As at 26-10-2021 Delay catchup

Task Name Duration Start Date End Date Delay Reason for delays Duration Start Date Finish Date

Conveyor Trestle 10 199 days 9/1/2021 3/18/2022 143 days 10/27/2021 3/18/2022
Civil Works 65 days 9/1/2021 11/4/2021 42 days 10/27/2021 12/7/2021
Concrete Frame 01 Construction 20 days 9/1/2021 9/20/2021 36 days 14 days 10/27/2021 11/9/2021
Embeded parts delivery delay

Concrete Frame 02 Construction 24 days 9/11/2021 10/4/2021 22 days 21 days 10/27/2021 11/16/2021
Embeded parts delivery delay

Concrete Frame 03 Construction 30 days 9/21/2021 10/20/2021 6 days 21 days 10/27/2021 11/16/2021
Embeded parts delivery delay
Concrete Frame 04 Construction 35 days 10/1/2021 11/4/2021 28 days 10/27/2021 11/23/2021
Modification of Transfer Tower 05 30 days 9/26/2021 10/25/2021 30 days Not attended 28 days 11/10/2021 12/7/2021
Steel Works 96 days 12/13/2021 3/18/2022 96 days 12/13/2021 3/18/2022
Metal Works & Steel Truss Erection 95 days 12/13/2021 3/17/2022 95 days 12/13/2021 3/17/2022
Completion of Conveyor Trestle 10 1 day 3/18/2022 3/18/2022 1 day 3/18/2022 3/18/2022