY REPAIR WORKS]
Removal of Damaged Asphalt from Dyke & Key
Backfilling, Contouring and Compaction of New Gatch
Application of MC-30 Capseal
Application of Bitumen
[STORM WATER DRAIN REPAIR WORKS]
Excavation of Burried Storm Water Drain
Removal Damaged Sections
Rebar Repair Works
Shuttering Works
Concrete Casting & Curing Works
Backfilling & Compaction Works in Adjacent Area

Works Executed Today :

Work Plan for Next Working Day :

Critical Activity if Any:

Work Stoppages & Delays if Any Due To : Operations Safety Maintenance Inclement Weather
Remarks:

Supervisor: Site Engineer: Planning Engineer:

Format No.CA/4079/002 Rev.0